Professional Documents
Culture Documents
www.cymru.gov.uk
Contents
Introduction ............................................................................................................................................................ 1
1. Earthworks ................................................................................................................................................. 2
2. Highways structures ................................................................................................................................. 3
2.1 Bridge foundations.................................................................................................................................... 3
2.2 Reinforced Concrete Retaining Walls ..................................................................................................... 7
3. Strengthened Earthworks ....................................................................................................................... 11
3.1 Reinforced soil slopes and retaining walls .......................................................................................... 11
3.2 Load transfer platform ............................................................................................................................ 11
4. Drainage ................................................................................................................................................... 14
4.1 Drainage in Cuttings ............................................................................................................................... 14
4.2 Drainage at Embankments ..................................................................................................................... 14
4.3 Drainage at Structures ............................................................................................................................ 14
5. Pavement Design, Sub-grade and Capping .......................................................................................... 15
6. Assessment of Potential Contamination .............................................................................................. 16
7. Ground Treatment (Including Underground Voids) ............................................................................. 17
8. Specification Appendices ....................................................................................................................... 18
9. Instrumentation and Monitoring ............................................................................................................ 19
10. References ............................................................................................................................................... 20
11. List of Drawings....................................................................................................................................... 21
12. Highways Structures Summary Table ................................................................................................... 22
B2191100/D2/1/2/059 ii
Geotechnical Design Report Volume 2: Structures
Introduction
The Geotechnical Design Report (GDR) is produced for the A465 Heads of the Valleys Section 5 & 6
Preliminary Design.
This GDR is not intended to be used for construction since detailed design is yet to be undertaken. The GDR
provides information on the Preliminary Design for the information of the detailed designer and other
organisations employed to complete follow-on work by the Client.
The GDR for Sections 5 and 6 (Dowlais to Hirwaun) of the A465 Dualling Project has been prepared in two
Volumes:
- Volume 1: Earthworks, Drainage and Pavement Design
- Volume 2: Highway Structures
This report represents Volume 2 of the GDR and presents the design concepts for bridge foundations, retaining
walls and load transfer platform.
The GDR follows the format specified in Appendix E of HD 22/08 (1) for managing geotechnical risk and is split
into the following sections:
• Section 1 - Earthworks (Volume 1)
• Section 2 - Structures (Volume 2)
• Section 3 - Strengthened Earthworks (Volume 2)
• Section 4 - Drainage (Volume 1)
• Section 5 - Pavement Design, Sub-grade and Capping (Volume 1)
• Section 6 - Assessment of Potential Contamination (Volume 1)
• Section 7 - Ground Treatment including Treatment of any underground voids etc (Volume 1)
• Section 8 - Specification Appendices (Volume 1)
• Section 9 - Instrumentation and Monitoring (Volume 1)
B2191100/D2/1/2/059 1
Geotechnical Design Report Volume 2: Structures
1. Earthworks
The earthworks section is presented in Volume 1 of this GDR report.
B2191100/D2/1/2/059 2
Geotechnical Design Report Volume 2: Structures
2. Highways structures
The proposed bridges and retaining walls are summarised in Table 12.1 and Table 12.2 respectively. The
location plan of the bridges is shown on the Earthworks General Arrangement Drawings 2191100-JAC-HGT-
DE-GE-0600-0001 to 0013, included in Volume 1 of this GDR report. The general arrangement plan for the
retaining walls is shown on Drawings 2191100-JAC-SWR-DE-SE-1600-10 to 60.
Details of the ground investigations undertaken, together with details of ground and groundwater conditions,
including the suggested ground model and characteristic soil parameters for individual structures, are
summarised in their Highway Structures Geotechnical Assessment Sheets in Appendix B.
The following sections discuss the various assumptions and concepts for design of the bridge foundations,
reinforced concrete retaining walls, reinforced earth walls and load transfer platform.
There are number of design assumptions and considerations common to all proposed structures, as described
below.
The geological cross-section across the whole route is presented in Drawing 2191100-JAC-HGT-DR-GE-0600-
0001 to 0016. The ground conditions relevant to each structure are summarised in their Geotechnical
Assessment Sheets, Appendix B.
The majority of the structures are expected to be founded within bedrock with some founded on Glacial Till.
Details of known mineworkings and mineral deposits are described in Section 3.5 of the Ground Investigation
Report (GIR) (2). In addition to the known mining history, where Lower Coal Measures is the underlying bedrock
and within the zone of influence of the foundation, there is a possibility for unrecorded mineworkings or voids
being encountered. In light of this, prior to construction, it is proposed that the ground beneath foundations
underlain by Lower Coal Measures, should be investigated for the presence of possible mineworkings or voids.
Groundwater level varies at each structure and their relevant levels are summarised in the Highway Structures
Geotechnical Assessment Sheets.
The global soil parameters assumed for the foundations of the structures within Sections 5 & 6 were discussed
in the GIR and are summarised below. However, these parameters have been reviewed and amended as
necessary, dependent on local ground conditions. In general, parameters were reduced if the local ground
conditions were assessed to be weaker than those assumed for the global values.
B2191100/D2/1/2/059 3
Geotechnical Design Report Volume 2: Structures
50
(between
10
ground 0.1 (between
Made level and 4 ground level
Cohesive and Granular 2.0 0 32 40
Ground m bgl) and 2 m bgl)
(below 4 m
bgl)
200 (below 0.05 (below
4 m bgl) 2 m bgl)
85 0.1 (between
20
ground level
85 + 10z and 2 m bgl)
Cohesive 20 + 6z
Stiff 2.0 (z = 2 32
Glacial (z = metres
metres 0.03 (below
Till below 5
below 2 m 2 m bgl)
m.bgl)
bgl)
Granular 2.0 - - 35 35 -
Possible Solifluction
1.9 35 0 28 7 0.5
Deposits
Geological
Material Strength Degree of
γb UCS
Bedrock Parameters constant, Index, GSI E’ (MN/m2) Disturbance
(Mg/m3) (MPa)
mi D
B2191100/D2/1/2/059 4
Geotechnical Design Report Volume 2: Structures
100 20
(between (between
ground ground
Made level & 2 level and 2
Cohesive and Granular 2.0 0 32 0.1
Ground m bgl) m bgl)
150
(below 2 30 (below 2
m bgl) m bgl)
75
20
75+ 10z 0.1
Stiff 20 + 3z
Cohesive (z =
2.10 2 32 (z = metres
metres
below 5 m
below 2
bgl)
Glacial Till m bgl)
30
30 + 17z
Granular 2.00 - 0 36 -
(z = metres
below 5 m
bgl)
Possible Solifluction
1.9 35 0 28 7 0.3
Deposits
γb Material Geological
UCS E’ D, Degree of
Bedrock Parameters (Mg/m3) constant Strength
(MPa) (MN/m2) Disturbance
mi Index, GSI
When the bridges are founded on retaining walls, in addition to the minimum required toe level for retainment,
additional length was incorporated to allow for the vertical loads from the bridge.
For the concept design, the bridge foundations were designed with unfactored loads and global factors of
safety.
The bearing capacity of all spread foundations founded on soils (Made Ground and Glacial Till) and rock were
carried out using hand calculations. Settlements of foundations founded within cohesive material were
B2191100/D2/1/2/059 5
Geotechnical Design Report Volume 2: Structures
assessed using the Elastic drained method (3) or Pdisp 19.3 (4) and within granular material using the Burland
and Burbage method (5).
The bearing capacity of the spread foundations within soils (cohesive and granular) were assessed using
conventional methods suggested by Skempton and Terzaghi. The bearing capacity on rock was based on the
values suggested in Tomlinson (6). The factor of safety on bearing capacity was taken as 3.
a) Shaft Capacity
In Gravels:
Ultimate shaft friction τsf = ks.σv’.tanδ
Where, ks = 0.7 (for Bored piles)
σv’ = effective overburden pressure
δ = interface friction angle, taken to be equal to φ’
In Clay:
Ultimate shaft friction τsf = α.cu
Where, α = adhesion factor, taken as 0.6 (Bored piles)
cu = undrained shear strength
A limiting value for average shaft friction, τsf, of 140 kPa was adopted.
b) Base Resistance
The ultimate base resistance (qb) in granular soils is based on the equation
qb = Nq σv’
Where, Nq = bearing capacity factor provided by Berezantsev
σv’ = effective overburden pressure
In cohesive soils the ultimate base resistance was taken as 9cu (kPa), where cu = undrained shear
strength at toe level, and will be limited to a value of 4.5 MPa.
c) Factor of Safety
The piles were designed with a global factor of safety of 2.5.
d) Settlements
Settlement calculation for piles were not analysed at this stage. However, it is anticipated the settlement
of piles founded on glacial till will be less than ~15 mm based on the safety factors applied.
The following correlations were used to determine the ultimate shaft friction of the bedrock:
fs,u = α x quc
B2191100/D2/1/2/059 6
Geotechnical Design Report Volume 2: Structures
where quc is the Unconfined Compressive Strength (UCS) of the bedrock and α was taken to be 0.05.
The rock formation along the route varies from weak mudstone (UCS range of 10 to 13 MPa) to strong
sandstone (UCS range of 35 – 50 MPa). A conservative UCS value of 10 MPa was used for the rock socket
design, which corresponds to an α value of 0.05(6). The base resistance of the bedrock was ignored due to
uncertainty of mining and unknown ground conditions, as well as to provide some conservatism for preliminary
design.
The bearing capacity and settlements for each structure are discussed in the individual Highway Structures
Geotechnical Assessment Sheets (Appendix B).
Initial consideration was given to adopting soil nails as a form of steepening cut slopes on the scheme,
however, during the initial 1:2500 Presentation to the Welsh Government, it was confirmed that the
design should not include any soil nails. It is understood that this was as a result of various problems
experienced with the use of soil nails in South Wales over the past years.
Similarly, the use of sheet piles was discounted due to perceived difficulties in driving the sheets
through the Glacial Till. The Till along the route of the A465 contains many large cobbles, which would
make driving extremely difficult, if not impossible.
On the basis of the above, it was decided to adopt contiguous bored piles for the preliminary design.
The general approach adopted, in order of preference and available land-take, is:
1. If land is available, cut to slope angle required to provide a sufficient FOS.
2. Construct L-shaped concrete retaining wall (only really appropriate for low height cuts where
temporary excavation is feasible).
3. Construct contiguous bored pile retaining wall at toe and regrade upper slope to safe slope
angle.
4. Construct contiguous pile retaining wall full height
Cantilever bored cast in-place contiguous piled walls are proposed to retain cuttings in areas where widening
cannot be carried out either by safe slope angles or by L-shape walls (See Table 12.2).The walls are to be
installed through the superficial deposits and in most cases, socketed into the underlying rock. A geocomposite
‘piledrain’ is proposed to control ground water flow through the gaps between the contiguous wall piles.
The piles at the top of the wall are connected by a reinforced concrete capping beam. To provide a safe barrier
at the edge of the wall, a parapet or a reinforced concrete wall (stone clad) cast integral with the capping beam
is proposed to be constructed at the top of the wall. The external face of the walls are to be faced as
appropriate, in accordance with the Environmental Statement.
• Type A: Installed from the existing ground level and connected by a 1 m thick capping beam (Drawing
2191100-JAC-SWR-DE-SE-1600-40) to tie with the existing ground level.
• Type B: Installed from the existing ground level and ‘built up’ by construction of a reinforced concrete
retaining wall to support new fill placed behind the wall (Drawing 2191100-JAC-SWR-DE-SE-1600-50).
B2191100/D2/1/2/059 7
Geotechnical Design Report Volume 2: Structures
This form of wall is used where the finished ground level behind the wall is above the existing ground
level.
The design height of a retaining wall is the length from the top of the wall or “built up” section to an excavation
level in front of the wall, taken as 1m below finished road level. This is to allow for a 1m pavement construction
in front of the wall. The details are provided in Table 12.2.
The general stratigraphy of the site is given on the Geological long sections in the GIR(2). The geology along the
proposed contiguous walls comprises various thicknesses of superficial deposits consisting of made ground,
dense to very dense granular and firm to very stiff cohesive Glacial Till, with possible soft to firm Solifluction
deposits. The superficial deposits are underlined by bedrock formation of Lower Coal Measures and Bishopston
formation of sandstones and mudstones.
The ground conditions at each particular structure are based on the nearest boreholes in the vicinity.
Detailed information on the ground water levels are provided within the Ground Investigation Report (2).
The design ground water level at the back of the wall is assumed at 1/3 of the design height of a retaining wall.
The characteristic geotechnical parameters of superficial deposits and bedrock are presented in the individual
retaining wall sheets (Appendix B) and are obtained from the GIR(2) with the following modifications:
• the stiffness parameters of superficial deposits are doubled for retaining wall design, as a retaining wall
will undergo smaller strains compared to a foundation ;
Bedrock parameters
The bedrock comprises mainly sandstone and mudstone. The shear strength parameters of mudstone were
assessed based the geological rock description and references given by Cripps and Taylor (7). Based on the test
data for the mudrocks across UK, Cripps and Taylor suggests the following range of values for the weathered
mudrock:
• c’ from 15 to 40 kN/m2.
A friction angle value of 40̊ and cohesion value of 20 kN/m2 have been assumed as retaining wall design
parameters for the mudstone.
The software ‘RockLab’ was used to determine the shear strength of Bishopston Sandstone using Hoek-Brown
failure criterion. The input parameters for RockLab used were that for the Lower Coal Measures Sandstone
(UCS, GSI, mi) given in GIR (2). Considering that the pile drilling will not cause significant disturbance to the
surrounding rock, the disturbance factor D for the analysis is assumed D=0. The output results indicated
strength parameters c’ of 2000 kN/m2 and ϕ’ of 33̊.
B2191100/D2/1/2/059 8
Geotechnical Design Report Volume 2: Structures
Although the analysis was carried out for Lower Coal Measures Sandstone, similar parameters have been
proposed for Bishopston Sandstone.
The geotechnical information for each structure, including the proposed design stratigraphy and summary of the
assumed design parameters, is given in the Highway Structures Geotechnical Assessment Sheets presented in
Appendix B.
At Cefn Coed (ch 11040 to ch 11140m) where the bedrock comprises Limestone and Twrch Sandstone
formation, the design parameters of these stratums were assumed as for Bishopston Formation due to absence
of sufficient laboratory test data.
At Baverstock (ch 7780 to ch 7860m) the Ka and Kp values are calculated to account for the sloping ground
(β=30) behind the wall (Appendix B).
The geotechnical parameters given in Table 2.1 to 2.2 were factored under Design Approach 1 in accordance
with BS EN 1997-1:2004.
The geotechnical design of the retaining walls are discussed below and summarised in the Highway Structures
Geotechnical Assessment Sheets (Appendix B).
The retaining structures are designed for a typical surcharge of 20kPa at the back of the walls as per BS
8002:2015, Table 7. This value is factored under Design Approach 1 according to BS EN 1997-1:2004.
The walls do not carry any vertical loading, except those sections where the wall piles are supporting bridge
abutments.
The stiffness of the concrete retaining wall is calculated using CIRIA C580 (8) guidance as follows:
where
s – pile spacing, m
The SLS case was modelled in accordance with BS EN 1997-1: 2004 (Eurocode 7) using the characteristic
values of soil parameters given in Table 2.1 and Table 2.2.
The excavation level for this case is assumed to be 1m below proposed design road level, to account for the
sub-base placement.
B2191100/D2/1/2/059 9
Geotechnical Design Report Volume 2: Structures
The ULS case design of the retaining walls has been undertaken using BS EN 1997-1: 2004, Design Approach
1. In this method, two analyses are undertaken using the following partial factors set out in Table 2.3. The
most onerous of the two analyses is then used for the structural design of the wall.
A 0.5m overdig below SLS excavation level was also considered. No increase of groundwater level is
considered as the drainage system will be in place to keep the water level at 1/3 of the wall height (ref to
Section 2.2.3.3)
The design of all retaining walls was completed using limit equilibrium techniques in the software programme
WALLAP, Version 6.05, distributed by Geosolve. For calculation of bending moments and shear forces, the
subgrade reaction model was used. For preliminary design, only the long term wall stiffness was analysed.
A series of analyses have been carried out to determine the required pile diameters, spacing and toe levels of
the contiguous piled and detailed results are given in Table 12.2.
B2191100/D2/1/2/059 10
Geotechnical Design Report Volume 2: Structures
3. Strengthened Earthworks
3.1 Reinforced soil slopes and retaining walls
• Baverstock:
o North of mainline carriageway between mainline and eastbound diverge (Ch 7700m –
Baverstock underbridge structure)
o North of mainline carriageway between eastbound merge and mainline (Ch 8040m – 8145m)
• Gurnos embankment :
o Western side of the eastbound approach embankment (from ch. 14,700m) to the new bridge
over Pant road (centre of deck at ch. 14,770m)
o Eastern side of the westbound approach embankment to the new bridge (up to ch. 14,820m)
o Reinforced earth abutments are proposed which will carry the bankseats to the new bridge
The ground investigation carried out in the area of Gurnos Farm Cottages (Embankment E16) indicates a
potential layer of solifluction deposits between chainage 12470m and 12870m (up to approximately 6m thick).
This is estimated from the borehole descriptions of ‘soft’ cohesive material encountered in 3/BH82. Elsewhere
along the route, the potential soliflucted deposits have been only up to about 3m thick and have therefore been
scheduled to be removed and replaced with compacted engineered fill prior to construction of any overlying
embankment. With up to 6m of soft deposits, this is considered to be impractical, especially as there are
buildings close to the highway boundaries, which would preclude any open excavation in this area. It is
therefore proposed that the embankment in this area is supported on a piled foundation with a load transfer
platform (LTP), formed with layers of geogrid reinforcement.
B2191100/D2/1/2/059 11
Geotechnical Design Report Volume 2: Structures
Ground conditions
7.5 m bgl – unproven Twrch Sandstone Formation (mainly) or Bishopston Mudstone Formation near Chainage
Groundwater was not encountered in 3/BH82, however it was encountered in 3/BH81 at 3 m bgl, rising to 2.6 m
bgl (293.2 m AOD) in twenty minutes.
Soil chemistry – The pH values of nearby boreholes (3/BH 80 and 3/BH 85) suggest values of the range 6 – 7.7
within the Glacial Till Cohesive.
The ground conditions are obtained from the ground model shown in Geological Long Section Sheets 9 and 10-
Appendix A of GIR (2). The following geotechnical parameters were used in the design :
Bishopston Mudstone
Possible solifluction Glacial Till (Cohesive) Twrch Sandstone
Formation
deposits
Design of the LTP has been based on BS8006-1:2016 (10) . For concept design, the following design parameters
have been adopted:
Pile capacity, 1000kN (based on 600mm diameter piles and 3m socket into bedrock)
B2191100/D2/1/2/059 12
Geotechnical Design Report Volume 2: Structures
The angle of constant volume shearing resistance for the embankment fill was taken to be 32o to reflect the
design parameters of Glacial Till (Cohesive), assuming the embankment fill is reworked Glacial Till.
The angle of constant volume shearing resistance when assessing the reinforcement bond was taken to be 35o,
to reflect the granular material that will be used above and below the geogrid. The interaction coefficient was
taken to be 0.84 (for granular material).
The following reinforcement bond lengths and strengths are suggested, for the various sections indicated
above.
It is considered that the soft ground beneath the existing road would have already settled following construction
of the original A465. It is considered therefore, that the piling and load transfer platform need not extend
beneath the existing road construction. It is suggested however, that transverse geogrid reinforcement (Tensar
400/50) is laid above the existing road, extending 2m into the new embankment construction, over the section of
load transfer platform, to reduce potential differential settlement between the old and new construction (Ref
Drawings 2191100-JAC-HGT-DE-GE-0600- 0014 and 00015).
B2191100/D2/1/2/059 13
Geotechnical Design Report Volume 2: Structures
4. Drainage
4.1 Drainage in Cuttings
General recommendations for drainage for cuttings are discussed in Section 1.1 of the Volume 1 of this report.
General recommendations for drainage for embankments are discussed in Section 1.2 of the Volume 1 of this
report.
General recommendations for drainage for structures are discussed in the individual Highway Structures
Assessment Appendix B.
Vertical drains for retaining wall are to be provided between each pile to collect groundwater flows. Drains are to
be set behind the sprayed concrete layer to the wall and outfall at the base of the wall above road carriageway
level into drainage channels provided in the raised verge. The drainage channels connect to a large diameter
filter drain located under the central reserve of the road carriageway. Half round channels collect the runoff from
embankments on top of the walls and direct this into the A465 road drainage system.
B2191100/D2/1/2/059 14
Geotechnical Design Report Volume 2: Structures
B2191100/D2/1/2/059 15
Geotechnical Design Report Volume 2: Structures
B2191100/D2/1/2/059 16
Geotechnical Design Report Volume 2: Structures
B2191100/D2/1/2/059 17
Geotechnical Design Report Volume 2: Structures
8. Specification Appendices
A 600 Series Specification has been produced for the A465 HOV Sections 5 & 6 Preliminary Design and is
included in Appendix C (Volume 1). It is not intended to be used for construction since detailed design is yet to
be undertaken and will define the final specification for construction. The Specification provides information and
requirements of the Preliminary Design for the information of the detailed designer and other organisations
employed to complete follow-on work by the Client.
It is anticipated that Specification Appendix Table 1/5 as per the Notes for Guidance, Volume 2 of the Manual of
Contract Documents for Highway Works (MCHW) shall be adopted and amended as appropriate by the detailed
designer and other organisations employed to complete follow-on work by the Client.
B2191100/D2/1/2/059 18
Geotechnical Design Report Volume 2: Structures
B2191100/D2/1/2/059 19
Geotechnical Design Report Volume 2: Structures
10. References
1. HD22/08 (August 2008) Design Manual for Roads and Bridges. Volume 4. Geotechnics and Drainage.
Section 1: Earthworks, Part 2. HD22/08 “Managing Geotechnical Risk”. Highways England.
2. Jacobs (2016) A465 Heads of the Valleys Dualling – Sections 5 and 6, Ground Investigation Report.
Report No. B2191100/D2/1/2/040, Revision W0
3. Jonathan Knappett, R.F. Craig (2012) Craig’s Soil Mechanics, Eighth edition, CRC Press
4. Pdisp 19.3, [Computer Software], Oasys 1997-2016
5. Burland and Burbage (1985), Settlement of foundations on sand and gravel, Proceedings of the
Institution of Civil Engineers, 78 (1), 1325 - 1381
6. Tomlinson (2001), Foundation Design and Construction, Seventh edition, Prentice Hall
7. Cripps and Taylor, (1981), The engineering properties of mudrocks, Quarterly Journal of Engineering
Geology and Hydrogeology, 14, 325-346
8. CIRIA Report C580 (2003), Embedded Retaining Walls : Guidance for economic design, Construction
Industry Research and Information Association
9. Jacobs (2016) A465 Abergavenny to Hirwaun Dualling Section 5 and 6 Dowlais Top to Hirwaun -
Interpretative Report on Phase 1 Land Quality Ground Investigation. Report No.
B2191100/D2/1/2/045.
10. BS8006-1:2010+A1:2016, Code of practice for strengthened/reinforced soils and other fills. BSI
2016
B2191100/D2/1/2/059 20
Geotechnical Design Report Volume 2: Structures
B2191100/D2/1/2/059 21
Geotechnical Design Report Volume 2: Structures
Section 5
Dowlais Junction 16160 2191100-JAC-SBR- B.1
West Bridge DE-SE-1600-3400
B2191100/D2/1/2/059 22
Geotechnical Design Report Volume 2: Structures
B2191100/D2/1/2/059 23
Geotechnical Design Report Volume 2: Structures
B2191100/D2/1/2/059 24
Geotechnical Design Report Volume 2: Structures
Swalec Pylon RW including wingwalls South 3460 3530 70 190.4 183.3 7.1 171.0 19.4 1.50 1.80 2.0 Type A B35.2
Afon Cynon Pond RW South 3660 3760 100 180.5 177.5 3.0 168.5 12.0 0.75 0.90 1.1 Type A B35.3
Cefn Coed Retaining Wall West (South) South 11040 11160 120 231.2 224.0 7.2 217.0 14.2 1.50 1.80 2.0 Type A B35.5
Cefn Coed East Retaining Wall (South) South 11160 11200 40 231.9 224.2 7.7 217.0 14.9 1.50 1.80 1.0 Type A B35.6
Cefn Coed Retaining Wall West (North) North 11000 11160 160 234.6 225.3 9.3 218.0 16.6 1.50 1.80 2.0 Type A B35.5
B2191100/D2/1/2/059 25
Geotechnical Design Report Volume 2: Structures
B2191100/D2/1/2/059 26
Geotechnical Design Report Volume 2: Structures
B2191100/D2/1/2/059 27
Geotechnical Design Report Volume 2: Structures
B2191100/D2/1/2/059 28
Geotechnical Design Report Volume 2: Structures
Drawings
B2191100/D2/1/2/059
NOTES:
1. ALL DIMENSIONS ARE IN MILLIMETRES UNLESS NOTED
OTHERWISE.
2. ALL EXPOSED ARRISES TO HAVE 25X25 CHAMFERS UNLESS
NOTED OTHERWISE.
B 3. ALL BURIED SURFACES OF THE REINFORCED CONCRETE
300MM THICK REINFORCED CONCRETE PARAPET ELEMENTS ACCESSIBLE AFTER CASTING SHALL BE PAINTED
WITH TWO COATS OF BITUMEN TO A LEVEL OF 150mm BELOW
WALL CAST INTEGRAL WITH CAPPING BEAM
FINISHED GROUND LEVEL.
TOP OF PARAPET TOP OF PARAPET 4. ALL DETAILS SHOWN ON THIS DRAWING ARE PART OF THE
CONCEPT DESIGN OF THE SCHEME FOR PRICING PURPOSES
SEE NOTE 6. ONLY AND SUBJECT TO DEVELOPMENT AT FURTHER DESIGN
STAGES.
1400
1400
5. IN ADDITION THE CONTRACTOR SHALL REFER TO THE CDM
REGISTER FOR THE RISKS RELEVANT TO CONSTRUCTION OF
THE STRUCTURE.
TOP OF THE WALL TOP OF CAPPING BEAM TOP OF CAPPING BEAM
6. THE CONTAINMENT LEVEL FOR THE PARAPETS IS N2. IN AREAS
WHERE PEDESTRIANS, ANIMALS, CYCLES AND VEHICLES
1
DRAWN BY ANIMALS ARE EXCLUDED (I.E. ON WALLS BETWEEN
1000
1 1800
6N/6P BACKFILL A SLIP ROAD AND THE MAINLINE) 1.0M HIGH PARAPETS ARE
(TYP)
PROPOSED. SEE THE TABLE ON DRAWING
2191100-JAC-SWR-DE-SE-1600-060 FOR DETAILS.
7. SEE DRAWING 2191100-JAC-SWR-DE-SE-1600-0050 FOR TYPICAL
CAPPING BEAM DETAILS OF THE TYPE B CONTIGUOUS BORED PILE WALLS.
8. SEE DRAWINGS 2191100-JAC-SWR-DE-SE-1600-0010 TO 0030
REINFORCED CONCRETE FOR PLANS OF THE PROPOSED CONTIGUOUS BORED PILE
CONTIGUOUS PILED WALL RETAINING WALLS.
9. SEE DRAWING 2191100-JAC-SWR-DE-SE-1600-0060 FOR A
SCHEDULE OF THE CONTIGUOUS BORED PILE RETAINING
SEE NOTE 11
A A WALLS.
10. SEE DRAWINGS 2191100-JAC-SWR-DE-SE-1600-4010 TO 4030
VARING
FOR DETAILS OF THE PROPOSED L-SHAPED CONCRETE
RETAINING WALLS.
VARING
11. APPEARANCE OF FINISHING TO BE IN ACCORDANCE WITH THE
ENVIRONMENTAL STATEMENT.
SEE NOTE 11
1000
1500
PROPOSED
5% FALL PROPOSED ROAD LEVEL
ROAD LEVEL
300
1 1
1000
5 5
1200
MAXIMUM
EXCAVATION LEVEL
DEPTH TO CROWN
TOE DRAIN WITH GRAVEL RC BORED PILES
1500 AROUND CONNECTS TO
CARRIER DRAIN
KEY PLAN
(TYP) CARRIER DRAIN
SCALE 1 : 50
PILE TOE LEVEL PILE TOE LEVEL
B 1800 1500
SAFETY, HEALTH AND ENVIRONMENTAL BOX
(TYP) (TYP)
responsibility whatsoever for, or in respect of, any use of, or reliance upon, this drawing by any third party.
R
AU
D
NOTES:
B 1. ALL DIMENSIONS ARE IN MILLIMETRES UNLESS NOTED
OTHERWISE.
300MM THICK REINFORCED CONCRETE PARAPET 2. ALL EXPOSED ARRISES TO HAVE 25X25 CHAMFERS UNLESS
WALL CAST INTEGRAL WITH CAPPING BEAM NOTED OTHERWISE.
3. ALL BURIED SURFACES OF THE REINFORCED CONCRETE
ELEMENTS ACCESSIBLE AFTER CASTING SHALL BE PAINTED
TOP OF PARAPET TOP OF PARAPET
WITH TWO COATS OF BITUMEN TO A LEVEL OF 150mm BELOW
FINISHED GROUND LEVEL.
SEE NOTE 6. 4. ALL DETAILS SHOWN ON THIS DRAWING ARE PART OF THE
CONCEPT DESIGN OF THE SCHEME FOR PRICING PURPOSES
1400
1400
ONLY AND SUBJECT TO DEVELOPMENT AT FURTHER DESIGN
STAGES.
TOP OF BUILT UP WALL TOP OF BUILT UP WALL 5. IN ADDITION THE CONTRACTOR SHALL REFER TO THE CDM
REGISTER FOR THE RISKS RELEVANT TO CONSTRUCTION OF
THE STRUCTURE.
6. THE CONTAINMENT LEVEL FOR THE PARAPETS IS N2. IN AREAS
REINFORCED CONCRETE BUILT UP WALL WHERE PEDESTRIANS, ANIMALS, CYCLES AND VEHICLES
DRAWN BY ANIMALS ARE EXCLUDED (I.E. ON WALLS BETWEEN
VARING
VARING
A SLIP ROAD AND THE MAINLINE) 1.0M HIGH PARAPETS ARE
6N/6P BACKFILL
1800 PROPOSED. SEE THE TABLE ON DRAWING
(TYP) 2191100-JAC-SWR-DE-SE-1600-0060 FOR DETAILS.
7. SEE DRAWING 2191100-JAC-SWR-DE-SE-1600 0040 FOR TYPICAL
DETAILS OF THE TYPE A CONTIGUOUS BORED PILE WALLS.
8. SEE DRAWINGS 2191100-JAC-SWR-DE-SE-1600-0010 TO 0030 FOR
EXISTING GROUND LEVEL TOP OF CAPPING BEAM TOP OF CAPPING BEAM PLANS OF THE PROPOSED CONTIGUOUS BORED PILE
RETAINING WALLS.
1 9. SEE DRAWING 2191100-JAC-SWR-DE-SE-1600-0060 FOR A
1000
1 1800 SCHEDULE OF THE CONTIGUOUS BORED PILE RETAINING
6N/6P BACKFILL
(TYP) WALLS.
10. SEE DRAWINGS 2191100-JAC-SWR-DE-SE-1600-4010 TO 4030
FOR DETAILS OF THE PROPOSED L-SHAPED CONCRETE
CAPPING BEAM RETAINING WALLS.
11. APPEARANCE OF FINISHING IN ACCORDANCE WITH THE
ENVIRONMENTAL STATEMENT.
REINFORCED CONCRETE
CONTIGUOUS PILED WALL
SEE NOTE 11
A A
N
VARING
R:\B1263600 - Welsh Assembly Government\Sections 5 & 6\150) GDR\Drawings for all deliverables\05 Retaining Wall Drawing 40 & 50\2191100-JAC-SWR-DE-SE-1600-0040-0050-0060.dwg - 04/09/2017 13:47:43 - Layout2-0050 - ptegg2
VARING
SEE NOTE 11
1000
1500
PROPOSED
5% FALL PROPOSED ROAD LEVEL
ROAD LEVEL
KEY PLAN
300
1 1
1000
5 5
1200
MAXIMUM
EXCAVATION LEVEL
SCALE 1 : 50
(TYP) (TYP)
HAZARD CONSTRUCTION 8th Floor, Churchill House, 17 Churchill Way,
LOG REF Cardiff, CF10 2HH
WALL TYPE - B
SECTION B-B 1. THE TYPE OF PILING EQUIPMENT AND METHODOLOGY TO
Client
responsibility whatsoever for, or in respect of, any use of, or reliance upon, this drawing by any third party.
R
AU
D
N
AREA
Gurn
os Farm GURNOS FARM
RETAINING WALL
GROUND IMPROVEMENT
EXISTING A465 AT GURNOS
Issue
s
(CH. 12470 m TO 12870 m
Gurn
os Farm
Cotta
ges
1
Issue 3
s
Sinks
Pond
KEY PLAN
Unde
rpass
SEE NOTE 3
Lay-by
12850
12750
HEADS OF THE VALLEY
Path
12650
(um
S ROAD
)
Rough Ground
12550
Y Graig
ck
Tra
IS
DOWLA
12450
Issues
Lay-by
Gurnos Farm
Path
Gurnos Farm
Cottages
Pond
1 3 y
Lay-b
12780
Ford
12820
12700
2
Issues
12570
Sinks
4
12870
12500
6
12470
12
20
AM
BE
TE SE
CLO
WHI
14
1
2
WEL
2
22
CLLING
by
Lay-
OS TONIA
GURNOS RING ROAD
5
D
E
EYS ROA
9
10
THE VALL
SEE NOTE 5
36
S OF
28
E
HEAD OS
AM
CL
Underpass
SEE NOTE 4
BE
FE
8
12
RN
7
RN 14
HO
Path HIL
7
30
L 1
CLO 12
Pol Sta
SE
13
13
21
RETAINING WALL N
5
44
AU
48
SEE NOTE 6
R:\B1263600 - Welsh Assembly Government\Sections 5 & 6\150) GDR\Drawings for all deliverables\02 Earthworks Drawing 14 & 15\Drawing 14\2191100-JAC-HGT-DE-GE-0600-0014_P02.dwg - 25/09/2017 09:16:55 - Layout1 - ptegg2
15
SEE NOTE 7
1
26
18
32 24
31
Pol S
IR
1
30
19
25 Ty Gwaunfarren
ta H
12 20
2
8
El
Sub Sta
FAN VIEW 18
PENY 56
NOS
PEN GUR
GROUND IMPROVEMENT
25 16
24
19
2
4
1
31 E
OS
8
2
S CL 15
TU
BU
AR 50
4
37
7
1
AT GURNOS
40
42 9
25 12
42
26
2
7
10
31
13
32
24
32
(CH. 12470 m TO 12870 m
Pen-y-garn Wood
34
Pen-y-garn
Wood
10
32
AM
k
ac
Tr
16
18
20
BEE
FE
6 83
48 M LOSE ITEOS
6
5 th
(um
) 16
75
EA C WHCL
Pa 1
RN
1
2
65
E
OS
NB
77
Subway CL
E 49
PL
AP
11
Spreads PEN-Y-DRE AB
HI
CR
R
67
47
9
HO
LL
9
43 57
55
19
13
12
16
21 to 26
2
70
GURNOS FARM
17 to 20
CL
Pond
2
64
27 to 32
OS
PEN GURNOS
1
57 2
UNDERPASS
Issues 14
52
76
E
20
47
Ty G
58
Subway
FO
RS
YTHIA
24
waun
CLOS
4
E
42
35
farre
El
BIRCH GROVE
Posts
1
1
Su
b Sta
1
10 6 Chy
16
11
89 41
82
79
69 Tank
9
16
14
83
85
34
WELLINGTONIA
Tank Tank
67
91
84
29
86
93
87
89
53
22
27
17
CLO
5
14
SE
1
18
LOCATION PLAN
22
12 8
1
7
PENYFAN VIEW
19
SCALE 1:1250
28
7
13
13
(um)
Path
31
30
37 25
21
42
15
24
24 26
44
1 6
8
12
30
4
20
El
18 Sub
Sta
PEN-
Y-DR 16
E Pen-
y-gar
k n Wo 2
Trac od
11
26 L OSE
21 to
UT US C 7
ARB 15
56
1
16
20
17 to
Pen-y
10
32 -garn
27 to Subw Woo
ay d
9
1
7
40
50
48
26
64
70
42
24
16
35 52
57 10
47
El Su
26
8
34
b Sta
42
32
P02 21/09/17 AMENDED FOLLOWING TAA REVIEW PT CR AD DS
32
P01 10/07/17 ISSUED FOR TAA REVIEW SC CR AD DS
CYPR
41
FO 18
RS Rev Rev. Date Purpose of revision Drawn Checkd Rev'd Apprv'd
YT
ESS
24
HI 16
58
A
CL R
OS
E
NOTES FOR GROUND IMPROVEMENT
8th Floor, Churchill House, 17 Churchill Way,
Cardiff, CF10 2HH
1. THE CHAINAGE IS IN m. 6. FROM CHAINAGE 12,700m TO 12,780m THE PROPOSED WIDENED A465
Client
EMBANKMENT/ROAD LEVEL IS LESS THAN 1.5m ABOVE THE EXISTING EMBANKMENT
2. BASED ON THE GEOLOGICAL LONG SECTION, SHEETS 9 AND 10 (DRAWING NO. /ROAD LEVEL. GROUND IMPROVEMENT IS NOT REQUIRED WITHIN THE FOOTPRINT
LEGEND 2191100-JAC-HGT-DR-GE-0600-0009 AND 0010, REV. P02 AND P03 RESPECTIVELY), OF THE EXISTING A465.
SOLIFLUCTION DESPOSITS ARE DEEMED TO BE PRESENT FROM CH. 12,470m TO
12,940m. FROM CH. 12,470m TO 12,590m THE GEOLOGICAL LONG SECTION IS 7. FROM CHAINAGE 12,780m ONWARDS THE WIDENED A465 WILL CUT INTO THE EXISTING
BASED ON GROUND INVESTIGATION THAT HAS BEEN UNDERTAKEN TO DATE, GROUND. THEREFORE NO GROUND IMPROVEMENT IS NECESSARY.
Project
AND LEVELS OF STRATA BETWEEN BORE HOLES ARE MERE INTERPRETATION.
1. BASAL REINFORCEMENT, SEE NOTE 12 WHERE THE DEPTH OF THE SOLIFLUCTION DEPOSITS IS LESS THAN 3m BELOW 8. THE THICKNESS OF SOLIFLUCTION DEPOSITS IS CONSIDERED TO BE LESS THAN 3m
EXISTING GROUND LEVEL, THE SOLIFLUCTION DEPOSITS SHALL BE EXCAVATED IN THIS AREA. THEREFORE IT IS REQUIRED TO EXCAVATE THE SOLIFLUCTION A465 SECTIONS 5 & 6
AND REPLACED WITH COMPACTED CLASS 1A/2 FILL. IF DEPTH IS GREATER THAN DEPOSITS AND REPLACE WITH WELL COMPACTED CLASS 1A OR 2 FILL.
3m THEN SOME FORM OF GROUND TREATMENT IS REQUIRED.
9. THE THICKNESS OF SOLIFLUCTION DEPOSITS IS CONDIDERED TO BE MORE THAN 3m. Drawing title
3. FROM CHAINAGE 12,470m TO 12,500m NO EXCAVATION IS NECESSARY WITHIN THEREFORE IT IS REQUIRED TO INSTALL A LOAD TRANSFER PLATFORM (LTP)
2. EXCAVATE AND REPLACE, SEE NOTE 8
THE FOOTPRINT OF THE EXISTING A465. IN THIS AREA. PROPOSED GROUND IMPROVEMENT
4. FROM CHAINAGE 12,500m TO 12,570m THE EMBANKMENT HEIGHT OF THE
EXISTING A465 IS LESS THAN 1.5m. EXCAVATION OF SOLIFLUCTION DEPOSITS
10. DETAILS OF THE PROPOSED LTP CAN BE SEEN ON DRAWING 2191100-JAC-HGT-DE-
SE-0600-0015
AT GURNOS (CH. 12470 m TO 12870 m)
AND REPLACEMENT IS THEREFORE REQUIRED.
3. LOAD TRANSFER PLATFORM, SEE NOTE 9 & 10. 11. THE THICKNESS OF SOLIFLUCTION DEPOSITS IS CONSIDERED TO BE ABOUT 6m.
5. FROM CHAINAGE 12,570m TO 12700m THE HEIGHT OF THE EXISTING A465 THE PROPOSED ROAD LEVEL OF THE WIDENED A465 AND THE SLIP ROAD IS LESS
IS MORE THAN 1.5m, GROUND IMPROVEMENT (LTP) IS NOT REQUIRED WITHIN THAN 2m ABOVE THE EXISTING GROUND LEVEL IN THIS AREA. IT IS THEREFORE
THE FOOTPRINT OF THE EXISTING A465. REQUIRED EXCAVATE THE SOLIFLUCTION DEPOSITS DOWN TO 2M BELOW THE Drawing status
PROPOSED ROAD LEVEL AND BACKFILL WITH WELL COMPACTED CLASS 1A OR DRAFT
2 MATERIAL.
4. EXCAVATE TO ACHIEVE 2M FILL HEIGHT, SEE NOTE 11 Scale AS SHOWN @ A1
12. FROM CHAINAGE 12,570m TO 12,870m BASAL REINFORCEMENT TO BE PLACED Jacobs No. B2191100
ACROSS THE EXISTING A465 (AT CURRENT ROAD LEVEL), EXTENDING 10m BEYOND DO NOT SCALE FROM THIS DRAWING
THE EDGE OF THE EXISTING A465, TO REDUCE DIFFERENTIAL SETTLEMENT. Drawing number Rev
2191100-JAC-HGT-DE-GE-0600-0014 P02
This drawing is not to be used in whole or part other than for the intended
AD
G purpose and project as defined on this drawing. Refer to the contract for full
AW I N
TOC
AU
D
NOTES:
2000 BASETEX 400/50 TEMPORARY EXCAVATION 7. THE DETAILS SHOWN ON THIS DRAWING ARE PART OF THE
150
274.4m AOD CONCEPT DESIGN OF THE SCHEME FOR PRICING PURPOSES
OPERATION/USE ONLY AND SUBJECT TO DEVELOPMENT AT FURTHER DESIGN
00
STAGES.
20
SEE NOTE 3
450
1800
GROUND IMPROVEMENT
AT GURNOS
(CH. 12470 m TO 12870 m
3000
KEY PLAN
PROPOSED EMBANKMENT
1
2
0 1 2 3 4 5m
00
Rev Rev. Date Purpose of revision Drawn Checkd Rev'd Apprv'd
20
278.95m AOD
R
3000
1800 8th Floor, Churchill House, 17 Churchill Way,
Cardiff, CF10 2HH
600 x 600 x 500
SQUARE PILE CAP Client
BASETEX 600/50
(TRANSVERSE)
6000
Project
Drawing status
PRELIMINARY
Scale AS SHOWN @ A1
Jacobs No. B2191100
DO NOT SCALE FROM THIS DRAWING
CROSS SECTION AT CH. 12,650m Drawing number
2191100-JAC-HGT-DE-GE-600-0015
Rev
P02
SCALE 1:50
This drawing is not to be used in whole or part other than for the intended
AD
G purpose and project as defined on this drawing. Refer to the contract for full
AW I N
TOC
AU
D
Geotechnical Design Report Volume 2: Structures
B2191100/D2/1/2/059
Geotechnical Design Report Volume 2: Structures
B2191100/D2/1/2/059
Geotechnical Design Report Volume 2: Structures
B2191100/D2/1/2/059
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Section 5 & 6 Heads of the Valleys Dualling Rev: 0 Sheet No: GAS/SP039A
Structure Name: Dowlais Junction West Bridges Date: March 2017
Prepared: DE/SN Checked: HM/CR Reviewed: AD Job No: B2191100
Proposed Structure:
Two bridges are proposed to support the proposed A465 carriageway over the Dowlais junction.
The two bridges will run roughly parallel to each other. This report discusses the foundation
design for the western bridge which is proposed to be a 17 m single span integral bridge with
abutments on the eastern and western side. The length of the bridge is 54.6 m.
≈ 373.5 to 372.2 m AOD (north and south respectively from the topographic survey)
The proposed A465 carriageway level is approximately 383 m AOD.
Ground Conditions:
The ground conditions although vary north to south, it does not vary between the east and west
abutments. As such ground conditions are assumed same for both the abutments.
Note:
Note : Coal workings were suspected in boreholes 2/BH188A, 2/BH189 and 2/BH193 as core loss recorded
between the following depths:
Groundwater:
Groundwater was recorded at 20.20mbgl (353.73m AOD) in 2/BH192 and 22.50mbgl (351.31m
AOD) in 2/BH193 within the bedrock. The highest groundwater level was recorded as 2.30mbgl
within 2/BH193 from water monitoring visit dated 27/06/1997 corresponding with the top of the
cohesive made ground.
The ground conditions described above suggest that global parameters from Jacobs GIR, 2016
(given below) are applicable except where mentioned.
Unit E’
Cohesion Angle of cu mv
Weight,
Stratum cp’, Friction, (MPa)
γ b,
(kN/m2) φp’, ° (kN/m2) (m2/M)
(Mg/m3)
0.1 10
Made Ground 50 (between
(between
(Cohesive and 2.0 0 32 ground level
ground level 40 (below 4
Granular) and 4 m bgl)
and 2 m bgl) m bgl)
0.1
20
(between
ground level
Glacial Till 20 + 6 z
2.0 2 32 75(1) and 2 m bgl)
(Cohesive) (where z is
metres below
0.03 (below
5 m bgl)
2 m bgl)
Glacial Till
2.0 0 35 - - 35
(Granular)
Bedrock γb UCS
GSI mi D E’ (MPa)
Parameters (Mg/m3) (MPa)
Lower Coal
2.5 13(1) 45 14 0.7 750
Measures
Note: (1) The parameters for glacial till and bedrock have been modified from the global GIR
values in order to reflect the description of boreholes at the location.
Foundation Consideration:
Due to the generally low bearing capacity of the cohesive glacial till and large amount of vertical
load from the bridge structure, it is proposed that the abutments are founded on piled
foundations. Thick coal seams were encountered at relatively shallow depth underlying the site
and core loss and fractures were also recorded in exploratory holes. Babtie report states that the
Lower 7 Feet Gellidelg Coal Seams have been worked in the area. The base of the Gellidelg Coal
seam, at the location of the proposed centre line at chainage 16000 m is approximately 350 m
AOD which also coincides with the base of the coal seams. Prior to construction, a series of
probe holes should be drilled beneath the abutment footprints to identify potential mine working. If
they are encountered, the voids should be grouted prior to the abutment piles being installed.
The estimated maximum load is approximately 1090 kN per metre length of pile cap which
applied over 52m (length of abutment) corresponds to 59500 kN. Assuming a pile group of fourty
piles per abutment in two rows, as suggested by Drawing B2191100-JAC-SBR-DE-SE-1600-
3300, the total load per pile is of the order 1490 kN. As the structure is an integral bridge, due to
the expansion of the deck, it is feasible that much of the load will be applied to one row of piles
with the other row in tension. It was therefore conservatively assumed that the full loading was
applied to a single row of piles. This therefore increases the load to 2975 kN per pile. Assuming a
0.9 m diameter piles socketed 5 m into the bedrock, the anticipated safe working load is 3675 kN
per pile, with an approximate toe elevation of 350 m AOD (the pile length becomes approximately
25 m).
Sulphate and pH tests were carried out on nine samples: one from within the made ground of
2/BH188A; two within glacial till from 2/BH189; four within glacial till from 2/BH190; one within
made ground from 2/BH192 and one within glacial till from 2/BH193. Results from these samples
suggest Aggressive Chemical Environment for Concrete AC-2z conditions in accordance with
BRE Special Digest 1: Concrete in Aggressive Ground (2005) and Design Sulfate class DS-1.
Only one result (2/BH192) indicated a slightly higher class of DS2 AC-2z, which is similar as for s
the whole route of section 5.
Construction Issues:
The existing traffic flows from the A465, the A40609 (T) and the A4102 will have to be temporarily
diverted during the construction of the bridge and associated embankments.
It has been reported (Babtie report) that the Lower 7 Feet Gellideg Coal Seams have been
worked in the area, and mine voids were encountered. The piles will therefore need to be
socketed below the coal seam, into more competent bedrock
A piled solution socketed at least 5.0m into the bedrock, beneath the coal working at an elevation
of 350 m AOD, is the most viable foundation option for the abutments and intermediate piers.
Due to the presence of coal seams and possible voids, the piles will need to be socketed beneath
the coal seam, into more competent bedrock and therefore deep piles (approximately 25 m long
with a diameter of 0.9 m) are recommended.
Design Sulfate DS-1 and ACEC AC-2z (BRE Special Digest 1, 2005) has been assumed for
concrete design for buried structures. Further chemical testing in this area is recommended to
confirm this assumption.
Prior to construction, a series of probe holes should be drilled beneath the abutment footprints to
identify potential mine working. If they are encountered, the voids should be grouted prior to the
abutment piles being installed.
B2191100/D2/1/2/059
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Heads of the Valleys Dualling Rev: 0 Sheet No: GAS/3400
Structure Name: Dowlais Junction East Bridges Date: March 2017
Prepared: DE/SN Checked: HM/CR Reviewed: AD Job No: B2191100
Proposed Structure:
Two bridges are proposed to support the proposed A465 carriageway over the Dowlais junction.
The two bridges will run roughly parallel to each other. This report discusses the foundation
design for the eastern bridge which is proposed to be a 14m single span integral bridge with
abutments on the eastern and western side.
≈ 374.4 to 372 m AOD (north and south respectively from the topographic survey)
The proposed A465 carriageway level is approximately 383.7 m AOD.
Ground Conditions:
The ground conditions although vary north to south, it does not vary between the east and west
abutments. As such ground conditions are assumed same for both the abutments.
Groundwater:
Groundwater was only encountered in 2/BH185 within the Made Ground as a slight seepage at
0.7m bgl (375 m AOD).
The ground conditions described above suggest that global parameters from Jacobs GIR, 2016
(given below) are applicable except where mentioned.
E’
Cohesion Angle of cu mv
γ b,
Stratum cp’, Friction, (MPa)
(Mg/m3) 2 2 2
(kN/m ) φp’, ° (kN/m ) (m /M)
Made Ground
(Cohesive and 2.0 0 32 40(1) 0.1 (1) 10 (1)
Granular)
0.1
20
(between
ground level
Glacial Till (1) 20 + 6 z
2.0 2 32 75 and 2 m bgl)
(Cohesive) (where z is
metres below
0.03 (below
5 m bgl)
2 m bgl)
Glacial Till
2.0 0 35 - - 35
(Granular)
Bedrock γb UCS
3 GSI mi D E’ (MPa)
Parameters (Mg/m ) (MPa)
Lower Coal
2.5 13(1) 45 14 0.7 750
Measures
Note: (1) The parameters for made ground, glacial till and bedrock have been modified from the
global GIR values in order to reflect the description of boreholes at the location.
Foundation Consideration:
Due to the generally low bearing capacity of the cohesive glacial till and large amount of vertical
load from the bridge structure, it is proposed that the abutments are founded on piled
foundations. Thick coal seams were encountered at relatively shallow depth underlying the site
and core loss and fractures were also recorded in exploratory holes. Babtie report states that the
Lower 7 Feet Gellidelg Coal Seams have been worked in the area. The base of the Gellidelg Coal
seam, at the location of the proposed centre line at chainage 16000 m is approximately 350 m
AOD which also coincides with the base of the coal seams. Prior to construction, a series of
probe holes should be drilled beneath the abutment footprints to identify potential mine working. If
they are encountered, the voids should be grouted prior to the abutment piles being installed.
The estimated maximum load is approximately 960 kN per metre length of pile cap which applied
over 52m (length of abutment) corresponds to 51800 kN. . Assuming a pile group of fourty piles
Sulphate and pH tests were carried out on nine samples: two from within the made ground of
2/BH183; one within made ground, two within glacial till and one within bedrock from 2/BH184;
one within glacial till from 2/BH185 and two within glacial till from 2/BH187. Results from these
samples suggest Aggressive Chemical Environment for Concrete AC-2z conditions in accordance
with BRE Special Digest 1: Concrete in Aggressive Ground (2005) and Design Sulfate class DS-
1, which is similar to that of the whole route of Section 5.
Construction Issues:
The existing traffic flows from the A465, the A40609 (T) and the A4102 will have to be temporarily
diverted during the construction of the bridge.
A piled solution socketed at least 5.0m into the bedrock, beneath the coal working at an elevation
of 350 m AOD, is the most viable foundation option for the abutments and intermediate piers.
Due to the presence of coal seams and possible voids, the piles will need to be socketed beneath
the coal seam, into more competent bedrock and therefore deep piles (approximately 30m long
with a diameter of 0.9m) are recommended.
Design Sulfate DS-1 and ACEC AC-2z (BRE Special Digest 1, 2005) has been assumed for
concrete design for buried structures. Further chemical testing in this area is recommended to
confirm this assumption.
Prior to construction, a series of probe holes should be drilled beneath the abutment footprints to
identify potential mine working. If they are encountered, the voids should be grouted prior to the
abutment piles being installed.
B2191100/D2/1/2/059
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Heads of the Valleys Dualling Section 5 & 6 Rev: 0 Calc No: GAS/0032/Rev0
Page 1 of 6
Structure Name: Reservoir Footbridge Date: April 2017
Prepared: SN Checked: SM Reviewed: AD Job No: B2191100
Proposed Structure:
The proposed structure will consist of a new footbridge over the widened A465 carriageway and
comprises a single span warren truss bridge, 45m long and 4.0m wide. A flight of stairs and 40m
long access ramp are proposed on the southern side, attached to the south abutment (see
Drawing. 2191100-JAC-SBR-DE-SE-1600-3200).
The proposed A465 carriageway level is approximately 357.28m AOD. The footbridge will have a
clearance of 5.7m above this carriageway.
Ground Conditions:
North Abutment (3/BH59, 3/BH59A, 3/BH59B, 3/BH59C, 3/BH59D and 3/BH59E)
Existing ground level: ≈ 361.70m AOD to 362.89m AOD
Core loss was recorded between 3.1mbgl and 4.5mbgl (359.79m AOD to 358.39m AOD). Flush
returns were recorded as 100% except between 4.00mbgl and 7.00mbgl (358.89m AOD to 355.89m
AOD) where it was recorded as 50%. A 0.5m thick coal seam was also encountered in 3/BH59E
between 7.40mbgl and 7.90mbgl (355.49m AOD to 354.99m AOD). This is most likely to correspond
with the Sun coal seam near the base of the Lower Coal Measures.
South Abutment
As there are no additional recent (Babtie/ Exploration Associates Ltd) boreholes in the vicinity of
this abutment, historic borehole SO00NE29 and the approximate dip of the bedrock have been
used to estimate the ground conditions.
Existing ground level: ≈ 358.8m AOD (topographic survey at abutment location)
Borehole ground levels = 360.1m AOD
Groundwater:
Water was encountered as overnight standing water in 3/BH59E (near the north abutment) at an
elevation of 5.0mbgl (357.9m AOD).
There were no available boreholes in the vicinity of the south abutment however the closest
borehole (SO00NE29) encountered groundwater at 2.7mbgl (357.4m AOD). For design,
groundwater has been assumed to be at 2.5 m depth, corresponding with the top of rock.
The ground conditions described above suggest that global parameters from Jacobs GIR, 2016
(given below) are applicable.
Bulk
density Angle
Cohesion of cu mv E’
Stratum 2
(kN/m ) (cp’) Friction, (kN/m2) 2
(m /MN) (MPa)
γb
φp’, °
3
(Mg/m )
0.1
(between
50 (between
ground
Made ground level 10
level and
Ground 2.0 0 32 and 4m.bgl)
2m.bgl) 40 (below
(Cohesive) 200 (below 4.0m.bgl)
0.05
4.0m bgl)
(below 2m
bgl)
Made 10
Ground 2.0 0 32 - - 40(below
(Granular) 4.0m bgl)
0.1
(between
20
85 ground
Glacial Till level and 20 + 6z (z
2 2 32 85 + 10z (z =
2m bgl) = metres
(Cohesive) metres below
below 5m
2.0m bgl) 0.03
bgl)
(below 2m
bgl)
Glacial Till
2 0 35 - - 35
(Granular)
Bulk
density
UCS
Stratum GSI mi D E’ (MPa)
(MPa)
γb
3
(Mg/m
Lower Coal
2.5 25 45 14 0.7 750
Measures
Foundation Considerations:
It is anticipated that the abutments will be founded on piles foundations socketed into bedrock.
North Abutment: Due to the generally lower bearing capacity of the cohesive glacial till and the
shallow depths of bedrock, it is proposed that this abutment be founded within bedrock. Although
rockhead was encountered at approximately 4.50m below existing ground level (358.4m AOD) a
Buried Concrete:
Chemical testing for aggressive ground conditions for buried concrete structures was not
undertaken on samples collected from these exploratory holes as part of the preliminary ground
investigation. It is therefore, suggested to adopt the Aggressive Chemical Environment for
Concrete AC-2z conditions in accordance with BRE Special Digest 1: Concrete in Aggressive
Ground (2005) and Design Sulfate class DS-1 as recommended for the whole route of Section 5.
Construction Issues:
A coal seam, core loss and reduced flush returns were recorded within 3/BH59E suggesting
possible voids or mine workings. The coal seam appears to be intact with a thick layer of more
competent rock above it and underlain by weak to moderately weak mudstone and strong
sandstone, however the conditions and presence of the coal seam can vary over short distances
due to mine workings. The lack of ground information at the location of the south abutment
means that extrapolation of the bedrock has been used to estimate the depth to bedrock. Probing
of the ground prior to construction is recommended to confirm depth and condition of bedrock if
additional ground investigations have not been carried out.
Core loss was experienced in exploratory hole 3/BH59E (near the north abutment) along with
reduced flush returns and a 0.5m coal seam suggesting possible mine workings in the locality.
There is a lack of intrusive ground investigation such as boreholes in vicinity to the south
abutment and therefore due to the shallow dip of the bedrock, it is anticipated these same
features will be present beneath the south abutment but at a deeper depth. The coal seam
encountered is anticipated to be the Sun seam which is stratigraphically below the ‘Farewell Rock’
which lies beneath the more significant coal seams, such as Gellideg seam, that are known to be
worked in the region. It is therefore unlikely further significant coal seams will be encountered
beneath the Sun seam at potential piling depths.
Further investigation works, such as additional exploratory holes, are recommended in order to
confirm the possibility of mineworkings beneath the proposed structure and to confirm the
location and nature of the bedrock. Prior to construction, probing of the ground is recommended
to confirm the presence of any voids or mineworkings. If the presences of mine workings are
noted beneath the structure, then grouting is required and appropriate piling depths installed in
accordance with the CIRIA special publications 32 (Healy and Head, 1989). Suggested values
can be assessed when further investigation results are available. An additional exploratory hole at
the location of the south abutment, extended into the bedrock, is also recommended in order to
confirm the location and nature of the glacial till and bedrock sequence.
Design Sulfate DS-1 and ACEC AC-2z (BRE Special Digest 1, 2005) has been assumed for
concrete design for buried structures. Further chemical testing in this area is recommended to
confirm this assumption.
B2191100/D2/1/2/059
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Heads of the Valleys Dualling – Section 5 & 6 Rev: 0 Sheet No:
GAS/0031/R0
Structure Name: Jones Street / Pen Y Wern Bridge Date: July 2016
Prepared: DE Checked: CR Reviewed: AD Job No: B2191100
vi. Jacobs (2016) A465 Heads of the Valleys Dualling Sections 5 and
6 Ground Investigation Report. Report No. B2191100/D2/1/2/040
Proposed Structure:
The existing structure is an underbridge consisting of a single simply supported span of 9.1 m
founded on propped reinforced concrete abutments with spread footings. The existing structure is
to be demolished and replaced with a 11.8 m span, 25.3 m long integral bridge with precast
beams.
The existing A465 carriageway level is approximately 346.4 m AOD. At the location of the
underbridge, the level of the centreline of the proposed A465 is approximately 347 m AOD. The
current level of the road (Jones Street) below the underbridge is approximately 340.2m AOD.
Groundwater:
Groundwater was struck and recorded standing at 6.5m.bgl (333.59m AOD) below the existing
ground level in 3/BH62. A standpipe piezometer was installed in 1997 in this exploratory hole with
response zone between 4.0m and 9.0m depth. The highest recorded water level was 4.9m
(335.17m AOD) below existing ground level as reported in the Babtie report, dated 1999. No
groundwater was encountered in exploratory hole 3/BH61. Overnight standing water was struck
at 13.0m bgl (333.97m AOD) in 3/BH60 and 2.7m bgl (337m AOD) in 3/BH63.
Angle of
Cohesion
Stratum γb, (Mg/m3) Friction, cu (kN/m2) mv (m2/MN) E’ (MPa)
cp’(kN/m2)
φp’, °
Made Ground
2.0 0 32 50 0.1 10
(Cohesive)
Glacial Till
2.0 2 32 40(1) 0.14(1) 7(1)
(Cohesive)
γb, E’
Bedrock
UCS (MPa) GSI mi D
Parameters
(Mg/m3) (MPa)
Lower Coal
2.5 12(2) 45 14 0.7 720
Measures
Notes :
(1) Undrained shear strength of cohesive Glacial Till have been reduced from those given in
the GIR to match the description in boreholes logs
(2) UCS of 12 correlated from Point load tests (value of 0.61) in a nearby borehole 3/BH65
which was lower than GIR value of 25
Foundation Consideration:
Due to the general low bearing capacity of cohesive Made Ground and Glacial Till, and the
shallow depths of bedrock (1.5 m bgl to 2.45 m bgl), it is proposed that the abutments are to be
founded within unweathered bedrock using spread foundations. Bedrock appears to deepen on
the north-west side of the structure compared to the south-east side and a maximum excavation
depth of 3 m is anticipated.
From the description of the bedrock encountered and based on Tomlinson’s presumed bearing
values for shallow foundations in rock, a safe bearing value of 1000 kN/m2 can be assumed for
the bedrock. Settlement is expected to be negligible from Pdisp 19.3 analysis, based on a 5 m
wide x 25.5 m long foundation with a loading of 200 kN/m2.
Buried Concrete:
Sulphate and pH tests were carried out on Made Ground recovered from the exploratory hole
3/BH61. The results and further tests carried out along the A465 route within the Made Ground
and Glacial Till suggest Aggressive Chemical Environment for Concrete AC-2z conditions in
accordance with BRE Special Digest 1: Concrete in Aggressive Ground (2005) and Design
Sulfate class DS-1. Further chemical testing in the area is recommended to confirm if these
results are applicable.
Construction Issues:
It is anticipated the construction of the foundations for the new bridge will be constrained by the
requirement to maintain traffic movements along the existing A465 and also along Jones Street.
Land take required for temporary working construction might not be a problem although existing
roads and services will impose restrictions.
Zones of core loss up to 0.5m thick were noted in exploratory holes 3/BH60 (located
approximately 20.0 m east of the proposed structure) and 3/BH61 at 331.9m OD and 317.3m OD
respectively. Flush returns were noted in all exploratory holes and the presence of possible
mining activity within the proposed foundation locations should be confirmed or eliminated.
Spread foundations within unweathered bedrock are proposed for this structure. The structure is
located where unrecorded mining works may have been carried out and thus probing and
grouting of potential voids beneath the foundations should be carried out.
B2191100/D2/1/2/059
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Heads of the Valleys Dualling Rev: 0 Sheet No: GAS/0030/R0
Page 1 of 6
Structure Name: Pant Road Viaduct Date: February 2017
Prepared: DE/SN Checked: CR Reviewed: AD Job No: B2191100
Proposed Structure:
The existing viaduct is a six-span bridge, of 116m total length spanning two roads and is
supported on piles. The existing structure is to be demolished and replaced with a new structure.
The road is to be widened on the north and south side of the existing alignment. The proposed
bridge is a 20 m single span integral structure with concrete bank seats founded on reinforced
soil abutments and wingwalls.
Ground Level:
The ground conditions vary across the length of the proposed new bridge; each abutment will
therefore be discussed separately.
Exploratory hole 3/BH65 is located approximately 15m to the north of the proposed east
abutment. Exploratory hole 3/BH64 is located adjacent to the existing east abutment and
approximately 50m east of the proposed new bridge east abutment. The ground conditions have
therefore been estimated as follows:
Ground Level Depth to top
Elevation of stratum Thickness
Stratum (m AOD) (m bgl) Description
(m)
Max Min
Made Soft to firm brown silty CLAY with some
Ground fine to coarse subangular to subrounded
337.8 328.3 0.0 1.5 to 11.7
(Cohesive) gravel and occasional cobbles of slag,
(1&5) clinker, plastic, limestone ash and brick
Exploratory hole 3/BH66 is located approximately 10m west of the proposed west abutment, the
ground conditions encountered can be summarised as follows:
Depth to
Ground Level
top of Thickness
Stratum Elevation Description
stratum (m)
(m AOD)
(m bgl)
Loose to medium dense dark grey
and brown slightly clayey silty very
Made Ground sandy (fine to coarse) angular to
327.85 0.00 6.30
(Granular) (5) subangular GRAVEL of clinker, slag,
brick, sandstone and occasional
subangular to angular cobbles
Medium dense brown and orange
Glacial Till slightly clayey slightly sandy (medium
321.55 6.30 16.70
(Granular) to coarse) silty fine to coarse angular
to subangular GRAVEL
Bishopston Grey very thinly to thinly bedded
Mudstone slightly weathered silty MUDSTONE
304.9 23.00 >3.30
Formation (6 & (moderately weak to moderately
7)
strong).
Notes:
(5) The historic borehole data shows larger depth of made ground present between both the abutments. There
is also a historic swimming pool between both the abutments which may be filled with made ground. Although
this not located immediately below the abutment, there is a possibility that larger depth of made ground is
encountered during the construction.
(6) As exploratory hole 3/BH66 was open holed from 13.5m to 23.0m bgl, where mudstone was subsequently
cored, it is conjectured that bedrock is at some depth (304m.AOD). Reduced flush returns were recorded in the
exploratory hole, indicating highly fractured rock. There are no recorded mineworkings near to the structure.
(7) Bedrock levels across the site are uncertain as exploratory hole 3/BH66 was open holed. Based on the
assumption that rockhead occurred where coring commenced at the end of the open hole section of the
borehole, rockhead depth increases steeply from east to west from 325.9m.AOD to 304.9m.AOD (11.90mbgl to
23.00mbgl). There was no evidence of coal bands within the bedrock
Groundwater:
Groundwater was encountered in 3/BH64 at 5.10m bgl (332.7m AOD) within the made ground,
rising to 5.00m bgl (332.8m AOD) during drilling.
An overnight seepage was recorded in exploratory hole 3/BH65 at 12.0mbgl (316.3m AOD). A
piezometer was installed with a response zone between 5.0m and 7.0m depth (323.3m AOD and
321.3m AOD) within the glacial till and the highest recorded groundwater reading was at a depth
of 6.2mbgl (322.1m AOD).
Groundwater was also recorded as standing water at the end of the shift in 3/BH66 at 6.90mbgl
(321 m AOD). Design ground water level has been assumed at 5 mbgl (322.1 m AOD) around
the abutment locations.
The ground conditions described above suggest that global parameters from Jacobs GIR, 2016
(given below) are applicable except where indicated.
Unit Angle of ’
Cohesion 2 2 E
Stratum Weight, γ, 2 Friction, cu (kN/m ) mv (m /MN) 2
3 cp’(kN/m ) (MN/m )
(Mgm ) φp’, °
50
(between 0.1 (between
ground level ground level 10
Made Ground
and 4 m and 2 m bgl)
(Cohesive and 2.0 2 32
bgl) 40 (below
Granular) 0.05 (below 2 4 m bgl)
200 (below m bgl)
4.0m bgl)
Glacial Till
(Cohesive)
2.0 2 32 35 0.1 10
(See note
below)
Glacial Till
2.0 - 35 - - 35
(Granular)
6I / 6J
Reinforced 2.0 - 40 - - -
Earth Fill
Bulk
UCS E’
density
Material Type GSI mi D
(MPa) (MPa)
(Mg/m3)
Lower Coal
2.5 25 45 14 0.7 750
Measures
Bishopston
Mudstone FM - 2.6 13 35 8 0.7 200
Mudstone
Bishopston
Mudstone FM - 2.6 50 50 15 0.7 3000
Sandstone
Note : The parameters for glacial till cohesive were reduced to reflect the local description of the
material given in the borehole.
Foundation Consideration:
It is proposed that the bridge is founded on reinforced soil abutments with concrete facing panels
and steel reinforcing strips. Due to the weak ground conditions present at the site location, the
upper 2m of Made Ground should be replaced with compacted granular engineered fill.
If soft material is present at the location of the foundations, it should be removed and replaced
with acceptable granular engineered fill.
The anticipated construction sequence requires the new bridge and approach embankment to be
constructed in two halves, such that the existing structure is demolished prior to the reinforced
soil (beneath the bridge) being constructed.
Buried Concrete:
Sulphate and pH tests were carried out on three samples taken from around this structure: one
within the glacial till and another from within the bedrock in 3/BH65 and one from within the glacial
till in 3/BH66. Results from this sample suggest Aggressive Chemical Environment for Concrete
AC-2z conditions in accordance with BRE Special Digest 1: Concrete in Aggressive Ground
(2005) and Design Sulfate class DS-1. These correspond with the conditions assessed from
chemical tests on samples collected across the whole route of section 5 and therefore the values
are recommended for design.
Construction Issues:
Zones of localised core loss and highly fractured rock, together with some loss of flush returns
were recorded in exploratory holes 3/BH65 and 3/BH66 suggesting there may be evidence of
voids or mineworkings. No known mineworkings are indicated near the structure location on
existing information (despite a coal seam recorded in a nearby outcrop) and therefore it is unlikely
they may be present beneath the structure foundations. However, as the underlying bedrock
comprises the Lower Coal Measures, there is a possibility for unrecorded mineworkings or voids
being encountered.
Further investigation works, such as additional exploratory holes that extend into the rock, are
recommended to confirm the location and nature of the bedrock as well as superficial deposits.
Design Sulfate DS-1 and ACEC AC-2z (BRE Special Digest 1, 2005) has been assumed for
concrete design for buried structures. Further chemical testing in this area is recommended to
confirm this assumption.
B2191100/D2/1/2/059
GEOTECHNICAL SUMMARY INFORMATION
Project: A465 Heads of the Valleys Dualling Section 5 & 6 Rev: 0 Sheet No: GAS/0029/R0
Structure Name: Bryniau Bridge Date: January 2017
Prepared: CR Checked: DE Reviewed: AD Job No: B2191100
Chainage: 13855 m
Exploratory Holes: References:
3/BH73, 3/BH74, 3/BH75 i. Babtie Group (2000) A465 Abergavenny
to Hirwaun Dualling Section 7 – Hirwaun
to Baverstock, Scheme Proposals and
Exploratory Hole Location Drawings,
Drawing No. BTI015586/11/172.
ii. Babtie Group (2000), A465 Abergavenny
to Hirwaun Dualling, Interpretative
Report on Preliminary Ground
Investigation, Cardiff, Report No.
BTI.015586/D4/118.
iii. Exploration Associates Ltd (1997) A465
Abergavenny to Hirwaun Dualling
Section 3. Volume Three of Nine,
Factual Report on Ground Investigation.
Report No. 166001-3.
iv. Jacobs (2015) A465 Section 5 and 6
Technical Advisor Presentation Plan.
v. Jacobs (2015) A465 Heads of the
Valleys Dualling Sections 5 and 6
Preliminary Sources Study Report.
Report No. B1855100/D4/2/017.
vi. Jacobs (2016) A465 Heads of the
Valleys Dualling Sections 5 and 6
Ground Investigation Report. Report No.
B2191100/D2/1/040
vii. Jacobs (2016) Vale of Neath Bridge –
General Alignment, Drawing. No.
B2191100-JAC-SBR-DE-SE-1600-2900.
Proposed Structure:
The current proposal is to demolish the existing Bryniau Road Bridge and replace it with a new
single span integral bridge. The new structure will connect the Galon Uchaf Roundabout with the
existing Bryniau Road which overlies the A465. The structure is proposed to be approximately 41
m long and 18.3 m wide. The north abutment is anticipated to be founded on 1.5m diameter piles
at 1.8m spacing forming the Gurnos/Galon Uchaf contiguous piled walls. The south abutment is
proposed to be founded on 6 piles of 1.5 m diameter at 3m spacing. There are existing retaining
walls on either side of the A465. For the south abutment, the existing abutment is proposed to be
partly demolished in order to incorporate the beams from the deck of the new bridge and the new
piles will be located behind the existing abutment.
Existing Ground Level:
≈ 325 m AOD (South) to 329 m AOD (North) (from the topographic survey)
Proposed A465 carriageway (running beneath bridge) is approximately 317.5 m AOD and the
elevation of the road over the bridge is approximately 325 m AOD.
Ground Level
Elevation Depth to
(m AOD) top of Thickness
Stratum Description
stratum (m)
Min Max (m bgl)
Groundwater:
Groundwater was encountered in 3/BH73 at 4.55 m bgl (321.2 m AOD) within the glacial till rising
to 4 m bgl (321.8 m AOD). Groundwater was also recorded as standing water at the end of the
shift in 3/BH74 within the Bishopston Mudstone Formation at 17.6m bgl (307.2 m AOD).
Summary of Soil Parameters:
The ground conditions described above suggest that global parameters from Jacobs GIR, 2016
(given below) are applicable.
Stratum cu mv E’
Angle of
Unit Weight, γb, Cohesion,
Friction, (kN/m2) (m2/MN)
(Mg/m )
3
cp’, (kN/m2) (MPa)
φp’, °
50
(between 0.1
10
ground (between
Made Ground level and ground level
40
(Cohesive/ 2 0 32 4 m bgl) and 2 m bgl)
(below
Granular)
4m
200 0.05 (below
bgl)
(below 4 2 m bgl)
m bgl)
0.1 20
85
(between
ground level 20 + 6z
85 + 10z
Glacial Till and 2 m bgl) (z =
(z =
(Cohesive) metres
2 2 32 metres
0.03 (below below
below 2 m
2 m bgl) 5m
bgl)
bgl)
Bedrock γb UCS E’
3 GSI mi D
Parameters (Mg/m ) (MPa) (MPa)
Bishopston
Mudstone 2.6 13 35 8 0.7 200
Formation
Foundation Considerations:
The proposed A465 mainline carriageway is anticipated to be within a cutting which will run
beneath the proposed overbridge.
North Abutment
The north bridge abutment is to be founded on Gurnos/Galon Uchaf contiguous piled walls and
acts as a prop to the wall. The contiguous walls are 1.5m in diameter, with 1.8m spacing. The
estimated maximum load from the bridge is 6650 kN. Assuming a pile group of 12 No (as
suggested by Drawing B2191100-JAC-SBR-DE-SE-1600-2900) the total load per pile is
approximately 550 kN. A minimum rock socket length of 1m is required to support the vertical
loading from the bridge. The contiguous piled walls were designed as a cantilever with a toe level
of 308 m AOD, with an assumed bedrock level at 315.3 m AOD. For design of the bridge piles, it
is proposed that the cantilever design is applied to the bridge piles with an additional metre of
embedment to allow for the additional load from the structure (i.e toe level at 307 m AOD,
depending on the elevation at which bedrock is encountered). The toe level of the piles are
dependent on the elevation at which bedrock is encountered, a minimum of 8m rock socket is
required for the current design.
South Abutment
The south bridge abutment is to be founded on 1.5m diameter piles, with 3.0m spacing.
Assuming a pile group of 6 piles, the total load per pile is 1110 kN. A minimum rock socket length
of 2 m is required to support the vertical loading from the bridge. The toe level of the piles are
dependent on the elevation at which bedrock is encountered, a toe level of 313 m AOD is
required for the current design and based on assumed bedrock level of 315.3 m AOD.
Buried Concrete:
Chemical testing was undertaken on samples from 3/BH74 and 3/BH75 collected from within the
Glacial Till and Bishopston Mudstone Formation respectively, as part of the preliminary ground
investigation. The results indicate Aggressive Chemical Environment for Concrete AC-2z
conditions in accordance with BRE Special Digest 1: Concrete in Aggressive Ground (2005) and
Design Sulfate class DS-1. These correspond with the conditions assessed from chemical tests
on samples collected across the whole route of section 5 and therefore the values are
recommended for design.
Construction Issues:
The control of localised groundwater will also have to be addressed by the Contractor. As noted
above, groundwater was recorded in 3/BH73 and 3/BH74 within the glacial till and Bishopston
Mudstone Formation respectively. Based on this assumption, groundwater is anticipated to be
encountered if excavation works are to be undertaken. In addition, glacial till formation is
susceptible to ‘Wetting-up’ upon exposure and therefore may have lower undrained shear
strength than anticipated. The traffic from existing A465 will have to be temporarily diverted
during the construction of the bridge.
Conclusions and Recommendations:
Contiguous piled foundations (Gurnos /Galon Uchaf contiguous retaining wall) are suggested for
the north abutment, socketed at least 8 m within the bedrock in the north abutment (toe level of
307 m AOD). Piled foundations are suggested for the south abutment (1.5 diameter with 3 m
spacing), socketed at least 2 m within the bedrock (toe level of 313 m AOD).
Design Sulfate DS-1 and ACEC AC-2z (BRE Special Digest 1, 2005) has been assumed for
concrete design for buried structures. Further chemical testing in this area is recommended to
confirm this assumption.
B2191100/D2/1/2/059
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Heads of the Valleys Dualling Rev: 0 Sheet No: GAS/2800/R0
Structure Name: Prince Charles Hospital Overbridge / Galon Uchaf Bridge Date: November 2016
(East and West)
Prepared: SM Checked: CR Reviewed: AD Job No: B2191100
The existing Byrniau / Galon Uchaf road bridge spans across a cutting with a single 18m span
and was constructed in 1965 (Glamorgan Engineering Consultancy, 2007).
The bridge is supported on mass concrete abutments and spread foundations, and is to be
demolished and replaced by two new structures- Prince Charles Hospital East and West bridges.
The current proposal is to construct a new single span overbridge both on the eastern side as
well as the western side. The structure is proposed to be approximately 42 m long and 11.4 m
wide for the eastern bridge. The structure is approximately 15.6m wide for the western bridge.
The abutments are anticipated to be founded on contiguous piles of 1500mm diameter at 1.8m
spacing forming the Gurnos (North and South of A465) retaining walls.
Eastern Bridge
North Abutment - 304.7 m AOD
South Abutment – 307.3 m AOD
The proposed A465 (running beneath the bridge) carriageway level is 302.5 m AOD and the
elevation of the road over the bridge is 310.6 m AOD.
Western Bridge
North Abutment – 306 m AOD
South Abutment – 305.5 m AOD
The proposed A465 (running beneath the bridge) carriageway level is 299.5 m AOD and the
elevation of the road over the bridge is 307.4 m AOD.
This assessment is based on the Exploration Associates Ground Investigation (1997) and two
historic boreholes available from BGS website. Further historic boreholes may be available from
BGS website. Due to limited ground investigation information available around this structure, the
ground conditions are assumed to be the same for both the East and West bridges and for both
north and south abutments.
Depth
Ground Level
to top
Elevation Thickness (m)
Stratum of Description
(m AOD)
stratum
Min Max (m bgl) Min Max
(2) 3/BH79A suggests bedrock is present 1 m bgl (306 m AOD), BGS Borehole SO00NW74
suggests bedrock is present at 2.4 m bgl (303.3 m AOD) and bedrock was not encountered in
SO00NE14 upto 2.7 m bgl (302.5 m AOD). Boreholes further away suggest bedrock was at 6 m
bgl (3/BH80 – 150 m west of the eastern bridge) and bedrock was not encountered up to 8 m in
3/BH78 (200 m east of the eastern bridge).
Groundwater:
Groundwater was encountered in 3/BH79A within the bedrock at 2 m bgl (305 m AOD) which rose
to 1.8 m bgl (305.2 m AOD) within twenty minutes. Groundwater was also encountered at 1.8 m
bgl (303.4 m AOD) in historic BGS Borehole SO00NE14.
The ground conditions described above suggest that global parameters from Jacobs GIR, 2016
(given below) are applicable, except where indicated.
10
50 0.1
(between
(between (between
ground
ground level ground level
level and 4
Made Ground and 4 m and 2 m
2.0 0 32 m bgl)
(Cohesive) bgl) bgl)
40
200 (below 0.05 (below
(below 4
4 m bgl) 2 m bgl)
m bgl)
Glacial Till (1)
2.0 2 32 35 0.03 20
Cohesive
Bulk UCS E’
Stratum density, γb, GSI mi D
(Mg/m3) (MPa) (MPa)
Lower Coal
2.5 25 45 14 0.7 750
Measures
Bishopston
Mudstone
2.6 13 35 8 0.7 200
Formation -
Mudstone
Bishopston
Mudstone
2.6 50 50 15 0.7 3000
Formation -
Sandstone
(1) The undrained shear strength of Glacial Till Cohesive was reduced from the GIR values to reflect the
description of boreholes.
Foundation Considerations:
The bridge is to be founded on the Gurnos contiguous piled walls (Gurnos - North and South of
A465 Retaining walls) and acts as a prop to the wall. The contiguous walls are 1500mm in
diameter, with 1800mm spacing. The estimated maximum load is approximately 5950kN from the
eastern bridge and 6800kN from the western bridge.
A minimum rock socket length of 3 m is required to support the loading from the bridge. Either
side of the bridge, the contiguous piled wall is designed as a cantilever with an embedded length
of 6m (toe level at 292 m AOD). For design it is proposed that the cantilever design is applied to
the bridge piles (i.e. toe at 292 m AOD, rock socket 11m). This will safely support the vertical load
from the structure, whilst also providing sufficient embedment for the propped retaining wall.
Buried Concrete:
Chemical testing for aggressive ground conditions for buried concrete structures was not
undertaken on samples collected from these exploratory holes as part of the preliminary ground
investigation. Aggressive Chemical Environment for Concrete AC-2z conditions in accordance
with BRE Special Digest 1: Concrete in Aggressive Ground (2005) and Design Sulfate class DS-1
were therefore assumed for buried structures at this location. These correspond with the
conditions assessed from chemical tests on samples collected across the whole route of section
5 and therefore the values are recommended for design. Further chemical testing in the area is
recommended to confirm if these results are applicable.
Construction Issues:
The existing traffic flows on A465 and Byrniau Road will have to be managed during the
construction works.
The control of localised groundwater will also have to be addressed by the Contractor. In addition,
glacial till formation is susceptible to ‘Wetting-up’ upon exposure and therefore may have lower
undrained shear strength than anticipated.
As the underlying bedrock comprises the Lower Coal Measures, there is a possibility for
unrecorded mineworkings or voids being encountered. In light of this, prior to construction, it is
proposed that the ground beneath the proposed foundations should be investigated for the
presence of possible mineworkings or voids. Any voids or mineworkings encountered is to be
grouted.
Contiguous piled foundations (1500 mm diameter with 1800 mm spacing) are suggested for the
foundations, socketed at least 6 m within the bedrock.
Further exploratory boreholes are proposed to confirm the level and nature of rockhead in the
vicinity of the structure and to confirm or eliminate the possible presence of mineworkings.
Design Sulfate DS-1 and ACEC AC-2z (BRE Special Digest 1, 2005) have been assumed for
concrete design for buried structures. Further chemical testing in this area is recommended to
confirm this assumption.
B2191100/D2/1/2/059
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Heads of the Valleys Dualling Rev: 0 Sheet No: GAS/0027/Rev0
Page 1 of 4
Structure Name: Gurnos Farm Underpass Date: July 2016
Prepared: SN Checked: CR Reviewed: AD Job No: B2191100
Chainage: 12275m
Exploratory Holes: References:
3/BH85 i. Babtie Group (2000) A465 Abergavenny
to Hirwaun Dualling Section 5 – Dowlais
Top to Nant Ffrywd Exploratory Hole,
Earthworks Area and Structures
Location Drawings, Drawing No.
BTI015586/11/149.
Proposed Structure
The current proposal is to build a new reinforced concrete box bridge to allow traffic to cross
beneath the A465 following the demolishing of the existing Gurnos Farm Underpass located to
the east of the proposed structure. The underpass bridge is proposed to be approximately 27.8m
long and 6.8 m to 8.5 m wide.
Existing Ground Level:
≈ 259.2 m AOD (obtained from exploratory hole 3/BH85)
The proposed underpass road level is approximately 2.2m above the existing ground level (as
shown in Drawing No. 2191100-JAC-SBR-DE-SE-1600-2700) corresponding with approximately
261.4m AOD. Due to the northwards slope of the road level within the underpass, the final road
level at the southern end of the underpass will be higher than the northern end, reflecting the
slope of the existing ground.
Groundwater:
Groundwater was struck at 4.7 m bgl which rose to 4.6 m bgl (254.6 m AOD) after 20 minutes
during drilling.
Foundation Considerations:
As the proposed underpass road level is higher than the existing ground level, it is assumed that
6N/6P engineered fill will be used beneath the base of the concrete box structure to build it up to
the required level. The proposed underpass road level is approximately 2.2m above the existing
ground level and the base of the underpass foundations is anticipated to be 0.8m below the final
road level (fill level) (as shown in Drawing No. 2191100-JAC-SBR-DE-SE-1600-2700). In addition,
the possible solifluction deposits are anticipated to be present and these weaker strength
deposits will need to be removed prior to construction and replaced with appropriate fill. This
replacement fill is likely to be reworked glacial till, with 6N/6P fill used above existing ground level.
For a 27.8m by 7.8m spread foundation (corresponding with the base of the concrete box)
founded on the engineered fill and reworked glacial till, the safe bearing capacity is anticipated to
be at least 175kN/m2. The maximum total load anticipated is 83kN/m2 (taking into account the
load distribution factor) and therefore total settlement is estimated to be in the range of 10 –
15mm. If 6N/6P engineered fill is to be used as replacement fill for the possible solifluction
deposits, bearing capacity is anticipated to be greater and settlement smaller.
Buried Concrete:
Chemical testing was undertaken on one sample from 3/BH85 within the glacial till as part of the
preliminary ground investigation. The results indicate Aggressive Chemical Environment for
Concrete AC-2z conditions in accordance with BRE Special Digest 1: Concrete in Aggressive
Ground (2005) and Design Sulfate class DS-1.
Construction Issues:
The new structure is approximately 120 m to the west of the existing Gurnos Farm Underpass. A
diversion route would be required to maintain access to Gurnos Farm. The existing traffic flows
will have to be maintained during the construction works.
The control of localised groundwater will also have to be addressed by the Contractor. In addition,
glacial till is susceptible to ‘wetting-up’ upon exposure and therefore may have decreased
undrained shear strength than anticipated.
Conclusions and Recommendations:
Design Sulfate DS-1 and ACEC AC-2z (BRE Special Digest 1, 2005) have been assumed for
concrete design for buried structures. Further chemical testing in this area is recommended to
confirm this assumption.
B2191100/D2/1/2/059
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Heads of the Valleys Dualling – Section 5 and 6 Rev: 0 Sheet No:
GAS/0026/R0
Page 1 of 6
Structure Name: Taf Fechan Viaduct Date: May 2017
Prepared: CR Checked: HM Reviewed: AD Job No: B2191100
Chainage: 11482 m
Exploratory Holes: References:
Babtie,(Exploration i. Babtie Group (2000) A465 Abergavenny to Hirwaun
Associates Ltd, 1997): Dualling Section 5 – Dowlais Top to Nant Ffrwd, Scheme
Proposals and Exploratory Hole Location Drawings,
East Side of the viaduct: Drawing No. BTI015586/11/150.
3/BH89 and 3/BH90 ii. Babtie Group (2000), A465 Abergavenny to Hirwaun
Dualling, Interpretative Report on Preliminary Ground
West side of the viaduct: Investigation, Cardiff, Report No. BTI.015586/D4/100.
3/BH91 and 3/BH92 iii. Coombs, & Hinch (1969) The Heads of the Valleys Road,
Proceedings of the Institution of Civil Engineers, 44(2), pp
89-118.
iv. Caves of South Wales (2016) , Central Northern Outcrop
Cave Location Map, [Online], Available from :
http://www.ogof.org.uk/Central-Northern-Outcrop-Cave-
Location-Map.html [Accessed 16th February 2016]
v. Glamorgan Engineering Consultancy (2004) A465 Heads
Of The Valley Trunk Road, Principal Inspection Report
Taf Fechan Viaduct, Structure No A465 540 (U). Report
No. A40150/20/01
vi. Glamorgan Engineering Consultancy (2005) A465 Taf
Fechan Viaduct Deck strengthening and re-waterproofing
report, Structure No A465 540 (U).
vii. Jacobs (2015) A465 Heads of the Valleys Dualling
Sections 5 and 6 Preliminary Sources Study Report.
Report No. B1855100/D4/2/017.
viii. Jacobs (2015) A465 Section 5 and 6 Technical Advisor
Presentation Plan
ix. Jacobs (2016) A465 Heads of the Valleys Dualling
Sections 5 and 6 Ground Investigation Report. Report No.
B2191100/D2/1/2/040
x. Jacobs (2016) Taf Fechan – General Alignment, Drawing.
No. B2191100-JAC-SBR-DE-SE-1600-2600.
xi. RocLab 1.0, software from Rocscience, Version 1.021,
April 2006
xii. Tomlinson (2001), Foundation Design and Construction,
Seventh edition, Prentice Hall
xiii. Wyllie, D.C. (1991) Foundations in Rock, Spon, London
Pier 15 on East Arch Abutment. The construction drawing shows that Piers 16, 17 and 18 are
supported by individual spread footings directly onto bedrock.
The existing arches are splayed at the west end which has hinged half joint to account for
possible settlement of abutment. The new structure is proposed to be a steel arch bridge tied to
the existing structure.
Figure 1-A Existing General Arrangement, A465 Taf Fechan Viaduct Deck strengthening and re-
waterproofing report, Glamorgan Engineering Consultancy, 2005
Ground Level:
From existing A465 alignment ≈ 227.8 to 228.3 m AOD
East side of the viaduct (from 3/BH89 and 3/BH90) ≈ 219.7 to 221.7 m AOD
West side of the viaduct (from 3/BH91 and 3/BH92) ≈ 219.14 to 227.51 m AOD
Proposed road level ≈ 227.8 m AOD
Ground Level
Elevation Depth to top Thickness (m)
Stratum (m AOD) of stratum Description
(m bgl)
Min Max Min Max
Medium dense slightly clayey
Made Ground silty fine to medium SAND with
(1) 221.68 0.00 0 4.9
(Granular) gravel of sandstone, quartzite,
slag and clinker
Medium dense silty sandy fine to
Glacial Till coarse angular GRAVEL with
(2) 0.00 0 2.8
(Granular) 219.68 occasional cobbles of sandstone
and limestone
Oxwich Head Slightly weathered strong to very
216.8 2.8 – 4.86 >25.23 > 35
Limestone strong LIMESTONE
Note: (1) Granular Made Ground was encountered from ground level to a depth of 4.9 m bgl only
in 3/BH89 comprising 1 m thick slag and clinker
(2)
Granular Glacial Till was encountered only in 3/BH90
Groundwater:
Groundwater was not encountered in any of the four exploratory holes (3/BH 89, 3/BH90, 3/BH91
and 3/BH92). A standpipe was installed in 1999 in borehole 3/BH90 with a response zone
between 25m and 30m below ground level. However, it was reported as ‘dry’ in the Babtie report
(2000).
Summary of Soil Parameters
The ground conditions described above suggest that global parameters from Jacobs GIR, 2016
(given below) are applicable.
Stratum cu mv E’
Angle of
γb, Cohesion,
Friction, (kN/m2) (m2/MN) (MPa)
(Mg/m3) cp’, (kN/m2)
φp’, °
0.1
(between
50 (between 10
ground
ground level
Made Ground level and
and 4 m bgl)
(Cohesive / 2.0 0 32 2 m bgl)
Granular) 200 (below 4 40 (below
0.05
m bgl) 4 m bgl)
(below 2
m bgl)
Glacial Till
2.0 - 35 - - 35
(Granular)
E’
Bedrock γb, UCS
GSI mi D
Parameters (Mg/m3) (MN/m2)
(MPa)
Oxwich Head
Limestone
2.7 50 65 12 0.7 7500
(Carboniferous
Limestone)
Foundation Considerations:
Since the bridge is to be symmetrically widened, it is proposed that the foundations to be
constructed at the same level as the existing structure (Drawing No. B2191100-JAC-SBR-DE-SE-
1600-2600). The north east topography could make accessibility for the arch foundation difficult.
It is suggested that the proposed foundations are similar to the existing foundations with arch
abutments on either side of the proposed steel arches and spread footings to support the piers.
The arch abutments and spread footings, due to their high loadings, are to be founded directly on
the bedrock at approximately 216m AOD (approx. 4 to 6 m below the sloping ground level) on the
eastern side and 207 m AOD (approx. 6 m below where the existing arch meets the ground) on
the western side. The suggested allowable bearing capacity of the bedrock, based on
Tomlinson’s (2001) values for foundations in Limestone, is 10000kN/m2. Based on Wylie’s
equation for foundation on sloping bedrock, this value is limited to 5500 kN/m2 for a 10 m by 7 m
foundation and 3800 kN/m2 for a 1.5 m by 1.5 m foundation. Due to the proximity of the existing
foundations and potential disturbance to the structure which may be caused by any blasting on
bedrock, splitting the bedrock with a hydraulic splitter might be a better option to excavate the
bedrock. Since the limestone tested in nearby areas showed a high UCS value of 133 - 154 MPa,
(note that a lower value of 50 MPa has been adopted for assessing shear strength properties)
excavation even using a hydraulic splitter for foundation is anticipated to be really difficult and
time consuming.
Due to the proximity of the existing foundations and difficulty in excavating strong limestone to
construct spread footings, piled foundations are an alternative design option. Assuming a 0.6 m
diameter piles socketed 2.0 m into the bedrock, the anticipated safe working load is usually
assumed as 0.5UCS, however, in this case the limiting end bearing value is restricted to 10 MPa.
The safe working load also depends on the concrete compressive strength, fcu and should not
exceed 25% fcu. The disadvantage of using this option in Taf Fechan is the difficulty in
accessibility of piling rig and would require the construction of access tracks, protection to
workers and working platform for the piling rig.
The ICE paper entitled “The Heads of the Valley’s Road (1969)” indicates that solution caverns in
the limestone to the east of Taf Fechan caused concern during construction of the existing bridge
after a large cavern was exposed. The paper doesn’t state the exact location of the cavern. The
paper also mentions about the “plugging” of a cavern under the east foundation of the Taf Fechan
arch ribs. The Cambrian Cave registry and Cave of South Wales website shows a cave entrance
at the location of SO 03620 08340, about 40 metres north from A465 and 200 m north east from
the existing Taf Fechan bridge. The cave (named Ogof Ffordd Y Blaenau) is approx. 30 m long
and passes under A465 and partway along the passage a 10m aven was present, along with few
sheep bones which suggests that the aven was once open at the surface. Another cave entrance
is also shown nearby with the entrance at the southern face of the disused Gurnos Quarry, at an
elevation of 224m AOD. Detailed inspection and survey of the rock face, along with ground
investigation for the detection of voids is therefore recommended. This should comprise probe
drilling techniques at close intervals at the proposed foundation locations. Bearing capacity and
length of the piles should be reassessed, upon discovery of any voids or cavities.
Buried Concrete:
Sulphate and pH tests were carried out on Made Ground recovered from the exploratory hole
3/BH92. The results and further tests carried out along the A465 route within the Made Ground
and Glacial Till suggest Aggressive Chemical Environment for Concrete AC-2z conditions in
accordance with BRE Special Digest 1: Concrete in Aggressive Ground (2005) and Design
Sulfate class DS-1. Further chemical testing in the area is recommended to confirm if these
results are applicable.
Construction Issues:
Both pile and pad foundation has its own construction issues and difficulties on this site. Difficulty
in excavating the strong limestone is anticipated and careful consideration should be taken in not
impacting the existing foundations if pad foundation design is chosen, especially where rock has
to be excavated or ripped. Widening of the existing bridge will require access to the base of the
steep sided Taf Fechan Gorge and formation of temporary tracks, access and protection will be
required if the pile option is chosen. The effects of construction of temporary accesses on the
stability of the side slopes would need to be evaluated as well as the environmental impact of
removing the trees along these accesses. The woodlands surrounding Taf Fechan Gorge are
classified as Sites of Special Scientific Interest (SSSI) as well as Local Nature Reserve (LNR).
Since limestone solution caverns proved to be a concern at the eastern side of Taf Fechan during
the construction of existing bridge, particular attention should be given to the existence of such
features during detailed design stage and construction. Depending on the results of the probe
holes, remedial options should be considered such as grouting the voids or piling through these
cavities into competent bedrock.
The existing traffic flows will have to be maintained during the construction works. The control of
localised groundwater, if encountered, will also have to be addressed by the Contractor.
Conclusions and Recommendations:
Both pile and pad foundation has its own construction issues on this site and careful
consideration should be taken during detailed design stage on which option to be chosen. Further
ground investigation would be necessary at the proposed location of the abutments to confirm the
location and nature of the bedrock and the existing foundations exposed to assess the conditions
of the existing footings. It is also recommended to investigate the presence of cavities and any
possible solutions features within the limestone. It is also recommended to subsequently re-
assess the bearing capacity of the foundations.
Design Sulfate DS-1 and ACEC AC-2z (BRE Special Digest 1, 2005) have been assumed for
buried concrete structures. Further testing to assess ground aggressivity towards buried concrete
structures is recommended to confirm this assumption.
B2191100/D2/1/2/059
` GEOTECHNICAL SUMMARY INFORMATION
Project: A465 Heads of the Valleys Dualling – Section 5 and 6 Rev: 0 Sheet No:
GAS/2650/R0
Page 1 of 4
Structure Name: Taf Fechan NMU bridge Date: March 2017
Prepared: DE Checked: CR Reviewed: AD Job No: B2191100
Ground Level
Elevation Depth to top Thickness (m)
Stratum (m AOD) of stratum Description
(m bgl)
Min Max Min Max
Ground Level
Elevation Depth to top Thickness (m)
Stratum (m AOD) of stratum Description
(m bgl)
Min Max Min Max
Groundwater:
Groundwater was not encountered in any of the five exploratory holes (SO00NW53, SO00NW54, 3/BH89,
3/BH91, 3/BH92). A standpipe was installed in 1999 in borehole 3/BH90 (located approximately 3 m North
of the NMU bridge) with a response zone between 25m and 30m below ground level. However, it was
reported as ‘dry’ in the Babtie report (2000).
Summary of Soil Parameters:
The ground conditions described above suggest that global parameters from Jacobs GIR, 2016 (given
below) are applicable.
’
Stratum γb Angle of cu mv E
Cohesion,
2 Friction,
3 cp’, (kN/m ) 2 2
(Mg/m ) φp’, ° (kN/m ) (m /MN) (MPa)
Foundation Considerations:
It is recommended that the arch abutment and spread footings be founded directly onto bedrock at
approximately 217.3 m AOD (approx. 1.8 to 8 m below the sloping ground level) on the eastern abutment
and 207 m AOD (approx. 11 m below the sloping ground level) on the western side. The suggested
allowable bearing capacity of the bedrock, according to Tomlinson’s (2001) values for foundations in
2
Limestone is 10000kN/m . Based on Wylie’s equation for foundation on sloping bedrock, this value is limited
2 2
to 4800 kN/m for a 10 m by 5 m foundation and 3700 kN/m for a 2 m by 5 m foundation. Due to the
proximity of the existing foundations and potential disturbance to the structure which may be caused by any
blasting on bedrock, splitting the bedrock with a hydraulic splitter might be a better option to excavate the
bedrock. Since the limestone tested in nearby areas showed a high UCS value of 133 - 154 MPa, (note that
a lower value of 50 MPa has been adopted for assessing shear strength properties) excavation even using a
hydraulic splitter for foundation is anticipated to be really difficult and time consuming.
Due to the proximity of the existing foundations and difficulty in excavating strong limestone to construct
spread footings, piled foundations are an alternative design option. Assuming a 0.6 m diameter piles
socketed 2.0 m into the bedrock, the anticipated safe working load is usually assumed as 0.5UCS, however,
in this case the limiting end bearing value is restricted to 10 MPa. The safe working load also depends on
the concrete compressive strength, fcu and should not exceed 25% fcu. The disadvantage of using this option
in Taf Fechan is the difficulty in accessibility of piling rig and would require the construction of access tracks,
protection to workers and working platform for the piling rig.
The ICE paper entitled “The Heads of the Valley’s Road (1969)” indicates that solution caverns in the
limestone to the east of the existing mainline Taf Fechan caused concern during construction of the existing
viaduct bridge (parallel to the new NMU bridge) after a large cavern was exposed. The paper doesn’t state
the exact location of the cavern. The paper also mentions about the “plugging” of a cavern under the east
foundation of the existing Taf Fechan arch ribs. The Cambrian Cave registry and Cave of South Wales
website shows a cave entrance at the location of SO 03620 08340, about 40 metres north from A465 and
200 m north east from the existing Taf Fechan bridge. The cave (named Ogof Ffordd Y Blaenau) is approx.
30 m long and passes under A465 and partway along the passage a 10m aven was present, along with few
sheep bones which suggests that the aven was once open at the surface. Another cave entrance is also
shown nearby with the entrance at the southern face of the disused Gurnos Quarry, at an elevation of 224m
AOD. Detailed inspection and survey of the rock face, along with ground investigation for the detection of
voids is therefore recommended. This should comprise probe drilling techniques at close intervals at the
proposed foundation locations. Bearing capacity and length of the piles should be reassessed, upon
discovery of any voids or cavities.
Buried Concrete:
Chemical testing for aggressive ground conditions for buried concrete structures was not undertaken on
samples collected from these exploratory holes as part of the preliminary ground investigation. However,
based on the chemical tests on samples collected across the whole route along Section 5, Design Sulfate
class DS-1 and Aggressive Chemical Environment for Concrete ACEC-AC2z (BRE Special Digest 1, 2005)
have been assumed for this site.
Construction Issues:
Both pile and pad foundation has its own construction issues and difficulties on this site. Difficulty in
excavating the strong limestone is anticipated and careful consideration should be taken in not impacting the
existing foundations at Taf Fechan Viaduct if pad foundation design is chosen, especially where rock has to
be excavated or ripped.
Construction of a new NMU bridge may require access to the base of the steep sided Taf Fechan Gorge
and formation of temporary tracks, access and protection will be required if the pile option is chosen. The
effects of construction of temporary accesses on the stability of the side slopes would need to be evaluated
as well as the environmental impact of removing the trees along these accesses. The woodlands
surrounding Taf Fechan Gorge are classified as Sites of Special Scientific Interest (SSSI) as well as Local
Nature Reserve (LNR).
Since limestone solution caverns proved to be a concern at the eastern side of the existing Taf Fechan
Viaduct during construction, particular attention should be given to the existence of such features during
detailed design stage and construction. Depending on the results of the probe holes, remedial options
should be considered such as grouting the voids or piling through these cavities into competent bedrock.
Open hole drilling techniques were used from 2m to 12 m depth in 3/BH91 and from 5.1m to 17.5m depth in
3/BH92. Depth and nature of the superficial deposits around the western side of the NMU bridge will need to
be confirmed prior to construction as the range stated above is only indicative.
The control of localised groundwater, if encountered, will also have to be addressed by the Contractor.
Conclusions and Recommendations:
Both pile and pad foundation has its own construction issues on this site and careful consideration should be
taken during detailed design stage on which option to be chosen. Further ground investigation would be
necessary at the proposed location of the abutments to confirm the location and nature of the bedrock and
the existing foundations exposed to assess the conditions of the existing footings. It is also recommended to
investigate the presence of cavities and any possible solutions features within the limestone. It is also
recommended to subsequently re-assess the bearing capacity of the foundations.
No sulfate or pH tests were carried out on samples taken from the exploratory holes drilled at the site.
Further chemical tests are suggested to confirm the assumptions made.
B2191100/D2/1/2/059
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Heads of the Valleys Dualling Rev: 0 Sheet No: GAS/SP027A
Page 1 of 5
Structure Name: Taff Trail Footbridge Date: May 2017
Prepared: LK Checked: DE/SN Reviewed: AD Job No: B2191100
Chainage: 11312m
Exploratory Holes: References:
Babtie Boreholes:3/BH93, 3/BH93A & i) Babtie Group (2000), A465 Abergavenny
3/BH93B(Located at the base of the cutting level, to Hirwaun Dualling Section 5 –
east of the south abutment) Downlais Top to Nant Ffrwd
and Exploratory Hole, Earthworks Area
3/BH94 (Located at the base of the cutting level, and Structures Location Drawings,
west of the south abutment) Drawing No. BTI015586/11/150.
South Abutment (historic borehole (1958) BH183B and BH184, and Babtie boreholes
3/BH93, 3/BH93A, 3/BH93B and 3/BH94)
Existing ground level: ≈ 234.30m AOD to 233.50m AOD (from cross section elevation values at
approximate location of north to south ends of abutment location, respectively)
>4.7
Oxwich Head Grey fine and medium to thickly
18.65 - (Depth
Limestone 216.11 224.81 >3.90 slightly weathered cystalline strong to
(2) 18.80 not
Formation very strong LIMESTONE.
proven)
(1)
Note: As the Twrch Sandstone Formation lies stratigraphically above the Oxwich Limestone Formation, it
can be assumed that the top of the Oxwich Limestone Formation encountered in the Babtie boreholes located
further from the south abutment location, corresponds with the base of the Twrch Sandstone Formation. This
suggests an approximate maximum thickness of 18.05m.
(2)
Encountered in 3/BH93, 3/BH93B and 3/BH94. Open hole techniques were used in 3/BH93B and thus the
depth to limestone bedrock is only indicative.
Groundwater:
Groundwater was encountered in exploratory hole 3/BH93 at 10.3m bgl (216.11m AOD) and rose
to 7.5m bgl (218.91m AOD) after 20 minutes. Overnight standing water was encountered in
3/BH94 at a level of 5.0 m bgl (222.31 m AOD), noted on 03/06/1997. No ground water was
encountered in the historic boreholes located closest to the abutment locations.
’
Stratum γb, Angle of cu mv E
Cohesion,
2 Friction,
3 cp’, (kN/m ) 0 2 2
(Mg/m ) φp , (kN/m ) (m /MN) (MPa)
Made Ground
(Cohesive and 2.0 0 32 50 0.1 10
Granular)
Glacial Till (1) (1)
(Cohesive)
2.0 2 32 50 0.1 10
E’
Bedrock γb,
UCS (MPa) GSI mi D
Parameters (Mg/m3)
(MPa)
Twrch
Sandstone 2.6 50 50 17 0.7 1500
Formation
Oxwich Head
Limestone 2.7 50 65 12 0.7 7500
Formation
(1) The undrained shear strength and Young’s Modulus of Glacial Till Cohesive were reduced from the GIR values
to reflect the description of boreholes.
Foundation Considerations:
North Abutment
At the location of the north abutment, competent bedrock is expected at existing ground level (an
elevation of 235.6m AOD). The estimated total maximum load to be applied to the abutment
foundation is 680 kN. Drawing 2191100-JAC-SBR-DE-SE-1600-2500 suggests a 2.3m by 2.3m
pad foundation at the north abutment. Assuming these pad dimensions, the total load applied to
the pad would be 130kN/m2. These values are well within the bearing capacity of the rock which
has a UCS value of 50 MPa. If the founding depth is at 231.3 m AOD (1.0m below ground level at
the southern end of the abutment) this corresponds with a foundation depth of 3.5m to 1.0m below
existing ground level (north to south ends of pad footing respectively). Settlement is estimated to
be negligible.
South Abutment
At the location of the south abutment, bedrock is expected at an elevation of 233.5m AOD
(approximately existing ground level) and competent bedrock is anticipated approximately 1.0m
below this (232.5m AOD to allow for any potential weathering). The estimated total maximum load
to be applied to the abutment foundation is 680 kN. Drawing 2191100-JAC-SBR-DE-SE-1600-
2500 suggests a 2.5m by 2.5m pad foundation at the south abutment. Assuming these pad
dimensions, the total load applied to the pad would be 110kN/m2. These values are well within the
bearing capacity of the rock which has a UCS value of 50 MPa. If the founding depth is at 1.0m
below competent bedrock level, this corresponds with an elevation of 231.5m AOD and therefore a
foundation depth of approximately 2.0m below existing ground level. Settlement is estimated to be
negligible.
Buried Concrete:
Chemical testing for aggressive ground conditions for buried concrete structures was undertaken
on one sample collected from exploratory hole 3/BH94 within the glacial till as part of the
preliminary ground investigation. The results indicate Aggressive Chemical Environment for
Concrete AC-1 conditions in accordance with BRE Special Digest 1: Concrete in Aggressive
Ground (2005) and Design Sulfate class DS-1 for the glacial till. However, based on the chemical
tests on samples collected across the whole route along Section 5, Design Sulfate class DS-1 and
Aggressive Chemical Environment for Concrete ACEC-AC2z have been assumed for this site.
Construction Issues:
Difficulty in excavating the sandstone is anticipated and careful consideration should be taken as
to not impacting the slope stability of the cutting or the existing carriageway, especially where rock
has to be excavated or ripped. Due to the strength of the sandstone encountered along this
section of the route, blasting may be required locally.
The existing traffic flows will have to be maintained during the construction works. Monitoring and
control of the localised groundwater, if encountered, will have to be addressed by the Contractor.
B2191100/D2/1/2/059
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Heads of the Valleys Dualling – Section 5 and 6 Rev: 0 Sheet No: GAS/2400
Page 1 of 5
Structure Name: High Street / Brecon Road Bridge Date: March 2017
Prepared: LK Checked: CR Reviewed: AD Job No: B2191100
Chainage: 11150 m
Exploratory Holes: References:
i) Babtie Group (2000), A465 Abergavenny
North abutment: 3/BH97 and 3/BH97A to Hirwaun Dualling Section 5 –
Historic boreholes (BGS Reference: SO00NW43) Downlais Top to Nant Ffrwd
– 177 and 180 Exploratory Hole, Earthworks Area
and Structures Location Drawings,
South abutment: 3/BH96 Drawing No. BTI015586/11/150.
Historic boreholes (BGS Reference: SO00NW43)
– 179 and 182 ii) Babtie Group (2000), A465 Abergavenny
to Hirwaun Dualling, Interpretative
Centre of the carriageway, prior to the Report on Preliminary Ground
construction of the existing A465 : Historic Investigation, Cardiff. Report No.
boreholes (BGS Reference: SO00NW43) – 178 BTI.015586/D4/100.
and 181
iii) Glamorgan Engineering Consultancy
(2006) - Principal inspection report
on Brecon Road Bridge. Report No.
A60150/04/01.
Note : In historic boreholes 177 (located north-west) and 180 (located north-east) , bedrock was
not encountered at the end of the borehole depth which was at 222.4 m AOD and 219.9 m AOD
respectively.
Central reserve
In historic borehole BH181, located east of the central reserve, bedrock was not encountered up
to a depth of 220.7 m AOD. In historic borehole BH178, located west of the central reserve
bedrock was not encountered up to a depth of 210 m AOD (16 m below existing A465
carriageway level).
Groundwater:
North abutment: A standing groundwater level of 8.35m (225.5m AOD) below ground level was
recorded in 3/BH97A.
South abutment: An overnight standing water level of 19.0m (208.0m AOD) below ground level
was noted in exploratory hole 3/BH96.
The highest groundwater level recorded was within the granular glacial till in 3/BH97A from a
piezometer reading taken on 03/06/1997 at 7.41 m bgl (226.4 m AOD).
Stratum cu mv E’
Unit Cohesion Angle of
Weight, γ, cp’, Friction,
(kN/m2) (m2/MN) (MN/m2)
(Mg/m3) (kN/m2) φp°,
Made
Ground
(Cohesive 2.0 2 32 40(1) 0.1(1) 10(1)
and
Granular)
Glacial Till
2.0 2 32 50(1) 0.1(1) 20(1)
(Cohesive)
Glacial Till
2.0 0 35 - - 35
(Granular)
Bedrock γb UCS
3 GSI mi D E’ (MPa)
Parameters (Mg/m ) (MPa)
Twrch
Sandstone 2.6 50 50 17 0.7 1500
Formation
Note : (1) The parameters for made ground and glacial till have been modified from those give in
the GIR in order to reflect the description given in the boreholes.
Foundation Considerations:
North and South Abutments
The High Street bridge is proposed to be founded on piled foundations formed as a contiguous
piled wall. Fourteen piles are proposed in the north and thirteen piles in the south, with 1.5m
diameter and 1.8m centre to centre spacing (as shown on Drawing No. 2191100-JAC-SBR-DE-
SE-1600-2400). The estimated maximum load from the bridge to the pile cap is 347 kN/m which
over the area of the north abutment (25 m long) is 8675 kN and over south abutment is (23.5 m
long) is 8155 kN. The load per pile is therefore 620 kN on the north side and 630 kN on the south
side. If rock is encountered, a minimum rock socket length of 2 m is required. The anticipated
safe working load is 9424.8 kN per pile. If rock is not encountered, assuming a 1.5 m diameter
pile and the same number of piles, the minimum length of the pile that is required within the
glacial till is 14 m. At north abutment, if the pile cut off level is 231 m AOD, the pile toe level is
estimated to be at 217 m AOD. At south abutment, if the pile cut off level is 228 m AOD , the pile
toe level is estimated to be at 214 m AOD. Further ground investigation is suggested at the
proposed abutment locations as well as the central reserve to confirm the ground, groundwater
conditions and the elevation of the bedrock.
Central reserve
As part of the construction sequence, it is proposed that a temporary pier is installed at the centre
of the carriageway. If rock is encountered, the temporary pier could be installed with spread
foundations on rock. However if rock is not encountered, then piled foundations installed within
the glacial till will be required, assuming the central pier loading will be 50% of the abutment
loads. It is anticipated that 15 m long, 1.5 m diameter piles may be required. This needs to be
confirmed during the detailed design stage and after further ground investigation.
Buried Concrete:
Chemical testing for aggressive ground conditions for buried concrete structures was not
undertaken on samples collected from these exploratory holes. However, based on the chemical
tests on samples collected across the whole route along Section 5, Design Sulphate class DS-1
and Aggressive Chemical Environment for Concrete ACEC-AC2z (BRE Special Digest 1, 2005)
have been assumed for this site.
Construction Issues:
The existing traffic flows on A465 and High Street will have to be maintained during the
construction works. There may be a need for a temporary pier required as part of the construction
sequence. The anticipated construction sequence is as follows:
1. Install the piles for both abutments (services will need to be diverted or a temporary
structure put in to carry them over the A465)
2. Excavate approximately 3m down the north abutment piles to allow the casting of the pile
cap (assuming 1:1 benching, the extents of which are shown on the plan)
3. Part excavate between the existing north abutment and new north abutment.
4. Remove the existing deck under a weekend closure (existing structure is upside down
precast beams with transverse bars tying them together. No deck slab)
5. Push A465 traffic as far to the south as possible (remove verge so traffic can run closer to
the abutment). Assume two way single lane running at 30mph.
6. Remove north abutment, excavating down to Finished Road Level (FRL), preferably
across to the south edge of the new central reserve.
7. Construct a temporary pier in the central reserve.
8. Lift part deck beams in between the north abutment and temporary pier
9. Switch A465 traffic to the completed north half of the road, running under the half deck.
10. Repeat steps 2-6 for the south abutment.
11. Lift beams in, bolt and plate the two sections together to make them continuous.
12. Remove temporary support
13. Install formwork and pour deck making deck integral with abutments.
B2191100/D2/1/2/059
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Heads of the Valleys Dualling Rev: 0 Sheet No: GAS/0022/R0
Structure Name: Taf Fawr Mainline bridge Date: May 2017
Prepared: CR Checked: SN Reviewed: AD Job No: B2191100
East Abutment – 3/BH98, 98A i. Babtie Group (Nov. 1999). A465 Abergavenny to Hirwaun
Dualling Section 5 – Dowlais Top to Nant Ffrwd
East Pier – 3/BH 99 Exploratory Hole, Earthworks Area and Structures
Location Drawings. Drawing No. BTI015586/11/150
West Pier On slip – 3/BH99
ii. Babtie Group (2000), A465 Abergavenny to Hirwaun
West Pier Mainline – 3/BH 99 Dualling, Interpretative Report on Preliminary Ground
Investigation, Cardiff. Reference No. BTI15586/D4/100
West Abutment Mainline-
3/BH100 iii. Exploration Associates Ltd (1997). A465 Abergavenny to
Hirwaun Dualling Section 3, Volume Two of Nine Factual
West Abutment On Slip – B79 Report on Ground Investigation. Report No. 166001-3
(Historic Borehole – Norwest
Holst Soil Engineering Ltd, iv. Glamorgan Engineering Consultancy (2006). A465 Trunk
1990, BGS Reference Road Principal Inspection Report, Structure No A465 510
SO00NW267, Grid Reference: (U).
302650,207900)
v. Jacobs (2016) A465 Heads of the Valleys Dualling
Sections 5 and 6 Ground Investigation Report No.
B2191100/D2/1/2/040.
At the location of Taf Fawr valley, it is proposed to have the following structures:
Taf Fawr (North) on-slip and Taf Fawr Mainline viaduct
Taf Fawr South Slip road – Existing bridge
This geotechnical assessment sheet discusses the ground conditions and foundation for the Taf
Fawr on-slip and the mainline viaduct north of the existing structure. At the mainline viaduct, it is
proposed to have a three span haunched post tensioned concrete box with similar profile to the
existing bridge (Taf Fawr South Slip Road – see Figure 1). The proposed length and width of the
bridge is 187 m and approximately 37 m respectively. The Taf Fawr on-slip and mainline structure
share the East Abutment and East pier foundations. The structure splits at the western half of the
span to form the on-slip and thus have independent west pier and west abutments.
Fig.1: Existing Taf Fawr - South Slip Road (Glamorgan Engineering Consultancy)
The existing ground levels mentioned below are taken from the topographic survey:
Depth
Ground Level
to top
Elevation Thickness (m)
Stratum of Description
(m AOD)
stratum
Min Max (m bgl) Min Max
Dense black slightly silty fine to
coarse sand with some fine to
Made
coarse angular to subangular
Ground 224.5 225.09 0.0 1.2
GRAVEL of sandstone and
(Granular)
quartzite, limestone, mudstone,
concrete and slag
Dense to very dense brown
slightly clayey silty fine to
medium SAND with some fine
to coarse subangular to
Glacial Till 223.2
1.2 subrounded gravel of
(Granular) 23.00
sandstone and quartz and
limestone. Encountered
possible boulder at 218 m AOD
in 3/BH98
Grey fine to coarse grained
thinly to medium bedded slightly
Twrch
23 >1.8m (Not weathered strong to very
Sandstone 202.1
proven) strong SANDSTONE and
Formation
moderately weak to moderately
strong SILTSTONE
From 23.0m to 24.6m bgl the bedrock consists of layers of strong sandstone and moderately weak
siltstone.
Note: A layer of possible solifluction deposits is suggested around chainage 10900m (thickness
unknown). This is due to the steep slopes in this area and abundant glacial till across the slope.
This is considered to be unusual for granular glacial till deposits in the area and could be
indicative of the large scale glaciation that affected the area in the past.
Due to poor sample recovery between 4.5m and 6.8m in 3/BH98 open hole techniques were used
from 6.05 m bgl (218 m AOD) to 23 m bgl (202.1 m AOD) in 3/BH98A and therefore the ground
profile in this range of depth is uncertain.
Depth to
Ground Level
top of Thickness
Stratum Elevation Description
stratum (m)
(m AOD)
(m bgl)
Note:
Based on the exploratory hole at the west abutment location 3/BH100, the ground conditions can
be summarised as below:
Groundwater:
Groundwater was encountered in exploratory hole 3/BH100 at the west abutment location. An
overnight seepage was recorded at a depth of 13.4m bgl (210.7 m AOD) in Bishopston Mudstone
Formation. A standpipe piezometer was installed with a response zone between 12.5 m and 15 m
bgl and the highest recorded level was 13.3 m bgl (210.8 m AOD).
Groundwater was encountered in exploratory hole 3/BH101 at a depth of 4.3m bgl (225.2m
AOD), rising to 4.2m bgl (225.3m AOD) in 20 minutes during drilling. A standpipe was installed in
exploratory hole B79 to a depth of 15 m (219.4 m AOD) however no groundwater was observed
during drilling and no recordings were available. Groundwater is assumed to be at 229.5m AOD
(above the granular glacial till) for design in West Abutment.
The ground conditions described above suggest that global parameters from Jacobs GIR, 2016
(given below) are applicable.
Bulk
Angle of
density, Cohesion mv
Stratum Friction, cu (kN/m2) E’ (MPa)
γb, cp’(kN/m2) (m2/MN)
φp’, °
(Mg/m3)
50
0.1
(between 10
(between
ground level (between
ground
and 4 m ground
Made Ground level and
bgl) level and 4
(Granular / 2.0 0 32 2 m bgl)
m bgl)
Cohesive)
0.05
40 (below
(below 2
200 (below 4 m bgl)
m bgl)
4 m bgl)
Glacial Till
2.0 - 35 - - 35
(Granular)
0.1
(between
85 20
ground
level and
Glacial Till 85 + 10z (z 20 + 6z (z
2.0 2 32 2 m bgl)
(Cohesive) = metres = metres
below 2 m below 5 m
0.03
bgl) bgl)
(below 2
m bgl)
Bulk
UCS E’
density,
Stratum GSI mi D
γb, (MPa) (MPa)
3
(Mg/m )
Twrch
Sandstone 2.6 50 50 17 0.7 1500
Formation
Bishopston
Mudstone
Formation 2.6 13 35 8 0.7 200
-Mudstone and
Siltstone
Bishopston
2.6 50 50 15 0.7 3000
Mudstone
Formation –
Sandstone
Foundation Considerations:
East Abutment
At the location of the eastern abutment, competent bedrock is expected at an elevation of 202.1
m AOD. The estimated total maximum load to be applied to the abutment foundation is 62,090
kN. Drawing 2191100-JAC-SBR-DE-SE-1600-2300 suggests a pile group of 28 (14x2) at the east
abutment. The total load per pile is 2220 kN. Assuming 1.5 m diameter piles, a minimum rock
socket length of 2 m is required. However, to ensure a good socket, it is suggested that a
minimum socket length of two diameter is adopted (i.e a minimum rock socket length of 3m). This
gives a pile length of 20 m and approximate toe level elevation of 199 m AOD.
East Pier
Due to the generally low bearing capacity of the underlying cohesive glacial till, and relatively
shallow depth to bedrock, it is proposed that piles are socketed within the bedrock. Competent
bedrock is estimated at approximately 195.4 m AOD, however as there are no boreholes at the
location of this pier it is possible bedrock is at greater or shallower depths. The estimated total
maximum load to be applied to the structure foundation is 153,530 kN. Assuming a pile group of
No. 30 (15 by 2, as suggested by Drawing 2191100-JAC-SBR-DE-SE-1600-2300) the total load
per pile is 5120 kN. Assuming 1.5 m diameter piles, a minimum rock socket length of 5 m is
required, corresponding with pile length of 15 m and with an approximate toe elevation of 190.4 m
AOD.
West Piers
The West Pier is considered to have similar ground conditions as the East Pier. However the on-
slip splits off from the mainline to have a separate foundation. At the location of the west piers,
competent bedrock is expected to be at 195.4 m AOD.
Mainline bridge
The estimated total maximum load to be applied to the mainline foundation is 133,360 kN.
Assuming a pile group of No. 24 (12 by 2) the total load per pile is 5560 kN. Assuming 1.5 m
diameter piles, a minimum rock socket length of 5 m is required, corresponding with pile length of
15 m and with an approximate toe elevation of 190 m AOD.
On-slip bridge
The estimated total maximum load to be applied to the on-slip foundation is 52,100 kN. Assuming
a pile group of No. 10 (5 by 2) the total load per pile is 5210 kN. Assuming 1.5 m diameter piles, a
minimum rock socket length of 5 m is required, corresponding with pile length of 20 m and with
an approximate toe elevation of 190 m AOD.
West Abutment
Due to the uncertainty of the nature of superficial deposits at this location and low bearing
capacity of cohesive glacial till (if present), it is proposed that this abutment will be founded on
piles socketed within the bedrock. At the location of the western abutment, competent bedrock is
expected at a depth of 218 m AOD (9 m bgl if the ground level is at 227 m AOD).
Mainline bridge
The estimated total maximum load to be applied to the mainline foundation is 53,940 kN.
Assuming a pile group of No. 24 (12 by 2) the total load per pile is 2250 kN. Assuming 1.5 m
diameter piles, a minimum rock socket length of 2 m is required. However, adopting a minimum
rock socket of two diameter i.e. 3 m, this corresponds to a pile length of 12 m and an approximate
toe level of 215 m AOD.
On-slip bridge
The estimated total maximum load to be applied to the on-slip foundation is 21,070 kN. Assuming
a pile group of No. 10 (5 by 2) the total load per pile is 2110 kN. Assuming 1.5 m diameter piles, a
minimum rock socket length of 2 m is required. However, adopting a minimum rock socket of two
diameter i.e. 3 m, this corresponds to a pile length of 12 m and an approximate toe level of 215 m
AOD.
West 12
32 m x 4.1 m (12 x
Abutment – 227 218.3 2250 215 (3 m rock
2 rows of piles)
Mainline socket)
West 12
12.5 m x 4.1 m (5 x
Abutment – 227 218.9 2110 215 (3 m rock
2 rows of piles)
On slip socket)
Buried Concrete:
Chemical testing for aggressive ground conditions for buried concrete structures was undertaken
on five samples as part of the preliminary ground investigation: one sample within the made
ground in 3/BH99, three samples from the bedrock in 3/BH100 and one sample within the glacial
till in 3/BH101. The results indicate Aggressive Chemical Environment for Concrete ACEC-2z
conditions in accordance with BRE Special Digest 1: Concrete in Aggressive Ground (2005) and
Design Sulfate class DS-1.
Construction Issues:
Zones of core loss were identified within the boreholes drilled at the west abutment. The
geological map shows that the zone of core loss is likely to be an area of highly fractured bedrock
rather than mineworkings due to the underlying bedrock comprising Bishopston Mudstone
Formation and Twrch Sandstone Formation, both of which lie stratigraphically below the Lower
Coal Measures and therefore any coal seams. However, further ground investigation is
suggested at the proposed bridge location to confirm if the voids are present, or whether the core
loss may have been drilling induced. If the presence of voids is confirmed beneath the structure
then they should be grouted prior to construction.
Construction of the bridge foundations will require access to the base of the steep sided Taf Fawr
valley. Temporary access roads will therefore have to be prepared to allow construction to
proceed, the localised stability of the adjacent slopes should be considered.
Further specific information is required at the proposed locations of the abutments and piers. The
soil and rock conditions should be determined along with appropriate testing to determine the
engineering parameters. Piezometers should be installed to monitor groundwater conditions.
Deeper boreholes are recommended to confirm the bedrock level.
Any solifluction deposits, if encountered, should be removed before any construction work, this is
especially important as an embankment and bridge structure is to be constructed at this location
B2191100/D2/1/2/059
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Section 5 & 6 - Heads of the Valleys Dualling Rev: 0 Calc No: GAS/0020/R0
Page 1 of 4
Structure Name: A465/A470 Underbridge Date: July 2016
Prepared: LK Checked: LAK / CR Reviewed: AD Job No: B2191100
North and South abutments: 3/BH102 and i) Babtie Group (2000), A465 Abergavenny to
3/BH102A. Hirwaun Dualling, Interpretative Report on
Preliminary Ground Investigation, Section
5 – Nant Ffrwd to Baverstock, Report No.
BTI.015586/D4/118.
Proposed Structure:
The current proposal is to build a new single span integral underbridge at A465/A470
interchange. The length and width of the proposed bridge is 35 m and 27 m respectively. The
new structure is proposed to have steel girders with concrete deck.
Project: A465 Section 5 & 6 - Heads of the Valleys Dualling Rev: 0 Calc No: GAS/0020/R0
Page 2 of 4
Structure Name: A465/A470 Underbridge Date: July 2016
Prepared: LK Checked: LAK / CR Reviewed: AD Job No: B2191100
Ground Conditions:
Ground profile for both North and South Abutment are assumed same.
North and South Abutments
Note: Assumed zone of core loss (AZCL) recorded between 6.4m bgl to 6.60 m bgl, 10.6m bgl to
10.7 m bgl, 10.90m to 11.15m and from 16.65m to 16.80m in Borehole 3/BH102A.
This assessment is based only on the Exploration Associates Ground Investigation (1997). Further
historic boreholes may be available from BGS website.
Project: A465 Section 5 & 6 - Heads of the Valleys Dualling Rev: 0 Calc No: GAS/0020/R0
Page 3 of 4
Structure Name: A465/A470 Underbridge Date: July 2016
Prepared: LK Checked: LAK / CR Reviewed: AD Job No: B2191100
Groundwater:
No groundwater strikes were recorded in the relevant boreholes. However, overnight standing
water levels of 5.89 m (225.4 m AOD) and 5.65 m (225.3 m AOD) below existing ground level
were recorded in borehole 3/BH102 and 3/BH102A respectively.
Summary of Soil Parameters:
The ground conditions described above suggest that global parameters from Jacobs GIR, 2016
(given below) are applicable, except where indicated.
Foundation Considerations:
There is limited available borehole data at this location, however based on the available
information it is anticipated that piled foundations will be founded on to intact bedrock.
The carriageway level is approximately 240.0m AOD. Existing ground level varies from 231 to
233 m AOD. At both abutments, a piled foundation socketed to the bedrock is anticipated. The
estimated total maximum load to be applied to the bridge abutment is 24000 kN. Assuming a pile
group of twenty piles per abutment in two rows, as suggested by Drawing B2191100-JAC-SBR-
DE-SE-1600-2000, the total load per pile is of the order 1200 kN. As the structure is an integral
bridge, due to the expansion of the deck, it is feasible that much of the load will be applied to one
row of piles with the other row in tension. It was therefore conservatively assumed that the full
loading was applied to a single row of piles. This therefore increases the load to 2400kN per pile.
Assuming a 0.9m diameter piles socketed 5 m into the bedrock, the anticipated safe working load
is 2825 kN per pile, with an approximate toe elevation of 218.8 m AOD.
Project: A465 Section 5 & 6 - Heads of the Valleys Dualling Rev: 0 Calc No: GAS/0020/R0
Page 4 of 4
Structure Name: A465/A470 Underbridge Date: July 2016
Prepared: LK Checked: LAK / CR Reviewed: AD Job No: B2191100
Buried Concrete:
Sulphate and pH tests for aggressive ground conditions for buried concrete structures were not
undertaken on samples collected from the exploratory holes at this location. However, based on
the chemical tests on samples collected across the whole route along Section 5 within Made
Ground and Glacial Till suggest Aggressive Chemical Environment for Concrete ACEC-AC2
conditions in accordance with BRE Special Digest 1: Concrete in Aggressive Ground (2005) and
Design Sulfate class DS-1. Further chemical testing in the area is recommended to confirm if
these results are applicable.
Construction Issues:
The existing traffic flows will have to be maintained during the construction works. The control of
localised groundwater, if encountered, will also have to be addressed by the Contractor. In
addition, Glacial Till is susceptible to ‘wetting-up’ and therefore may have decreased undrained
shear strength than anticipated.
Conclusions and Recommendations:
Due to limited information available on site further ground investigation is recommended at both
abutments of the proposed bridge.
According to Borehole records, core loss was noted between 6.4m to 6.60m, 10.6m to 11.15m
and from 16.65m to 16.80m below existing ground level. Therefore, further investigation works,
are recommended in order to find out the possibility of mine workings beneath the proposed
structure and to confirm the location and nature of the soil. If the presence of mine workings are
noted beneath the structure, then the allowable bearing pressures should be reduced in
accordance with the CIRIA special publications 32 (Healy and Head, 1989). Suggested values
can be assessed when further investigation results are available.
Design Sulfate DS-1 and ACEC AC-2z (BRE Special Digest 1, 2005) has been assumed for
concrete design for buried structures. Further chemical testing in the area is recommended to
confirm if these results are applicable.
The above recommendations are intended to give a general guidance for preliminary design
purposes only. Bearing capacities and settlement will also vary according to the actual foundation
dimensions adopted in the detailed design option.
B2191100/D2/1/2/059
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Heads of the Valleys Dualling Section 5 & 6 Rev: 0 Sheet No: GAS/1/R0
Structure Name: Nant Ffwd Overbridge (Mainline) Date: February 2017
Prepared: LAK Checked: CR Reviewed: AD Job No: B2191100
Chainage: 10355 m
Exploratory Holes: References:
i) Babtie Group (2000), A465 Abergavenny to
East and West abutment: 3/BH106, Hirwaun Dualling, Interpretative Report on
3BH106a, 3/BH108, 3/BH107 Preliminary Ground Investigation, Section
5 – Nant Ffrwd to Baverstock, Report No.
BTI.015586/D4/118.
ii) Exploration Associates Ltd (1997), A465
Abergavenny to Hirwaun Dualling Section
3. Volume One of Nine, Factual Report on
Ground Investigation. Report No. 166001-
3.
iii) Healy, P.R and Head, J.M. (1989), CIRIA
Special Publication 32: Construction over
abandoned mine workings.
iv) Babtie Group (2000), A465 Abergavenny to
Hirwaun Dualling Section 5 – Hirwaun to
Baverstock, Scheme Proposals and
Exploratory Hole Location Drawings,
Drawing No. BTI015586/11/150.
v) Jacobs (2015), A465 Heads of the Valleys
Dualling Sections 5 and 6 Preliminary
Sources Study Report. Report No.
B1855100/D4/2/017.
vi) Tomlinson (2001), Foundation design and
construction, 7th Edition, Pearson
Education.
vii) Jacobs (2016) A465 Heads of the Valleys
Dualling Sections 5 and 6 Ground
Investigation Report. Report No.
B2191100/D2/1/040
viii) Jacobs (2016) Nant Ffrwd Off-Slip Viaduct –
General Alignment, Drawing. No.
B2191100-JAC-SBR-DE-SE-1600-1801 to
1802.
Proposed Structure:
The current proposal is to construct a new mainline overbridge to the north of the existing Nant
Ffrwd structure and to the south of the proposed Nant Ffrwd Off-slip Viaduct. The existing
structure is proposed to remain to act as the Nant Ffrwd South Slip Road. The northern off-slip
viaduct and the mainline viaduct crosses Nant Ffrwd (at approximately Ch 10360), which is
surrounded by woodland on either side.
The Nant Ffrwd mainline viaduct consists of a 150 m three span bridge, which has fixed bearings
on both abutments. The east abutment and intermediate piers are proposed to be founded on
spread foundations. The west abutment is proposed to be founded on piled foundations.
Groundwater:
Borehole 3/BH107 recorded a standing water level of 3.10 m bgl (238.5 m AOD) and borehole
3/BH108 indicated standing water at 3.25 m bgl (241.4 m AOD).
A summary of the groundwater level measured from piezometer monitoring at this chainage is
summarised below:
Bishopston
3/BH108 Piezometer 15/05/97 4.00 2.00 – 4.50 Mudstone 244.7 0.00 0.00 - -
Formation
These values have been taken from the global parameters in Jacobs GIR (2016), except where
indicated:
Stratum Unit cu mv E’
Cohesion, Angle of
Weight, 2 2
cp’, Friction, (kN/m ) (m /MN) (MPa)
γb
(kN/m2) φp’, °
(Mg/m3)
Glacial Till
(1) 2 2 32 35 0.1 10
(Cohesive)
Unit
Bedrock Weight, UCS
GSI mi D E’ (MPa)
Parameters γb (MPa)
3
(Mg/m )
Bishopston
Mudstone
2.6 50 50 15 0.7 3000
Formation –
Sandstone
Bishopston
Mudstone (2)
2.6 9 35 8 0.7 200
Formation -
Mudstone
Note: (1) The glacial till parameters have been reduced from the values given in GIR, in order to reflect the
description given in boreholes.
(2) A lower UCS value for Mudstone has been selected for this site based on the converted point load test
results from borehole 3/BH100.
Foundation Considerations:
21000 kN. Assuming a 900 mm diameter pile group of 15 x 2 piles, the load per pile is about 710
kN.. A minimum rock socket length of 2 m (i.e. toe level of 238 m AOD depending on the level at
which bedrock is encountered) is suggested to support the vertical loading from the bridge.
Buried Concrete:
Chemical testing for aggressive ground conditions for buried concrete structures was not
undertaken on samples collected from the exploratory holes. However, based on the chemical
tests on samples collected across the whole route along Section 5, Design Sulfate class DS-1
and Aggressive Chemical Environment for Concrete ACEC-AC2z (BRE Special Digest 1, 2005)
have been assumed for this site.
Construction Issues:
This structure is off-line and will be located within an area where there is little significant existing
development, apart from a high voltage pylon located close to the east abutment. High voltage
power cables also span the proposed alignment. As such, consideration will be needed to avoid
undermining the existing pylon foundations, especially during the temporary works. A small
retaining structure may be needed to this aim; however this depends on the final design for the
works which is not yet confirmed. The contractor will also need to liaise with Western Power to
determine an appropriate construction methodology.
There is considerable variation in the existing ground level across the site (up to approximately 11
m) which will affect the carriageway approach and may require the construction of earthworks.
The control of localised groundwater will also have to be addressed by the Contractor. The
Interpretive Report on Preliminary Ground Investigation produced by Babtie in 2000 indicates that
there is an existing waterfall located near the centre of the west abutment; care will need to be
taken to avoid disturbance of this natural feature.
Conclusions and Recommendations:
Due to limited information available on site, further ground investigation is recommended to
confirm the nature of the superficial deposits and depth to bedrock.
Design Sulfate DS-1 and ACEC AC-2z (BRE Special Digest 1, 2005) has been assumed for
concrete design for buried structures. Further chemical testing in the area is recommended to
confirm if these results are applicable.
Spread foundations within unweathered bedrock are recommended for the east abutment and
intermediate piers. A piled foundation on unweathered bedrock is recommended for the west
abutment.
Note that the above recommendations are intended to give a general guidance for preliminary
design purposes only and may be required to be revised depending on the outcome of further
ground investigation. Bearing capacities and settlement may vary according to the actual
structure dimensions in the detailed design option.
Bishopston
Intermediate 240 (See 3 m x 21
Mudstone 1000
Piers Note) m
Formation
Note: The toe level shown above are indicative only, the toe level will depend on the level at which bedrock
is encountered on site.
PILE DESIGN
Founding Toe Level Pile Width Pile Length Pile Working Load
Structure Element
Stratum (m AOD) (m) (m) (kN)
Bishopston
West Abutment 238 (See 18 (See Note
Mudstone 0.9 710 per pile
(15 x 2 pile group) Note) 1)
Formation
Note 1). The toe level and pile length shown above are indicative only, the toe level and length will depend
on the level at which bedrock is encountered on site. A minimum rock socket length of 2 m is required.
B2191100/D2/1/2/059
GEOTECHNICAL SUMMARY INFORMATION
Project: A465 Heads of the Valleys Dualling Section 5 & 6 Rev: 0 Sheet No: GAS/0017/R0
Structure Name: Nant Ffwd Off-Slip Viaduct (North) Date: February 2017
Prepared: LAK/DE Checked: CR Reviewed: AD Job No: B2191100
Chainage: 10310 m
Exploratory Holes: References:
3/BH107, 3/BH108 (80 m away) i. Babtie Group (2000), A465 Abergavenny
to Hirwaun Dualling, Interpretative
Report on Preliminary Ground
Investigation, Section 5 – Nant Ffrwd to
Baverstock, Report No.
BTI.015586/D4/118.
ii. Exploration Associates Ltd (1997), A465
Abergavenny to Hirwaun Dualling
Section 3. Volume One of Nine, Factual
Report on Ground Investigation. Report
No. 166001-3.
iii. Healy, P.R and Head, J.M. (1989),
CIRIA Special Publication 32:
Construction over abandoned mine
workings.
iv. Babtie Group (2000), A465 Abergavenny
to Hirwaun Dualling Section 5 – Hirwaun
to Baverstock, Scheme Proposals and
Exploratory Hole Location Drawings,
Drawing No. BTI015586/11/150.
v. Jacobs (2015), A465 Heads of the
Valleys Dualling Sections 5 and 6
Preliminary Sources Study Report.
Report No. B1855100/D4/2/017.
vi. Tomlinson (2001), Foundation design
and construction, 7th Edition, Pearson
Education.
vii. Jacobs (2016) A465 Heads of the
Valleys Dualling Sections 5 and 6
Ground Investigation Report. Report No.
B2191100/D2/1/040
viii. Jacobs (2016) Nant Ffrwd Off-Slip
Viaduct – General Alignment, Drawing.
No. B2191100-JAC-SBR-DE-SE-1600-
1700.
Proposed Structure:
The current proposal is to construct a new off-slip viaduct to the north of the proposed new
mainline Nant Ffrwd viaduct. The existing structure is proposed to remain to act as the Nant
Ffrwd South Slip Road. The northern off-slip viaduct and the mainline viaduct crosses Nant Ffrwd
(at approximately Ch 10360), which is surrounded by woodland on either side.
The Nant Ffrwd off-slip viaduct consists of a 60 m span bridge which is proposed to be integral at
the east abutment and to have fixed bearings on the west abutment. The east abutment is also
anticipated to be founded on a spread foundation shared with the wingwall foundation. The west
abutment of the structure is anticipated to be founded on a spread foundation, with a retaining
wall to the south of the abutment connecting the mainline viaduct.
Depth to
Ground Level
top of
Elevation Thickness (m)
Stratum stratum Description
(m AOD)
(m bgl)
Min Max Min Max Min Max
Soft red-brown friable slightly
Glacial Till silty, very sandy CLAY and
241.6 244.7 0.0 1.1 4.4
(Cohesive) GRAVEL of sandstone,
cobbles and boulders.
Note: Zones of core loss (up to 0.5 m) were noted between 5.60 and 6.00 m bgl, 8.05 and 8.30 m
bgl and between 24.50 and 25.00 m bgl in 3/BH107. Open hole techniques were used in 3/BH108
between ground level and 4.4 m bgl.
Groundwater:
Borehole 3/BH107 recorded a standing water level of 3.10 m bgl (238.5 m AOD) and borehole
3/BH108 indicated standing water at 3.25 m bgl (241.4 m AOD).
A summary of the groundwater level measured from piezometer monitoring at this chainage is
summarised below:
Bishopston
3/BH108 Piezometer 15/05/97 4.00 2.00 – 4.50 Mudstone 244.7 0.00 0.00 - -
Formation
Note : (1) The glacial till parameters have been reduced from the values given in GIR, in order to
reflect the description given in boreholes.
(2) A lower UCS value for Mudstone has been selected for this site based on the converted point
load test results from borehole 3/BH100.
Foundation Considerations:
Due to the low bearing capacity of soft cohesive Glacial Till, and the shallow depths of bedrock
(1.5m to 6 m below existing ground level), it is proposed that the abutments are founded within
the unweathered bedrock using spread foundations. The estimated maximum load for the
structure at the east abutment is 15230 kN whilst at the west abutment is 13040 kN. Assuming a
5 m x 13.7 m wide spread foundations for both abutments, the loadings on east and west
2 2
abutment is 225 kN/m and 190 kN/m .
From the description of the bedrock encountered and based on Tomlinson’s presumed bearing
values for shallow foundations in bedrock, a safe bearing value of 1000 kN/m2 can be assumed
for the bedrock. Settlement is expected to be negligible.
Buried Concrete:
Chemical testing for aggressive ground conditions for buried concrete structures was not
undertaken on samples collected from the exploratory holes. However, based on the chemical
tests on samples collected across the whole route of Section 5, Design Sulfate class DS-1 and
Aggressive Chemical Environment for Concrete ACEC-AC2z (BRE Special Digest 1, 2005) have
been assumed for this site.
Construction Issues:
The control of localised groundwater will also have to be addressed by the Contractor. It is
understood overhead electric cables are in close proximity to the east abutment. It is essential the
contractor liaise with Western Power to determine an appropriate construction methodology.
Conclusions and Recommendations:
Spread foundations within unweathered bedrock are recommended due to the low bearing
capacity of the cohesive glacial till and the shallow depths to bedrock.
Due to limited information available on site, further ground investigation is suggested at both
abutments of the proposed bridge, especially at the east abutment where no ground information
is currently available.
Design Sulfate DS-1 and ACEC AC-2z (BRE Special Digest 1, 2005) has been assumed for
concrete design for buried structures. Further chemical testing in the area is recommended to
confirm if these results are applicable.
Note that the above recommendations are intended to give a general guidance for preliminary
design purposes only and may be required to be revised depending on the outcome of further
ground investigation. Bearing capacities and settlement may vary according to the actual
structure dimensions in the detailed design option.
B2191100/D2/1/2/059
GEOTECHNICAL SUMMARY INFORMATION
Project: A465 Heads of the Valleys Dualling Section 5 & 6 Rev: 0 Sheet No: GAS/1650/R0
Structure Name: Nant Ffwd Approach Viaduct Date: May 2017
Prepared: CR Checked: AD Reviewed: AD Job No: B2191100
Chainage: 9900 m
Exploratory Holes: References:
3/BH111 (near the structure) i. Babtie Group (2000), A465 Abergavenny
3/BH110 (150 m east of the structure) to Hirwaun Dualling, Interpretative
Historic BGS Boreholes : Report on Preliminary Ground
SO00NW31, SO00NW32 Investigation, Section 5 – Nant Ffrwd to
(BGS Grid Reference 302070,207340) Baverstock, Report No.
BTI.015586/D4/118.
ii. Exploration Associates Ltd (1997), A465
Abergavenny to Hirwaun Dualling
Section 3. Volume One of Nine, Factual
Report on Ground Investigation. Report
No. 166001-3.
iii. Healy, P.R and Head, J.M. (1989),
CIRIA Special Publication 32:
Construction over abandoned mine
workings.
iv. Babtie Group (2000), A465 Abergavenny
to Hirwaun Dualling Section 5 – Hirwaun
to Baverstock, Scheme Proposals and
Exploratory Hole Location Drawings,
Drawing No. BTI015586/11/150.
v. Jacobs (2015), A465 Heads of the
Valleys Dualling Sections 5 and 6
Preliminary Sources Study Report.
Report No. B1855100/D4/2/017.
vi. Tomlinson (2001), Foundation design
and construction, 7th Edition, Pearson
Education.
vii. Jacobs (2016) A465 Heads of the
Valleys Dualling Sections 5 and 6
Ground Investigation Report. Report No.
B2191100/D2/1/040
viii. Jacobs (2016) Nant Ffrwd Approach
Viaduct – General Alignment, Drawing.
No. B2191100-JAC-SBR-DE-SE-1600-
1650.
Proposed Structure:
The current proposal is to construct a new approach viaduct to the north of the existing A465 to
support the eastbound carriageway as it goes off the mainline. The Nant Ffrwd approach viaduct
consists of a 125 m span steel arch bridge which is proposed to be founded on spread
foundations.
Existing Ground Level:
≈ 280 m AOD (from 3/BH111)
Existing ground level at West Abutment (approx. Ch 9840)
North ≈ 282 m AOD
South ≈ 285 m AOD
Depth to
Ground Level
top of
Elevation Thickness (m)
Stratum stratum Description
(m AOD)
(m bgl)
Min Max Min Max Min Max
Firm to stiff yellow brown
slightly silty sandy (fine to
medium) CLAY with a little
Glacial Till
279.95 0 3.4 fine to medium angular to
(Cohesive)
subangular gravel and
cobbles of sandstone,
quartzite and silty sandstone.
Very dense clayey sandy
(fine to coarse) fine to
> 0.8 m (Not
Glacial Till medium subangular GRAVEL
(1) 276.6 3.4 proven in
(Granular) of silty mudstone. (Driller’s
3/BH110)
description: Possible
Weathered bedrock)
Very stiff brown grey very
silty sandy (fine to medium)
Glacial Till 274.6 m AOD - CLAY with a little fine to
5.4 5.5
(Cohesive) Estimated medium angular to
subangular gravel of
sandstone.
Dark grey thickly laminated to
thinly bedded generally
moderately occasionally
Lower Coal 267 m AOD - >9.4
13 (1) highly weathered silty
Measures Estimated Not proven
MUDSTONE moderately
strong to locally moderately
weak.
Note: (1) Although the borehole description suggests possible weathered bedrock, the historic
boreholes and the geological ground model suggest that the bedrock might be at a greater depth
(approximately 267 m AOD). The steepness of the existing ground level suggests that there is the
possibility that the bedrock is present at a more shallow level. Due to the uncertainty of the
bedrock level at this location, it is recommended that further ground investigation is carried out.
Groundwater:
Groundwater was not encountered during drilling within 3/BH111. Groundwater was recorded
however, in a piezometer installed in the borehole, within the granular Glacial Till. A summary of
the groundwater levels measured from piezometer monitoring at this chainage is summarised
below:
Glacial Till
3/BH111 Piezometer 19/06/97 4.00 3.4-4.2 279.95 - - 3.51 3.35
(Granular)
75 + 10 z
Glacial Till
(1) 2 2 32 (where z = 0.1 10
(Cohesive)
metres
below 4 m
bgl)
Glacial Till
2 - 35 - - 35
(Granular)
Unit
Bedrock Weight, UCS
GSI mi D E’ (MPa)
Parameters γb (MPa)
(Mg/m3)
South Wales
Lower Coal 2.5 25 45 14 0.7 750
Formation
Note: (1) The glacial till parameters have been reduced from the values given in GIR, in order to
reflect the description given in boreholes.
Foundation Considerations:
Although the borehole description suggests possible weathered bedrock, the historic boreholes
and the geological ground model suggest that the bedrock might be at a greater depth
(approximately 267 m AOD). The steepness of the existing ground level however, suggests that
bedrock may be at a more shallow level. Due to the uncertainty of the bedrock level at this
location, it is recommended that further ground investigation is carried out.
If bedrock is encountered at shallow depth, a safe bearing value of 1000 kN/m2 can be assumed
for foundations bearing on the bedrock. Settlement is expected to be negligible if founded on
bedrock.
Buried Concrete:
Chemical testing was undertaken on two samples from 3/BH110 within the glacial till as part of
the preliminary ground investigation. The results indicate Aggressive Chemical Environment for
Concrete AC-2z conditions in accordance with BRE Special Digest 1: Concrete in Aggressive
Ground (2005) and Design Sulfate class DS-1. This corresponds with the conditions assessed
from chemical tests on samples carried across the whole route of section 5. Chemical analysis to
be confirmed after further chemical testing in the area.
Construction Issues:
The control of localised groundwater will also have to be addressed by the Contractor. Firm to
stiff cohesive glacial tell (material with an undrained shear strength less than 80kN/m 2)
encountered at founding level should be dug out and replaced with acceptable granular fill
material.
B2191100/D2/1/2/059
GEOTECHNICAL SUMMARY INFORMATION
Project: A465 Heads of the Valleys Dualling Rev: 0 Sheet No: GAS/0016/Rev0
Page 1 of 5
Structure Name: Baverstock Junction Bridge Date: May 2017
Prepared: SN Checked: HM / AD Reviewed: AD Job No: B2191100
Proposed Structure:
It is proposed that the existing A465 in the vicinity of the proposed bridge location will be
symmetrically widened and built up on an embankment. The proposed structure will consist of a
new underbridge which will carry a new road under the proposed A465 (Drawing No. 2191100-
JAC-SBR-DE-SE-1600-1600). The elevation of the existing A465 carriageway is approximately
329.2 m AOD, whilst that of the proposed widened A465 is expected to be approximately 340.0 m
AOD.
The proposed structure will be an integral bridge comprising reinforced concrete with a 20 m span
with a clearance of approximately 7.5 m above the finished underbridge road level. Engineered fill
will be placed above the proposed structure to build the mainline carriageway embankment up to
the proposed level.
Ground Conditions:
West Abutment (historic borehole (1958) BH117)
Existing ground level: ≈ 333.70 m AOD to 328.80 m AOD (from cross sections elevation values
at approximate location of north to south ends of abutment location, respectively)
Bedrock was not encountered in any boreholes in vicinity to the proposed bridge and therefore
rockhead was interpolated from boreholes 3/BH128 and 3/BH125 located further west and east of
the structure location, respectively. From these boreholes, it is suggested that the elevation of
bedrock beneath the structure is approximately 318.5 m AOD beneath the west abutment and
321.5 m AOD beneath the east abutment. These correspond with depths of approximately 15.2 m
bgl to 10.3 m bgl, north to south, respectively beneath the west abutment and approximately 12.8
m bgl to 8.5 m bgl, north to south, respectively beneath the east abutment.
The Twyn Ddisgwylfa Fault is anticipated to lie beneath the proposed bridge. It is possible that
there may be a possible fracture zone either side of this fault suggesting the number of fractures
within the bedrock around this chainage may increase which in turn may affect the competency of
the bedrock. The groundwater behaviour may also vary slightly from that anticipated in the
ground further away.
Existing information shows that 2 No. mine entries (identified as adits by the Coal Authority, 2016)
are located within 200m of the proposed structure (one to the north and one to the south). This
indicates there are mine workings within the area and, as the underlying bedrock comprises the
Lower Coal Measures, there is a possibility for unrecorded mineworkings or voids being
encountered. However, the anticipated direction of the adits suggests that they are unlikely to
extend to the bridge location.
Groundwater:
Water was recorded as surface water (331.4m AOD) in historic borehole BH117 corresponding
with the topsoil. Ground water was also encountered within the granular glacial till in 3/BH127 at
2.0mbgl (329.6m AOD) rising to 1.95m bgl (329.7m AOD) in 20 minutes during drilling.
γb Angle of cu mv E’
Cohesion,
Stratum Friction,
(Mg/m ) 3 cp’ (kN/m2) (kN/m ) 2 2
(m /MN) (MPa)
φp’ (°)
Possible
Solifluction 0 28 35 0.3 7
Deposits 1.9
75
20
Glacial Till 75+10z
2 32 0.1 20+3z
(Cohesive) (z = metres
2.1 (z = metres
below 2.0 m
below 5.0 mbgl)
bgl)
30
Glacial Till
2.0 0 36 - - 30+17z (z =
(Granular) metres below
5.0 m bgl)
Bedrock γb UCS
3 GSI mi D E’ (MPa)
Parameters (Mg/m ) (MPa)
Lower Coal
Measures - 2.5 35 50 15 0.7 1050
Sandstone
Lower Coal
Measures - 2.5 10 35 8 0.7 150
Mudstone
Foundation Considerations:
Due to the lower bearing capacity of the glacial till, it is anticipated that the abutments will be
founded on piled foundations socketed within the bedrock. The estimated total maximum load to
be applied to the structure foundation is of the order of 108600kN. Assuming a pile group of No.
48 for the west abutment (24 by 2) and 46 for the east abutment (23 by 2), as suggested by
Drawing 2191100-JAC-SBR-DE-SE-1600-1600, the total load per pile is approximately 2265 kN
and 2365kN for the west and east abutment, respectively. As this bridge is an integral bridge, due
to the expansion of the deck, it is feasible that much of the load will be applied to the outer row of
piles with the front row possibly in tension. This could increase the load to about 4530 kN per pile
for the west abutment and 4730 kN per pile for the east abutment. Assuming 0.9m diameter piles,
a minimum rock socket of 9.0m is required.
At the west abutment, a nominal value of 15.5 m has been estimated for the pile length assuming
the pile cut of level (COL) for the structure is approximately 3.5 m bgl (325.0 m AOD). At the east
abutment, a nominal value of 12.5 m has been estimated for the pile length assuming the pile cut
of level (COL) for the structure is approximately 6.5 m bgl (325.0 m AOD). The actual pile length
may differ depending on the rockhead elevation which will need to be confirmed with further
ground investigation. Settlement within the bedrock is estimated to be <10 mm.
Buried Concrete:
Chemical testing for aggressive ground conditions for buried concrete structures was not
undertaken on samples collected from previous exploratory holes drilled in the Baverstock area.
Based on the conditions assessed from chemical tests on samples collected across the whole
route of section 6 in accordance with BRE Special Digest 1: Concrete in Aggressive Ground
(2005), an Aggressive Chemical Environment for Concrete AC-2z and Design Sulfate class DS-1
are recommended for design. Further chemical testing in the area is recommended to confirm if
these results are applicable.
Construction Issues:
Prior to construction, any soft material (undrained shear strengths of <40 kN/m2), such a possible
solifluction deposits, encountered within the footprint of the proposed structure should be
removed and replaced with appropriate fill.
Depth to bedrock was not confirmed due to lack of available boreholes in the vicinity of the
proposed structure and therefore pile lengths may vary. Rockhead assumptions should be
confirmed on site.
As the underlying bedrock comprises the Lower Coal Measures, there is a possibility of
unrecorded mineworkings or voids being encountered. In light of this, prior to construction, it is
suggested that the area beneath the proposed foundations should be investigated thoroughly for
the presence and condition of possible mineworkings or voids. Any voids or mineworkings
encountered will require grouting.
B2191100/D2/1/2/059
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Section 5 & 6 Heads of the Valleys Dualling Rev: 0 Sheet No: GAS/SE018
Page 1 of 7
Structure Name: Nant Hir Viaduct Date: April 2017
Prepared: SN Checked: HM/CR Reviewed: AD Job No: B2191100
East Arch Abutment: Historic boreholes (1965) ii) Babtie Group (2000) A465 Abergavenny to
BH102A-D BH103A-D, BH104A-D Hirwaun Dualling Section 7 – Hirwaun to
Historic boreholes (1965) BH93A, BH94A and BH95A) Baverstock, Scheme Proposals and
Exploratory Hole Location Drawings,
West Arch Abutment: Historic boreholes (1965) Drawing No. BTI015586/11/170.
BH93A, BH94A and BH95A
iii) Babtie Group (2000), A465 Abergavenny to
West End Abutment and Pier Support No. 1: Historic Hirwaun Dualling, Interpretative Report
boreholes (1965) BH93A & B, BH94A and BH95A & B on Preliminary Ground Investigation,
Cardiff, Report No. BTI.015586/D4/118.
Proposed Structure:
The current proposal is that the existing viaduct which crosses over the Nant Hir Reservoir is to be retained
and a new structure is to be built to the north. The current structure is a reinforced concrete arch structure
with a seventeen span continuous reinforced concrete deck slab, which is supported at the ends by
reinforced concrete skeletal type abutments (Atkins, 2011). The sixteen intermediate supports are reinforced
concrete piers comprising a crosshead member and a pair of rectangular columns.
The new structure is proposed to be a reinforced concrete arch bridge, similar to the existing bridge. The
pier supports are numbered 1 to 16 from west to east and supported at its ends by concrete abutments.
Piers 4 to 13 are founded on a pair of reinforced concrete arches, which itself is supported by arch
abutments on both sides (West Arch Abutment and East Arch Abutment). Piers 2 and 3 are supported
directly on the West Arch Abutment and similarly Pier 14 and 15 on the East Arch Abutment. Piers 1 and 16
are supported on individual pile caps.
The proposed width of the bridge is 15.8 m and the length of the bridge (between the centre of piers 3 and
14) is 56.1 m.
1-7
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Section 5 & 6 Heads of the Valleys Dualling Rev: 0 Sheet No: GAS/SE018
Page 2 of 7
Structure Name: Nant Hir Viaduct Date: April 2017
Prepared: SN Checked: HM/CR Reviewed: AD Job No: B2191100
Top of Stratum
Elevation Depth to top Thickness (m)
Stratum (m AOD) of stratum Description
(m bgl)
Min Max Min Max
Medium dense, slightly clayey
silty sandy (fine to medium) fine
Made Ground
(1) 279.4 0.00 0.00 1.50 to coarse angular to subangular
(Granular)
GRAVEL and cobbles of clinker,
ash, sandstone and brick
0.7m thick soft brown silty CLAY
cobbles and boulders with some
organic material recorded in the
Glacial Till historic boreholes
(2) 274.3 277.9 0.00 – 1.50 4.2 6.40
(Cohesive)
Firm to very stiff slightly sandy,
silty CLAY with occasional
gravel, cobbles and boulders
Weathered
Grey laminated weathered
Bishopston
270.1 272.0 4.2 - 5.5 0.0 2.0 SHALE with small bands of
Mudstone
(3) brown clay
Formation
Interbedded very weak to
moderately weak, dark grey,
thinly bedded, slightly weathered
Bishopston > 19.9 SILTSTONE and grey, thinly
>0.9
Mudstone 269.8 271.5 4.3 – 7.90 Not bedded very weak to moderately
Formation proven weak MUDSTONE with grey,
fine to coarse grained, thinly
bedded strong to moderately
strong SANDSTONE layers.
Notes: (1) Only encountered in 3/BH132
(2) A 1 m thick layer of gravel occurs at 6.8mbgl (272.6 m AOD) within the glacial till in 3/BH132.
(3) Encountered in 3/BH133 and historic borehole BH102E
2-7
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Section 5 & 6 Heads of the Valleys Dualling Rev: 0 Sheet No: GAS/SE018
Page 3 of 7
Structure Name: Nant Hir Viaduct Date: April 2017
Prepared: SN Checked: HM/CR Reviewed: AD Job No: B2191100
Top of Stratum
Elevation Depth to top Thickness (m)
Stratum (m AOD) of stratum Description
(m bgl)
Min Max Min Max
Soft brown silty clay with traces
(1)
Topsoil 267.6 273.5 0.0 0.0 1.1 of shale and some organic
matter
Soft to firm brown CLAY with
Glacial Till
(2) 262.7 274.5 0.0 0.0 6.4 cobbles and boulders (locally
(Cohesive)
sandy)
Hard laminated blue-grey
Weathered
weathered SHALE and
Bishopston
262.2 270.6 0.0 - 6.3 0.0 5.0 MUDSTONE oxidised yellow
Mudstone
brown with small bands of stiff
Formation clay
Laminated dark grey slightly
Bishopston weathered MUDSTONE with
Mudstone 260.4 268.3 1.8 - 6.4 >9 >17.7 bands of SILTSTONE overlying
Formation medium to coarse grey
SANDSTONE
Notes: (1) Encountered in BH102B, BH102C, and BH102D
(2) Encountered in BH103A, BH103D, BH104A, and BH104D. BH103A and BH104A are located west of the
proposed arch abutment location.
West Arch Abutment (Historic boreholes (1965) BH93A, BH94A and BH95A)
Existing ground level: ≈ 265.0m AOD to 271.7m AOD (from topographic survey at approximate location of
proposed west arch abutment, east to west respectively)
Top of Stratum
Elevation Depth to top Thickness (m)
Stratum (m AOD) of stratum Description
(m bgl)
Min Max Min Max
Weathered Weathered grey SHALE with
Bishopston small partings of firm brown clay
266.3 266.8 0.0 0.0 3.7
Mudstone and weathered grey-brown
Formation SILTSTONE
Bishopston Interbedded grey SILTSTONE
Mudstone 261.5 265.3 0.0 - 3.7 >8.5 >10.7 and SANDSTONE with thin
Formation bands of MUDSTONE.
Note: The boreholes are located further south and at a lower elevation than the proposed abutment location.
It is anticipated the ground conditions are similar at the abutment location but elevations of the top of the
strata interfaces are anticipated to be slightly higher beneath the proposed abutment.
3-7
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Section 5 & 6 Heads of the Valleys Dualling Rev: 0 Sheet No: GAS/SE018
Page 4 of 7
Structure Name: Nant Hir Viaduct Date: April 2017
Prepared: SN Checked: HM/CR Reviewed: AD Job No: B2191100
West Abutment and Pier No. 1 (Historic boreholes (1965) BH93A & B, BH94A and BH95A & B)
Existing ground level: ≈ 273.8m AOD to 271.5m AOD (from topographic survey at approximate locations
of proposed west end abutment and support No. 1, respectively)
Top of Stratum
Elevation Depth to top Thickness (m)
Stratum (m AOD) of stratum Description
(m bgl)
Min Max Min Max
(1)
Topsoil 272.2 0.0 0.0 0.2 Topsoil
Groundwater:
At the east abutment location, a standing groundwater level was noted at 1.5mbgl (277.9m AOD) in
3/BH132 and 1.80mbgl (272.5m AOD) in 3/BH133 following overnight seepages. A standpipe piezometer
was installed in 3/BH132 with a response zone between 6.8mbgl (272.6m AOD) and 9.0mbgl (270.4m
AOD). The highest groundwater level recorded within the piezometer was 7.6mbgl (271.8m AOD) on
02/07/1997.
Standing groundwater was recorded at 3.7m bgl (268.8m AOD) in 3/BH135 (which is located further west of
the west end abutment) following an overnight seepage.
4-7
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Section 5 & 6 Heads of the Valleys Dualling Rev: 0 Sheet No: GAS/SE018
Page 5 of 7
Structure Name: Nant Hir Viaduct Date: April 2017
Prepared: SN Checked: HM/CR Reviewed: AD Job No: B2191100
’
Stratum Angle of cu mv E
γ b, Cohesion,
3 2 Friction,
(Mg/m ) cp’, (kN/m ) 2 2
φp’, ° (kN/m ) (m /MN) (MPa)
100 20 (between
(between ground level and
ground 2 m bgl)
Made Ground
level & 2 m
(Cohesive and 2.0 0 32 0.1
bgl)
Granular)
150 (below 30 (below 2 m
2 m bgl) bgl)
10
Foundation Considerations:
Arch Abutments
At the location of the east and west arch abutments, competent bedrock is expected at an elevation of 260
m and 261 m AOD respectively. The estimated total maximum load to be applied to the arch foundation is
10,460 kN. Drawing 2191100-JAC-SBR-DE-SE-1600-1500 suggests a 15.8 m by 10.2 m pad foundation at
2
the arch abutments. Assuming these pad dimensions, the total load applied to the pad will be 65kN/m . The
suggested allowable bearing capacity of the bedrock, based on Tomlinson’s (2001) values for foundations in
2
Sandstone and Siltstone is of the order of 1000 kN/m .
The depth to foundation level (~260 m AOD) varies between 4 m and 11m below existing ground level and
will require excavation within the rock. The Sandstone associated with the Bishopston Mudstone in this
area, recorded UCS values in the order of 98 MPa. Excavation within the Sandstone is therefore anticipated
to be difficult, probably requiring pre-splitting and chemical jacking.
5-7
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Section 5 & 6 Heads of the Valleys Dualling Rev: 0 Sheet No: GAS/SE018
Page 6 of 7
Structure Name: Nant Hir Viaduct Date: April 2017
Prepared: SN Checked: HM/CR Reviewed: AD Job No: B2191100
Founding Footing
Structure Founding Allowable Bearing Pressure
Level Size 2
Element Stratum kN/m
(mAOD) (m x m)
Bishopston
East Arch
Mudstone 260 15.8 x 10.2 1000
Abutment
Formation
Bishopston
West Arch
Mudstone 260 15.8 x 10.2 1000
Abutment
Formation
Expected Toe
Pile
Structure Founding Bedrock Level
Pile Width Length
Element Stratum Level (m (1) Load per pile (kN)
(m) (m)
AOD)
(1)
East End
Bishopston
Abutment
Mudstone 270 268 0.6 8 140
(single row of 9
Formation
piles)
Pier Support Bishopston
No 16 (single Mudstone 270 268 0.6 7 140
row of 9 piles) Formation
Buried Concrete:
Chemical testing for aggressive ground conditions for buried concrete structures was not undertaken on
samples collected from these exploratory holes as part of the preliminary ground investigation. It is therefore
anticipated that Aggressive Chemical Environment for Concrete AC-2z conditions in accordance with BRE
Special Digest 1: Concrete in Aggressive Ground (2005) and Design Sulfate class DS-1 are considered
6-7
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Section 5 & 6 Heads of the Valleys Dualling Rev: 0 Sheet No: GAS/SE018
Page 7 of 7
Structure Name: Nant Hir Viaduct Date: April 2017
Prepared: SN Checked: HM/CR Reviewed: AD Job No: B2191100
applicable for design. These correspond with the conditions assessed from chemical tests on samples
collected across the whole route of section 6.
Construction Issues:
The existing traffic flows will have to be maintained during the construction works.
The control of localised groundwater, if encountered, will also have to be addressed by the Contractor.
Any deep excavation for foundations adjacent to the existing foundation could potentially damage the
existing foundations, especially where rock has to be excavated or ripped.
Conclusions and Recommendations:
Piled foundations, socketed into the bedrock are considered the most appropriate design option beneath the
abutments and piers. Pad foundations are considered beneath the arch abutments.
Further ground investigation should be carried out at the proposed location of the abutments to confirm the
location and nature of the bedrock.
Design Sulfate DS-1 and ACEC AC-2z (BRE Special Digest 1, 2005) have been assumed for concrete
design for buried structures. Further testing in this area is recommended to confirm this assumption.
7-7
Geotechnical Design Report Volume 2: Structures
B2191100/D2/1/2/059
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Heads of the Valleys Dualling Rev: 0 Calc No: GAS/0014/Rev
0
Page 1 of 4
Structure Name: Nant Moel Reservoir Underpass Date: September 2016
Prepared: SN Checked: HM/CR Reviewed: AD Job No: B2191100
Chainage: 6350m
Exploratory Holes: References:
i. Babtie Group (2000) A465 Abergavenny
to Hirwaun Dualling Section 7 – Hirwaun
3/BH136, 3/BH137, 3/BH138 to Baverstock, Scheme Proposals and
Exploratory Hole, Location Drawings,
Drawing No. BTI015586/11/170,
Proposed Structure:
The current proposal is to demolish the existing Nant Moel Access overbridge and construct a
reinforced concrete box underpass slightly north east to the existing structure. The underbridge is
proposed to be 34 m long and 6 m wide.
Ground Level
Depth to
Elevation Thickness (m)
top of
Stratum (m AOD) Description
stratum
Min Max (m bgl) Min Max
Groundwater:
In exploratory hole 3/BH137, seepage was encountered at 5.0mbgl (255.2m AOD) during the
drilling operations, although no rise was recorded. However, standing groundwater level at
2.5mbgl (257.7m AOD) was recorded early next morning. A standpipe piezometer was installed in
with a response zone between 5.5m (254.7m AOD) and 8.0m (252.2m AOD) below the existing
ground level. The highest recorded water level was collected from water level monitoring
(27/06/1997) at 3.4mbgl (256.8 m AOD).
In exploratory hole 3/BH138, groundwater was recorded at 1.35mbgl (256.6m AOD) following an
overnight seepage when the borehole had advanced to sandstone at 6.5m depth.
In exploratory hole 3/BH136, groundwater was recorded at 5 m bgl (265.4 m AOD) which rose to
4.5 m bgl (265.9 m AOD) within twenty minutes. It was also encountered at 8.4 m bgl (262 m
AOD) which rose to 6.6 m bgl (263.8 m AOD) within twenty minutes.
15
75 0.03 (0 to
2m bgl)
Glacial Till 15 + 16z (z
2.1 2 32 75 + 75z (z =
(Cohesive) = metres
metres below 0.13 (below
below 6.5m
6.5m bgl) 2m bgl)
bgl)
30
30 + 18 z (
Glacial Till
2 - 35 - - where z =
(Granular)
metres
below 5 m
bgl)
Bulk E’
UCS
Material density
GSI mi D
Type (MPa)
3 (MPa)
(Mg/m )
Bishopston
Mudstone
2.6 50 50 15 0.7 1500
Formation -
Sandstone
Bishopston
Mudstone
2.6 6 (*) 35 8 0.7 200
Formation -
Mudstone
Note : (*) A lower UCS value for Mudstone has been selected for this site based on the results in a nearby borehole
3/BH131.
Foundation Considerations:
As the bedrock is anticipated at shallow depths from the underpass road level, it is proposed that
the foundations are placed on bedrock. It is anticipated the bedrock will be encountered at
approximately 256 m AOD (which is approximately 6 to 8 m below existing ground level and
approximately the same level as the proposed underpass road level). The estimated maximum
load to be applied to the structure foundation is 22310 kN which for a 34 m by 6 m concrete box
becomes 110 kN/m2. The safe bearing capacity for a strip foundation in Mudstone (weakest
material compared to Sandstone and Siltstone) is estimated as 1000 kN/m2. Settlement is
expected to be negligible in bedrock.
Buried Concrete:
Chemical testing for aggressive ground conditions for buried concrete structures was undertaken
on two samples collected from two exploratory holes as part of the preliminary ground
investigation: one groundwater sample collected from within the glacial till in 3/BH137 and one
soil sample collected from within the glacial till in 3/BH138. The results indicate Aggressive
Chemical Environment for Concrete ACEC-2z conditions in accordance with BRE Special Digest
1: Concrete in Aggressive Ground (2005) and Design Sulfate class DS-1. These correspond with
the conditions anticipated across the whole route of section 6 and therefore the values are
recommended for design.
Construction Issues:
It should be noted that cohesive glacial till is susceptible to ‘Wetting-up’ upon exposure leading to
softening and therefore, any formation in cohesive glacial till, if wetted up, may have lower
undrained shear strength than anticipated. Any soft material (undrained shear strength less than
40 kN/m2) such as peat traces should be excavated.
The traffic of the existing reservoir overbridge will have to be temporarily diverted during the
construction of the bridge and associated earthworks.
Conclusions and Recommendations:
Foundations are proposed to be founded within the bedrock as they are anticipated at shallow
depths to the proposed underpass level.
Further ground investigations, such as additional boreholes, are recommended at the proposed
location to confirm the location and nature of the bedrock at the site location.
Design Sulfate DS-1 and ACEC AC-2z (BRE Special Digest 1, 2005) have been assumed for
concrete design for buried structures. Further chemical testing in this area is recommended to
confirm this assumption.
B2191100/D2/1/2/059
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Heads of the Valleys Dualling Rev: 0 Sheet No: GAS/0013/R0
Page 1 of 6
Structure Name: Nant Melyn Viaduct Date: March 2017
Prepared: SN Checked: AD Reviewed: AD Job No: B2191100
Proposed Structure
The current proposal is to demolish the existing viaduct and replace it with a new single span
deck structure comprising reinforced concrete slabs, which is offline (south) from the original
A465 carriageway alignment. The proposed structure is 100 m long, 50 m wide at the eastern
end, 60 m wide at the western end and is anticipated to be fixed at the eastern end. Information
regarding the existing structure can be found in the Atkins report (2011).
The proposed carriageway level is approximately 217.60 m AOD and 212.15 m AOD at the east
and west abutments respectively.
Top of stratum
Depth to top
Elevation Thickness (m)
Stratum of stratum Description
(m AOD)
(m bgl)
Stiff, slightly silty CLAY with
Glacial Till occasional gravel and
204.87 0.00 1.05
(Cohesive) cobbles of sandstone,
siltstone and mudstone
Slightly weathered, strong
SANDSTONE underlain by
slightly weathered,
moderately strong
Bishopston
SILTSTONE, underlain by
Mudstone 203.82 1.05 > 19.00
moderately strong, locally
Formation
moderately weak
MUDSTONE containing
nodules and bands of
ironstone (from 12.0mbgl).
Note: The mudstone contained nodules and bands of ironstone below 12.0 m (192.9 m AOD) and
20% flush returns is noted throughout the length of 3/BH142). The rock mass however, does not
appear to be highly fractured and there is no evidence of mineworkings beneath this abutment.
The top of the bedrock is anticipated to be weathered at its upper boundary with the overlying
Glacial Till. The vertical extent of the weathering is unknown due to the lack of detailed information
of this boundary.
Top of stratum
Depth to top Thickness
Elevation
Stratum of stratum (m) Description
(m AOD)
(m bgl)
Min Max Min Max
Groundwater
At the east abutment location, groundwater was encountered in the form of overnight seepage
from the bedrock into 3/BH142, with a recorded level of 3.0 mbgl (201.87 m AOD).
At the west abutment location, an overnight seepage from the bedrock into 3/BH144A was noted
with a groundwater level recorded at 13.9 mbgl (199.3 m AOD). A piezometer was installed in the
borehole with a response zone between 10.0 mbgl (203.2 m AOD) and 14.5 mbgl (198.70 m
AOD). The highest standing water level recorded was 7.33 mbgl (205.63m AOD) on 26/06/1997.
The Nant Melyn (river) is located beneath the viaduct and therefore groundwater is anticipated to
be encountered close to ground surface towards the river.
Angle of cu mv E’
Cohesion,
Stratum 3 Friction,
γb,(Mg/m ) cp’, (kN/m2) (kN/m2) (m2/MN)
φp’, ° (MPa)
20
20 + 3z
Glacial Till
0.1 (z = metres
(Cohesive) 2.1 2 32
(1) below
150
5.0m.bgl)
30
30 + 17z
Glacial Till
2.0 0 36 - - (z = metres
(Granular)
below
5.0m.bgl)
Bedrock γb UCS
3 GSI mi D E’ (MPa)
Parameters (Mg/m ) (MPa)
Bishopston
Mudstone FM - 2.60 50 50 15 0.7 1500
Sandstone
Bishopston
Mudstone FM - 2.60 13 35 8 0.7 200
Mudstone
Note: (1) This parameter for glacial till (cohesive) has been modified from the global GIR values in
order to reflect the log descriptions and in situ testing of borehole 3/BH144 at the location of the
west abutment where foundations within the glacial till may be considered.
Foundation Considerations
Spread foundations are considered an appropriate design option for the east abutment and piled
foundations for the west abutment. It is anticipated that the abutments will be founded on
bedrock. Details of the foundations at each location are given below.
East Abutment
It is proposed that pad foundations are founded directly on the bedrock at approximately 203.7 m
AOD (1.2 m below existing ground level). The estimated total maximum load to be applied to the
structure foundation is 61650.6 kN. Assuming a 50.0 m by 4.0 m spread footing (based on the
50.0 m width of the bridge at the abutment location the total unfactored bearing pressure from the
2
loading is 310 kN/m . This is well within the allowable bearing capacity of the sandstone
(Bishopston Mudstone Formation) as the suggested allowable bearing capacity of the bedrock,
based on Tomlinson’s (2001) values for foundations in Sandstone, is in the order of 10000 kN/m2.
Settlement is anticipated to be less than 5 mm.
West Abutment
Existing ground level at the proposed abutment location is approximately 212.2 m AOD (at the
centreline). Possible foundation options are either spread foundations founded within the
cohesive glacial till or piled foundations socketed into the bedrock.
For spread foundations, if the foundation level is assumed at 2.0 m ground level (approximately
210.2 m AOD) then the abutment will be founded on stiff clay (glacial till). The safe bearing
2
capacity for the glacial till at 2.0 mbgl is estimated as 340 kN/m (based on undrained shear
2
strength of 150 kN/m and a factor of safety of 3). The estimated total maximum load to be
applied to the structure foundation is 61650.6kN. Assuming a 60 m by 4 m spread footing (based
on the 60m width of the bridge at the abutment location), the total unfactored bearing pressure
from the loading is 260 kN/m2. This is less than the bearing capacity of the cohesive glacial till.
However, predicted settlement at this location is between 25 mm and 30 mm. Within the cohesive
materials, half of the total settlements are expected to be completed soon after construction.
Differential settlement is the main issue with this spread foundation option as the predicted
settlement of 25 mm to 30 mm at this abutment is far greater than the predicted values of <5 mm
at the east abutment. This would be unsuitable for the structure. It is therefore proposed that this
abutment is founded directly onto the bedrock (anticipated at approximately at 205.4 m AOD,
corresponding with approximately 8.0 m below existing ground level). Founding on the bedrock
would also reduce the differential settlement between the abutments supports. Due to the extent
of glacial till anticipated beneath the abutment, piled foundations are considered an appropriate
design option.
Competent bedrock is anticipated at approximately 205.4 m AOD (approximately 6.8 m bgl at
location of the proposed abutment) corresponding with the strong sandstone of the Bishopston
Mudstone Formation. The estimated total maximum load to be applied to the structure foundation
is 61650.6 kN. Assuming a pile group of 43 no. of piles at this abutment (22 pile for the inner row
and 21 for the outer row, based Drawing No.2191100-JAC-SBR-DE-SE-1600-1300), the total
load per pile is 1433 kN. Assuming a 0.9m diameter piles socketed 3.0 m into the bedrock, the
anticipated safe working load is 1695 kN per pile, with an approximate toe elevation of 202 m
AOD. This corresponds with a pile length of approximately 10.0 m. Settlement of the piles is
anticipated to be less than 10 mm.
Buried Concrete
Chemical testing for aggressive ground conditions for buried concrete structures was undertaken
on three samples as part of the preliminary ground investigation: two samples from within the
topsoil and glacial till in 3/BH143 and one sample from the glacial till in 3/BH144. The results
indicate Aggressive Chemical Environment for Concrete ACEC-2z conditions in accordance with
BRE Special Digest 1: Concrete in Aggressive Ground (2005) and Design Sulfate class DS-1.
These correspond with the conditions assessed from chemical tests on samples collected across
the whole route of section 6 and therefore the values are recommended for design.
Construction Issues
It should be noted that glacial till is susceptible to ‘Wetting-up’ leading to softening and therefore,
any formation in the cohesive glacial till, if wetted up, may have lower undrained shear strengths
than anticipated.
Zones of localised core loss and highly fractured rock, together with some loss of flush returns
were recorded in exploratory holes 3/BH143A and 3/BH144A (near the west abutment)
suggesting there may be evidence of voids or mineworkings. However no mineworkings are
indicated near the structure location from existing information. It is also unlikely they may be
present beneath the structure foundations because the Bishopston Mudstone Formation occurs
stratigraphically below the Lower Coal Measures and the ‘Farewell Rock’ (as previously
discussed) therefore coal seams are unlikely to be encountered. The coal seams and ironstone
layers/nodules encountered were also not identified on any geological/mining maps. It is possible
that the zones of localised core loss and highly fractured rock may be related to drilling
disturbance.
B2191100/D2/1/2/059
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Heads of the Valleys Dualling – Section 5 & 6 Rev: 0 Calc No: GAS/0011/R0
Structure Name: Croesbychan Junction Bridge Date: August 2016
Prepared: SM Checked: CR Reviewed: AD Job No: B2191100
Chainage: 5087m
Exploratory Holes: References:
i. Babtie Group (2000) A465 Abergavenny
3/BH145, and 3/BH146 to Hirwaun Dualling Section 7 – Hirwaun
to Baverstock, Scheme Proposals and
Exploratory Hole Location Drawings,
Drawing No. BTI015586/11/171,
Proposed Structure:
The current proposal is to construct a new single span integral underbridge with precast beams.
The structure is proposed to be 33m long and 16m wide.
Ground Level
Elevation Depth to top Thickness (m)
Stratum (m AOD) of stratum Description
(m bgl)
Min Max Min Max
Soft to firm yellow brown
Possible slightly clayey sandy (fine to
solifluction 195.7 0 0 1.8 medium) SILT with a little
deposits (1) fine to medium subrounded
gravel
Firm slightly silty sandy CLAY
Glacial Till with a little fine to coarse
(Cohesive) 193.9 205.8 0 to 1.8 5.7 8.6 angular to subrounded gravel
(2)
of sandstone. Very stiff from
4 m bgl (191.7 m AOD).
Possible
Highly
Not proven Recovered as very stiff
Weathered
(Borehole slightly silty CLAY and
bedrock - 188.16 197.2 7.5 to 8.6
terminated at GRAVEL of weathered
(Bishopston
10.2 m bgl) siltstone.
Mudstone
Formation)
Notes:
(1) Encountered only in 3/BH146, and also in 3/BH147 which is further west of the structure.
(2) In addition to the cohesive glacial till, granular glacial till was encountered in shallow
thicknesses in the boreholes. Granular glacial till was encountered in 3/BH145 at depths
between 5 to 5.7 m bgl (200.8 to 200.1 m AOD) as GRAVEL and in 3/BH146 at depths
between 1.75 to 1.85 m bgl (193.9 to 193.5 m AOD) as loose to medium dense SAND.
Groundwater:
Groundwater was encountered in 3/BH145 at 5 mbgl (200.8m AOD) and rose to 3.40m bgl
(202.4m AOD) in 20 minutes. Groundwater was also struck in 3/BH146 at 3.50mbgl (192.2m
AOD) and rose to 3.40mbgl (192.3m AOD) in 20minutes. A piezometer installed in 3/BH146 with a
response zone of 6.5 m to 8 m bgl , recorded the highest groundwater level as 3.3 m bgl (192.3 m
AOD).
Foundation Considerations:
The estimated maximum total load to be applied per abutment is 21620 kN. Assuming a pile
group of twenty six per abutment (13 by 2, as suggested by Drawing 2191100-JAC-SBR-DE-SE-
1600-1100), the total load per pile is 835 kN. However, as the underpass is an integral structure,
due to the expansion of the deck, it is feasible that much of the load will be applied to one row of
piles with the other row in tension. This therefore increases the load to 1670 kN per pile. Due to
the uncertainty in the bedrock level at this structure, it is conservatively assumed that the
cohesive glacial till parameters extend for the full depth of piling. Assuming 0.9 m diameter piles,
and a pile cut off level of 196 m AOD a minimum pile length of 20 m is required, corresponding
with a toe elevation of 176 mAOD.
Buried Concrete:
Chemical testing for aggressive ground conditions for buried concrete structures was not
undertaken in the two relevant exploratory holes. However, the results across the whole route of
Section 6 indicate Aggressive Chemical Environment for Concrete AC-2z conditions in
accordance with BRE Special Digest 1: Concrete in Aggressive Ground (2005) and Design
Sulfate class DS-1.
Construction Issues:
During the course of construction, groundwater encountered will have to be controlled and the
water disposed of in accordance with Natural Resources Wales guidelines. In addition, exposed
glacial till is susceptible to ‘Wetting-up’ upon exposure and therefore, any formation in glacial till, if
wetted up, may have lower undrained shear strength than anticipated.
The construction of the foundations will have to be carried out in phases so that the existing flow
of traffic can be maintained on the A465 carriageway.
B2191100/D2/1/2/059
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Heads of the Valleys Dualling Rev: 0 Calc No: GAS/0010/R0
Structure Name: Court Lodge Underbridge Date: July 2016
Prepared: SN Checked: CR Reviewed: AD Job No: B2191100
Chainage: 4661m
Exploratory Holes: References:
i. Babtie Group (2000) A465 Abergavenny
3/BH150, 3/BH150A and 3/BH149 to Hirwaun Dualling Section 7 – Hirwaun
to Baverstock, Scheme Proposals and
Exploratory Hole Location Drawings,
Drawing No. BTI015586/11/171,
Ground Level
Elevation Depth to top Thickness (m)
Stratum (m AOD) of stratum Description
(m bgl)
Min Max Min Max
Groundwater
At the location of the northwest abutment, groundwater was struck in 3/BH150 at 4 m bgl (191.0m
AOD) and rose to 3.85m bgl (191.2m AOD) in 35 minutes. The Babtie Interpretative Report
(2000) states that groundwater was also recorded at 3.1m bgl (191.9m AOD) following an
overnight seepage from the glacial till or weathered bedrock in the borehole. Overnight standing
water was also recorded in 3/BH150A at 8 m bgl (187.9 m AOD).
On the southeast side of the route, groundwater was recorded standing at 6.1mbgl (190.23m
AOD) following an overnight seepage from the glacial till into 3/BH149. This rose to 1.3mbgl
(195.03m AOD). It was also noted seeping from the siltstone bedrock with a level of 1.8m bgl
(195.5m AOD) at the end of the drilling operations.
75 20
Glacial Till 75 + 10 z 20 + 3 z
0.1
(Cohesive) 2.1 2 32 (z = (z = metres
metres below 5 m
below 2 bgl)
m bgl)
30
30 + 17z
Glacial Till
2 0 36 - - (z = metres
(Granular) below 5 m
bgl)
Bedrock γb UCS
3 GSI mi D E’ (MPa)
Parameters (Mg/m ) (MPa)
Lower Coal
Measures - 2.50 35 50 15 0.7 1050
Sandstone
Lower Coal
Measures –
2.50 10 35 8 0.7 150
Siltstone or
Mudstone
Foundation Considerations:
Due to the generally lower bearing capacity of the cohesive glacial till and its extent, it is proposed
that this abutment is founded on piles socketed into the bedrock. Bedrock was encountered at
approximately 188m AOD in 3/BH150, corresponding with approximately 7.5m below existing
ground level. However, it is estimated that the bedrock at the structure location will be
encountered approximately at 187m AOD, which is 9 m below existing ground level. The
estimated maximum load to be applied to the structure foundation is 34840kN. Assuming a pile
group of No. 64 per abutment (32 by 2, as suggested by Drawing 2191100-JAC-SBR-DE-SE-
1600-1000) the total load per pile is 550kN. However, as this bridge is an integral bridge, due to
the expansion of the deck, it is feasible that much of the load will be applied to one row of piles
with the other in tension. This therefore increases the load to 1100kN per pile. Assuming 0.6m
diameter piles, a minimum rock socket of 3 m is required, corresponding to a pile length of 7m
and with a toe elevation of 184m AOD (depending on the elevation at which bedrock is
encountered).
Buried Concrete:
Chemical testing for aggressive ground conditions for buried concrete structures was undertaken
on three samples collected from the boreholes at this structure location: two from the glacial till in
3/BH149 and one groundwater sample from within the glacial till in 3/BH150. The results indicate
Aggressive Chemical Environment for Concrete AC-2z conditions in accordance with BRE
Special Digest 1: Concrete in Aggressive Ground (2005) and Design Sulfate class DS-1. This
corresponds with the conditions assessed from chemical tests on samples collected across the
whole route of section 6 and therefore the values are recommended for design.
Construction Issues:
During the course of construction, groundwater will be encountered in superficial deposits. These
will have to be controlled and the water disposed of in accordance with Natural Resources Wales
guidelines. In addition, exposed glacial till formation is susceptible to ‘Wetting-up’ and therefore,
any formation in glacial till, if wetted up, may have lower undrained shear strength than
anticipated.
The construction of the foundations will have to be carried out in phases so that the existing flow
of traffic can be maintained on the A465 carriageway.
B2191100/D2/1/2/059
GEOTECHNICAL SUMMARY INFORMATION
Project: A465 Heads of the Valleys Dualling Rev: 0 Sheet No: GAS/0009/R0
Page 1 of 6
Structure Name: Vale of Neath Railway Bridge Date: March 2017
Prepared: SN Checked: AD Reviewed: AD Job No: B2191100
Proposed Structure:
The current proposal is to demolish the existing bridge and replace it with a new single span
integral deck underbridge structure comprising a pre-stressed beam & slab portal. The new
structure is proposed to be 51.5m long and 25.1m wide with a 17.0m skew span (Drawing No.
2191100-JAC-SBR-DE-SE-1600-0900).
The existing structure is a single span, simply supported, steel beam and reinforced concrete
composite deck (Glamorgan Engineering Consultancy, 2007). The steel beams are cased in
reinforced concrete and reinforced concrete cantilever walls support the bridge deck with cast in
situ concrete pile foundations. The proposed carriageway level is anticipated to vary from 196.0m
AOD to 193.0m AOD from east to west respectively.
East Abutment:
(Ref: Interpreted from 3/BH152, SN/90NE/33A, SN90NE33B, SN90NE33C and Geological long
section)
Existing ground level: ≈ 190.0m AOD (track level beneath bridge is approximately 186.7m
AOD)
Groundwater:
At 3/BH152, groundwater was encountered in the form of seepage from the glacial till at 8.0mbgl
(182.3m AOD). Groundwater level assumed to be at approximately 8.0mbgl (182.3m AOD) for
design purposes. Artesian groundwater was encountered in nearby boreholes 3/BH151 as well as
3/BH154 and therefore further investigation is recommended to quantify the risks to the
construction works.
The ground conditions described above suggest that global parameters from Jacobs GIR, 2016
(given below) are applicable.
Stratum Cohesion, Angle of cu mv E’
γb
3
(Mg/m )
cp’, Friction,
(kN/m2) φp’, ° (kN/m2) (m2/MN) (MPa)
30
Bedrock γb UCS
3 GSI mi D E’ (MPa)
(Mg/m ) (MPa)
Parameters
Lower Coal
2.50 35 50 15 0.7 1050
Measures -
Sandstone
Lower Coal
2.50 10 35 8 0.7 150
Measures -
Mudstone
Foundation Considerations:
Piled foundations are considered the most appropriate design option for the abutments.
The estimated total maximum load to be applied to the structure foundation is 13406kN.
Assuming a pile group of No. 36 per abutment (18 by 2, as suggested by Drawing
2191100-JAC-SBR-DE-SE-1600-0900 the total load per pile is 373kN.
As this bridge is an integral bridge, due to the expansion of the deck, it is feasible that
much of the load will be applied to one row of piles with the other row in tension. For
design, it is assumed that the full loading is carried by one row of piles.
West:
Due to the generally lower bearing capacity of the glacial till (cohesive and granular) and
the extent of the glacial till, it is proposed that this abutment is founded on piles socketed
at least 3.0m into the bedrock.
Bedrock is encountered at approximately 178.3m AOD, corresponding with approximately
12.05m below existing ground level and 8.4m below the ground level of the underlying
railway lines).
Assuming 0.6m diameter piles, a minimum rocket socket of 3.0m is required,
corresponding with pile length of 11.5m and with a toe elevation of 175.0m AOD.
East:
Due to the generally lower bearing capacity of the glacial till (cohesive and granular) and
the extent of the glacial till, it is proposed that this abutment is founded on piles socketed
at least 3.0m into the bedrock.
Bedrock is encountered at approximately 181.0m AOD, corresponding with approximately
9.0m below existing ground level and 5.7m below the ground level of the underlying
railway lines.
Assuming 0.6m diameter piles, a minimum rocket socket of 3.0m is required,
corresponding with pile length of 9.0m and with a toe elevation of 178.0m AOD.
Buried Concrete:
No chemical testing for aggressive ground conditions for buried concrete structures was
undertaken within 3/BH152 as part of the preliminary ground investigation. However chemical
testing was undertaken on three samples collected from exploratory hole 3/BH151 (located
approximately 40m east of the proposed structure): one from within the made ground and two
from within the glacial till.
The results suggest Aggressive Chemical Environment for Concrete AC-2z conditions in
accordance with BRE Special Digest 1: Concrete in Aggressive Ground (2005) and Design
Sulfate class DS-1. These correspond with the conditions assessed from chemical tests on
samples collected across the whole route of section 6 and therefore the values are recommended
for design.
Construction Issues:
The existing traffic flow will have to be maintained during the construction works and the
foundations will have to be constructed in phase.
In addition, exposed cohesive glacial till is susceptible to ‘softening on wetting up and hence
could be an issue for earthworks.
As the underlying bedrock comprises the Lower Coal Measures, there is a possibility for
unrecorded mineworkings or voids being encountered. In light of this, prior to construction, it is
proposed that the ground beneath the proposed foundations should be investigated thoroughly
for condition and the presence of possible mineworkings or voids. Any voids or mineworkings
encountered will be grouted.
Design sulfate DS-1 and ACEC AC-2z (BRE Special Digest 1, 2005) have been estimated for
concrete design for buried structures. Further chemical testing in this area is recommended to
confirm these values.
B2191100/D2/1/2/059
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Heads of the Valleys Dualling Rev: 0 Sheet No: GAS/0950/R0
Page 1 of 6
Structure Name: Vale of Neath Footbridge Date: March 2017
Prepared: SN/LK Checked: CR Reviewed: AD Job No: B2191100
Chainage: 4470 m (About 100m north from the existing A465 carriageway)
Exploratory Holes: References:
i. Babtie Group (2000) A465 Abergavenny to
North abutment: Historic BH 57, 58 and Hirwaun Dualling Section 7 – Hirwaun to
59 (BGS Reference: SN90NE33; Grid Baverstock, Scheme Proposals and Exploratory
Reference : 297320,205500) Hole Location Drawings, Drawing No.
BTI015586/11/171.
South abutment: 3/BH153, 3/BH152 ii. Babtie Group (2000), A465 Abergavenny to
(Exploration Associates Ltd. 1997), Hirwaun Dualling, Interpretative Report on
Historic BH 54 (BGS Reference: Preliminary Ground Investigation, Cardiff, Report
SN90NE33; Grid Reference : No. BTI.015586/D4/118.
297320,205500)
iii. John Laing and Son Limited (1957). Hirwaun-
Abergavenny Trunk Road – Exploratory holes.
Investigation no: SS/399. BGS Reference:
SN90NE33; Grid Reference: 297320,205500.
Note: Due to the limited available
recent exploratory holes at this iv. Exploration Associates Ltd (1997) A465
location, relevant historic boreholes Abergavenny to Hirwaun Dualling Section 3.
have also been used for this structure. Volume Three of Nine, Factual Report on Ground
Investigation. Report No. 166001-3.
v. Glamorgan Engineering Consultancy (2007)
Welsh Assembly Government, A465 Trunk Road,
Principal Inspection Report On: Vale Of Neath
Railway Bridge. Report No. A60150/02/01.
vi. BGS Boreholes
http://mapapps.bgs.ac.uk/geologyofbritain/home.ht
ml
vii. Jacobs (2015) A465 Section 5 and 6 Technical
Advisor Presentation Plan.
viii. Jacobs (2016) A465 Heads of the Valleys Dualling
Sections 5 and 6 Ground Investigation Report.
Report No. B2191100/D2/1/040.
ix. Jacobs (2016) A465 Sections 5 & 6 – Vale of
Neath Railway NMU Footbridge General
Arrangement, Drawing No. 2191100-JAC-SBR-
DE-SE-1600-0950
Proposed Structure
The current proposal is to build a new single span NMU (Non-Motorised User) bridge, which is
100 m north-west of the Vale of Neath bridge, over the existing railway tracks. The new footbridge
is proposed to be approximately 32.9 m long and 3.50 m wide with a 29.4m clear span. This
structure is to be designed for equestrian use and hence it requires a ramp on either side as well
as a minimum headroom of 3.7m. The height of the bridge over the railway tracks is a minimum
of 5.2m as shown on Drawing no. 2191100-JAC-SBR-DE-SE-1600-0950.
Existing Ground Level
North ≈ 193.2 to 193.9 m AOD, South ≈ 189.2 to 189.8 m AOD
The existing ground level for the underlying railway track is approximately 188 to 188.6 m AOD
Top of stratum
Elevation Depth to top of
Stratum (m AOD) stratum Thickness (m) Description
(m bgl)
Min Max
Made
Driller’s description: Black
Ground 186.7 0.15 0.31
Crushed cinder
(Granular)(1)
Glacial Till Firm to stiff sandy grey CLAY
185.8 186.4 0.5 to 0.91 3.2
(Cohesive)(2) with ‘shale fragments’
Laminated weathered
SHALE. From 181.6 m AOD,
it is fine grained grey
Lower Coal Not proven
182.5 183.1 3.7 to 4.3(3) SANDSTONE with thin bands
Measures >6.1
of siltstone, underlain by
laminated grey SILTSTONE
with traces of coal
Notes:
Please note that the above ground information is from historic boreholes, due to unavailable
Exploration Associates borehole at the location, and these historic boreholes are located
approximately 100 m east of the NMU bridge.
(1) Only encountered in Historic Borehole BH 59
(2) Encountered soft to firm light grey clay in Historic Borehole BH 58
(3) The depth to the top of Lower Coal measures increases up to 11m from existing ground level
using the topographic survey results
South Abutment
3/BH153, 3/BH152 (Exploration Associates Ltd. 1997), Historic boreholes BH 52, 54 (BGS
Reference: SN90NE33; Grid Reference: 297320, 205500)
Borehole 3/BH153 is the closest borehole to the South Abutment and is located 70 m south of the
structure. The historic boreholes and 3/BH152 are located approximately 120 m east of the
structure.
Existing ground level: ≈ 189.2 to 189.8 m AOD (from Topographic survey)
Depth to
Top of stratum
top of
Stratum Elevation Thickness (m) Description
stratum
(m AOD)
(m bgl)
Stiff slightly silty slightly
Made sandy (fine to coarse) CLAY
Ground with some fine to coarse
187.9 191.2 0 4.6 to 6.5
(Cohesive) angular to subangular gravel
(1)
of slag and clinker
Very stiff from 5.2 m bgl
Stiff to very stiff slightly silty
slightly sandy CLAY with
some medium to coarse
Glacial Till
subangular to subrounded
(Cohesive) 188 181.4 4.6 to 6.5 5.3
(2) gravel and cobbles of
sandstone, quartzite,
limestone with rare fine
angular gravel of coal
Dark grey thickly laminated to
thinly bedded slightly
weathered MUDSTONE
moderately weak to
Lower Coal moderately strong with
>8
Measures 178.3 183 4 to 12 occasional plant remains.
(3,4) Not proven
From 175 m AOD : grey
thickly laminated to medium
bedded slightly weathered
SILTSTONE moderately
strong.
Note:
Please note that the above ground information is from historic boreholes and Exploration
Associates boreholes that are located far away (approx. 70 to 125 m ) from the structure, due to
unavailable Exploration Associates borehole at the proposed structure location.
(1) From borehole 3/BH153 and historic borehole BH 52
(2) From borehole 3/BH153, historic boreholes BH 52 and BH 54
(3) From borehole 3/BH152, historic boreholes BH 52 and BH 54
(4) Flush returns within the bedrock were recorded as ‘good’ with values of 63% to 80% recorded
towards the top of the bedrock unit and with the majority of values between 92% and 100% at
deeper depths.
Groundwater
Within 3/BH153, groundwater was encountered within the cohesive glacial till at 7.5 m bgl (180.4
m AOD), rising up to 5.7 m bgl (182.2 m AOD) within twenty minutes.
Within 3/BH152, groundwater was encountered in the form of seepage from a layer of granular
glacial till at 8.0mbgl (182.3m AOD). An overnight standing water level of 12.30m bgl (178.0m
AOD) was also recorded the following morning.
Groundwater level in both boreholes is at approximately 182.3m AOD which corresponds to
approximately 9.4 m bgl and 5 m bgl beneath the north and south abutments, respectively.
Therefore, for design purpose, groundwater level was assumed to be at 5 m bgl.
Groundwater information recorded from historic boreholes were not used due to the age of the
borehole and information (collected at the end of November/beginning of December 1957).
Summary of Soil Parameters
The ground conditions described above suggest that global parameters from Jacobs GIR, 2016
are applicable:
Cohesion Angle of cu mv E’
γb
Stratum cp’, Friction,
(Mg/m3)
(kN/m2) φp’, ° (kN/m2) (m2/MN) (MPa)
Made
Ground 50 0.13 7.5
2.0 0 32
(Cohesive/
(1)
Granular)
75 20
Glacial Till
2.0 0 36 - - 30 + 17z
(Granular)
(where z is metres
below 5 m bgl)
γb UCS
Bedrock 3 GSI mi D E’ (MPa)
Parameters (Mg/m ) (MPa)
Lower Coal
2.50 35 50 15 0.7 1050
Measures -
Sandstone
Lower Coal
Measures – 2.50 10 35 8 0.7 150
Mudstone
and Siltstone
(1) Please note that parameters of Made Ground Cohesive have been reduced from the global
parameters due to the uncertainty of the nature of Made Ground at this location.
Foundation Considerations
North abutment
It is estimated that the proposed foundation for the north abutment will be founded on cohesive
glacial till and the foundation level will be approximately 191.65 m AOD. The safe bearing
2
capacity of the cohesive glacial till is estimated at approximately 140 kN/m based on the
description of ‘firm to stiff CLAY’. The maximum estimated load to be applied to the north
abutment foundation is 360 kN. Based on the proposed foundation length of 5 m and width of 2.1
m (Drawing no. 2191100-JAC-DE-SE-1600-0950), the load per foundation area is 35 kN/m2. The
total settlement for the load applied is estimated to be of the order 10 to 15mm.
South abutment
The south abutment is estimated to be founded on either cohesive glacial till or cohesive made
ground and the estimated foundation level is approximately 187.4 m AOD. The safe bearing
capacity is estimated to be at 100 kN/m2. The maximum estimated load, is however slightly higher
than the north abutment, at 385 kN. Based on the same proposed foundation dimensions as the
2
north abutment, the load per foundation area is 40 kN/m . The total settlement for the load
applied is estimated to be of the order 15 to 20 mm.
Buried Concrete
Chemical testing for aggressive ground conditions for buried concrete structures was not
undertaken on samples collected from these exploratory holes as part of the preliminary ground
investigation. Aggressive Chemical Environment for Concrete AC-2z conditions in accordance
with BRE Special Digest 1: Concrete in Aggressive Ground (2005) and Design Sulfate class DS-1
were therefore assumed for buried structures at this location. These correspond with the
conditions assessed from chemical tests on samples collected across the whole route of section
6 and therefore the values are recommended for design. Further chemical testing in the area is
recommended to confirm if these results are applicable.
Construction Issues
It should be noted that glacial till is susceptible to ‘wetting-up’ upon exposure and therefore, may
have lower undrained shear strength than anticipated.
As the underlying bedrock comprises the Lower Coal Measures, there is a possibility for
unrecorded mineworkings or voids being encountered. In light of this, prior to construction, it is
proposed that the ground beneath the proposed foundations should be investigated for the
presence of possible mineworkings or voids. Any voids or mineworkings encountered should be
grouted.
Design sulfate DS-1 and ACEC AC-2z (BRE Special Digest 1, 2005) have been estimated for
concrete design for buried structures. Further chemical testing in this area is recommended to
confirm these values.
B2191100/D2/1/2/059
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Heads of the Valleys Dualling – Section 5 & 6 Rev: 1 Calc No: GAS/0800/R0
Structure Name: Court Farm Underpass Date: June 2017
Prepared: SN Checked: CR / LK Reviewed: AD Job No: B2191100
Chainage: 4140m
Exploratory Holes: References:
3/BH154 i. Babtie Group (2000) A465 Abergavenny
to Hirwaun Dualling Section Exploratory
Hole Location Drawings, Drawing No.
BTI015586/11/172.
1-4
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Heads of the Valleys Dualling – Section 5 & 6 Rev: 1 Calc No: GAS/0800/R0
Structure Name: Court Farm Underpass Date: June 2017
Prepared: SN Checked: CR / LK Reviewed: AD Job No: B2191100
Groundwater:
Groundwater was struck in 3/BH154 at 3.7mbgl (170.3m AOD) and rose to 2.4mbgl (171.6 m
AOD) after 20 minutes. Overnight seepages from the bedrock into this borehole are also noted,
and the highest recorded groundwater level was 0.6m above existing ground level (174.6m AOD)
(artesian conditions).
A piezometer was installed in this exploratory hole with a response zone between 3.0mbgl
(171.0m AOD) and 5.0mbgl (169.0m AOD) within the glacial till. The highest groundwater level
recorded was 0.24mbgl (173.75m AOD).
2-4
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Heads of the Valleys Dualling – Section 5 & 6 Rev: 1 Calc No: GAS/0800/R0
Structure Name: Court Farm Underpass Date: June 2017
Prepared: SN Checked: CR / LK Reviewed: AD Job No: B2191100
Angle of cu mv E’
Bulk density, Cohesion,
Stratum 3 2 Friction,
(Mg/m ) cp’, (kN/m ) 2 2
φp’, ° (kN/m ) (m /MN) (MPa)
Made Ground
2.0 - 32 0.1 20
(Granular)
20
75
20 + 3z
75 + 10 z
Glacial Till
2.1 2 32 0.1 (z =
(Cohesive) (z = metres
metres
below 2 m
below 5 m
bgl)
bgl)
30
30 + 17z
Glacial Till
2.0 - 36 - - (z =
(Granular)
metres
below 5 m
bgl)
Foundation Considerations:
It is not proposed to found the new culvert on the Made Ground. The Made Ground contains
lenses of peat and as such, there would be a risk of adverse differential settlements across the
culvert if this was left in place beneath the culvert. It is suggested that the Made Ground is
excavated and replaced with compacted Class 6N/6P granular fill material. The estimated culvert
2
loading is off the order of 75 kN/m . The safe bearing capacity of the 6N/6P fill material is
estimated to be about 250kN/m . Estimated settlements, under the culvert load of 75 kN/m2 , are
2
3-4
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Heads of the Valleys Dualling – Section 5 & 6 Rev: 1 Calc No: GAS/0800/R0
Structure Name: Court Farm Underpass Date: June 2017
Prepared: SN Checked: CR / LK Reviewed: AD Job No: B2191100
Buried Concrete:
Chemical testing was undertaken on one groundwater sample from within the glacial till as part of
the preliminary ground investigation. The results indicate Aggressive Chemical Environment for
Concrete ACEC-2z conditions in accordance with BRE Special Digest 1: Concrete in Aggressive
Ground (2005) and Design Sulfate class DS-1. These correspond with the conditions assessed
from chemical tests on samples collected across the whole route of section 6 and therefore the
values are recommended for design.
Construction Issues:
The existing structure will have to be supported during the construction phase to stop possible
undermining of the foundations.
Excavation may also encounter groundwater which will need to be controlled. It is not anticipated
that artesian groundwater will be encountered as excavation does not extend beneath the
cohesive Glacial Till deposits.
Conclusions and Recommendations:
It is suggested that Made Ground beneath the proposed culvert is removed and replaced with
compacted granular fill (Class 6N/6P). The allowable bearing capacity of the compacted granular
fill is of the order of 250 kN/m2.
Further ground investigations are recommended along the proposed length of the structure to
confirm the type and condition of the existing foundation and the nature of the founding material.
Further investigation of the artesian groundwater is also recommended to quantify the risks to the
construction works.
Design sulfate DS-1 and ACEC AC-2z (BRE Special Digest 1, 2005) has been assumed for
concrete design for buried structures. Further chemical testing in this area is recommended to
confirm this assumption.
4-4
Geotechnical Design Report Volume 2: Structures
B2191100/D2/1/2/059
GEOTECHNICAL SUMMARY INFORMATION
Project: A465 Heads of the Valleys Dualling Rev: 0 Sheet No: GAS/0007/R1
Structure Name: Afon Cynon Bridge Date: March 2017
Prepared: SN Checked: SM Reviewed: AD Job No: B2191100
Proposed Structure
The current proposal is to replace the existing bridge with a wider reinforced concrete slab
integral bridge. The existing bridge is a 3 span concrete beam and slab structure as detailed by
the Glamorgan Engineering Consultancy report (2007). The proposed replacement structure is a
reinforced concrete integral bridge, 26.1m wide with a 16.7m clear span (17.7m square span) as
shown in Drawing 2191100-JAC-SBR-DE-SE-1600-0700.
Minimum ≈ 167.0m AOD (river banks of the River Cynon at approximate water level, estimated
from topographic survey)
Borehole 3/BH156 is located approximately 10m northeast of the proposed abutment location and
at an elevation approximately 4.0m higher. The following ground profile description below the
abutment location has therefore been estimated from both the historic boreholes 40 – 46 and
borehole 3/BH156, starting from an elevation of 169m AOD (4.0m depth into borehole 3/BH156)
to reflect the ground level at the location of the abutment.
Top of Stratum
Elevation (m Depth to top
Thickness
Stratum AOD) of stratum Description
(m)
(m bgl)
Max Min
Sandy topsoil with fine to coarse gravel
Topsoil 169.0 167.4 0 0 – 1.2
and cobbles
‘Sand and gravel’ (compact, fine to
Glacial Till coarse sand with fine to coarse gravel,
169.0 167.0 0 – 1.2 1.2 - 5.6
(Granular) cobbles and boulders. Some areas are
clayey.)
Firm grey, mottled sandy clay with fine
to coarse gravel of rock fragments
Weathered
(siltstone, mudstone, shale). Also
Lower Coal 166.4 164.4 2.0 – 4.6 0 – 4.6
described as ‘grey shaly siltstone with
Measures
bands of weathering’ and ‘weathered
laminated mudstone’.
Interbedded slightly weathered,
moderately strong laminated
Lower Coal MUDSTONE, slightly weathered, strong
166.4 160.7 1.95 – 7.3 > 10.0
Measures SANDSTONE with some areas of
interbedded SANDSTONE and
SILTSTONE
Note: There are no records of mineworkings in the vicinity of this structure. However, highly
fractured rock strata, frequent zones of core loss, reduced flush returns and a 2.2m band of gravel
occurring from 12.5mbgl to 14.7mbgl (160.5m AOD to 158.3m AOD) were recorded. These could be
associated with drilling disturbance (from ODEX- open hole and rotary drilling methods) or past
unrecorded mining activities. Coal bands were encountered in historic boreholes 43, 44, 45 and 46.
It should also be noted that the ‘Sand and gravel’ driller description given in 3/BH156 may include
some of the weathered bedrock towards the base of the Glacial Till (Granular) stratum. It is also
possible that the ‘Sand and gravel’ recorded is totally fractured/destructed bedrock disturbed by the
drilling processes. Further investigations would be needed to confirm this.
The weathered bedrock level is noted to be just below the river level (167.0m AOD) at this abutment.
Top of Stratum
Elevation Depth to top
Stratum (m AOD) of stratum Thickness (m) Description
(m bgl)
Max Min
(1)
Peat 170.0 0 0 - 0.15 ‘Soft Peat’
Interbeds of ironstone and coal are recorded within the mudstone and siltstone strata respectively;
however there are no records of mineworkings in the vicinity of this structure. These strata are
however highly fractured and zones of core loss are frequently recorded. These could be associated
with drilling disturbance (from ODEX-open hole and rotary drilling methods) or past mining activities
(e.g. unrecorded collapsed mineworkings). Coal bands were encountered in historic boreholes 38
and 40 and borehole 3/BH157.
Groundwater
Near to the east abutment location, an overnight standing water level of 10.1mbgl (163.0m AOD)
was noted in 3/BH156 on reaching 10.2m depth (162.9m AOD). A standpipe was installed in this
borehole with response zone within the glacial till between 1.5m (171.6m AOD) and 10.3mbgl
(162.7m AOD). The highest recorded groundwater level was 5.36mbgl (167.7m AOD).
To the west of the bridge, a slight seepage was noted in 3/BH157 at 7.0mbgl (171.9m AOD)
during the drilling operations within fractured mudstone.
River level is anticipated to be approximately 167.0m AOD.
75 20
75+ 10z 20 + 3z
Glacial Till
2 32 0.1
(Cohesive)
2.10 (z = metres (z = metres
below below
2.0m.bgl) 5.0m.bgl)
30
30 + 17z
Glacial Till
0 36 - - (z = metres
(Granular)
2.00 below
5.0m.bgl)
Bedrock γb UCS
GSI mi D E’ (MPa)
Parameters (Mg/m3) (MPa)
Lower Coal
Measures - 2.50 35 50 15 0.7 1050
Sandstone
Lower Coal
Measures - 2.50 10 35 8 0.7 150
Mudstone
N/B cp’ and φp’ refer to peak cohesion and peak angle of friction respectively.
Foundation Considerations
With bedrock at relatively shallow depth at each abutment, it is considered reasonable to found
the new bridge structure on pad footing bearing on the rock (i.e. similar to the existing bridge).
However, excavation into the hillside to form the foundations could require significant temporary
works to avoid extensive excavations up-the-slope and also to maintain traffic flow on the existing
bridge during the works. On this basis, it may be preferable to adopt piled foundations at each
abutment, with the pile caps formed at a higher elevation, to limit the amount of excavation
required. The piles would be socketed into bedrock.
East Abutment
The top of the weathered bedrock is anticipated to be at about 164m to 166m AOD at this
abutment location (corresponding with approximately 3.0m to 5.0m bgl). The estimated total
maximum load to be applied to the structure foundation is 16600kN. Assuming this total
maximum vertical load and a pad size of say 4m x 30m (estimated from Drawing 2191100-JAC-
SBR-DE-SE-1600-0700), the bearing pressure is estimated to be of the order of 150kN/m2. This
is well within the allowable bearing capacity of the weathered Lower Coal Measures. Settlement is
anticipated to be less than 10mm.
Alternatively, as indicated above, piled foundations socketed into the bedrock are suggested, with
the pile cap constructed at or near existing ground level. Competent bedrock is anticipated at
162.0m AOD (7.0m bgl) corresponding with the ‘moderately strong’ mudstone of the Lower Coal
Measures. Assuming the base of the pile cap is 0.5m bgl (where ground level is 169.0m AOD at
the abutment location), the cut off level (COL) for the pile corresponds with 168.5m AOD.
Assuming a pile group of 26 no. 0.75m diameter piles per abutment (13 by 2, as indicated in
Drawing 2191100-JAC-SBR-DE-SE-1600-0700), the total load per pile would be of the order of
640kN. However, as this bridge is an integral bridge, it is feasible that thermal expansion and
contraction of the deck could result in the entire load being applied to one row of piles, with the
other row being in tension. This therefore increases the potential load per pile to about 1280kN. A
minimum rock socket length of 3.0m is therefore suggested, corresponding to a pile length of
9.5m. However, due to the numerous sections of core loss and low RQD values recorded within
borehole 3/BH156, it is suggested that the pile rock socket is increased to 5.0m, corresponding
with a competent sandstone layer. This gives a pile length of 11.5m (pile toe level at 157.0m
AOD). Settlement of the piles is anticipated to be less than 10mm.
West Abutment
Weathered bedrock is anticipated at or very near ground level (170.0m AOD) to 167.2m AOD
(approximately 2.8m bgl) at this abutment location. On this basis, it would be feasible to support
the bridge on a shallow pad foundation. Based on the anticipated loading (16600 kN) and a 4m x
30m pad, the bearing pressure will be of the order of 150kN/m2 , which is well within the allowable
bearing capacity of the weathered Lower Coal Measures. Settlement is anticipated to be less than
10mm.
Alternatively, piled foundations could be adopted, with the pile cap constructed at or near existing
ground level (assume 0.5m bgl; 169.5m AOD). At the location of the proposed abutment,
competent bedrock is anticipated at about 167m AOD (3.0m bgl) corresponding with the ‘weak’
mudstone and siltstone of the Lower Coal Measures. Assuming a pile group of 26 no. 0.75m
diameter piles per abutment (13 by 2, as indicated in Drawing 2191100-JAC-SBR-DE-SE-1600-
0700), the total load per pile would be of the order of 640kN. However, as indicate above, this
could increase to about 1280kN due to the bridge deck being cast integral with the abutments. A
minimum rock socket length of 3.0m is therefore suggested, corresponding with a pile length of
5.5m (pile toe at 164m AOD). At this depth however, the rock is described as very weak to weak,
with RQD values of zero. It is therefore suggested that the rock socket is extended to 161.5m
AOD (8.0m long pile), to found in the moderately strong sandstone beneath the fractured layers.
Settlement of the piles is anticipated to be less than 10mm.
Buried Concrete
Chemical testing was undertaken on one sample from 3/BH157 within the bedrock as part of the
preliminary ground investigation. The results indicate Aggressive Chemical Environment for
Concrete AC-2z conditions in accordance with BRE Special Digest 1: Concrete in Aggressive
Ground (2005) and Design Sulfate Class DS-1. These correspond with the conditions assessed
from chemical tests on samples collected across the whole route of section 6 and therefore these
values are recommended for design.
Construction Issues
Mineworkings or voids are potentially present. Prior to construction, it is proposed that the ground
beneath the abutments will be probed and any voids encountered will be grouted.
To the south of the west abutment, a small spring within the bedrock outcrop was observed
during a site visit. The control and disposal of groundwater will have to be addressed by the
Contractor.
The site of the structure is within a floodplain and therefore a number of environmental issues and
concerns surround further development of the site.
B2191100/D2/1/2/059
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Heads of the Valleys Dualling – Section 5 & 6 Rev: 0 Calc No: GAS/0006/R0
Structure Name: Pentwyn Cynon (Tramway) Footbridge Date: August 2016
Prepared: SN Checked: CR Reviewed: AD Job No: B2191100
Chainage: 3525m
Exploratory Holes: References:
3/BH159, 3/BH159A, 3/BH159B, 3/BH159BR, i. Babtie Group (2000) A465 Abergavenny
3/BH159C and 3/BH160 to Hirwaun Dualling Section 7 – Hirwaun
to Baverstock, Scheme Proposals and
Exploratory Hole Location Drawings,
Drawing No. BTI015586/11/172.
31m span warren truss, with steel ramps to the north and earth ramps to the south. The southern
side of the bridge will be resting on SWALEC Pylon secant retaining wall.
The existing structure comprises an in situ reinforced concrete continuous beam and slab bridge
deck comprising a single span with two end cantilevers (Glamorgan Engineering Consultancy,
2005). The deck cantilevers support running-on and running-off slabs. There are curtain walls
suspended from the outer ends of the cantilevers. The bridge deck is supported by stem and
column piers. The existing structure has a central skew span of 15.85m with end cantilevers of
6.1m and a carriageway width of 10.06m (three lanes).
Ground Level:
Existing Ground Level ≈ 183.66m AOD to 190.91m AOD (relevant exploratory holes located at
the locations of the proposed abutments, north and south abutments respectively)
The proposed carriageway level is 183.8 (northern side) to 183m AOD (southern side) and the
underside level of the footbridge is approximately 189 m AOD.
Interbedded slightly
Lower Coal 6.80 to
177.91 179.17 7.6 >13.20 weathered MUDSTONE
Measures (3) 11.50
weak to moderately weak
with occasional carbonised
plant remains,
SANDSTONE strong and
SILTSTONE moderately
strong to strong.
Note: (1) Encountered in 3/BH159, 3/BH159A and 3/BH159B
(2)
Encountered only in 3/BH160
(3)
Encountered in 3/BH159C and 3/BH160
(4)
Open hole techniques were used in 3/BH159BR and C through the superficial deposits and
through the weathered bedrock in 3/BH160. The ground description and strata boundaries are
therefore uncertain at this location.
All strata encountered are generally highly fractured and zones of core loss and/or loss of flush
returns are frequently recorded.
As the underlying bedrock comprises the Lower Coal Measures, there is a possibility for
unrecorded mineworkings or voids being encountered. In light of this, prior to construction, it is
proposed that the ground beneath the foundations should be investigated for the presence of
possible mineworkings or voids. Any voids or mineworkings encountered should be grouted.
Groundwater:
Groundwater was encountered in 3/BH159 at 1.2 m bgl (182.5 m AOD) which rose to 1.15 m bgl
(182.5 m AOD) within twenty minutes. Groundwater is recorded standing at 185.0m AOD in
3/BH159B, which corresponds with ground level, following an overnight seepage from the made
ground/glacial till interface. Artesian water was also noted in 3/BH159C within the bedrock.
Cohesion Angle of cu mv E’
γb,
Stratum , cp’, Friction,
(Mg/m3)
(kN/m )
2
φp’, ° (kN/m2) (m2/MN) (MPa)
20 (between ground
Made Ground (1) level and 2 m bgl)
2.0 2 32 40 0.1
(Cohesive) (1)
30 (below 2 m bgl)
30
30
E’
Bedrock γb, UCS
GSI mi D
Parameters (Mg/m3) (MPa)
(MPa)
Lower Coal
Measures - 2.5 10 35 8 0.7 150
Mudstone
Note : The parameters for Made Ground cohesive and Made Ground granular are modified from
the GIR values to reflect the borehole description at the bridge location.
Foundation Considerations:
Abutments
North
On the northern side, two piers from the footbridge are founded on a base with dimensions of 4.5
m length, 1.5 m width and 0.5 m deep. The maximum anticipated load is 125 kN/m2 based on the
previously mentioned foundation dimension. The existing ground level on the northern side is
185.5 m AOD and the proposed carriageway level is 183.8 m AOD. From the drawing 2191100-
JAC-SBR-DE-SE-1600-0600, it is understood that the base is to be buried underneath the side
slope of the proposed carriageway cutting, at approximately 183.3 m AOD. If the base is founded
at 183.3 m AOD, it will be within either granular Made Ground or granular Glacial Till and the
bedrock is anticipated to be at 179.2 m AOD which is approximately 6.3 m below the existing
ground level and 4.6 m below the proposed carriageway level. Based on the previously
mentioned foundation dimensions, a safe bearing capacity of 190 kN/m2 is estimated for granular
glacial till. For an applied loading of 125 kN/m2, estimated settlements are anticipated to be of the
order 20-25mm.
South
The southern side of the bridge will be founded on SWALEC Pylon Retaining Wall which is a
secant piled wall. A minimum rock socket length of 1m is required to support the vertical loading
from the bridge. The piled walls were designed with a toe level of 171 m AOD. For design of the
bridge piles, it proposed that the bridge piles with an additional metre of embedment to allow for
the additional load from the structure (i.e toe level at 170m AOD, depending on the elevation at
which bedrock is encountered).
Buried Concrete:
Chemical testing was undertaken on two samples from 3/BH160 as part of the preliminary ground
investigation: one within the made ground and one within the glacial till. The results indicate
Aggressive Chemical Environment for Concrete AC-2z conditions in accordance with BRE
Special Digest 1: Concrete in Aggressive Ground (2005) and Design Sulfate class DS-1. These
correspond with the conditions assessed from chemical tests on samples collected across the
whole route of section 6 and therefore the values are recommended for design.
Construction Issues:
The contractor will have to control and dispose of any groundwater encountered during the
course of construction. Artesian groundwater was encountered within the bedrock, during ground
investigation. Although it is unlikely to be encountered within the excavation; it needs to be
considered during construction.
The existing and new structure will have to be demolished and constructed in phases to maintain
the flow of traffic on the A465 carriageway.
As the underlying bedrock comprises the Lower Coal Measures, there is a possibility for
unrecorded mineworkings or voids being encountered. In light of this, prior to construction, it is
proposed that the ground beneath the foundations should be investigated for the presence of
possible mineworkings or voids. Any voids or mineworkings encountered should be grouted.
Conclusions and Recommendations:
Design sulfate DS-1 and ACEC AC-2z (BRE Special Digest 1, 2005) has been assumed for
concrete design for buried structures. Further chemical testing in this area is recommended to
confirm this assumption.
Further investigations, such as additional exploratory holes, are recommended to identify the
presence of mineworkings or voids beneath the proposed structure and to quantify the problems
that might arise if artesian conditions are encountered. If the presences of mine workings are
confirmed beneath the structure the allowable bearing pressures should be reduced in
accordance with the CIRIA special publications 32 (Healy and Head, 1989).
B2191100/D2/1/2/059
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Heads of the Valleys Dualling Rev: 0 Calc No: GAS/0005/R0
Structure Name: Trewaun East Overbridge Date: December 2016
Prepared: SN Checked: CR Reviewed: AD Job No: B2191100
Chainage: 3240m
Exploratory Holes: References:
i. Babtie Group (2000) A465 Abergavenny
North Abutment: 3/BH164 and 3/BH164A to Hirwaun Dualling Section 7 – Hirwaun
to Baverstock, Scheme Proposals and
South Abutment: 3/BH165 and 3/BH166 Exploratory Hole Location Drawings,
Drawing No. BTI015586/11/172.
ii. Babtie Group (2000), A465 Abergavenny
to Hirwaun Dualling, Interpretative
Report on Preliminary Ground
Investigation, Cardiff, Report No.
BTI.015586/D4/118.
iii. Exploration Associates Ltd (1997) A465
Abergavenny to Hirwaun Dualling
Section 3. Volume Three of Nine,
Factual Report on Ground Investigation.
Report No. 166001-3.
iv. Healy, P.R and Head, J.M. (1989) CIRIA
Special Publication 32: Construction
over abandoned mine workings.
v. Jacobs (2015) A465 Section 5 and 6
Technical Advisor Presentation Plan.
vi. Jacobs (2015) A465 Heads of the
Valleys Dualling Sections 5 and 6
Preliminary Sources Study Report.
Report No. B1855100/D4/2/017.
vii. Jacobs (2016) A465 Heads of the
Valleys Dualling Sections 5 and 6
Ground Investigation Report. Report No.
B2191100/D2/1/040
viii. Jacobs (2016) Vale of Neath Bridge –
General Alignment, Drawing. No.
B2191100-JAC-SBR-DE-SE-1600-0500.
ix. Jacobs (2016) Calculation 4, Secant
Piled Retaining Wall Design at Trewaun
nd
RW1 and RW2, Revision 3, 22 August
2016
Proposed Structure:
The current proposal is to construct a new single span integral structure made of precast
reinforced concrete beams and an in-situ reinforced concrete deck which connects Brecon Road
with the A4059 (Hirwaun Road). The structure is proposed to be approximately 40 m long and 18
m wide. The abutments are anticipated to be founded on 1500 mm diameter piles at 1.8m
spacing forming the Trewaun contiguous piled walls proposed either side of the A465
carriageway.
Ground Level
Elevation Depth to top Thickness (m)
Stratum (m AOD) of stratum Description
(m bgl)
Min Max Min Max
Soft to firm silty CLAY with
Made Ground gravel and cobbles of
0.00
(Cohesive) 195.03 1.00 sandstone, quartzite, slag and
limestone
Firm to stiff sandy silty CLAY
Glacial Till
194.03 194.25 0.00 to 1.00 2.00 17.20 with gravel and cobbles of
(Cohesive)
sandstone and quartzite
Medium dense to dense slightly
Glacial Till 2.05 (Not proven
(1) 192.03 3.00 silty sandy GRAVEL of
(Granular) in 3/BH164)
sandstone and quartzite
Interbedded slightly weathered
to fresh, weak MUDSTONE,
slightly weathered, sandy
Lower Coal > 3.85
(2) 177.05 17.20 moderately weak to moderately
Measures (Not proven)
strong SILTSTONE and slightly
weathered to fresh, moderately
strong SANDSTONE.
Note: (1) Granular glacial till encountered in 3/BH164
(3) Open hole drilling techniques were used in 3/BH164A between the depths of 0 m bgl to 17.5 m
bgl and therefore the ground profile in this range of depth is uncertain.
Groundwater:
At the north abutment location, groundwater was not encountered in borehole 3/BH164A although
water was noted at ground level when drilling commenced in 3/BH164.
Babtie report (2000) states that in borehole 3/BH165 (south abutment), groundwater was
recorded at 5.9mbgl (189.36m AOD). Groundwater was recorded at 7.75mbgl (187.51m AOD)
following overnight seepage, when the depth of the borehole was 19.5mbgl (175.76m AOD). A
standpipe was installed in 3/BH165 with a response zone between 1.50mbgl to 10.0mbgl
(193.76m AOD to 185.26m AOD). The highest recorded water level was 3.2 mbgl (192.1 m
AOD). Groundwater was also recorded in 3/BH166 at 2.5 m bgl (197.35 m AOD).
Summary of Soil Parameters:
These values have been taken from the Jacobs GIR (2016).
Stratum γb Cohesion Angle of cu mv E’
, cp’, Friction,
(Mg/m )
3
(kN/m2) φp’, ° (kN/m2) (m2/MN) (MPa)
(1)
Made Ground 2.0 0 32 50 0.1 20
20
75
20 + 3z
Glacial Till 75+ 10z
0.2 (z = metres
(Cohesive) 2.1 2 32 (z = metres
below
below 2 m bgl)
5.0m.bgl)
30
30 + 17z
Glacial Till
2.0 0 36 - - (z = metres
(Granular)
below
5.0m.bgl)
Bedrock γb UCS
3 GSI mi D E’ (MPa)
Parameters (Mg/m ) (MPa)
Lower Coal
Measures - 2.50 10 35 8 0.7 150
Mudstone
Lower Coal
Measures - 2.50 35 50 15 0.7 1050
Sandstone
Note (1): The undrained shear strength of Made Ground Cohesive was reduced from GIR values
to reflect the description in site specific boreholes.
Foundation Considerations:
The bridge is to be founded on contiguous piled walls and acts as a prop to the wall. The
contiguous walls are 1500 mm in diameter, with 1800mm spacing. The estimated maximum load
from the bridge is 7000 kN. Assuming a pile group of 10 No per abutment (as suggested by
Drawing B2191100-JAC-SBR-DE-SE-1600-0500) the total load per pile is about 700 kN. A
minimum rock socket length of 1m is required to support the vertical loading from the bridge.
Either side of the bridge, initial consideration was given to adopting contiguous piled retaining
walls to form the road cutting. The contiguous piled walls were designed as a cantilever with a
toe level of 173.2 m AOD). For design of the bridge piles, it proposed that the cantilever design is
applied to the bridge piles with an additional metre of embedment to allow for the additional load
from the structure (i.e toe level at 172.2 m AOD, depending on the elevation at which bedrock is
encountered).
Buried Concrete:
A limited number of sulphate and pH (chemical) tests were carried out on samples taken from the
site specific exploratory holes as part of the preliminary ground investigation: one sample from
within the glacial till in 3/BH164 and one within the glacial till of 3/BH165. The results indicate
Aggressive Chemical Environment for Concrete AC-2z conditions in accordance with BRE
Special Digest 1: Concrete in Aggressive Ground (2005) and Design Sulfate class DS-1. These
correspond with the conditions assessed from chemical tests on samples collected across the
whole route of section 6 and therefore the values are recommended for design.
Construction Issues:
The existing traffic flows from the A4059 Brecon Road will have to be temporarily diverted during
the construction of the bridge. Encroachment on the surrounding houses and buildings will also
need to be managed to prevent damage to structures. There is an existing culvert present
underneath the proposed bridge location, this is proposed to be demolished and relocated to the
east of the new structure. During piling, care should be taken to case the piling when it is drilled
through the existing culvert, so as to prevent the overflow of the concrete to the culvert.
The control of localised groundwater will also have to be addressed by the Contractor. In addition,
glacial till formation is susceptible to ‘Wetting-up’ upon exposure and therefore may have lower
undrained shear strength than anticipated.
As the underlying bedrock comprises the Lower Coal Measures, there is a possibility for
unrecorded mineworkings or voids being encountered. In light of this, prior to construction, it is
proposed that the ground beneath the foundations should be investigated for the presence of
possible mineworkings or voids. Any voids or mineworkings encountered should be grouted.
Conclusions and Recommendations:
Contiguous piled foundations are suggested for the foundations, socketed at least 4 m within the
bedrock.
Design Sulfate DS-1 and ACEC AC-2z (BRE Special Digest 1, 2005) has been assumed for
concrete design for buried structures. Further chemical testing in this area is recommended to
confirm this assumption.
Further investigations, such as additional exploratory holes, are also recommended to confirm the
nature and engineering properties of the made ground, glacial till and bedrock at the pile
locations.
B2191100/D2/1/2/059
GEOTECHNICAL SUMMARY INFORMATION
Project: A465 Heads of the Valleys Dualling Section 5 & 6 Rev: 0 Sheet No: GAS/0004/R0
Structure Name: Trewaun West Overbridge Date: January 2017
Prepared: SN Checked: CR Reviewed: AD Job No: B2191100
Chainage: 3147m
Exploratory Holes: References:
i. Babtie Group (2000) A465 Abergavenny
South Abutment: 3/BH166 to Hirwaun Dualling Section 7 – Hirwaun
to Baverstock, Scheme Proposals and
North Abutment: 3/BH167 Exploratory Hole Location Drawings,
Drawing No. BTI015586/11/172.
ii. Babtie Group (2000), A465 Abergavenny
to Hirwaun Dualling, Interpretative
Report on Preliminary Ground
Investigation, Cardiff, Report No.
BTI.015586/D4/118.
iii. Exploration Associates Ltd (1997) A465
Abergavenny to Hirwaun Dualling
Section 3. Volume Three of Nine,
Factual Report on Ground Investigation.
Report No. 166001-3.
iv. Healy, P.R and Head, J.M. (1989) CIRIA
Special Publication 32: Construction
over abandoned mine workings.
v. Jacobs (2015) A465 Section 5 and 6
Technical Advisor Presentation Plan.
vi. Jacobs (2015) A465 Heads of the
Valleys Dualling Sections 5 and 6
Preliminary Sources Study Report.
Report No. B1855100/D4/2/017.
vii. Jacobs (2016) A465 Heads of the
Valleys Dualling Sections 5 and 6
Ground Investigation Report. Report No.
B2191100/D2/1/040
viii. Jacobs (2016) Vale of Neath Bridge –
General Alignment, Drawing. No.
B2191100-JAC-SBR-DE-SE-1600-0400.
Proposed Structure:
The current proposal is to construct a new single span structure with bearings connecting the
existing A465 road with the Trewaun Junction. The structure is proposed to be approximately 95
m long (including wing walls) and 16.3 m wide. The abutments are anticipated to be founded on
1500 mm diameter contiguous piles at 1.8m spacing.
Existing Ground Level:
≈ 197 m AOD(North) to 198.3 m AOD (South) (from the topographic survey)
Proposed A465 carriageway (running beneath bridge) is approximately 188.5 m AOD and the
elevation of the road over the bridge is approximately 197.3 m AOD.
Groundwater:
South of the A465, an overnight seepage was recorded from the granular glacial till into 3/BH166
and the groundwater was noted at 2.5mbgl (197.4m AOD). Groundwater was encountered at
4.0mbgl (193.3m AOD) within the granular glacial till rising to 3.1mbgl (194.2m AOD) during
drilling in 3/BH167.
30 + 17z
Glacial Till
2.0 0 36 - - (z =
(Granular)
metres
below 5 m
bgl)
75 20
75 + 10z 20 + 3z
Glacial Till
(z = 0.1 (z =
(Cohesive)
2.1 2 32 metres metres
below 2 m below 5 m
bgl) bgl)
Bedrock γb UCS
3 GSI mi D E’ (MPa)
Parameters (Mg/m ) (MPa)
Lower Coal
Measures –
2.50 10 35 8 0.7 150
Mudstone /
Siltstone
Foundation Considerations:
The proposed A465 mainline carriageway is anticipated to be within a cutting which will run
beneath the proposed overbridge. The bridge is to be founded on contiguous piled walls and acts
as a prop to the wall. The contiguous walls are 1500 mm in diameter, with 1800mm spacing. The
estimated maximum load from the bridge is 10400 kN. Assuming a pile group of 15 No per
abutment (as suggested by Drawing B2191100-JAC-SBR-DE-SE-1600-0400) the total load per
pile is about 700 kN. A minimum rock socket length of 1m is required to support the vertical
loading from the bridge. Either side of the bridge, initial consideration was given to adopting
contiguous piled retaining walls to form the road cutting. The contiguous piled walls were
designed as a cantilever with a toe level of 177 m AOD and an assumed bedrock level at 180m
AOD. For design of the bridge piles, it is proposed that the cantilever design is applied to the
bridge piles, with an additional metre of embedment to allow for the additional load from the
structure (i.e toe level at 176 m AOD, depending on the elevation at which bedrock is
encountered). The toe level of the piles are dependent on the elevation at which bedrock is
encountered, a minimum of 4m rock socket is required for the current design.
Buried Concrete:
Chemical testing was undertaken on one groundwater sample from 3/BH166 collected from within
the glacial till as part of the preliminary ground investigation. The results indicate Aggressive
Chemical Environment for Concrete AC-2z conditions in accordance with BRE Special Digest 1:
Concrete in Aggressive Ground (2005) and Design Sulfate class DS-1. These correspond with
the conditions assessed from chemical tests on samples collected across the whole route of
section 6 and therefore the values are recommended for design.
Construction Issues:
The control of localised groundwater will also have to be addressed by the Contractor. In addition,
glacial till formation is susceptible to ‘Wetting-up’ upon exposure and therefore may have lower
undrained shear strength than anticipated.
The traffic from the existing A465 will have to be temporarily diverted during the construction of
the bridge.
As the underlying bedrock comprises the Lower Coal Measures, there is a possibility for
unrecorded mineworkings or voids being encountered. In light of this, prior to construction, it is
proposed that the ground beneath the proposed foundations should be investigated thoroughly
for condition and the presence of possible mineworkings or voids. Any voids or mineworkings
encountered should be grouted.
Conclusions and Recommendations:
Contiguous piled foundations are suggested for the foundations, socketed at least 4 m within the
bedrock.
Design Sulfate DS-1 and ACEC AC-2z (BRE Special Digest 1, 2005) has been assumed for
concrete design for buried structures. Further chemical testing in this area is recommended to
confirm this assumption.
Further investigation, is recommended to confirm or eliminate the presence of mineworkings or
voids beneath the proposed structure. If mine workings are confirmed, grouting to fill these
cavities may be required.
B2191100/D2/1/2/059
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Heads of the Valleys Dualling Rev: 0 Calc No: GAS/0003/Rev 0
Page 1 of 7
Structure Name: Wind Farm Access Bridge Date: December 2016
Prepared: LK Checked: SN/SM Reviewed: AD Job No: B2191100
Proposed Structure:
It is proposed to build a new access bridge at Chainage 3013 over the proposed A465 which
would lie within a cutting. The current proposal is a single lane single span integral structure, with
a 4.5m carriageway width, 1.2m hard verge and a 2 m footway (Drawing. 2191100-JAC-SBR-DE-
SE-1600-0300). The total length of the bridge is approximately 60m (76.5 m including the wing
walls).
Existing Ground Level:
≈ 201.9m AOD in the south to 204.8 m AOD in the north (from relevant boreholes and
topographic survey)
The proposed level of the A465 beneath the bridge structure is approximately 191.0m AOD.
Ground Conditions:
North and South Abutments
Existing ground level: ≈ 200.8m AOD to 204.0m AOD (from exploratory holes)
The relevant boreholes are as follows (see Figure 1: BGS Borehole location plan):
Approximate distance from Depth of the exploratory
Exploratory Hole ID
the structure hole (m)
3/BH168 (BGS Reference No.
50 m east 9.3
SN90NE151)
3/BH169 (BGS Reference No.
70 m west 12
SN90NE161)
3/TP70 (BGS Reference No.
At the structure 2.2
SN90NE151)
25 m north west of the
BGS Reference No. SN90NE9 3.7
structure
25 m north east of the
BGS Reference No. SN90NE8 2.4
structure
Note:
(1)
Encountered in borehole 3/BH169 only.
(2)
Encountered in borehole 3/BH168 only.
(3)
Bedrock was not encountered in any of the boreholes.
1.0m Granular Glacial Till is ignored in the foundation design due to long distance of 3/BH169 from
structure compared to 3/BH168.
Bedrock was not encountered in any of the exploratory holes.
Figure 1: BGS Borehole location plan (proposed bridge location shown as black lines)
The design ground condition for the proposed bridge foundation can be presented as below:
GL (m AOD) Thickness (m) Soil Strata
203.0 – 202.9 0.1 Top Soil
202.9 – 202.0 0.9 Made Ground
202.0 – 200.0 2.0 Possible Solifluction Deposits
200.0 – Borehole terminated at 192 m AOD Cohesive Glacial Till
Groundwater:
A groundwater level of 1.5m (200.2m AOD) and 1.2m (199.9m AOD) below ground level was
recorded in SN90NE8 and SN90NE9 respectively. A seepage water level of 0.8m bgl (201.7m
AOD) was noted in 3/TP70. An overnight standing water level of 2.3m bgl (198.5m AOD) was
recorded in exploratory hole 3/BH168. However, a groundwater level of ground level (0m bgl) is
suggested for design.
Stratum Angle of cu mv E’
3 Cohesion,
γb, (Mg/m ) 2 Friction, 2 2
cp’, (kN/m ) (kN/m ) (m /MN) (MPa)
φp’, °
Made Ground (1) (1)
2.0 0 32 40 0.1 8
(Cohesive/Granular)
30
Lower Coal
2.5 35 50 15 0.7 1050
Measures -
Sandstone
Lower Coal
2.5 10 35 8 0.7 150
Measures -
Mudstone
Note : (1) – Undrained shear strength for Made Ground Cohesive based on local SPT N value of 8 (c u =
SPT N x f1, f1 = 5) and material description. The stiffness E’ was estimated from SPT N value, based on
E≈N.
Foundation Considerations:
Abutments
It is recommended that topsoil, made ground and possible solifluction deposits are removed prior
to construction work. Due to the generally lower bearing capacity of the near surface cohesive
glacial till and the extensive depths to bedrock (which were not confirmed in any nearby
boreholes), it is proposed that both abutments are founded on piles. Drawing 2191100-JAC-SBR-
DE-SE-1600-0300 suggests that the pile caps for each abutment will be embedded within the
cohesive glacial till with an estimated cut off level of 200 m AOD.
The estimated maximum load to be applied to the abutment foundations is of the order of
8400kN. Assuming a pile group of 4 No. per abutment (as suggested by Drawing 2191100-JAC-
SBR-DE-SE-1600-0300) the total load per pile is about 2100kN.
The nearby bridges at Trewaun are supported on 1.5 m diameter contiguous piles at 1.8m
spacing. Given the proximity of the two structures, it is considered reasonable to adopt similar
piled foundations for the Wind Farm Access Bridge.
For preliminary design, it is assumed that the glacial till extends to significant depth and that the
pile will be fully within the glacial till deposits. Further investigation is required to confirm the
ground conditions to the full pile depth at the proposed pile locations. Assuming 1.5 m diameter
piles with 1.8m spacing and 200 m AOD as the pile cut off level, a minimum pile length of 18m is
suggested, corresponding with a toe elevation of 182 m AOD. Settlement on the piles is
anticipated to be less than 10mm.
Buried Concrete:
Chemical testing for aggressive ground conditions for buried concrete structures was not
undertaken on samples collected from these exploratory holes. However, based on the chemical
tests on samples collected across the whole route along Section 6, Design Sulfate class DS-1
and Aggressive Chemical Environment for Concrete ACEC-AC2z (BRE Special Digest 1, 2005)
have been assumed for this site. Further chemical testing in the area is recommended to confirm
if these results are applicable.
Construction Issues:
The existing traffic flows will have to be maintained during the construction works. The proposed
foundation levels are below the highest groundwater level and hence the contractor will have to
address the control and disposal of groundwater during the construction of the foundations such
as through dewatering. In addition, Glacial Till is susceptible to ‘Wetting-up’ upon exposure and
therefore may have decreased undrained shear strength than anticipated.
Several mine entries are recorded within this area (between chainages 2350 – 3360) towards the
south of the existing A465. It is possible that unrecorded mine entries and bell pits accessing the
Garw seam and ironstone veins may be encountered. Therefore, further investigation works, such
as additional exploratory holes and probing are recommended in order to find out the possibility of
mineworkings or voids beneath the proposed structure and to confirm the location and nature of
the soil. If the presence of mineworkings or voids is noted beneath the structure, these will require
grouting prior to construction.
Conclusions and Recommendations:
Piled foundations embedded within the cohesive glacial till are considered the most appropriate
foundations for design. Limited ground information is available and several mine entries were
identified within this area. Therefore, additional ground investigation to the full pile depth is
recommended at the site of the proposed bridge.
Design Sulfate DS-1 and ACEC AC-2z (BRE Special Digest 1, 2005) has been assumed for
concrete design for buried structures. Further chemical testing in this area is recommended to
confirm this assumption.
The above recommendations are intended to give a general guidance for preliminary design
purposes only and may be revised depending on the outcome of further ground investigation.
Pile area Pile Cut-off Level Pile Length Diameter Total No.
Abutments 200 m AOD 18 m 1500 mm with 1800 mm 4 per abutment
spacing
B2191100/D2/1/2/059
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Heads of the Valleys Dualling Rev: 0 Sheet No: GAS/0002/R0
Structure Name: Nant y Bwlch Bridge Date: March 2017
Prepared: SN Checked: AD Reviewed: AD Job No: B2191100
Chainage: 2320m
Exploratory Holes: References:
i. Babtie Group (2000) A465 Abergavenny
3/BH174 to Hirwaun Dualling Section 7 – Hirwaun
to Baverstock, Scheme Proposals and
Note: There are no other exploratory holes Exploratory Hole Location Drawings,
(recent or historic) in close proximity to the Drawing No. BTI015586/11/173.
structure location. ii. Babtie Group (2000), A465 Abergavenny
to Hirwaun Dualling, Interpretative
Report on Preliminary Ground
Investigation, Cardiff, Report No.
BTI.015586/D4/118.
iii. Exploration Associates Ltd (1997) A465
Abergavenny to Hirwaun Dualling
Section 3. Volume Three of Nine,
Factual Report on Ground Investigation.
Report No. 166001-3.
iv. Jacobs (2015) A465 Section 5 and 6
Technical Advisor Presentation Plan.
v. Jacobs (2015) A465 Heads of the
Valleys Dualling Sections 5 and 6
Preliminary Sources Study Report.
Report No. B1855100/D4/2/017.
vi. Jacobs (2015) A465 Heads of the
Valleys Dualling, Sections 6 Nant Ffrwd
to Hirwaun Chainage 1500 - 3000.
Drawing No. 7202216/RW/06.
vii. Jacobs (2016) A465 Heads of the
Valleys Dualling - Sections 5 and 6,
Ground Investigation Report. Report No.
B2191100/D2/1/2/040
viii. Jacobs (2016) Nant Bwlch Bridge
General Arrangement. Drawing.
2191100-JAC-SBR-DE-SE-1600-0200.
Construction Proposals:
The current proposal is that a new integral bridge will be built beneath the proposed carriageway
as show on Drawing No. 2191100-JAC-SBR-DE-SE-1600-0200. The structure is proposed to be
an integral reinforced concrete bridge with a 10.0m clear span and is 36.0m wide.
1-4
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Heads of the Valleys Dualling Rev: 0 Sheet No: GAS/0002/R0
Structure Name: Nant y Bwlch Bridge Date: March 2017
Prepared: SN Checked: AD Reviewed: AD Job No: B2191100
Groundwater:
Groundwater was struck at 4.2mbgl (211.2m AOD) with a standing level recorded as 3.8mbgl
(211.6m AOD). Water was also struck at 19.0mbgl (196.4m AOD) and its level rose to 18.1mbgl
(197.3m AOD) after 20minutes although its standing level is uncertain. An overnight seepage is
recorded from the granular glacial till at 7.0mbgl (208.4m AOD) into the borehole and the
standing groundwater was noted at 2.3mbgl (213.1m AOD).
Cohesion, Angle of cu mv E’
Stratum cp’, Friction,
γb 2 2 2
3
(Mg/m ) (kN/m ) φp’, ° (kN/m ) (m /MN) (MPa)
75 20
Glacial Till 0.1
75+ 10z 20 + 3z
(Cohesive) 2 32
2.10 (z = meters (z = metres
below 2m.bgl) below 5.0m.bgl)
2-4
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Heads of the Valleys Dualling Rev: 0 Sheet No: GAS/0002/R0
Structure Name: Nant y Bwlch Bridge Date: March 2017
Prepared: SN Checked: AD Reviewed: AD Job No: B2191100
30
Glacial Till 30 + 17z
2.00 0 36 - -
(Granular) (z = metres
below 5.0m.bgl)
3-4
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Heads of the Valleys Dualling Rev: 0 Sheet No: GAS/0002/R0
Structure Name: Nant y Bwlch Bridge Date: March 2017
Prepared: SN Checked: AD Reviewed: AD Job No: B2191100
Foundation Considerations:
Due to the generally lower bearing capacity of the cohesive glacial till and the extensive depths to
bedrock (which were not confirmed in any nearby boreholes), it is proposed that both abutments
will be founded on piles embedded within the granular glacial till. Drawing 2191100-JAC-SBR-DE-
SE-1600-0200 suggest that the pile caps for each abutment will be embedded within the glacial
till, however the pile cap depth (therefore cut off level (COL)) is unknown. For preliminary design,
a pile COL of 212m AOD has been assumed; that being equivalent to 0.5m below the
approximately river level at the bridge site. The estimated total maximum load to be applied to the
structure foundation is 9570kN. Assuming a pile group of No. 26 per abutment (13 by 2, as
suggested by Drawing 2191100-JAC-SBR-DE-SE-1600-0200) the total load per pile is
approximately 370kN. As this bridge is an integral bridge, due to the expansion and contraction of
the deck, it is feasible that more load will be applied to one row of piles with the other row in
tension. This therefore increases the load to 740kN per pile. Assuming 0.75m diameter piles, a
minimum pile length of 14m is required (assuming a pile COL of 212m AOD), corresponding with
a toe elevation of 198.0m AOD. Settlement on the piles is anticipated to be less than 10mm. If
soft material is present at the location of the foundations, it should be removed and replaced with
granular engineered fill.
Buried Concrete:
Chemical testing was undertaken on two samples collected from boreholes drilled at Nant Bwlch,
as part of the preliminary ground investigation: one soil sample and one groundwater sample,
both from within the glacial till. The results indicate Aggressive Chemical Environment for
Concrete AC-2z conditions in accordance with BRE Special Digest 1: Concrete in Aggressive
Ground (2005) and Design Sulfate class DS-1. These correspond with the conditions assessed
from chemical tests on samples collected across the whole route of section 6 and therefore the
values are recommended for design.
Construction Issues:
Exposed glacial till formation is susceptible to ‘Wetting-up’ and therefore may have decreased
undrained shear strength than anticipated.
4-4
Geotechnical Design Report Volume 2: Structures
B2191100/D2/1/2/059
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Heads of the Valleys Dualling – Section 5 & 6 Rev: 0 Calc No: GAS/SP001B
Page 1 of 4
Structure Name: Hirwaun Junction Southeast Bridge Date: August 2016
Prepared: SN Checked: CR Reviewed: AD Job No: B2191100
Chainage: 1815 m
Exploratory Holes: References:
i. Babtie Group (2000) A465 Abergavenny
3/BH179, 3/BH180 and 3/BH180A to Hirwaun Dualling Section 7 – Hirwaun
to Baverstock, Scheme Proposals and
Exploratory Hole Location Drawings,
Drawing No. BTI015586/11/173.
1-4
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Heads of the Valleys Dualling – Section 5 & 6 Rev: 0 Calc No: GAS/SP001B
Page 2 of 4
Structure Name: Hirwaun Junction Southeast Bridge Date: August 2016
Prepared: SN Checked: CR Reviewed: AD Job No: B2191100
Ground Level
Elevation Depth to top Thickness (m)
Stratum (m AOD) of stratum Description
(m bgl)
Min Max Min Max
Groundwater
2-4
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Heads of the Valleys Dualling – Section 5 & 6 Rev: 0 Calc No: GAS/SP001B
Page 3 of 4
Structure Name: Hirwaun Junction Southeast Bridge Date: August 2016
Prepared: SN Checked: CR Reviewed: AD Job No: B2191100
A groundwater level of 3.15 m bgl (203.9 m AOD) was recorded following an overnight seepage
in borehole 3/BH180A within the Glacial Till. Groundwater was also recorded in 3/BH179 as a
seepage at a depth of 2 m bgl (205.5 m AOD), at 5 m bgl which rose to 4.8 m bgl (202.7 m AOD)
and also at 19 m bgl which rose to 15.4 m bgl (192.1 m AOD) after twenty minutes.
γb Angle of cu mv E’
Cohesion,
Stratum 2 Friction,
(Mg/m3) cp’ (kN/m ) 2 2
φp’, ° (kN/m ) (m /MN) (MPa)
20 (between
100 (between
ground level
ground level
Made Ground and 2 m bgl)
and 2 m bgl)
(Cohesive / 2 0 32 0.1
Granular)
150 (below 2
30 (below 2
m bgl)
m bgl)
75 20
75 + 10 z 20 + 3z
Glacial Till
2.1 2 32 0.2
(Cohesive) (z = metres (z = metres
below 2 m below 5 m
bgl) bgl)
30
30 + 17 z
Glacial Till
2 - 36 - -
(Granular) (z = metres
below 5 m
bgl)
Note : (1) Please note that the parameters for glacial till cohesive and glacial till granular are
different to those submitted in the AIP (Approval in Principle). This is because the global
parameters were revised for the latest GIR submission (Revision W0, dated November 2016).
The values given above are more appropriate for the structure at this location and reflects the
nearby borehole description.
Foundation Considerations:
Due to the generally lower bearing capacity of the cohesive glacial till and the depth to bedrock, it
is proposed that both abutments will be founded on piles founded within the glacial till rather than
pad foundations. The maximum total load to be applied to the bridge abutment is estimated to be
18600 kN. Assuming a pile group of twenty piles (10 x 2) per abutment, as suggested by Drawing
2191100-JAC-SBR-DE-SE-1600-0102, the total load per pile is of the order 930 kN. As the
structure is an integral bridge, due to the expansion of the deck, it is feasible much of the load will
be applied to one row of piles with the other row in tension. It was therefore conservatively
3-4
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Heads of the Valleys Dualling – Section 5 & 6 Rev: 0 Calc No: GAS/SP001B
Page 4 of 4
Structure Name: Hirwaun Junction Southeast Bridge Date: August 2016
Prepared: SN Checked: CR Reviewed: AD Job No: B2191100
assumed that the full loading was applied to a single row of piles. This therefore increases the
load to 1860 kN per pile. Assuming 0.9m diameter piles, a minimum length of at least 20 m would
be required to achieve the required pile capacity. This corresponds with a toe level of at least
187 m AOD, founded in stiff to very stiff cohesive glacial till.
Buried Concrete:
Sulphate and pH tests for aggressive ground conditions for buried concrete structures were
undertaken on groundwater samples from 3/BH179. These results and results from the nearby
borehole samples along the route suggest Aggressive Chemical Environment for Concrete
ACEC-AC2 conditions in accordance with BRE Special Digest 1: Concrete in Aggressive Ground
(2005) and Design Sulfate class DS-1. These correspond with the conditions assessed from
chemical tests on samples collected across the whole route of section 6. Further chemical testing
in the area is recommended to confirm if these results are applicable.
Construction Issues:
The existing traffic flows will have to be maintained during the construction works. The control of
localised groundwater, if encountered, will also have to be addressed by the Contractor.
It should be noted that glacial till is susceptible to softening on exposure or ‘wetting up’ and
therefore may have decreased undrained shear strength than anticipated.
4-4
Geotechnical Design Report Volume 2: Structures
B2191100/D2/1/2/059
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Heads of the Valleys Dualling – Section 5 & 6 Rev: 0 Calc No: GAS/SP001A
Page 1 of 4
Structure Name: Hirwaun Junction Northwest Bridge Date: August 2016
Prepared: SN Checked: CR Reviewed: AD Job No: B2191100
Chainage: 1735m
Exploratory Holes: References:
i. Babtie Group (2000) A465 Abergavenny
3/BH181, 3/BH182 and 3/BH182A to Hirwaun Dualling Section 7 – Hirwaun
to Baverstock, Scheme Proposals and
Exploratory Hole Location Drawings,
Drawing No. BTI015586/11/173.
1-4
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Heads of the Valleys Dualling – Section 5 & 6 Rev: 0 Calc No: GAS/SP001A
Page 2 of 4
Structure Name: Hirwaun Junction Northwest Bridge Date: August 2016
Prepared: SN Checked: CR Reviewed: AD Job No: B2191100
Groundwater:
Within 3/BH181 and 3/BH182, the groundwater was encountered as confined aquifers within the
granular glacial till. Groundwater was encountered in 3/BH181 at a depth of 18.4 m bgl which
rose to 11.4 m bgl (196.3 m AOD) within twenty minutes. It was encountered in 3/BH182 at a
depth of 16 m bgl which rose to 14.2 m bgl (194.1 m AOD) within thirty minutes. The piezometer
and slotted standpipe installed within 3/BH182 recorded the highest groundwater level as 2.52 m
bgl (205.2 m AOD).
2-4
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Heads of the Valleys Dualling – Section 5 & 6 Rev: 0 Calc No: GAS/SP001A
Page 3 of 4
Structure Name: Hirwaun Junction Northwest Bridge Date: August 2016
Prepared: SN Checked: CR Reviewed: AD Job No: B2191100
Angle of cu mv E’
Bulk density, Cohesion,
Stratum 3 2 Friction,
(Mg/m ) cp’, (kN/m ) 2 2
φp’, ° (kN/m ) (m /MN) (MPa)
20
75
20 + 3z
75 + 10 z
Glacial Till
(1) 2.1 2 32 0.1 (z =
(Cohesive) (z = metres
metres
below 2 m
below 5 m
bgl)
bgl)
30
30 + 17z
Glacial Till
(1) 2.0 - 36 - - (z =
(Granular)
metres
below 5 m
bgl)
Note : (1) Please note that the parameters for glacial till cohesive and glacial till granular are
different to those submitted in the AIP (Approval in Principle). This is because the global
parameters were revised for the latest GIR submission (Revision W0, dated November 2016).
The values given above are more appropriate for the structure at this location and reflects the
nearby borehole description.
3-4
GEOTECHNICAL ASSESSMENT SHEET
Project: A465 Heads of the Valleys Dualling – Section 5 & 6 Rev: 0 Calc No: GAS/SP001A
Page 4 of 4
Structure Name: Hirwaun Junction Northwest Bridge Date: August 2016
Prepared: SN Checked: CR Reviewed: AD Job No: B2191100
Foundation Considerations:
Due to the generally lower bearing capacity of the cohesive glacial till and the depth to bedrock, it
is proposed that both abutments are founded on piles founded within the glacial till rather than
pad foundations. The maximum total load to be applied to the bridge abutment is estimated to be
17400 kN. Assuming a pile group of twenty (10 x 2) per abutment, as suggested by Drawing
2191100-JAC-SBR-DE-SE-1600-0101, the total load per pile is of the order 870 kN. As the
structure is an integral bridge, due to the expansion of the deck, it is feasible much of the load will
be applied to one row of piles with the other row in tension. It was therefore conservatively
assumed that the full loading was applied to a single row of piles. This therefore increases the
load to 1740 kN per pile. Assuming 0.9 m diameter piles, a minimum length of at least 20 m
would be required to achieve the required pile capacity. This corresponds with a toe level of at
least 188 m AOD, founded in granular glacial till.
Buried Concrete:
Sulphate and pH tests for aggressive ground conditions for buried concrete structures were
undertaken on two groundwater samples as part of the preliminary ground investigation: both
collected within the glacial till from 3/BH181 and 3/BH182. The results indicate Aggressive
Chemical Environment for Concrete AC-2z conditions in accordance with BRE Special Digest 1:
Concrete in Aggressive Ground (2005) and Design Sulfate class DS-1. These correspond with
the conditions assessed from chemical tests on samples collected across the whole route of
section 6. Further chemical testing in the area is recommended to confirm if these results are
applicable.
Construction Issues:
The existing traffic flows will have to be maintained during the construction works. The control of
localised groundwater, if encountered, will also have to be addressed by the Contractor.
It should be noted that glacial till is susceptible to softening on exposure or ‘wetting up’, which
could have implications on earthworks.
4-4
Geotechnical Design Report Volume 2: Structures
B2191100/D2/1/2/059
Geotechnical Design Report Volume 2: Structures
B2191100/D2/1/2/059
Geotechnical Summary Information Sheet - TREWAUN
STRUCTURE NAME
CHAINAGE Reference /
Trewaun Contiguous Bored Pile Retaining Westbound: ch. 3280m to 3390m Comments
walls Eastbound: ch. 3390m to 3460m
GEOTECHNICAL PARAMETERS
Earth Pressure: These coefficients assume horizontal retained ground level.
Made Ground
Glacial Till (cohesive) Glacial Till (granular) LCM
(cohesive)
Ko = 0.470 Ko = 1.000 Ko = 0.412
Ko = 1.500
Ka = 0.307 Ka = 0.307 Ka = 0.260
Kp = 3.255 Kp = 3.255 Kp = 3.852
1
Unit
Material c’ cu mv E’
Weight Φp’ (⁰)
Type (kN/m2) (kPa) (m2/MN) (MPa)
(Mg/m3)
Made
100
Ground
(between
(cohesive)
ground
40 (between ground
level and
2.0 0 32 0.1 level and 2mbgl)
2mbgl)
60 (below 2mbgl)
150 (below
2mbgl)
Glacial Till
75
(cohesive)
40
75 + 10 z (z
2.1 2 32 0.1
= metres 40 + 6 z (z = metres
below below 5mbgl)
2mbgl)
Glacial Till
60
(granular)
2.0 0 36 - -
60 + 34 z (z = metres
below 5mbgl)
Unit
Material UCS
Weight GSI mi E’ (MPa) D
Type (MPa)
(Mg/m3)
LCM
(Mudstone) 2.5 10 35 8 150 0.7
BEARING CAPACITY
Not applicable.
Face Height
Face Angle 90⁰ 6.7m
(max)
2
PILE DESIGN N/A
Pile Width Pile Pile Working Load (kN)
Founding Toe Level
Structure Element (m) Length
Stratum (mAOD)
(m)
SETTLEMENT N/A
Immediate Total
Founding Level Time Settlement remaining
Structure Element Settlement Settlement
(mAOD) for 90% at completion
(mm) (mm)
CHEMICAL ANALYSIS
pH - 3.8 to 7.8 - -
Mg - - - -
REDOX - - - -
Water soluble
1480
sulfate (mg/l)
Buried Concrete Design Sulfate and Aggressive Chemical
DS1 AC-2z
Environment for Concrete Classes:
Notes:
Chemical analyses were undertaken on samples from boreholes 3/BH162A, 3/BH164, 3/BH165 and
3/BH166. 3/BH162A differs the results compared to other boreholes; this is considered to be
anomaly. Therefore, further GI and testing is recommended for this site.
N/A
NOTES
None.
3
Geotechnical Design Report Volume 2: Structures
B2191100/D2/1/2/059
Geotechnical Summary Information Sheet – SWALEC PYLON
STRUCTURE NAME
Reference /
CHAINAGE
Swalec Pylon Contiguous Bored Pile Comments
Westbound: ch. 3460m to 3530m
Retaining wall
GEOTECHNICAL PARAMETERS
Earth Pressure: These coefficients assume horizontal retained ground level.
Made Ground (Cohesive and
Glacial Till (Granular) LCM
Granular)
Ko = 0.470 Ko = 0.412
Ko = 1.500
Ka = 0.307 Ka = 0.260
Kp = 3.255 Kp = 3.852
1
Unit
Material c’ cu mv E’
Weight Φp’ (⁰)
Type (kN/m2) (kPa) (m2/MN) (MPa)
(Mg/m3)
Made
100
Ground
(between
(cohesive
ground
and granular) 40 (between ground
level and
2.0 0 32 0.1 level and 2mbgl)
2mbgl)
60 (below 2mbgl)
150 (below
2mbgl)
Glacial Till
60
(granular)
2.0 0 36 - -
60 + 34 z (z = metres
below 5mbgl)
Unit
Material UCS
Weight GSI mi E’ (MPa) D
Type (MPa)
(Mg/m3)
LCM
(Mudstone) 2.5 10 35 8 150 0.7
BEARING CAPACITY
Not applicable.
Face Height
Face Angle 90⁰ 7.1m
(max)
Bored pile
1.5m Pile Length (m) 19.4m
diameter
CHEMICAL ANALYSIS
CHLORIDE (%) - - - -
Mg - - - -
REDOX - - - -
Water soluble
-
sulfate (mg/l)
Buried Concrete Design Sulfate and Aggressive Chemical
DS1 AC-2z
Environment for Concrete Classes:
Notes:
Chemical analyses were undertaken on samples from borehole 3/BH160.
NOTES
None.
3
Geotechnical Design Report Volume 2: Structures
B2191100/D2/1/2/059
Geotechnical Summary Information Sheet – AFON CYNON POND
STRUCTURE NAME
Afon Cynon Pond Contiguous Bored Pile CHAINAGE Reference /
Retaining wall Westbound: ch. 3660m to 3760m Comments
GEOTECHNICAL PARAMETERS
Earth Pressure: These coefficients assume horizontal retained ground level.
Made Ground Glacial Till
Glacial Till (Granular) LCM
(Granular) (Cohesive)
Ko = 0.470 Ko = 1.000 Ko = 0.412
Ko = 1.500
Ka = 0.307 Ka = 0.307 Ka = 0.260
Kp = 3.255 Kp = 3.255 Kp = 3.852
1
Unit
Material c’ cu mv E’
Weight Φp’ (⁰)
Type (kN/m2) (kPa) (m2/MN) (MPa)
(Mg/m3)
Made 40
Ground (between ground
(Granular) 2.0 0 32 - - level and 2m.bgl)
60 (below 2m.bgl)
Glacial Till 75
40
(Cohesive) 75+ 10z
40 + 6z
(z = meters
2.1 2 32 0.1 (z = metres
below
below 5.0m.bgl)
5.0m.bgl)
Glacial Till
60
(Granular)
2.0 0 36 - - 60 + 34 z (z =
metres below
5mbgl)
Unit
Material UCS
Weight GSI mi E’ (MPa) D
Type (MPa)
(Mg/m3)
LCM
(Mudstone) 2.5 10 35 8 150 0.7
BEARING CAPACITY
Not applicable.
Face Height
Face Angle 90⁰ 3.0m
(max)
Bored pile
0.75m Pile Length 12.0m
diameter
2
PILE DESIGN N/A
Pile Width Pile Pile Working Load (kN)
Founding Toe Level
Structure Element (m) Length
Stratum (mAOD)
(m)
SETTLEMENT N/A
Immediate Total
Founding Level Time Settlement remaining
Structure Element Settlement Settlement
(mAOD) for 90% at completion
(mm) (mm)
CHEMICAL ANALYSIS
CHLORIDE (%) - - - -
pH - 5.4 to 8.1 - -
Mg - - - -
REDOX - - - -
Water soluble
-
sulfate (mg/l)
Buried Concrete Design Sulfate and Aggressive Chemical
DS1 AC-2z
Environment for Concrete Classes:
Notes:
Chemical analyses were undertaken on samples from borehole 3/BH157 and 3/BH160
N/A
NOTES
None.
3
Geotechnical Design Report Volume 2: Structures
(Designed Out)
B2191100/D2/1/2/059
Geotechnical Design Report Volume 2: Structures
B2191100/D2/1/2/059
Geotechnical Summary Information Sheet – CEFN COED (west)
STRUCTURE NAME
Reference /
CHAINAGE
Cefn Coed Contiguous Bored Pile Comments
Westbound: ch. 11040m to 11140m
Retaining walls, West of High Street
Eastbound: ch. 11000m to 11140m
Bridge
GEOTECHNICAL PARAMETERS
Earth Pressure: These coefficients assume horizontal retained ground level.
Made Ground
Glacial Till (Granular) Sandstone
(Cohesive)
Ko = 0.470 Ko = 0.426
Ko = 1.5
Ka = 0.307 Ka = 0.271
Kp = 3.255 Kp = 3.690
1
Unit
Material c’ cu mv E’
Weight Φp’ (⁰)
Type (kN/m2) (MPa) (m2/MN) (MPa)
(Mg/m3)
Made
50 (between 0.1 (between
Ground
ground level ground level
(Cohesive) 20 (between ground
and 4mbgl) and 2mbgl)
2.0 0 32 level and 4mbgl)
200 (below 0.05 (below 80 (below 4mbgl)
4mbgl) 2mbgl)
Glacial Till
(granular) 2.0 0 35 - - 70
Unit
Material UCS
Weight GSI mi E’ (MPa) D
Type (MPa)
(Mg/m3)
Twrch
Sandstone 2.6 50 50 17 1500 0.7
Formation
BEARING CAPACITY
Not applicable.
Face Height
Face Angle 90⁰ 9.3m
(max)
2
SETTLEMENT N/A
Immediate Total
Founding Level Time Settlement remaining
Structure Element Settlement Settlement
(mAOD) for 90% at completion
(mm) (mm)
CHEMICAL ANALYSIS
CHLORIDE (%) - - - -
Mg - - - -
REDOX - - - -
Water soluble
20
sulfate (mg/l)
Buried Concrete Design Sulfate and Aggressive Chemical
DS1 AC-2z
Environment for Concrete Classes:
Notes:
Chemical analyses were undertaken on samples from borehole 3/BH97A.
N/A
NOTES
None.
3
Geotechnical Design Report Volume 2: Structures
B2191100/D2/1/2/059
Geotechnical Summary Information Sheet – CEFN COED (east)
STRUCTURE NAME
CHAINAGE
Cefn Coed Contiguous Bored Pile Reference /
Westbound: ch. 11160m to
Retaining wall, East of High Street Bridge Comments
11200m
STRUCTURE TYPE AIP Ref No.
GEOTECHNICAL PARAMETERS
Earth Pressure: These coefficients assume horizontal retained ground level.
Made Ground Glacial Till
Limestone
(Granular) (Cohesive)
Ko = 0.470 Ko = 1.000
Ko = 1.500
Ka = 0.307 Ka = 0.307
Kp = 3.255 Kp = 3.255
1
Unit
Material c’ cu mv E’
Weight Φp’ (⁰)
Type (kN/m2) (kPa) (m2/MN) (MPa)
(Mg/m3)
Made
0.1
Ground
(between
(Granular)
ground 20 (between
level and ground level and
2.0 0 32 -
2mbgl) 4mbgl)
80 (below 4mbgl)
0.05 (below
2mbgl)
Glacial Till
0.1
(Cohesive)
85 (between
40
85 + 10z ground
40 + 12z
(z = metres level and
2.0 2 32 (z = metres
2mbgl)
below 2 m
below 5 m bgl)
bgl)
0.03 (below
2mbgl)
Unit
Material UCS
Weight GSI mi E’ (MPa) D
Type (MPa)
(Mg/m3)
Limestone
2.7 50 65 12 7500 0.7
BEARING CAPACITY
Not applicable.
Face Height
Face Angle 90⁰ 7.7m
(max)
Bored pile
1.5m Pile Length 14.9m (South)
diameter
2
PILE DESIGN N/A
Pile Width Pile Pile Working Load (kN)
Founding Toe Level
Structure Element (m) Length
Stratum (mAOD)
(m)
SETTLEMENT N/A
Immediate Total
Founding Level Time Settlement remaining
Structure Element Settlement Settlement
(mAOD) for 90% at completion
(mm) (mm)
CHEMICAL ANALYSIS
SO4 (%) - - - -
CHLORIDE (%) - - - -
pH - - - -
Mg - - - -
REDOX - - - -
Water soluble
-
sulfate (mg/l)
Buried Concrete Design Sulfate and Aggressive Chemical
DS1 AC-2z
Environment for Concrete Classes:
Notes:
No chemical analyses were undertaken on samples from nearby boreholes
None.
3
Geotechnical Design Report Volume 2: Structures
B2191100/D2/1/2/059
Geotechnical Summary Information Sheet – GURNOS (h ≤ 4.5m)
CHAINAGE
Eastbound: ch. 12850m-12920 Reference /
STRUCTURE NAME
and 13270m-13340m Comments
Westbound (main line): ch.
Gurnos Contiguous Bored Pile Retaining
13290m-13360m
walls (h ≤ 4.5m)
Westbound (slip road): ch.
12790m-12975m
GEOTECHNICAL PARAMETERS
Earth Pressure: These coefficients assume horizontal retained ground level.
Possible Solifuction
Glacial Till (Cohesive) LCM
Deposits
Ko = 0.530 Ko = 1.000
Ko = 1.500
Ka = 0.361 Ka = 0.307
Kp = 2.770 Kp = 3.255
1
Unit
Material c’ cu mv E’
Weight Φp’ (⁰)
Type (kN/m2) (kPa) (m2/MN) (MPa)
(Mg/m3)
Possible
Solifuction 1.9 - 28 35 0.5 14
Deposits
Glacial Till 0.1
(Cohesive) (between
85
ground
level and 40
85 + 10 z (z
2.0 2 32 2mbgl)
= metres 40+ 12z (z = metres
below below 5mbgl)
0.03
2mbgl)
(below
2mbgl)
Unit
Material UCS
Weight GSI mi E’ (MPa) D
Type (MPa)
(Mg/m3)
BMF
(Mudstone) 2.6 13 35 8 200 0.7
BEARING CAPACITY
Not applicable.
RETAINING STRUCTURE DETAILS
Face Height
Face Angle 90⁰ 4.5
(max)
Bored pile
0.75m Pile Length Varies 10.0m – 13.6m
diameter
2
SETTLEMENT N/A
Immediate Total
Founding Level Time Settlement remaining
Structure Element Settlement Settlement
(mAOD) for 90% at completion
(mm) (mm)
CHEMICAL ANALYSIS
CHLORIDE (%) - - - -
pH - 5.9 - -
Mg - - - -
REDOX - - - -
Water soluble
- -
sulfate (mg/l)
Buried Concrete Design Sulfate and Aggressive Chemical
DS1 AC-2z
Environment for Concrete Classes:
Notes:
Chemical analyses were undertaken on samples from borehole 3/BH80
N/A
NOTES
None.
3
Geotechnical Design Report Volume 2: Structures
B2191100/D2/1/2/059
Geotechnical Summary Information Sheet – GURNOS (h ≥ 4.5m)
CHAINAGE
Eastbound: ch. 12920m-13120m Reference /
STRUCTURE NAME
and 13220m-13270m Comments
Westbound (main line): ch.
Gurnos Contiguous Bored Pile Retaining
13060m-13290m
walls (h ≥ 4.5m)
Westbound (slip road): ch.
12995m-13060m
GEOTECHNICAL PARAMETERS
Earth Pressure: These coefficients assume horizontal retained ground level.
Made Ground Glacial Till
Glacial Till (Granular) LCM
(Granular) (Cohesive)
Ko = 0.470 Ko = 0.426 Ko = 0.470
Ko = 1.500
Ka = 0.307 Ka = 0.271 Ka = 0.307
Kp = 3.255 Kp = 3.690 Kp = 3.255
1
Unit
Material c’ cu mv E’
Weight Φp’ (⁰)
Type (kN/m2) (kPa) (m2/MN) (MPa)
(Mg/m3)
Made 0.1
Ground (between
(Granular) ground
level and
20 (between ground
2mbgl)
2.0 - 32 - level and 4mbgl)
80(below 4mbgl)
0.05
(below
2mbgl)
Glacial Till
(Granular) 2.0 - 35 - - 70
Glacial Till 0.1
(Cohesive) (between
85
ground
level and 40
85 + 10 z (z
2.0 2 32 2mbgl)
= metres 40+ 12z (z = metres
below below 5mbgl)
0.03
2mbgl)
(below
2mbgl)
Unit
Material UCS
Weight GSI mi E’ (MPa) D
Type (MPa)
(Mg/m3)
BMF
(Mudstone) 2.6 13 35 8 200 0.7
Face Height
Face Angle 90⁰ 8.6m
(max)
Bored pile
1.5m Pile Length Varies 15.0m – 24.1m
diameter
BEARING CAPACITY
Not applicable.
2
PILE DESIGN N/A
Pile Width Pile Pile Working Load (kN)
Founding Toe Level
Structure Element (m) Length
Stratum (mAOD)
(m)
SETTLEMENT N/A
Immediate Total
Founding Level Time Settlement remaining
Structure Element Settlement Settlement
(mAOD) for 90% at completion
(mm) (mm)
CHEMICAL ANALYSIS
CHLORIDE (%) - - - -
pH - 5.9 - -
Mg - - - -
REDOX - - - -
Water soluble
- -
sulfate (mg/l)
Buried Concrete Design Sulfate and Aggressive Chemical
DS1 AC-2z
Environment for Concrete Classes:
Notes:
Chemical analyses were undertaken on samples from borehole 3/BH80
N/A
NOTES
None.
3
Geotechnical Design Report Volume 2: Structures
B2191100/D2/1/2/059
Geotechnical Summary Information Sheet – GURNOS (at roundabout)
GEOTECHNICAL PARAMETERS
Earth Pressure: These coefficients assume horizontal retained ground level.
Made Ground Glacial Till (Cohesive) LCM
Ko = 0.470 Ko = 1.000
Ko = 1.500
Ka = 0.307 Ka = 0.307
Kp = 3.255 Kp = 3.255
1
Unit
Material c’ cu mv E’
Weight Φp’ (⁰)
Type (kN/m2) (kPa) (m2/MN) (MPa)
(Mg/m3)
Made 0.1 (between
Ground ground level
20 (between
and 2mbgl)
ground level and
2.0 - 32 -
4mbgl)
0.05 (below
80(below 4mbgl
2mbgl)
Glacial Till
85 0.1 (between
(Cohesive)
ground level 40
85 + 10 z (z and 2mbgl)
2.0 2 32 40+ 12z (z =
= metres
metres below
below 0.03 (below
5mbgl)
2mbgl) 2mbgl)
Unit
Material UCS
Weight GSI mi E’ (MPa) D
Type (MPa)
(Mg/m3)
LCM
(Mudstone) 2.5 25 45 14 750 0.7
BEARING CAPACITY
Not applicable.
RETAINING STRUCTURE DETAILS
Face Height
Face Angle 90⁰ 8.3
(max)
Bored pile
1.5m Pile Length 14.7m
diameter
2
SETTLEMENT N/A
Immediate Total
Founding Level Time Settlement remaining
Structure Element Settlement Settlement
(mAOD) for 90% at completion
(mm) (mm)
CHEMICAL ANALYSIS
SO4 (%) - - - -
CHLORIDE (%) - - - -
pH - - - -
Mg - - - -
REDOX - - - -
Water soluble
- -
sulfate (mg/l)
Buried Concrete Design Sulfate and Aggressive Chemical
DS1 AC-2z
Environment for Concrete Classes:
Notes:
-
None.
3
Geotechnical Design Report Volume 2: Structures
B2191100/D2/1/2/059
Geotechnical Summary Information Sheet – GURNOS/ GALON UCHAF
GEOTECHNICAL PARAMETERS
Earth Pressure: These coefficients assume horizontal retained ground level.
Made Ground Glacial Till (Cohesive) BMF
Ko = 0.470 Ko = 1.000
Ko = 1.500
Ka = 0.307 Ka = 0.307
Kp = 3.255 Kp = 3.255
1
Unit
Material c’ cu mv E’
Weight Φp’ (⁰)
Type (kN/m2) (kPa) (m2/MN) (MPa)
(Mg/m3)
Made 0.1 (between
Ground ground level
20 (between
and 2mbgl)
ground level and
2.0 - 32 -
4mbgl)
0.05 (below
80(below 4mbgl
2mbgl)
Glacial Till
85 0.1 (between
(Cohesive)
ground level 40
85 + 10 z (z and 2mbgl)
2.0 2 32 40+ 12z (z =
= metres
metres below
below 0.03 (below
5mbgl)
2mbgl) 2mbgl)
Unit
Material UCS
Weight GSI mi E’ (MPa) D
Type (MPa)
(Mg/m3)
BMF
(Mudstone) 2.6 13 35 8 200 0.7
Face Height
Face Angle 90⁰ 10.7
(max)
BEARING CAPACITY
Not applicable.
2
PILE DESIGN N/A
Pile Width Pile Pile Working Load (kN)
Founding Toe Level
Structure Element (m) Length
Stratum (mAOD)
(m)
SETTLEMENT N/A
Immediate Total
Founding Level Time Settlement remaining
Structure Element Settlement Settlement
(mAOD) for 90% at completion
(mm) (mm)
CHEMICAL ANALYSIS
CHLORIDE (%) - - - -
pH - 7.9, 8.5 - -
Mg - - - -
REDOX - - - -
Water soluble
- -
sulfate (mg/l)
Buried Concrete Design Sulfate and Aggressive Chemical
DS1 AC-2z
Environment for Concrete Classes:
Notes:
Chemical analyses were undertaken on samples from boreholes 3/BH72, 3/BH74, 3/BH75
N/A
NOTES
None.
3
Geotechnical Design Report Volume 2: Structures
B2191100/D2/1/2/059
Geotechnical Summary Information Sheet – GURNOS/BRYNIAU RD
STRUCTURE NAME
CHAINAGE
Reference /
Eastbound: ch. 13,880m
Bryniau Road Contiguous Bored Pile Comments
Retaining walls
STRUCTURE TYPE AIP Ref No.
GEOTECHNICAL PARAMETERS
Earth Pressure: These coefficients assume horizontal retained ground level.
Made Ground Glacial Till (Cohesive) Sandstone
Ko = 0.470 Ko = 1.000
Ko = 1.500
Ka = 0.307 Ka = 0.307
Kp = 3.255 Kp = 3.255
1
Unit
Material c’ cu mv E’
Weight Φp’ (⁰)
Type (kN/m2) (kPa) (m2/MN) (MPa)
(Mg/m3)
Made
50
Ground 0.1 (between
(between
ground level
ground 20 (between
and 2mbgl)
level &4m ground level and
2.0 - 32
bgl) 4mbgl)
0.05 (below
80(below 4mbgl)
200 (below 2mbgl)
4m bgl)
Glacial Till
85 0.1 (between
(Cohesive)
ground level 40
85 + 10 z (z and 2mbgl)
2.0 2 32 40+ 12z (z =
= metres
metres below
below 0.03 (below
5mbgl)
2mbgl) 2mbgl)
Unit
Material UCS
Weight GSI mi E’ (MPa) D
Type (MPa)
(Mg/m3)
Sandstone
2.6 50 50 17 1500 0.7
BEARING CAPACITY
Not applicable.
RETAINING STRUCTURE DETAILS
Face Height
Face Angle 90⁰ 2.4
(max)
Bored pile
0.6m Pile Length 10.8m
diameter
2
SETTLEMENT N/A
Immediate Total
Founding Level Time Settlement remaining
Structure Element Settlement Settlement
(mAOD) for 90% at completion
(mm) (mm)
CHEMICAL ANALYSIS
CHLORIDE (%) - - - -
pH - 7.9 - -
Mg - - - -
REDOX - - - -
Water soluble
- -
sulfate (mg/l)
Buried Concrete Design Sulfate and Aggressive Chemical
DS1 AC-2z
Environment for Concrete Classes:
Notes:
Chemical analyses were undertaken on samples from boreholes 3/BH74 and 3/BH75
N/A
NOTES
None.
3
Geotechnical Design Report Volume 2: Structures
B2191100/D2/1/2/059
Geotechnical Summary Information Sheet – GALON UCHAF
STRUCTURE NAME
CHAINAGE
Reference /
Westbound: ch. 14080m-14320m
Galon Uchaf Industrial Estate Contiguous Comments
Bored Pile Retaining wall
STRUCTURE TYPE AIP Ref No.
Made Ground
Loose to very loose Sand 0 to 10.00 GIR/PSSR/
Exploration
Associates Ltd (1999)
Bishopston Mudstone Formation Below 10.00 or +313.00mAOD
Moderately strong Mudstone, very stiff
Siltstone
PREVIOUS GROUND HISTORY Existing Highway (A465) PSSR
CONTAMINATION RISK ASSESSMENT Preliminary contamination
assessment risk is LOW.
Detailed assessment to be
PSSR
presented in the final Land Quality
Ground Investigation Report (Ref:.
B2191100/D2/1/2/045).
GROUNDWATER GIR/PSSR/
No records available at the wall
Exploration
location
Associates Ltd (1999)
GEOTECHNICAL PARAMETERS
Earth Pressure: These coefficients assume horizontal retained ground level.
Made Ground BMF
Ko = 0.470
Ko = 1.500
Ka = 0.307
Kp = 3.255
1
Unit
Material c’ cu mv E’
Weight Φp’ (⁰)
Type (kN/m2) (kPa) (m2/MN) (MPa)
(Mg/m3)
Made 0.1 (between
Ground ground level
20 (between
and 2mbgl)
ground level and
2.0 - 32 -
4mbgl)
0.05 (below
80(below 4mbgl
2mbgl)
Unit
Material UCS
Weight GSI mi E’ (MPa) D
Type (MPa)
(Mg/m3)
BMF
2.6 13 35 8 200 0.7
BEARING CAPACITY
Not applicable.
RETAINING STRUCTURE DETAILS
Face Height
Face Angle 90⁰ 4.5
(max)
Bored pile
1.2m Pile Length 14.0m
diameter
2
SETTLEMENT N/A
Immediate Total
Founding Level Time Settlement remaining
Structure Element Settlement Settlement
(mAOD) for 90% at completion
(mm) (mm)
CHEMICAL ANALYSIS
SO4 (%) - - - -
CHLORIDE (%) - - - -
pH - - - -
Mg - - - -
REDOX - - - -
Water soluble
- -
sulfate (mg/l)
Buried Concrete Design Sulfate and Aggressive Chemical
DS1 AC-2z
Environment for Concrete Classes:
Notes:
N/A
NOTES
None.
3
Geotechnical Design Report Volume 2: Structures
B2191100/D2/1/2/059
Geotechnical Summary Information Sheet – Nant Moel
STRUCTURE NAME
Nant Moel Contiguous Bored Pile CHAINAGE Reference /
Retaining wall ch. 6350m Comments
GEOTECHNICAL PARAMETERS
Earth Pressure: These coefficients assume horizontal retained ground level.
Glacial Till (Cohesive) BMF
Ko = 1.0
Ko = 1.500
Ka = 0.307
Kp = 3.255
Unit
Material cp’ cu mv E’
Weight Φp’ (⁰)
Type (kN/m2) ( kN/m2) (m2/MN) (MPa)
(Mg/m3)
Glacial Till 75
40
(Cohesive) 75+ 10z
40 + 6z
(z = meters
2.1 2 32 0.1 (z = metres
below
below 5.0m.bgl)
5.0m.bgl)
1
BMF
(Mudstone) 2.0 20 42 - - 200
BEARING CAPACITY
Not applicable.
Face Height
Face Angle 90⁰ 3.5m
(max)
Bored pile
0.90m Pile Length 11.5m
diameter
2
PILE DESIGN N/A
Pile Width Pile Pile Working Load (kN)
Founding Toe Level
Structure Element (m) Length
Stratum (mAOD)
(m)
SETTLEMENT N/A
Immediate Total
Founding Level Time Settlement remaining
Structure Element Settlement Settlement
(mAOD) for 90% at completion
(mm) (mm)
CHEMICAL ANALYSIS
SO4 (%) - - - -
CHLORIDE (%) - - - -
pH - 7.1 - -
Mg - - - -
REDOX - - - -
Water soluble
170
sulfate (mg/l)
Buried Concrete Design Sulfate and Aggressive Chemical
DS1 AC-2z
Environment for Concrete Classes:
Notes:
Chemical analyses were undertaken on samples from borehole 3/BH137
N/A
NOTES
None.
3
Geotechnical Design Report Volume 2: Structures
B2191100/D2/1/2/059
Geotechnical Summary Information Sheet –A470 Junction
STRUCTURE NAME
A470 Contiguous Bored Pile Retaining CHAINAGE Reference /
wall ch. 10350m to 10660m Comments
GEOTECHNICAL PARAMETERS
Earth Pressure: These coefficients assume horizontal retained ground level.
Glacial Till (Cohesive) Glacial Till (Granular) BMF
Ko = 1.0 Ko = 0.412
Ko = 1.500
Ka = 0.307 Ka = 0.260
Kp = 3.255 Kp = 3.852
1
Unit
Material cp’ cu mv E’
Weight Φp’ (⁰)
Type (kN/m2) ( kN/m2) (m2/MN) (MPa)
(Mg/m3)
Glacial Till
60
(Granular)
2.0 0 36 - - 60 + 34z
(z = metres below
5mbgl)
Glacial Till 75
(Cohesive) 75+ 10z 40
(z = meters 40 + 6z
2.1 2 32 0.1
(z = metres below
below
5.0m.bgl)
5.0m.bgl)
BMF
(Mudstone) 2.0 20 42 - - 200
BEARING CAPACITY
Not applicable.
Face Height
Face Angle 90⁰ 4m
(max)
Bored pile
0.60m Pile Length 10.0m
diameter
2
PILE DESIGN N/A
Pile Width Pile Pile Working Load (kN)
Founding Toe Level
Structure Element (m) Length
Stratum (mAOD)
(m)
SETTLEMENT N/A
Immediate Total
Founding Level Time Settlement remaining
Structure Element Settlement Settlement
(mAOD) for 90% at completion
(mm) (mm)
CHEMICAL ANALYSIS
CHLORIDE (%) - - - -
pH - 8.9 - -
Mg - - - -
REDOX - - - -
Water soluble
-
sulfate (mg/l)
Buried Concrete Design Sulfate and Aggressive Chemical
DS1 AC-2z
Environment for Concrete Classes:
Notes:
Chemical analyses were undertaken on samples from borehole 3/BH106
N/A
NOTES
None.
3
Geotechnical Design Report Volume 2: Structures
B2191100/D2/1/2/059
Geotechnical Summary Information Sheet – A470 CEMETERY
RETAINING WALL
STRUCTURE NAME
CHAINAGE
Reference /
Southbound Ch. 300m – 510m;
A470 Cemetery Retaining Wall Comments
on A470
STRUCTURE TYPE AIP Ref No.
RELEVANT BOREHOLES
SOILS / GEOLOGY BGS
SO00NW/276 and SO00NW/278
GEOTECHNICAL PARAMETERS
Earth Pressure: These coefficients assume horizontal retained ground level.
Glacial Till (Cohesive) Glacial Till (Granular) LCM
K0 = 0.47 K0 = 0.47
Ka = 0.31 Ka = 0.31
Kp = 3.3 Kp = 3.3
1
Unit
C p’ mv E’
Material Type Weight Φp’ (⁰)
(kN/m2) (m2/MN) (MPa)
(Mg/m3)
Glacial Till
20
(Cohesive) 2.0 2 32 0.1
Glacial Till
2.0 0 32 - 35
(Granular)
Weathered Lower
2.5 20 42 - 500
Coal Measures
BEARING CAPACITY
Not applicable.
Bored pile
0.9m Pile Length (m) 14.0m
diameter
2
SETTLEMENT N/A
Immediate Total
Founding Level Time Settlement remaining
Structure Element Settlement Settlement
(mAOD) for 90% at completion
(mm) (mm)
CHEMICAL ANALYSIS
SO4 (%) - - - -
CHLORIDE (%) - - - -
pH - - - -
Mg - - - -
REDOX - - - -
Water soluble
-
sulfate (mg/l)
Buried Concrete Design Sulfate and Aggressive Chemical
DS1 AC-2z
Environment for Concrete Classes.
Note: These correspond with the conditions assessed from chemical tests on samples collected across
the whole route of section 6 of A465.
OTHER DESIGN FEATURES (e.g. foundation treatment/hazards)
N/A
NOTES
None.
3
Geotechnical Design Report Volume 2: Structures
B2191100/D2/1/2/059
Geotechnical Design Report Volume 2: Structures
B2191100/D2/1/2/059
Approval in Principle: Reinforced Earth Retaining Walls
STRUCTURE NAME
CHAINAGE Reference /
Gurnos Farm cottages Ch. 12530m to 12620m Comments
GEOTECHNICAL PARAMETERS
cu
Unit
Cohesion mv E’
Material Weight Angle of
(MPa)
Type 2 Friction, φp’, ° 2
3 (kN/m ) (cp’) (m /MN) (MPa)
(kN/m )
6I/6J
Reinforced - -
20 0 36 -
Fill
0.1 20
(between
ground 20 +6 z
Embankment
85 level and 2 (where z
Fill 20 2 32
m bgl) = metres
below 5
0.03 (below m bgl)
2 m bgl)
Glacial Till
- 35
(Granular) 20 - 36 -
Unit
Bedrock Weight mi E’ (MPa)
Parameters UCS (MPa) GSI D
3
(kN/m )
Twrch
Sandstone 17 1500
26 50 50 0.7
Formation
BEARING CAPACITY
Founding
Footing Allowable Bearing
Structure Founding Level
Size Pressure
Element Stratum mAOD / 2
(m x m) kN/m
(mbgl)
Notes: Bearing capacities are to be confirmed once the retaining wall option has been chosen.
Approval in Principle: Reinforced Earth Retaining Walls
Face Height
Face Angle 90 ˚ 6.45 m
(max)
Layer
Facing Type Concrete Panels 0.5m
Spacing
Foundation
Granular Glacial Till (replaced)
Conditions
PILE DESIGN
N/A
SETTLEMENT N/A
Immediate Total
Founding Level Time Settlement remaining
Structure Element Settlement Settlement
(mAOD) for 90% at completion
(mm) (mm)
N/A
Note : The reinforced soil retaining wall structure will be designed to accommodate differential settlement
of up to 1 in 100 (Table 17, p.87, BS 8006-1:2010),corresponding with maximum differential settlements of
100mm along a 10m length of wall.
During detailed design stage, a full assessment of the settlement will be required.
CHEMICAL ANALYSIS
SO4 (%) - - - -
CHLORIDE (%) - - - -
pH - - - -
Approval in Principle: Reinforced Earth Retaining Walls
Mg - - - -
REDOX - - - -
Buried Concrete Design Sulfate and Aggressive Chemical
DS1 AC-2z
Environment for Concrete Classes:
Notes:
1) No chemical analysis was carried out in this borehole.
2) These correspond with the conditions assessed from chemical tests on samples collected across the
whole route of section 5.
OTHER DESIGN FEATURES (e.g. foundation treatment/hazards)
N/A
NOTES
2
1) Soft spots (material with an undrained shear strength less than 40kN/m ) encountered at founding
level shall be dug out and replaced with acceptable granular fill material
2) Ground Conditions at the formations to be confirmed by the Designer’s Geotechnical Site
Representative (DGSR) to confirm that the ground conditions are in accordance with the design
assumptions.
3) Exposed cohesive glacial till is susceptible to softening on wetting up upon exposure and hence
could be an issue for earthworks and formations.
Geotechnical Design Report Volume 2: Structures
B2191100/D2/1/2/059
Approval in Principle: Reinforced Earth Retaining Walls
STRUCTURE NAME
CHAINAGE
Reference /
Ch. 12390m to 12510m
Gurnos Ring Road South Comments
Ch. 12560m to 12660m
STRUCTURE TYPE AIP Ref No.
GEOTECHNICAL PARAMETERS
cu
Unit
Cohesion mv E’
Material Weight Angle of
(MPa)
Type 2 Friction, φp’, ° 2
3 (kN/m ) (cp’) (m /MN) (MPa)
(kN/m )
6I/6J
Reinforced - -
20 0 36 -
Fill
0.1 20
(between
ground 20 +6 z
Embankment
85 level and 2 (where z
Fill 20 2 32
m bgl) = metres
below 5
0.03 (below m bgl)
2 m bgl)
Glacial Till
- 35
(Granular) 20 - 36 -
Unit
Bedrock Weight mi E’ (MPa)
Parameters UCS (MPa) GSI D
3
(kN/m )
Twrch
Sandstone 17 1500
26 50 50 0.7
Formation
BEARING CAPACITY
Founding
Footing Allowable Bearing
Structure Founding Level
Size Pressure
Element Stratum mAOD / 2
(m x m) kN/m
(mbgl)
Notes: Bearing capacities are to be confirmed once the retaining wall option has been chosen.
Approval in Principle: Reinforced Earth Retaining Walls
Layer
Facing Type Concrete Panels 0.5m
Spacing
Foundation
Granular Glacial Till (replaced)
Conditions
PILE DESIGN
N/A
SETTLEMENT
Immediate Total
Founding Level Time Settlement remaining
Structure Element Settlement Settlement
(mAOD) for 90% at completion
(mm) (mm)
N/A
Note : The reinforced soil retaining wall structure will be designed to accommodate differential settlement
of up to 1 in 100 (Table 17, p.87, BS 8006-1:2010),corresponding with maximum differential settlements of
100mm along a 10m length of wall.
During detailed design stage, a full assessment of the settlement will be required.
CHEMICAL ANALYSIS
SO4 (%) - - - -
CHLORIDE (%) - - - -
Approval in Principle: Reinforced Earth Retaining Walls
pH - - - -
Mg - - - -
REDOX - - - -
Buried Concrete Design Sulfate and Aggressive Chemical
DS1 AC-2z
Environment for Concrete Classes:
Notes:
1) No chemical analysis was carried out in this borehole.
2) These correspond with the conditions assessed from chemical tests on samples collected across the
whole route of section 5.
OTHER DESIGN FEATURES (e.g. foundation treatment/hazards)
N/A
NOTES
2
1) Soft spots (material with an undrained shear strength less than 40kN/m ) encountered at founding
level shall be dug out and replaced with acceptable granular fill material
2) Ground Conditions at the formations to be confirmed by the Designer’s Geotechnical Site
Representative (DGSR) to confirm that the ground conditions are in accordance with the design
assumptions.
3) Exposed cohesive glacial till is susceptible to softening on wetting up and hence could be an issue
for earthworks and formations.
Geotechnical Design Report Volume 2: Structures
B2191100/D2/1/2/059
Approval in Principle: Reinforced Earth Retaining Walls
the structure.
From 3/BH66
(3)
Made Ground (Granular)
Loose to medium dense dark grey and 6.3 m bgl
brown slightly clayey silty very sandy (fine
to coarse) angular to subangular GRAVEL
of clinker, slag, brick, sandstone and
occasional subangular to angular cobbles
GEOTECHNICAL PARAMETERS
Unit
Material Cohesion Angle of cu (MPa) mv E’
Weight 2 2
Type 3 (kN/m ) (cp’) Friction, φp’, ° (m /MN) (MPa)
(kN/m )
6I/6J
Reinforced - -
20 0 40 -
Fill
20
0.1
20 +6 z
Embankment (between
- (where z
Fill 20 2 32 ground
= metres
level and 2
below 5
m bgl)
m bgl)
10
0.1 (between
(between ground
Made
ground level and
Ground 75
level and 2 4 m bgl)
(Cohesive / 19.6 0 32 ˚
Granular) m bgl)
40
0.05 (below (below 4
2 m bgl) m bgl)
Unit
Bedrock Unit
UCS (MPa) GSI mi D E’ (MPa)
Parameters Weight
3
(kN/m )
Bishopston
Mudstone
8 200
Formation – 26 13 35 0.7
Mudstone
Lower coal
14 750
Measures 25 25 45 0.7
Approval in Principle: Reinforced Earth Retaining Walls
BEARING CAPACITY
Founding
Footing Allowable Bearing
Structure Founding Level
Size Pressure
Element Stratum mAOD / 2
(m x m) kN/m
(mbgl)
Notes: Bearing capacities are to be confirmed once the retaining wall option has been chosen.
Layer
Facing Type Concrete Panels 0.5m
Spacing
Foundation
Cohesive Made Ground
Conditions
PILE DESIGN
N/A
SETTLEMENT
Immediate Total
Founding Level Time Settlement remaining
Structure Element Settlement Settlement
(mAOD) for 90% at completion
(mm) (mm)
N/A
Note : The reinforced soil retaining wall structure will be designed to accommodate differential settlement
of up to 1 in 100 (Table 17, p.87, BS 8006-1:2010),corresponding with maximum differential settlements of
100mm along a 10m length of wall.
During detailed design stage, a full assessment of the settlement will be required.
Approval in Principle: Reinforced Earth Retaining Walls
CHEMICAL ANALYSIS
CHLORIDE (%) - - - -
pH - 4.3-7.6 - -
Mg - - - -
REDOX - - - -
Buried Concrete Design Sulfate and Aggressive Chemical
DS1 AC-2z
Environment for Concrete Classes:
Notes:
1) No chemical analysis was carried out in this borehole.
2) These correspond with the conditions assessed from chemical tests on samples collected across the
whole route of section 5.
OTHER DESIGN FEATURES (e.g. foundation treatment/hazards)
N/A
NOTES
2
4) Soft spots (material with an undrained shear strength less than 40kN/m ) encountered at founding
level shall be dug out and replaced with acceptable granular fill material
5) Ground Conditions at the formations to be confirmed by the Designer’s Geotechnical Site
Representative (DGSR) to confirm that the ground conditions are in accordance with the design
assumptions.
6) Exposed cohesive glacial till (or embankment fill) is susceptible to softening on wetting up upon
exposure and hence could be an issue for earthworks and formations.
Geotechnical Design Report Volume 2: Structures
Appendix C. Specifications
Appendix 1/5
It is anticipated that Specification Appendix Table 1/5 as per the Notes for Guidance, Volume 2 of the Manual of
Contract Documents for Highway Works (MCHW) shall be adopted and amended as appropriate by the detailed
designer and other organisations employed to complete follow-on work by the Client.
B2191100/D2/1/2/059
Geotechnical Design Report Volume 2: Structures
B2191100/D2/1/2/059
A465 – Heads of the Valleys Dualling Sections 5 & 6
Welsh Government
B2191100-D2-1-2-174 | W0
6 June 2017
B2191100
© Copyright 2017 Jacobs U.K. Limited. The concepts and information contained in this document are the property of Jacobs. Use or copying of
this document in whole or in part without the written permission of Jacobs constitutes an infringement of copyright.
Limitation: This document has been prepared on behalf of, and for the exclusive use of Jacobs’ client, and is subject to, and issued in accordance with, the
provisions of the contract between Jacobs and the client. Jacobs accepts no liability or responsibility whatsoever for, or in respect of, any use of, or reliance
upon, this document by any third party.
B2191100-D2-1-2-174 i
Strengthened Earthworks Appraisal Form – Outline SEAF
Contents
1. Scheme Details .......................................................................................................................................... 1
1.1 Name of Scheme ......................................................................................................................................... 1
1.2 Type of Highway .......................................................................................................................................... 1
1.3 Permitted Traffic Speed ............................................................................................................................... 1
1.4 Nature of scheme/scheme elements ........................................................................................................... 1
2. Strengthened Earthwork Type, Purpose and Location ......................................................................... 1
2.1 Generic Type of Strengthened Earthwork ................................................................................................... 1
2.2 Purpose of Strengthened Earthwork ........................................................................................................... 1
2.3 Intended Location(s) for Use ....................................................................................................................... 1
3. Outline of Existing Ground and Groundwater Conditions .................................................................... 3
3.1 Ground Investigation Data........................................................................................................................... 3
3.2 Existing Ground Conditions ......................................................................................................................... 3
3.3 Existing Groundwater Conditions ................................................................................................................ 3
3.4 Soil and Groundwater Chemistry ................................................................................................................ 3
3.5 Existing Geotechnical Problems.................................................................................................................. 3
4. Proposed Strengthened Earthworks ....................................................................................................... 4
4.1 Description of Strengthened Earthwork....................................................................................................... 4
4.2 Foundation Preparation, including any Measures to deal with Geotechnical Problems ............................. 4
4.3 Materials to be used in Construction ........................................................................................................... 4
4.4 Drainage Measures ..................................................................................................................................... 4
4.5 Arrangements for Highway Furniture and Buried Services and Landscaping ............................................ 4
4.6 Inspection and Maintenance ....................................................................................................................... 4
4.7 Interface with Other Structures.................................................................................................................... 5
5. Design Methods ......................................................................................................................................... 5
5.1 Internal Stability ........................................................................................................................................... 5
5.2 External/Global Stability .............................................................................................................................. 5
6. Design/Assessment Criteria..................................................................................................................... 5
6.1 List of Relevant Documents ........................................................................................................................ 5
6.2 Limit State Design Criteria ........................................................................................................................... 5
6.3 Serviceability Design Criteria ...................................................................................................................... 5
6.4 Design Parameters for Soils and Materials ................................................................................................. 6
6.5 Design Groundwater Conditions ................................................................................................................. 6
6.6 Live Loadings .............................................................................................................................................. 6
6.7 Description/Diagram of Idealised Structure Model to be used in Analysis.................................................. 6
6.8 Precautions against Chemical Attack to Materials ...................................................................................... 7
6.9 Proposed Departures from Design Standards ............................................................................................ 7
7. Checking .................................................................................................................................................... 7
8. Drawings and Documents ........................................................................................................................ 7
8.1 List of drawings and documents accompanying submission ...................................................................... 7
B2191100-D2-1-2-174 ii
Strengthened Earthworks Appraisal Form – Outline SEAF
B2191100-D2-1-2-174 iii
Strengthened Earthworks Appraisal Form – Outline SEAF
1. Scheme Details
1.1 Name of Scheme
The Welsh Government has proposed to undertake improvement works to the existing ‘A465 Heads of
the Valleys Road’ which involves widening the current A465 from a single to a dual carriageway.
Jacobs have been commissioned to continue these improvements along Section 5 and 6, comprising
the western end of the route.
Within the Baverstock area, the alignment of the mainline carriageway requires the construction of a
new embankment. In order to limit land-take, it is proposed to construct parts of the new embankment
using reinforced soil. The reinforced soil embankments are to be permanent structures with a design
life of 60 years.
Strengthened (reinforced) soil slopes, up to 50°, constructed using granular Class 6I/6J material and
founded on Cohesive Glacial Till.
To allow a new highway embankment to be constructed in areas where there is insufficient space for a
conventional embankment.
The locations of the proposed earthworks are indicated in Table 2-1 and are shown in Figure 2.1.
B2191100-D2-1-2-174 1
Strengthened Earthworks Appraisal Form – Outline SEAF
Maximum
Maximum
reinforced
Section Chainages (m) Location slope
slope height
angle (o)
(m)
Cross sections illustrating the critical slopes within each section are provided in Appendix D.
B2191100-D2-1-2-174 2
Strengthened Earthworks Appraisal Form – Outline SEAF
Relevant exploratory holes within this zone are 3/BH119 to 3/BH128. The Geological long section is
shown in Appendix A.
Stiff to very stiff mottled grey and brown fine to medium sandy silty CLAY with little fine to coarse sub-
angular to sub-rounded gravel and cobbles of sandstone and siltstone was recorded up to 5.5m before
encountering weathered bedrock (Lower Coal Measures).
Grey thickly laminated to very thinly bedded slightly to moderately weathered SANDSTONE,
SILTSTONE and MUDSTONE, moderately weak to moderately strong, generally recovered as
angular, tabular, coarse gravel and cobbles.
The groundwater in the area has been recorded very close to the existing ground level within 3/BH119
- 3/BH121, 3/BH125 and 3/BH127. The highest ground water level of 0.7m below ground level was
recorded in borehole 3/BH121. An overnight standing water level of 1.4m, 2.3m, 0.9m and 1.95m
below the ground levels were observed in boreholes 3/BH119, 3/BH120, 3/BH125 and 3/BH127
respectively.
The reinforcement geogrids will be placed in Class 6I/6J fill derived from site won granular glacial
till deposits. Chemical testing of the Glacial Till indicates a Design Sulfate class of DS-1.
The underlying Glacial Till is stiff to very stiff and not susceptible to significant settlements under
embankment loadings.
B2191100-D2-1-2-174 3
Strengthened Earthworks Appraisal Form – Outline SEAF
The strengthened earthworks comprise reinforced embankments with slopes up to 50° constructed
using Class 6I/6J material. The reinforced soil will be founded on cohesive Glacial Till. Details of the
reinforced embankment locations, slope angles and maximum heights are given in Table 2-1. Cross
sections of the critical slopes within each section are provided in Appendix D.
Following excavation to the foundation level, the formation shall be inspected. The formation is
expected to comprise stiff to very stiff cohesive Glacial Till. Any deleterious material at formation level
shall be removed and replaced with suitable fill.
Soil reinforcement will be polymer geogrid reinforcement, Tensar 40 RE or similar, constructed with
steel reinforcement facing units. Material partial factors used in the design shall be those stated in
the BBA certificate.
Main body fill material: Class 6I/6J complying with the Specification for Highway Works is proposed as
backfilling materials in construction in accordance with MCHW Series 600 Table 6/1.
Face topsoil: Class 5A or 5B (locally derived or imported topsoil), in accordance with MCHW Series
600 Table 6/1.
No specific drainage measures are proposed for the reinforced soil slope. The reinforced soil slope
will be constructed of relatively free draining Class 6I/6J granular fill.
4.5 Arrangements for Highway Furniture and Buried Services and Landscaping
A safety barrier is to be accommodated in the road verge and may have a localised effect on the
upper reinforcement layers of the reinforced soil slope.
Details of topsoiling, seed mix and maintenance will be determined during final design.
Routine inspection of the finished structure shall be in accordance with HD41/15. The face of the
slope will be seeded with a low-growing seed mix, precluding the need for ongoing
maintenance.
A RRS (Road Restraint System) is to be provided between the slope and the carriageway.
The front facing units will comprise steel reinforcement units and as such, would be unaffected
by fire. In the short-term, there may be some damage to the erosion matting, but this can be
replaced by attaching replacement matting over the top of the reinforcement in the damaged
area. In the long-term, the face will be covered by vegetation.
B2191100-D2-1-2-174 4
Strengthened Earthworks Appraisal Form – Outline SEAF
N/A
5. Design Methods
5.1 Internal Stability
The design of the reinforced soil slope shall be carried out in accordance with BS 8006-1:2016, as BS
EN 1997-1 does not currently cover the detailed design of reinforced soil slopes.
The internal stability of the reinforced soil slope will therefore be designed in accordance with BS8006-
1:2016 Code of Practice for Strengthened Reinforced Soils and other fills (Section 7). The design and
analysis will use Ultimate Limit State (ULS) and Serviceability Limit State (SLS) approaches where the
soil weight and live loading will be increased by appropriate partial load factors and the soil properties
and reinforcement strength will be reduced by appropriate partial material factors.
Internal stability calculations will be undertaken in accordance with BS8006-1:2016 Code of practice
for strengthened/reinforced soils and other fills.
The external stability assessment will be in accordance with BS8006-1:2016. Circular failure surfaces
will be analysed, passing beneath and beyond the reinforced zone to provide moment equilibrium.
6. Design/Assessment Criteria
6.1 List of Relevant Documents
Partial factors for ultimate limit state shall be in accordance with BS8006-1:2016 Code of practice for
strengthened/reinforced soils and other fills.
Partial factors for serviceability limit state shall be in accordance with BS8006-1:2016 Code of practice
for strengthened/reinforced soils and other fills.
B2191100-D2-1-2-174 5
Strengthened Earthworks Appraisal Form – Outline SEAF
Table 6.1 : Summary of characteristic design parameters for soils and rock
The shear strength parameters for the Lower Coal Measures will be derived using the Generalised
Hoek-Brown strength criterion for a fractured rock mass.
The highest overnight standing ground water level is recorded at 0.7m below ground level in 3/BH121.
The design groundwater level has therefore been considered at existing ground level as a worst case
scenario.
Eurocodes are generally ambiguous on the issue of surcharge loadings on embankments, with BS EN
1991-1 (Eurocode 1) only referring to ‘Actions on Structures’. The recommendations given in
BS8002:2015 shall therefore be adopted for design of the reinforced soil slope. In this regard, a live
load surcharge of 20 kN/m2 shall be applied at the top of the embankment.
B2191100-D2-1-2-174 6
Strengthened Earthworks Appraisal Form – Outline SEAF
None required.
7. Checking
The design will be subject to a Category 1 check.
Appendix B Relevant Correspondence and Documents from Consultation with Relevant Authorities.
The above Design and Construction Proposals are Submitted for Review.
Date: .....20/9/17.....
* delete as appropriate.
Signed: .....................................................................................
Employer's Agent
Name: ........................................................................................
Date: .........................................................................................
B2191100-D2-1-2-174 7
Strengthened Earthworks Appraisal Form – Outline SEAF
B2191100-D2-1-2-174
Crown copyright and database rights 2017 NOTES
Ordnance Survey 0100031673
1. Do not scale from this drawing.
2. Proposed layouts are shown indicatively and subject to
0-0005
further development and approval.
3. The Geological Long Section has been interpreted based on
-GE-060
the Exploration Associates LTD (1997) borehole information.
PLAN
R
C-HGT-D Existing Borehole (Exploration Associates Ltd, 1997)
7150
191100-J
7200
Historic Investigations (BGS)
7 250
2
730
ION SEE
735
S206
5
740
LQW Jacobs 2016 GI Trial Pits
S206
8500
NTINUAT
8450
0
745
8400
LQW
8350
750
S207
7 Proposed LQ Exploratory Holes
8300
FOR CO
7550
LQW
S206
8250
7600
7
LEGEND
8200
7650
LQW
-HGT-DR-GE-0600-0007
LQCP
8150
S207
7700
2014 LQW 4
S207 LQWS20
8100
7750
Ground Profile
2 73
8050
7800
LQW LQW
8000
TP11
7850
LQCP S207
7950
7900
2013 S206 4 0 Proposed Design Profile
9
TP11
5(WS
N:\HIG\B2191100 - A465 Section 5&6 Technical Advisor\D2 Deliverables\D2-2 Drawings\01 DRAWINGS\01 WIP\01 DRAWINGS\0600 Earthworks\2191100-JAC-HGT-DR-GE-0600-0006.dwg - 06/03/2017 11:50:50 - 2191100-JAC-HGT-DR-GE-0600-0006 - LoveysC
)
LQW Topsoil
S206 LQW
8 S20LQW
75 S2076 LQW
S207LQW Made Ground - Granular (MGG)
8 S20
79
LQW LQCP Made Ground - Cohesive (MGC)
S207
1
Peat
3/BH119
365
Open Hole Section
0.10 T
GTC
360 Void
3/BH120
LONG SECTION ?
?
?
2.90
3.80
4.25
GTG
GTG
LCM ?
?
?
Horizontal Scale = 1:2500,Vertical Scale= 1:1000 5.75 LCM Standing Water/Standpipe Water Level
355 GTC
? 7.10 LCM
?
Datum=240.000 1.50 LCM
Seepage level
3/BH121
2.30 LCM
? s
4.30 LCM
350 ?
3/BH123A
T
3/BH123
3/BH125
0.30 GTC
14.75 LCM
14.95 LCM
15.20 LCM
15.35 LCM
3/BH124B
3/BH124A
345
3/BH124
16.50 LCM
10.20 LCM 16.75 LCM
? 11.30 LCM
17.10
17.35
LCM
LCM
11.80 LCM
0.10 Peat
GTC 5.40 LCM
13.20 LCM
20.00
2.00 GTG
?
340
14.80 LCM
MGC
MGC 15.27 LCM
3.00 GTG T
0.25 GTC 8.40 LCM
3.40 LCM
? ? 16.15 LCM
4.50 LCM
2.06
2.25 GTC
?
2.60
2.55 LCM
3/BH127
? ? GTC
GTC 19.10 LCM
335 ? 20.20
? 1.90
2.55
? 15.05
GTC
? 8.00 Void
0.25 GTG
?
?
Level
330
Possible Solifluction deposits
9.60 LCM
?
2.60
?
?
325
(up to 3m depth). ?
?
?
?
?
13.18 LCM
? 19.60 LCM
17.00 LCM
? 19.20 LCM
320 ? ?
3/BH128
? 23.60
24.00
LCM
LCM
? ? 24.50 LCM
? ? ? 25.40
?
315 Peat
?
? ?
24.60
?
0.70 GTC
? ?
?
3/BH129
? 2.45 GTC
?
?
? ? ?
310 ?
? ?
? ? 5.90 GTG
? 0 75 150
? ?
? 7.10 LCM
? ? 0.15
Peat
GTC ?
? ? ?
? Metres
Level
? ? ? ? 8.90 LCM
305 2.00
3.00
GTC
? 11.35 LCM
- - - - - - -
?
?
300
14.20
6.90 GTC
0.15
Peat
GTC ? - - - - - - -
9.70 GTC
1.70 GTC 10.10 ? LCM
- - - - - - -
Twyn Ddisgwylfa Fault
295 ?
?
15.00
290
P01 06/05/16 - AG SN JL AD
285 Rev Rev. Date Purpose of revision Drawn Checkd Rev'd Apprv'd
R
280
?
?
Werfa Fa
265
260
Project
?
255
A465 SECTIONS 5 & 6
250
?
Drawing title
? ? ? ? ?
? ? ?
?
245 ? ? ? ? ?
GEOLOGICAL LONG
240
SECTION
329.281
334.411
296.560
339.722
360.762
300.688
303.968
307.436
309.534
309.890
311.429
310.963
313.625
316.077
316.817
320.078
324.680
326.969
331.830
337.024
341.978
341.368
343.598
346.396
349.127
352.075
354.284
357.557
361.084
362.130
362.136
EXISTING GL 6 OF 16
Drawing status
WORK IN PROGRESS
296.947
299.947
302.947
305.947
308.947
311.947
314.947
317.947
320.947
323.947
326.947
329.947
332.947
335.947
338.947
341.806
344.415
346.774
348.884
350.743
352.352
353.712
354.821
355.680
356.289
356.649
356.758
356.617
356.227
355.586
354.695
PROPOSED GL Scale 1:2500 @ A1
Jacobs No. 2191100
DO NOT SCALE FROM THIS DRAWING
Drawing number Rev
2191100-JAC-HGT-DR-GE-0600-0006 P03
7050.000
7100.000
7150.000
7200.000
7250.000
7300.000
7350.000
7400.000
7450.000
7500.000
7550.000
7600.000
7650.000
7700.000
7750.000
7800.000
7850.000
7900.000
7950.000
8000.000
8050.000
8100.000
8150.000
8200.000
8250.000
8300.000
8350.000
8400.000
8450.000
8500.000
8547.215
CHAINAGE Copyright 2017 Jacobs U.K. Limited. The concepts and information contained in this document are the property of Jacobs.
Use or copying of this document in whole or in part without the written permission of Jacobs constitutes an infringement of
AD
G
AW I N
T OC
responsibility whatsoever for, or in respect of, any use of, or reliance upon, this drawing by any third party.
R
AU
D
TOPSOIL ** (Possible made ground).
MUDSTONE **
Remarks Chiselled from 1.30m to 1.60m (55 mins), 1.80m to 2.lOm (30 mins), 2.70m to 2.90m (30 mins), 3.20m to
3.40m (60 mins), 3.40m to 3.80m (60 mins)
Overnight standlng water level of 1.40m noted on the 18/5/97.
ke key sheir
lnd appendices
br explanations. Form l/O
Remarks
1Remarks
97%
(63%) (48%)
a25
99%
(51%) (31%)
8
; 17.35
1) Bedding fractures subhorizontal 0” to IO”
planar smooth clean sometimes polished. t-
4
Dark gre slightly weathered MUDSTONE
moderate Yy weak with some carbonised plant
remains and with very closely spaced randomly -
orientated irregular incipient
discontinuities.
19.25
100%
(95%) (83%) 6
Remarks
ee kev sheer
nd appendices
1r explanations. Form l/O
Project Contract 166001-3
Borehole Record A465 Abergavenny to Hirwaun-Dualling
Ground Investigation, Section 3
Welsh Office Highways Directorate Borehole
Exploration Associates 3/BH119(4 of 4)
1 Sampling Strata
TYPO 1 :asing Date/ ;PT N Depth
lescription .evel Legend
CmSCR ROD1 Nater :ul /FI (Thickness)
8 o/o5 55.22
997 Stiff to very stiff grey and brown slightly
RY silt sandy (fine to medium) CLAY with a
litt Y e fine
- to coarse angular to subangular
gravel of sandstone and siltstone (possible
made ground).
7%
1.20-1.30
;m;.;g
. . ::/
F;;;;a”,“y PO PD
SK MJC
Checked gy RML AJ
100% >25 /
(13%) (0%)
cxxxxx
Grey very thinly to thinly bedded slightly cxxxxx
cxxxxx
weathered SILTSTONE moderately weak to cxxxxx
NI occasionally moderately strong. xxxxx
xxxxx
Prominent discontinuitles: xxxxx
1) Bedding fractures 0" to IO" planar locally _ xxxxx
xxxxx
undulating smooth open grey and brown sandy xxxxx
>25 clay smeared and iron stained. xxxxx
xxxxx
2) Subvertical fractures 75" to 90" lanar xxxxx
smooth closed and open brown sandy c v ay xxxxx
smeared and iron stained. xxxxx /
9.20 _ xxxxx
NI 3) Inclined fractures 20" to 40" closely - (1.85) xxxxx
spaced undulating irregular smooth open brown 1 xxxxx
xxxxx
sandy clay smeared-and iron stained. xxxxx
xxxxx
From 8.35m to 8.90m: with two intersecting xxxxx
sets of subvertical very closely to closely 1 xxxxx
-xXxXx
spaced cxxxxx
From 8.7Om to 8.90m: locally recovered non- - :xxxxx
100% 24 intact as fine to coarse angular gravel in - :XxXxX
:xxxxx
(50%) (12%) a matrix of a little sandy clay ~XXXXX
From 9.20m to 9.35m: recovered non-intact :xxxxx
:XxXxX
as grey clayey sandy fine to coarse angular - :xxxxx
gravel rxxxxx
Remarks
(weathered mudstone)
: black vitreous
with intersectin
irregular rough
discontinuities
Remarks
.
. 1.20-1.65
. 2.70-2.70
- 4.00-4.45
Remarks Chiselled from 1.70m to 1.85m (45 mins), 2.70m to 2.90m (60 mins), 2.90m to 3.OOm (60 mins), 3.00m to
3.15m (45 mins), 5.20m to 5.30m (60 mins), 5.30m to 5.40m (60 mins)
Water added to assist boring from 2.70m to 5.20m
See key sheet Flush returns 80%.
andappendices
for explanations. Form110
7
iampling , Strata
T
zpth / Drill Run rwe I Zasing late/ NPT N Depth
)escription -eve1 Legend
XSCR ROD) Water :u) IFI (Thickness)
E
5.00-5.31 C 3.90 I
3
3.90 2.90
5.20- 2/06 /
3.90
/
/
IO
,
6.90 /
.I
9.90 >2!
L
I-
:qoiPmeot: Cable Tool Percussion
d-ounawarer Ground Level 347.98 m 00
Rotary Coring-Mist Flush No. Struck Behaviour Sealed Coordinates
3o0355
207177.90 -70 24
lorehole Dia (mm) Casing Dia (mm)
200 to 5.40m EO$tcg :$Om “,;;r+-;;“,“y PO PD
S to 15.05m SK see
Checked gy AJ AJ
Remarks
ee key sheet
nd appendices
3r explanations. Form l/O
..
From 11.49m to Il.&m: recovered non-intact
as fine to coarse angular to subrounded
gravel sized fragments
Coordinates
Remarks
Sampling ’ Strata
Drill Run TCR Casing Date! SPT N Depth
Description Level Legend
(SCR) (RQD) Water FI (Thickness)
03/06
5.30 2.90 .............................................. - 15.05 332.93 /
15.05
End of Borehole.
Remarks
tY
RY
. 3.00- l/O5
1.90
3.00-3.01
3.30-3.40
3.60-3.65 3.6(
Remarks Chiselled from 1.60m to 1.70m (30 mins), 3.OOm to 3.1Om (45 mins), 3.3Om to 3.3Om (15 mins), 3.3Om to
3.60m (60 mins), 3.60m to 3.90m (60 mins), 5.50m to 5.7Om (60 mlns)
Mater added to assist boring from 3.90m to 5.70m
See key sheet Overnight standing water level of 1.90m noted on the 31/5/97.
andappendices
for explanations. Form l/O
End of Borehole.
ercussion
Remarks
Remarks Chiselled from .70m to .90m (15 mins), 1.50m to 1.90m (45 mins)
Borehole terminated at 1.90m on engineers instruction, unable to advance casing past large boulder.
Borehole repositioned to 3/BH123A.
lee key sheet
nd appendices
or explanations. Form I/O
. . . .._..............*.....................m...
End of Borehole.
Remarks Chiselled from 2.25m to 2.50m (60 mins), 2.50m to 2.50m (30 mins), 2.50m to 2.55m (30 mins)
No groundwater encountered
Borehole Dia (mm) Casing Dia (mm)
200 to 2.06m 200 to 1.20m
No groundwater encountered
Borehole Dia (mm) Casing Dia (mm)
200 to 2.55m 200 to 2.55m
Remarks Chiselled from .90m to .90m (45 mins), .90m to 1.20m (60 mins), 2.50m to 2.50m (60 mins), 2.50m to
2.50m (60 mins), 2.50m to 2.55m (30 mans)
Borehole terminated at 2.55m on clients instruction; large obstruction (boulder **). Borehole
Seekey sheet repositioned to 3/BH124B.
and appendices
for explanations. Form 110
Remarks Flush returns: 2.25-5.50m (60%), 5.50-8.00m (20%), 8.00-ll.ZOm (30%), 11.20-12.95m (60%), 12.95-20.9Om
(40%), 20.90-24.60m (60%).
Water level of 6.20m noted at end of shift (5/6/97).
lee key sheet
nd appendices
or explanations. Form 110
Remarks
64%
(0%) I%) NI
(1.27)
100%
(47%) 3%) 17
12.95
13.18
23
Light grey fine grained slightly weathered
100% SANDSTONE moderately stron thin1 to thickly
(54%) I%) interlaminated with slight 9 y weat x ered (0.42)
NI ;;s;;;one moderately weak to moderately
17
Light gre and grey fine and medium grained
very thin Y y to medium bedded slightly
weathered SANDSTONE moderately strong to
!%%%nt discontinuities:
1) Bedding fractures 0’ to IO” irregular
rough and clean occasionatly sand or silty
fine to medium sand coated (<lmm) frequent
iron staining.
2) Subvertical fractures 70” to 90” irregular
I( partially curved rough sand coated (<lmm) and -(2.30)
96% iron stalned,occasionally clean.
(72%: 24%)
9/06 .............
.............
.............
.............
.............
:::::::::::::
.............
~;iiiiiiiiiii
.............
.............
.............
.............
.............
.............
Ii .............
.............
.............
.............
.............
.............
.............
.............
.............
.............
.............
.............
.............
3.99
6.00 NF
From 15.90m to 16.10m: AZCL
i
I 16.10
90%
(31%) 1%) 1 (1.00)
-
I 17.10
18.15
h
z (1.35
I%)
-
18.70
30% - - 19.05
(12% I%)
19.20
91%
(91% 55%
-(I.851
20.00
Groundwater Ground Level 339.89 m 00
:oaiPIaeat: Odex Open Holed No. Struck Behaviour Sealed Coordinates 300155.30 I
Rotary Coring-Mist Flush 207085.41 I
Remarks
.I
Sampling Strata
Depth I Drill Run Type / Casing Date/ Depth
Description (Thickness) Level Legend
TCR(SCR) (RQD) Water KullFI
09/06 ..............
..............
.:::::::::::::
.............
.............
............. ,
.............
... .........
... . .........
.............
.............
.............
.............
.............
.............
.............
.............
.............
.............
:::::::::::::
.............
.............
.............
96% 9 .............
.............
.............
.............
(96%) (73%) :::::::::::::
.............
From 20.56m to 20.64m: 35" fracture .............
:::::::::::::
.............
irregular rough and clean- .............
.............
.............
.............
.............
.............
.............
.............
.............
.............
.............
.............
.............
:::::::::::::
.............
.............
20.90 I 20.90 318.99
I 21.33
57%
(28%) (0%)
>25
12 /;
/
86%
(81%) (44%)
,
J-K - 22.50 317.39 ::::::::::::::
6
22.60 From 22.50m to 22.60m: AZCL I 22.60 317.29 .w
... ...... .: ...
..............
..............
:::::::::::::
............. /,
.............
.............
:::::::::::::
.............
.............
.............
.............
............. /'
.............
.............
.............
.............
.............
.............
.............
:::::::::::::
............. i ,/"
.............
.............
9 .............
.............
.............
.............
.............
.............
............. :'
:::::::::::::
.............
.............
.............
:::::::::::::
.............
.............
.............
:::::::::::::
.............
............. I
:::::::::::::
.............
.............
.............
- (1.81) .............
.............
.............
91% :::::::::::::
.............
.............
............. /
(88%) (81%) .............
:::::::::::::
.............
.............
.............
:::::::::::::
.............
.............
.............
.............
:::::::::::::
.............
.............
.............
.............
.............
4 .............
.............
.............
.............
.............
:::::::::::::
............. ./
.............
.............
From 24.14m to 24.19m: with some fine to .............
.............
.............
.............
coarse subanguiar to rounded gravel sized .............
.............
clasts of dark grey sittstone :::::::::::::
.............
.............
.............
.............
.............
315.48 .............
- 24.41
NR 4 /
From 24.41m to 24.60m: AZCL //
24.60 12.50 11.00 ......................................... ..- ..- 1 24.60 315.29
End of Borehole.
Remarks
1.00-1.18 C
l-30-1.75
1.00-2.00 ii
F (2.90)
-#
77% 1) Bedding fractures IO" to 20" planar often
(54%: undulating rough open brown silt fine to
coarse sand coated or occasional Y y infilled
(~3~0 often iron stained,cross bedding in
15
5 kagigiorizontal fractures 25" to 40" widely
spaced planar occasionally undulating rough
open brown silty fine to medium sand coated
4.50 and iron stained.
3) Subvertical fractures 70" to 90" planar:
occasionally irregular rough open brown silty
fine to coarse sand coated or occasionally
infilled (<Smm) by silty fine to coarse sand
with some fine angular to subangular gravel
of sandstone.
Remarks Chiselled from 1.20m to 1.30m (30 mins), 2.35m to 2.50m (45 mins), 3.10m to 3.25m (60 mins), 3.25m to
3.35m (60 mins)
Flush returns: 3.40-25.40m (80%).
;eekey sheet Standpipe and piezometer installed: grout from 25.40 to 9.00m, bentonite seal from 9.00 to 8.00m,
Ind appendices slotted ipe and pea gravel filter from 8.00 to 4.25m, bentonlte seal from 4.25 to 3.75m, sand filter
br explanations. from 3.7 F to 1.5Om, plezometer tip at 3.50m, bentonlte seal from 1.50 to l.OOm, concrete and cover&WI,0
Ill-l to Cl
Project Contract 166001~3
Borehole Record A465 Abergavenny to Hirwaun.Dualling
Ground Investigation, Section 3
Welsh Office Highways DIrectorate Borehole
Exploration Associates 3/BH125(1 of 6)
Sampling - Strata
Drill Run TCR Casing Date/ SPT N Depth
Description Legend
(SCR) (RQD) Water FI (Thickness) Leve*
1 O/O6
From 3.40m to 3.55m: AZCL
100% From 3.55m to 3.75m: moderately weathered,
(88%) (46%) recovered non-intact as fine to coarse
15 angular ravel and cobble sized fragments
From 3.5 ? m to 4.10m 4.20m to 4.50m, 4.63m
to 4.70m, 4.80m to $.02m and 5.27m to
5.43m: moderately weak to moderately strong, I
often with brown discolouration
5.80
100%
(85%) (65%)
5
7.10
4.00 FOAM 15
7.85 -II/O6
4.00 2.70
80%
(43%) (0%) From 8.08m to 8.15m: 60" fracture planar
a.15 rough open silty fine sand coated iron
stained
97%
(97%) (63%)
.. ...... .. ... ... .. .....
..... . . ....
... ... ..... ... . ... ... .... ... .. ...
. . . . . . . . . . . ..
... ... ... ... ... ... ... ... .. ... ... ... ...
... ... .. ... ... .. ... ... ... ... ... ... ...
.. .. .. .. .. .... .. .... .. . ..
:::::::::::::
. . . . . .. . . . . . .
... ... ...... ... ...... ... ...... ... .....
.. .. .... .. . .. .. ... .. . ..
:::::::::::::
.. .. ... .. .... .. .. .. .. ....
11 :::::::::::::
. . .. .. .
.. .. .. .. .... .. .... ... .....
9.55 ...... ......... ... ...... ...,... ..
:::::::::::::
.. .. ... .. .... . .... .. ..
:::::::::::::
.. .. ......
.. .. ... .. .. .. .. .... .. ..
~~~~~~~~~~~~~
.. . . . . . . . . . . .
...... ... ...... ... ..... ... ..... ... .
. . . .. . . . . .
:::::::::::::
... .. .... .. .... .. .. .. ..
From lO.OOm to 12.50m: moderately weak and ..,. .. .. .. ... .. .. ..
,.../, I.
!YiPment: Cable Toot Percussion Groundwater Ground Level 342.74 m OD
Rotary Coring-Mist Flush No. Struck Behaviour Sealed Coordinates
3o0133m20
207120.50 %
lorehole Dia (mm) Casing Dia (mm)
200 to 3.40m gOy,t; ziiOrn Drilled by PO PD
S to 19.60m
P to 25.40m P to 2b.OOm ::::;:db gy ELM;::
Remarks
moderately strong
Depth
.c:nickness) -eve1 Legend
3
99%
(99%) (39%)
13
10.90
87%
(69%) (49%)
11.80
NR
From 11.80m to 12.00m: AZCL
;;(;7,22.OOm to 12.05m: brown sandy silt - 12.00
NI -.
12.50
(1.75)
17
From 13.10m to 15.25m: locally moderately
89% weak (zones 20-1001~1 thick)
(68%) (93%) From 13.10m to 16.85m: subvertical
fractures,2 intersecting sets present,
closely spaced in places
- 13.75
NR
From 13.75m to 13.90m: AZCL
13.90 13.90
97%
(97%) (28%)
Project Contract
Borehole Record A465 Abergavenny to Hirwaun Dualling
166001-3
13
15.40 I (2.95)
1 16.85
NR
From 16.85m to 17.00m: AZCL - 17.00
98%
(94%) (20%)
18.30
100%
(77%) (41%)
19.60 ‘-19.60.
Remarks
; a
!.
13,z....__I
E No. Struck Behaviour
207120.50 mN
I3
] Remarks
i ee key sheet
nd appendices
I Jr explanations. Form l/O
End of Borehole.
ercussion
Remarks Chiselled from 1.60m to 1.80m (45 mins), 2.40m to 2.65m (60 mins), 3.00m to 3.20m (60 mins), 3.20m to
3.30m (60 mins)
.._...........................................
.End of Borehole.
kernarks Chiselled from 1.80m to 1.90m (45 mins), 2.30m to 2.50m (60 mins), 2.5Om to 2.60m (60 mins)
Inspection pit to 1.20m.
:ekey shrrt
Id appendices
r explanations. Form l/O
Project Contract
3orehole Record A465 Abergavenny to Hirwaun Dualling
166001-3
Ground Investigation, Section 3
Welsh Office HIghways Directorate Borehole
Exploration Associates 3/BH127(1 of 1)
GamDline
- -----x- -~ D
I Strata
C . Date/ SPT N . .._ Depth
Depth Type Description Legend
D?$if Water (Cu) (Thickness) Leve'
_ G.L. 314.69 .
. .,\I,,d
:
w Soft brown slightly clayey sandy (fine to
DRY medium) PEAT (fibrous and spongy). .\I/; : .'A\1
. 'Tic
.\lL.'. . : .A
I (0.70) -h\ll,. :
.\w.'~\\l\I.
0.50 D . . . &\I/,..
JL'. . : Ai
1.45-1.50 D -(I.551
- 2.25 312.44
3.45-3.50 D
*-.
D * x
.
4.00 DRY 85
4-50-4-95 ? x m *
4.50-5.00
.- *
D 7.
.
x a -
D
x-e
D - x
a , ,
Remarks Chiselled from 4.80m to 5.00m (30 mins1 5.70m to 6.00m (40 minsl, 6.65m to 7.00m (60 mins)
Water level of 5.26m noted on evening shift 14/6/97.
ee key sheet
nd appendices
zrexplanations. Form l/O
Remarks
hmolin9 I Strata
End of Borehole.
Remarks
None
B2191100-D2-1-2-174
Strengthened Earthworks Appraisal Form – Outline SEAF
None
B2191100-D2-1-2-174
Strengthened Earthworks Appraisal Form – Outline SEAF
1. Ch. 7720m, Northern side of Baverstock mainline embankment, 8.7m high, 50°
2. Ch. 8090m, Northern side of Baverstock mainline embankment, 6.2m high, 30°
3. Ch. 8030m, Northern side of westbound diverge Slip Road, 12.0m high, 45°
B2191100-D2-1-2-174
Strengthened Earthworks Appraisal Form – Outline SEAF
8.7m
50°
1. Ch. 7720m, Northern side of Baverstock mainline embankment, 8.7m high, 50°.
6.2m
30°
2. Ch. 8090m, Northern side of Baverstock mainline embankment, 6.2m high, 30°.
12.0m
45°
3. Ch. 8030m, Northern side of westbound diverge Slip Road, 12.0m high, 45°.
B2191100-D2-1-2-174
Strengthened Earthworks Appraisal Form – Outline SEAF
5.7m
35°
B2191100-D2-1-2-174