Line 202 (Bapu dham) CB R phase Gas kit replacement

SR.No Requied tools QTY


1 Sf6 handlind plant 1 NOS
2 stroge tank 1 NOS
3 hose pipe 10 mtr 1 nos,5mtr 2 nos
4 Adaptor Dn-12,Dn-7 1 nos
5 L-N key set 1 set
6 Ratchet set 1 set
7 Vacuum cleaner 1 nos

Consumbale
SR.No Requied
1 Alcohal
2 UT18
3 Tissue paper
4 Gas kit
5 silicon Grease

work timing
SR.No work description timing
1 Gas recovery G0,G4,G9 Compartment 2:30 hrs
2 vacuum break G0 Compartment 15 minute
3 Gas kit replacement work 40 minute
4 G0 Compartment vacuum 2:30 hrs
5 G0,G4,G9,Gas filling 40 minute
6 GAS quality test 30 minute
total timing 7 hrs

note- Gas man-1,fitter-2,electrician-1 man power required