Professional Documents
Culture Documents
Structural failures
in cast-in-place reinforced
concrete building structures
under construction
8
Manuel Buitrago, Juan J. Moragues, Pedro A. Calderón, Jose M. Adam
ICITECH, Universitat Politècnica de València, Valencia, Spain
1 INTRODUCTION
Many published studies agree that the construction phase of a structure is one of the
most critical as regards its safety [1–5]. During this phase the loads borne by the
slabs can be even higher than their design loads [6–8]. When combined with the pos-
sible failure of the shores supporting the slabs, this situation can be critical during the
construction phase of building structures [9–11].
There have been many recent cases of reinforced concrete (RC) buildings collapsing
during the construction phase, in most of which a local failure was followed by a chain
of failures that ended up with the loss of the entire structure or a large part of it. Consid-
ering the serious personal and material consequences involved in these cases, one of the
aims of the present study was to understand why building structures can collapse during
the construction phase. Another was to publicize the causes and thus avoid the same
mistakes being committed in the future, as well as to define the minimum requirements
of a building under construction to reduce the risk of potential collapses.
Diverse authors have previously followed the method used here, either by case
studies or studying the causes and proposing remedial measures. In this way it is pos-
sible to prevent or at least reduce the number of this type of accident. However, the
building world is in continual evolution, so it is essential to keep databases up to date
with the most common causes of these failures and the measures required to prevent
them. Given this need, the present paper compiles the most recent cases of structural
collapse during construction, including an analysis of their causes, and proposes a
number of remedial actions besides considering the most serious historical cases. In
short, this chapter offers the readers a review that provides them with all the informa-
tion available to date in a single document. Its principal novelty lies in the fact that
never before has such a specific or detailed study been carried out on collapses of
cast-in-place RC building structures.
This chapter is divided into six sections, starting with the introduction. The sec-
ond section briefly describes the usual construction method of buildings with RC
Handbook of Materials Failure Analysis. http://dx.doi.org/10.1016/B978-0-08-101928-3.00008-2 153
Copyright © 2018 Elsevier Ltd. All rights reserved.
154 CHAPTER 8 Structural failures in cast-in-place RC building structures
structures. The third section reviews the most serious cases of historical collapses,
based on a compilation of publications by a number of authors, followed by an a nalysis
of the most recent cases. The fourth section reviews the causes of failure as identified
by different authors, including the most recent accidents. The fifth section proposes a
number of preventive measures designed to achieve safer construction processes, and
the main conclusions drawn from the work are given in the sixth section.
operation involves reshoring, in which 100% of both shores and formwork are first
removed and the shores are immediately reinstalled to help support future load incre-
ments in the upper floors. In this process the slabs must be able to support their own
self-weight only a few days after pouring.
The SS and SRS methods are well known all over the world, while SCS is
perhaps less so, although it is widely used in Spain and in many South American
countries. Fig. 8.2 shows a scheme of the different steps of each of the variants
FIGURE 8.2 Construction processes most often used today. (SS) shoring/striking,
(SCS) shoring/clearing/striking, and (SRS) shoring/reshoring/striking.
156 CHAPTER 8 Structural failures in cast-in-place RC building structures
defined for the case of two consecutively shored floors, up to the casting of the third
floor. Fig. 8.3 gives an example of two buildings under construction using the SCS
process.
According to these figures, and in spite of the fact that the United States is one of the
countries with the most advanced building codes in the world, there is an average
figure of approximately one fatality every two days in buildings under construction.
Over the years, reviews of failures in buildings under construction have been
carried out and this has made it possible to investigate their most common causes in
order to prevent the same mistakes being made in the future. These reviews include,
for example, Hadipriono and Wang [2,37], Eldukair and Ayyub [35], and Yates and
Lockley [38]. Although it was possible to reach interesting conclusions on the dif-
ferent causes involved in these cases, none of these reviews is actually up to date, so
that the most recent cases need be analyzed in order to deduce protective measures to
reduce the risk of similar cases in the future.
In this and the subsequent sections the period under study runs from January 2012
to April 2017, which is large enough and recent enough for an up-to-date study of
the causes of collapses of cast-in-place RC building structures during construction.
Sixty-six cases of buildings in all parts of the world that collapsed under construc-
tion were considered in the study period in: the USA, India, Chile, Brazil, Thailand,
Mexico, Argentina, Spain, Dominican Republic, Israel, Peru, Colombia, Bangladesh,
China, Saudi Arabia, Malaysia, Jamaica, Pakistan, Nigeria, Ghana, Tanzania, Kenya,
The Philippines, South Africa, Australia, Paraguay, and Bolivia. Details of the cases
are given in the next sections, including the number of collapsed floors and the num-
ber of deaths and cases of injuries involved. The subsequent sections describe the
most common causes and suggest possible measures to be adopted to reduce the risk
of failures.
Fig. 8.4 gives the number of collapsed floors in each case during the study
period; in the 66 cases analyzed, a total of 171 floors collapsed, giving an average
FIGURE 8.4 Number of collapsed floors in each failure over the period under review.
158 CHAPTER 8 Structural failures in cast-in-place RC building structures
FIGURE 8.5 Cracks and excessive deflections after striking of a floor in one-way
RC slab.
of 2.6 floors per case, a value higher than 1. It can therefore be seen that when
one floor collapses, it is highly likely that other floors will be progressively in-
volved. As regards the trend of the number of collapsed floors throughout the
years of the study period, although this is quite short, the number of cases cannot
be said to be growing any fewer, nor are the consequences getting less serious.
Therefore, neither can it be said that the risk of collapse has been reduced with
the passage of time. It should also be pointed out here that only catastrophic
cases were included in the study, however, there must be a considerable num-
ber of finished buildings with deficient structures that did not actually collapse.
Such cases, which are not usually reported, evidently involve a risk of future pa-
thologies and seriously compromised service conditions. As an example, Fig. 8.5
shows a building in which excessive cracking and deflections can be appreciated
after the striking of a floor.
Figs. 8.6 and 8.7 give the numbers of dead and injured, respectively, in each of
the incidents in the period studied. There were 405 deaths and 711 cases of injuries
in the total of 66 cases under study, which underlines the high risks run by construc-
tion workers. In fact, 36.3% of those involved in these accidents died. As mentioned
earlier, the number of dead and injured has not been reduced, which shows that the
risks to those involved in the construction industry have not been reduced with the
passage of time.
3 Collapses during construction 159
FIGURE 8.6 Number of deaths in each failure over the period under review.
FIGURE 8.7 Number of injuries in each failure over the period under review.
Source: J.K. Yates, E.E. Lockley, Documenting and analyzing construction failures, J. Constr. Eng.
Manage 1 (2002) 8–17. doi:10.1061/(ASCE)0733-9364(2002)128:1(8).
After studying the multiple causes that could trigger a collapse, below we give the
causes attributed to the collapse in each of the 66 cases studied in the present work
in the period between January 2012 and April 2017 to show the reasons for the most
recent cases of structural collapse during construction in cast-in-place RC building
structures. Fig. 8.8 gives the causes that triggered the collapse in these cases together
with the percentage of importance of each one. This importance is quantified in di-
rect proportion to the number of times the cause was cited in all the cases studied.
As can be seen in Fig. 8.8, more than 50% of the triggering causes are due to fail-
ures of the shoring system and the deficient design of the permanent RC structures.
In Figs. 8.9 and 8.10 these two leading causes are shown as: (1) shoring failures and
(2) deficient design of permanent RC structures.
From Figs. 8.9 and 8.10 it can be concluded that the triggering causes most likely
to occur are: (1) shore failure due to having to bear higher than the allowed loads
(20% of importance) (Fig. 8.11) and (2) failure due to insufficient anchorage length
of rebars or insufficient reinforcement against punching shear (5% of importance).
In the 66 cases of structural collapse studied other causes and errors were also
found to affect safety and could have triggered the failure. Fig. 8.12 gives the per-
centage importance of each of these causes calculated in direct proportion to the
number of times each one appeared in the different accident reports studied.
From Fig. 8.12 it can be concluded that it is vitally important to think about and
prepare the construction process by means of schemes or plans to avoid all types of
errors during this phase. It can also be stated that the inspection of work during con-
struction (including checking concrete strength before striking of slabs) is crucial.
FIGURE 8.12 Causes/mistakes that affect safety and might trigger a failure.
• Any loads during the construction stage, in addition to the safety coefficients
adopted during this transitory stage, should be expressly specified in the
standards in force in each country, in expectation of an international agreement,
which does not exist at the present time [52–55].
• There is a need for a standardized shoring system so that all the suppliers can
offer similar products and consequently can contribute to improving the safety
of the shoring systems used at the present time.
• It is absolutely necessary to carry out an accurate calculation of the loads
between shores and slabs [6]. There is no sense in carrying on using the
oversimplified calculation methods drawn up in the mid-20th century when
we can use the more precise simplified methods now available [12] and the
application of these new calculation methods should be specified in the design
standards.
166 CHAPTER 8 Structural failures in cast-in-place RC building structures
• In order to reduce the number of accidents due to building site collapses, all
those involved must comply with all the possible safety measures. Both research
groups and business companies should be aware of their obligation to introduce
measures to improve the resilience of the shores in order to obtain structural
redundancy and so avoid disproportionate collapse or, in other words, the
progressive collapse of an entire structure after a local failure. The concepts of
the structural resilience and redundancy of falsework should also be included in
the building standards.
• One of the measures at present being put into operation is based on the use of
load limiters on shores [56], which are equipped with a device that yields at
a specified value and redistributes the load over the neighboring shores. This
avoids the failure of individual shores, and thus, as described in earlier sections,
avoids the possible collapse of the complete shoring system.
6 CONCLUSIONS
This work is based on the analysis of the collapse of cast-in-place RC building struc-
tures during construction and contains a wide-ranging review of the current bibliog-
raphy on this type of incident, including their causes and the preventive measures that
have been proposed by various authors. Some new cases of recent accidents are in-
cluded, with an investigation on their causes and measures proposed to prevent their
being repeated. The authors believe there is a great need for the thorough analysis of
the causes of these accidents in order to reduce the frequency of their occurrence in
the future.
From the results of the study it can be concluded that:
1. In each failure an average of 2.6 floors collapsed, showing the high probability
of a progressive collapse after a local failure.
2. 36.3% of the persons involved in the recent cases were killed, which means a
local failure in any part of the permanent or temporary structure involves a high
risk to building workers.
3. The most frequent causes that trigger collapses are the failure of the shoring
system and the deficient design of the RC structure, or, more specifically:
a. Loads on shores higher than the design loads.
b. Insufficient anchorage length of rebars or insufficient reinforcement against
punching shear.
4. Other frequently found secondary causes or errors:
a. Lack of attention to or absence of shoring plan and construction process.
b. Striking operation on shores without first checking concrete strength.
c. Lack of inspection during construction.
5. Diverse authors have proposed measures to avoid collapses, such as those
described above, the most important being:
a. An international consensus is needed on the actions to be considered as well
as on safety coefficients during construction.
References 167
ACKNOWLEDGMENTS
The authors would like to express their gratitude to the Spanish Ministry of Education, Culture
and Sport for funding received under the FPU Program [FPU13/02466], to the Generalitat
Valenciana [GV/2015/063] and also to the Levantina, Ingeniería y Construcción S.L., and
Encofrados J. Alsina S.A. companies for their invaluable cooperation.
REFERENCES
[1] K.L. Carper, Structural failures during construction, J. Perform. Constr. Facil. 1 (1987)
132–144, doi: 10.1061/(ASCE)0887-3828(1987)1:3(132).
[2] F.C. Hadipriono, H.-K. Wang, Causes of falsework collapses during construction, Struct.
Saf. 4 (1987) 179–195, doi: 10.1016/0167-4730(87)90012-9.
[3] D.C. Epaarachchi, M.G. Stewart, D.V. Rosowsky, Structural reliability of multistory
buildings during construction, J. Struct. Eng. 128 (2002) 205–213, doi: 10.1061/
(ASCE)0733-9445(2002)128:2(205).
[4] D.V. Kaminetzy, P.C. Stivaros, Early-age concrete: construction loads, behavior, and fail-
ures, Concr. Int. 16 (1994) 58–63.
[5] K. Terwel, M. Mud, A. Frijters, Structural safety during construction, IABSE Madrid Symp.
Eng. Progress, Nat. People 102 (2014) 1071–1078, doi: 10.2749/222137814814067248.
[6] P.A. Calderón, Y.A. Alvarado, J.M. Adam, A new simplified procedure to estimate loads
on slabs and shoring during the construction of multistorey buildings, Eng. Struct. 33
(2011) 1565–1575, doi: 10.1016/j.engstruct.2011.01.027.
[7] M. Buitrago, J.M. Adam, Y.A. Alvarado, P.A. Calderón, I. Gasch, Maximum loads on
shores during the construction of buildings, Proc. Inst. Civ. Eng. Struct. Build. 169 (2016)
538–545, doi: 10.1680/jstbu.15.00089.
[8] M. Buitrago, J.M. Adam, P.A. Calderón, Y.A. Alvarado, J.J. Moragues, Estimating loads
on shores during the construction of RC building structures, Struct. Concr. 17 (2016)
502–512, doi: 10.1002/suco.201500130.
[9] D. Kaminetzky, Structural failures and how to prevent them, Civ. Eng. 46 (1976) 60–63.
[10] R. Hauser, Lessons from European failures, Concr. Int. 1 (1979) 21–25.
[11] N. Fitzsimons, D. Vannoy, Establishing patterns of building failures, Civ. Eng. New York
54 (1984) 54–57.
[12] J.M. Adam, M. Buitrago, J.J. Moragues, P.A. Calderón, Limitations of Grundy &
Kabaila’s simplified method and its repercussion on the safety and serviceability of
successively shored building structures, J. Perform. Constr. Facil. 31 (5) (2017), doi:
10.1061/(ASCE)CF1943-5509.0001038.
[13] Alsina Formwork Solutions, Encofrados J. Alsina S.A. 2017.
168 CHAPTER 8 Structural failures in cast-in-place RC building structures
[14] M. Buitrago, J.M. Adam, Y.A. Alvarado, J.J. Moragues, I. Gasch, P.A. Calderón,
Designing construction processes in buildings by heuristic optimization, Eng. Struct. 111
(2016) 1–10, doi: 10.1016/j.engstruct.2015.12.009.
[15] Y.A. Alvarado, Estudio experimental y numérico de la construcción de forjados hor-
migonados in situ mediante procesos de cimbrado, clareado y descimbrado de plantas
consecutivas, (Ph.D. thesis), Universitat Politècnica de València, (2009) (in Spanish).
[16] I. Gasch, Estudio de la evolución de cargas en forjados y estructuras auxiliares de apun-
talamiento durante la construcción de edificios de hormigón in situ mediante procesos
de cimbrado, clareado y descimbrado de plantas consecutivas, (Ph.D. thesis), Universitat
Politècnica de València, (2012) (in Spanish).
[17] J. Feld, Building failures: floor support shoring in multi-storey construction, Build. Res.
Pract. 2 (1974) 151–155, doi: 10.1080/09613217408550309.
[18] N.J. Carino, E.V. Leyendecker, S.G. Fattal, Review of the skyline plaza collapse, Concr.
Int. 5 (1983) 35–42.
[19] S. King, N.J. Delatte, Collapse of 2000 Commonwealth Avenue: punching shear case
study, J. Perform. Constr. Facil. 18 (2004) 54–61, doi: 10.1061/(ASCE)0887-3828
(2004)18:1(54).
[20] J. Schellhammer, N.J. Delatte, P.A. Bosela, Another look at the collapse of skyline
plaza at Bailey’s Crossroads, Virginia, J. Perform. Constr. Facil. 27 (2013) 354–361,
doi: 10.1061/(ASCE)CF.1943-5509.0000333.
[21] C.F. Scribner, C.G. Culver, Investigation of the collapse of L’Ambiance Plaza, J. Perform.
Constr. Facil. 2 (1988) 58–79, doi: 10.1061/(ASCE)0887-3828(1988)2:2(58).
[22] F.J. Heger, Public-safety issues in collapse of L’Ambiance Plaza, J. Perform. Constr.
Facil. 5 (1991) 92–112, doi: 10.1061/(ASCE)0887-3828(1991)5:2(92).
[23] L’Ambiance Plaza: what have we learned, Civ. Eng. 61 (1992) 38.
[24] R. Martin, N.J. Delatte, Another look at the L’Ambiance Plaza collapse, J. Perform. Con-
str. Facil. 14 (2000) 160–165, doi: 10.1061/(ASCE)0887-3828(2000)14:4(160).
[25] OSHA, Investigation of the October 30, 2003, Fatal Parking Garage Collapse at Tropicana
Casino Resort, Atlantic City, NJ, United States, 2004.
[26] OSHA, Investigation of the December 6, 2007, Fatal Parking Garage Collapse at
Berkman Plaza 2 in Jacksonville, FL, United States, 2008.
[27] OSHA, Investigation of the October 10, 2012, Parking Garage Collapse During
Construction at Miami Dade College, Doral, FL, United States, 2013.
[28] OSHA, Investigation of the May 23, 2013, Partial Collapse of a Prestressed Concrete
Double Tee at Montgomery Mall in Bethesda, MD, United States, 2013.
[29] OSHA, Investigation of the November 13, 2013, Collapse of Precast Walls at a Garage
Construction Site. Ft. Lauderdale, FL, United States, 2014.
[30] OSHA, Investigation of the Collapse of a Building, Tranquility at Hobe Sound, Hobe
Sound, FL, United States, 2004.
[31] OSHA, Investigation of the September 6, 2012, Partial Collapse of a Slab During Con-
struction at Hyatt Place, Omaha, NE, United States, 2013.
[32] Eight killed as Under-Construction Building Collapses in Kanpur, New Indian Express,
2017. http://www.newindianexpress.com/nation/2017/feb/01/eight-killed-as-under-con-
struction-building-collapses-in-kanpur-1565881.html.
[33] Siete muertos al derrumbarse un edificio en construcción en Ciudad de México. La Inf
2017. http://www.lainformacion.com/catastrofes-y-accidentes/muertos-derrumbarse-
construccion-Ciudad-Mexico_0_1016298442.html.
References 169
[34] T.G. Padgett, Manufactured wood joists: noncollapse failure, J. Perform. Constr. Facil. 6
(1992) 58–64, doi: 10.1061/(ASCE)0887-3828(1992)6:1(58).
[35] Z.A. Eldukair, B.M. Ayyub, Analysis of recent US structural and construction fail-
ures, J. Perform. Constr. Facil. 5 (1991) 57–73, doi: 10.1061/(ASCE)0887-3828(1991)
5:1(57).
[36] Bureau of Labor Statistics of the United States Department of Labor, 2017. https://
www.bls.gov/home.htm.
[37] F.C. Hadipriono, Analysis of events in recent structural failures, J. Struct. Eng. 111 (1985)
1468–1481, doi: 10.1061/(ASCE)0733-9445(1985)111:7(1468).
[38] J.K. Yates, E.E. Lockley, Documenting and analyzing construction failures, J. Constr.
Eng. Manage. 1 (2002) 8–17, doi: 10.1061/(ASCE)0733-9364(2002)128:1(8).
[39] J.G. Gross, Building structural failures: their cause and prevention, J. Prof. Issues Eng.
112 (1986) 236–248, doi: 10.1061/(ASCE)1052-3928(1986)112:4(236).
[40] J.L. Peng, A.D. Pan, D.V. Rosowsky, W.F. Chen, T. Yen, S.L. Chan, High clearance
scaffold systems during construction I: structural modelling and modes of failure, Eng.
Struct. 18 (1996) 247–257, doi: 10.1016/0141-0296(95)00144-1.
[41] R.G. Beale, Scaffold research: a review, J. Constr. Steel Res. 98 (2014) 188–200,
doi: 10.1016/j.jcsr.2014.01.016.
[42] A. Soane Bsc, Learning from experience to avoid collapse, Proc. Inst. Civ. Eng. Forensic
Eng. 169 (2016) 127–132, doi: 10.1680/jfoen.16.00004.
[43] D. Friedman, The Darlington Building Collapse: Modern Engineering and Obsolete
systems. 4th Forensic Eng Congr Cleveland, OH; United States, (2007); 217:339–352.
doi: 10.1061/40853(217)27.
[44] N.E. Ojukwu-Ogba, The imperative of effective insurance regulations to safe
building culture in Nigeria, Common. Law BullV 37 (2011) 281–293, doi:
10.1080/03050718.2011.570902.
[45] J.I. Ortega, Prevention of Construction Failures: A Systematic Approach. Forensic
Eng 2015 Perform Built Environ – Proc 7th Congr Forensic Eng (2015) 349–360. doi:
10.1061/9780784479711.032.
[46] K. Kim, Y. Cho, S. Zhang, Integrating work sequences and temporary structures into
safety planning: automated scaffolding-related safety hazard identification and preven-
tion in BIM, Autom. Constr. (2016) 70, doi: 10.1016/j.autcon.2016.06.012.
[47] H.C. Uzoegbo, G.A. Harli, Collapse of a multi-storey building at the final stages of con-
struction, Adv. Trends Struct. Eng. Mech. Comput. – Zingoni, Taylor & Francis Group
(2010) 316.
[48] S. Khudeira, Building collapse during construction, Pract. Period Struct. Des. Constr. 15
(2010) 99–100, doi: 10.1061/(ASCE)SC.1943-5576.0000058.
[49] I. Erdem, D.B. Peraza, A case study on the partial collapse of a building with a light
gage steel framing system. Forensic Eng 2015 Perform Built Environ – Proc 7th Congr
Forensic Eng, (2015) 328–336. doi: 10.1061/9780784479711.032.
[50] DOSH, Recommendations of Accident Prevention Measures, 2015.
[51] DOSH, Recommendations of Safety Measures, 2015.
[52] F.A. Webster, Reliability of multistory slab structures against progressive collapse dur-
ing construction, J. Am. Concr. Inst. 77 (1980) 449–457.
[53] D.C. Epaarachchi, M.G. Stewart, Human error and reliability of multistory reinforced-
concrete building construction, J. Perform. Constr. Facil. 18 (2004) 12–20, doi: 10.1061/
(ASCE)0887-3828(2004)18:1(12).
170 CHAPTER 8 Structural failures in cast-in-place RC building structures
[54] D. Fang, C. Geng, C. Zhang, H. Zhu, X. Liu, Reliability of reinforced concrete buildings
during construction, Tsinghua Sci. Technol. 9 (2004) 710–716.
[55] X.X. Yuan, W.L. Jin, Structural reliability and human error of reinforced-concrete build-
ing during construction, Adv. Mater. Res. 368–373 (2011) 1365–1369, doi: 10.4028/
www.scientific.net/AMR.368-373.1365.
[56] M. Buitrago, Y.A. Alvarado, J.M. Adam, P.A. Calderón, I. Gasch, J.J. Moragues,
Improving construction processes of concrete building structures using load limiters on
shores, Eng. Struct. 100 (2015) 104–115, doi: 10.1016/j.engstruct.2015.06.007.