Factors Governing Selection of Equipment

Construction Equipment Suitability for


Job Conditions
Size of the
Equipment
Standardisation
Availability of
Equipment
Availability of
Spare Parts
Multipurpose
Equipment
(versatility)

Management Availability of Use in Future The Economical Reliability of the Operating


Service Support
know-how Projects Aspects Equipment Requirements
CMT 522
Session 14 – Planning and Selection of Adequacy of
Equipment - 2 Past
Reputation of
Warranty or Standard
drive
the mechanism or
Performance guarantee Components
manufacturer power of the
prime-mover

Aritra Halder
| Aritra Halder | Assistant Professor
Assistant Professor | School of Construction

Forward Planning for Equipment in Projects Equipment Records


• The planning of a project should be made at least 6 to 9 months in Progress Data Compilation
advance of commencement of work.
Resource Utilization Analysis
• The main tasks for Equipment Planning are –
Performance Check
Purchase of Equipment The purpose of maintaining
equipment related records Cost Management

Workshop Installation at the construction jobsites : Safety data Compilation

Spare Parts Stock Skill data Compilation

Equipment productivity analysis


Posting of Personnel

| Aritra Halder | Assistant Professor | Aritra Halder | Assistant Professor

1
12-04-2023

Types of on-site equipment records Equipment Forms at Construction Sites


• Daily Operation Report
Progress Records Work Output Records Equipment Record • Eight Hours Maintenance Report
• Daily Field Repair Report
• Work Programme • Tasks on which employed • Log Book • Daily Servicing Report
• Bar Graph • Total • How the m/c is performing • Accident/Breakdown Report
• Line Charts trips/mileage/haulage/carriage • Daily/Monthly working data
• Pictorial Records • Minutes worked per hour • Sickness/Idleness etc. • Shift Change Report
• Servicing Period • History Books • Weekly Plant Detail and Progress Report
• Remarks on delay • Usage data
• Maintenance Register
• Monthly Consumable use Report
• Daily/weekly maintenance • Transfer Debit notes
• Hourly maintenance

| Aritra Halder | Assistant Professor | Aritra Halder | Assistant Professor

Responsibility of an Equipment Manager Purchase or Not to Purchase?


• Ensure all concerned are aware about their
responsibilities.
• Optimum utilization of machines. Conditions favoring Conditions against
• Adherence to SOP
purchase purchase
• Risk analysis and appraising the workers • When the machine is • When the machine doesn’t
supposed to fulfill its service serve the full life during the
• Thinking ahead and anticipate possible damages life while working in the project, it is better to hire
and bottlenecks etc. project. than purchase.
• Mechanical Servicing • It remains available for use • Purchase requires higher
• Adherence to safety whenever required. initial capital requirement.
• Maintenance and condition • Owning carries the risk of
• Keep records of processes will always be better. obsolescence.

| Aritra Halder | Assistant Professor | Aritra Halder | Assistant Professor

2
12-04-2023

Purchase of Equipment
• Hiring with option to Purchase • Purchase of Used Equipment
– In this system user hire the – Return on Investment

Thank You!
equipment at the Prevailing rate – Firm’s Financial Condition
with a provision that he may – Quick and Easy Availability
purchase it at a later date if he
wishes to do so. – Satisfying user need
– In case he decides to purchase – Use as back up/Stand by/Top up
Contact Me
the equipment, a specified – Analysis of Workable
at
portion (generally about 80%) of Life/Payback Period/O&M Cost ahalder@nicmar.ac.in
the hire charges paid shall be +91-8504017164
adjusted against the original
purchase price of the equipment.

| Aritra Halder | Assistant Professor


| Aritra Halder | Assistant Professor