Activity Predecessors Time c) Activities that have slack : (1) B by 2 weeks and (2) E by 2 weeks also
A - 7
B A 2 d)
C A 4 Activity Normal Time Crash Time Normal Cost Crash Cost
D B,C 5 A 7 6 ($ 7,000.00) ($ 8,000.00)
E D 2 B 3 2 ($ 5,000.00) ($ 7,000.00) Notes
F D 4 C 4 3 ($ 9,000.00) ($ 10,200.00) CC -- Crash Cost
G E,F 5 D 5 4 ($ 3,000.00) ($ 4,500.00) CT -- Crash Time
E 2 1 ($ 2,000.00) ($ 3,000.00) NC -- Normal Cost
Question F 4 2 ($ 4,000.00) ($ 7,000.00) NT -- Normal Time
a) identify the critical path G 5 4 ($ 5,000.00) ($ 8,000.00)
b) what is the length of time to complete the project ?
Cost per week to Weeks that activity
c) which activities have slack, and how much ? Activity CC-NC NT-CT
expedite may be shortened
A ($ 1,000.00) 1 ($ 1,000.00) 1
d) Here is a table of normal and crash time and costs. Which activities would you shorten to cut two weeks from the B ($ 2,000.00) 1 ($ 2,000.00) 1
schedule in a rational fashion ? What would be the incremental cost? Is the critical path changed C ($ 1,200.00) 1 ($ 1,200.00) 1
D ($ 1,500.00) 1 ($ 1,500.00) 1
E ($ 1,000.00) 1 ($ 1,000.00) 1
Activity Normal Time Crash Time Normal Cost Crash Cost F ($ 3,000.00) 2 ($ 1,500.00) 2
A 7 6 7000 8000 G ($ 3,000.00) 1 ($ 3,000.00) 1
B 3 2 5000 7000 critical path the one that could be crash
C 4 3 9000 10200
D 5 4 3000 4500 Crashing 2 weeks Remaining Weeks 23 weeks
Remaining
Number of
Total Cost of all Project
Current Critical Weeks Activity Cost per day to Least Cost
E 2 1 2000 3000 activities in Completion
Path May be expedite each activity Activity that
network Tome
Shortened
(Weeks)
All Activities
F 4 2 4000 7000 ACDFG times and cost ($ 35,000.00) 25
are normal
G 5 4 5000 8000 ACDFG A-6; C-3 A=1000; C=1200 ($ 2,200.00) ($ 37,200.00) 23
ACDFG A-6; D-4 A=1000; C=1500 ($ 2,500.00) ($ 37,500.00) 23
Answer ACDFG A-6; F-3 A=1000; F=1500 ($ 2,500.00) ($ 37,500.00) 23
a) ACDFG A-6; G-4 A=1000; G=3000 ($ 4,000.00) ($ 39,000.00) 23
ACDFG C-3; D-4 C=1200; D=1500 ($ 2,700.00) ($ 37,700.00) 23
ACDFG C3; F-3 C=1200; F=1500 ($ 2,700.00) ($ 37,700.00) 23
ACDFG C3; F-3 C=1200; F=1500 ($ 4,500.00) ($ 41,700.00) 23
ACDFG C3; F-3 C=1200; F=1500 ($ 1,000.00) ($ 38,500.00) 23
ACDFG C3; G-4 C=1200; G=3000 ($ 4,200.00) ($ 39,200.00) 23
ACDFG D-4; F-3 D=1500; F=1500 ($ 3,000.00) ($ 38,000.00) 23
ACDFG D-4; G-4 D=1500; G=3000 ($ 4,500.00) ($ 39,500.00) 23
ACDFG F-3; G-4 F=1500; G=3000 ($ 4,500.00) ($ 39,500.00) 23
ACDFG; ABDEG B-3; D-4 B=2000; D=1500 ($ 3,500.00) ($ 38,500.00) 23
ACDFG; ABDEG F-3; E-1 E=1000; F =1500 ($ 2,500.00) ($ 39,700.00) 23
We would crash activity A and C at the same time since the incremental cost would be the lowest amongst others (2200)
The critical path would be the same which is ACDFG