Research and Development in Food

Spain S.L

Quote ST230042 for HPP-6000


13. July 2023

Presented by: Presented to:


Pétur Jakob Pétursson Julio Montero
Héðinn was established in Reykjavik in 1922
to provide engineering services to the
Icelandic fisheries sector. This relationship
has become very strong over the years and
we are now a key player in the industry.

In addition, Héðinn also serves a number of


heavy and light industries in Iceland and beyond.
With a workforce of around 120 people, Héðinn
operates mechanical engineering and steel
fabrication departments with technical
engineering at its core. We also invest heavily in
Research and Development.

We are a private holding company, owned by the


founder’s family and management.

Our headquarters is at the main industrial site in


Hafnarfjordur town, spanning some 8000 square
meters on a 22,000 square meter site.

HPP Solutions | Gjáhella 4 | 221 Hafnarfjörður | Iceland | Tel: + 354 596 2100 | sales@proteinplant.is | proteinplant.is 1
Introduction to HPP Process
The HPP solution is new solution to the fishmeal industry. The solution has been in
development for more than a decade and first units have been in operation since 2016. We
are proud to say that the customers already selected HPP are among the best in fish industry
with decades of experience in fish meal industry.

With the HPP solution all aspects of the process have been redesign.

The main benefits of the HPPs process are compared to traditional process:

 Full utilization of dry matter and oil. No stick water discarded.


 Simpler process. Easier to operate and maintain.
 Better quality of oil and meal. Low temperature processing.
 Automatic operation. Does not need constant human operators.
 Energy efficiency. Energy usage reduced 1/3 compared to traditional process.
 Space required for machinery reduced 1/3 compared to traditional process.

HPP Solutions | Gjáhella 4 | 221 Hafnarfjörður | Iceland | Tel: + 354 596 2100 | sales@proteinplant.is | proteinplant.is 2
The importance of collaboration
We at HPP Protein Plant passionately believe in client-supplier partnerships. Trust and
collaboration are the foundations of this alliance.
Héðinn hf. has been building fishmeal factories since 1936 and considers itself a service firm
rather than a sales organization. As a result, we are highly familiar with both older and
contemporary fishmeal processing processes.

The main benefits of the HPPs process are compared to traditional process:

 100% utilization of dry matter and oil. No stick water discarded.


 Simpler process. Easier to operate and maintain.
 Better quality of oil and meal. Low temperature processing.
 Space required for machinery reduced 1/3 compared to traditional process.
 Energy efficiency. Energy usage reduced 1/3 compared to traditional process

Below in this quote is an example of what is included within our quotes.

With the utmost regard


Pétur Jakob Pétursson
Director of Sales & Marketing HPP Solutions

HPP Solutions | Gjáhella 4 | 221 Hafnarfjörður | Iceland | Tel: + 354 596 2100 | sales@proteinplant.is | proteinplant.is 3
HPP-6000 technical specification

Technical description of Equipment

Raw material Fish offal, mixture of heads, bones, guts and liver without
additional water. Free of foreign objects like stones,
plastics, metal parts etc.

Production capacity of raw Min 75.000 kg/h.


material
Max 150.000 kg/h.

Recovery of meal App. 20% of dry RM, depending on RM type

Recovery of fish oil 0-10% of dry RM, depending on RM type

Additional water in product 0 – 5%

Additional water can/will reduce capacity of the HPP


plant

Production stability The process runs on optimum if variations in production


parameters are kept at minimum. Constant flow of raw
material, even raw material content, operating
parameters on machine etc are essential.

Production start-up It can take hours from starting of process until process
has reached stability to be operated in semi-automatic
mode

Production stops and cleaning. The process can operate continuously without cleaning
for weeks even though the machinery is stopped for
short period of time. For longer stops the machinery
needs to be cleaned to prevent build-up of material on
surfaces and pipe clogging.

Production learning curve Fishmeal process is complex process where raw material
supply, operator skills, tuning of new equipment and
product pipeline can take months to get full control of.
This can/will affect the production for the first season of
operation and can/will cause additional cost for the
buyer and requires good cooperation between seller and
buyer.

Meal humidity content 6 – 12%

HPP Solutions | Gjáhella 4 | 221 Hafnarfjörður | Iceland | Tel: + 354 596 2100 | sales@proteinplant.is | proteinplant.is 4
Raw material Temperature +2 - +15°C

Environmental conditions +5 - +25°C in a well-ventilated room.

Installed electrical power 480kW, 3*400V, 50Hz

Maximal use of steam 2500 kg/h, 1600kW @ 3,5bar(g) [max]

Average use steam for each ton 350 kg/Ton raw material
raw material

Air from the process 20.000 m3/h of process air

Water from the process 60m3/h from the exhaust scrubber (Seawater)

Dry weight of factory room App. 60.000 kg

HPP Solutions | Gjáhella 4 | 221 Hafnarfjörður | Iceland | Tel: + 354 596 2100 | sales@proteinplant.is | proteinplant.is 5
EQUIPMENT breakdown
№ Description Total price
EUR
1,01 HPP RM Grinder made of stainless steel with Hardox knives Included
1,02 Process deck receiver with bottom screw conveyor Included
1,03 Feeding pump from process deck to RM tank Included
1,04 RM tank Bottom section w. bottom screw conveyor Included
1,05 RM tank bridge braker and filling screw conveyor Included
1,06 RM feeding pump from RM tank to cooker Included
2,01 HPP Pre-Cooker Included
2,02 HPP Cooker Included
2,03 Feeding pump for Decanter Defender Included
2,04 HPP Decanter Defender Included
2,05 Feeding pump for Decanter Included
2,06 Decanter Included
2,07 Fish oil receiving bin under decanter Included
2,08 Loading pump of fish oil to storage tanks Included
2,09 Protein liquid bin under Decanter Included
2,10 Protein liquid pump from Decanter to Pre-Dryer Included
2,11 HPP Pre-Dryer Included
2,12 Primary steam condense system Included
2,13 HPP MVR Energy saving system Included
2,14 HPP Feeding pump from Pre-Dryer to Secondary-Dryer Included
2,15 HPP Secondary Dryer Included
2,16 Secondary steam condense system Included
2,17 Air heater Included
2,18 Fan for drying air Included
2,19 Cyclone Included
2,20 Air lock valves Included
2,21 Air exhaust scrubber system for steam and odour cleaning Included
3,01 Unloading pump system from oil storage tanks to land. Included
3,02 Meal transport system with fan Included
3,03 Meal Bag filter Included
3,04 Air lock valve for meal system Included
3,05 Meal Mill Included
3,06 Meal tank Bottom section w. bottom screw conveyor Included
3,07 Meal antioxidant system Included
3,08 Meal circulation system Included
3,09 Bagging conveyor for big bags Included
3,10 Level sensors for RM and fish oil tanks. Included

HPP Solutions | Gjáhella 4 | 221 Hafnarfjörður | Iceland | Tel: + 354 596 2100 | sales@proteinplant.is | proteinplant.is 6
w/n Electrical cabinets. Main components Allen Bradley (PLC, frequency Included
converters etc)
w/n Electronic touch screen installed on one main cabin for the total Included
system to control the factory
w/n Lockout-tagout system on all Hazardous energy releases Included
w/n Valves and sensors on pipes connecting the HPP system within its tie Included
in points.

Electrical and control system

Electrical cabinets. Main components Allen Bradley (PLC, frequency converters etc)

Electronic touch screen installed on one main cabin for the total system to control the factory

Cables between sections and cabinets

Technical job and supervision

Description

Supervision for installation and commissioning

HPP Solutions | Gjáhella 4 | 221 Hafnarfjörður | Iceland | Tel: + 354 596 2100 | sales@proteinplant.is | proteinplant.is 7
Sample - HPP-6000 Layout for Tuna in Spain

HPP Solutions | Gjáhella 4 | 221 Hafnarfjörður | Iceland | Tel: + 354 596 2100 | sales@proteinplant.is | proteinplant.is 8
Excluded

Description

High pressure water for cleaning

Pressurized air

Sea Water supply for cooling app. 4 m3/h

Fresh water supply

Supply of electricity to cabinets

Steam boiler

Installation work (less supervision)

Exhaust canal/chimney

Pipes for installation

Electrical cables

Spare parts

HPP Solutions | Gjáhella 4 | 221 Hafnarfjörður | Iceland | Tel: + 354 596 2100 | sales@proteinplant.is | proteinplant.is 9
Price and conditions

Price

Price € 5.782,000 -

DPU according to INCOTERMS 2020

Conditions are according to:


- ORGALIME - General Conditions for the Supply of Mechanical, Electrical and Electronic
Products - S 2012
- ORGALIME - Supplementary Conditions for the Supervision of Installation of Mechanical,
Electrical and Electronic Products - S 2012 S

Payments: 30% on contract.

35% before shipment of main components.

15% at beginning of installation.

15% after installation and beginning of commissioning.

5% after SAT acceptance test.

Time of project estimated 14 months after signing of contract.

This quote expires 01. of September. 2023.

Best regards

Pétur Jakob Pétursson


Director of Sales & Marketing HPP Protein Plant

HPP Solutions | Gjáhella 4 | 221 Hafnarfjörður | Iceland | Tel: + 354 596 2100 | sales@proteinplant.is | proteinplant.is 10
Annex 1
Orgalime - General Conditions
for the Supply of Mechanical,
Electrical and Electronic
Products - S 2012

HPP Solutions | Gjáhella 4 | 221 Hafnarfjörður | Iceland | Tel: + 354 596 2100 | sales@proteinplant.is | proteinplant.is 11
HPP Solutions | Gjáhella 4 | 221 Hafnarfjörður | Iceland | Tel: + 354 596 2100 | sales@proteinplant.is | proteinplant.is 12
HPP Solutions | Gjáhella 4 | 221 Hafnarfjörður | Iceland | Tel: + 354 596 2100 | sales@proteinplant.is | proteinplant.is 13
HPP Solutions | Gjáhella 4 | 221 Hafnarfjörður | Iceland | Tel: + 354 596 2100 | sales@proteinplant.is | proteinplant.is 14
HPP Solutions | Gjáhella 4 | 221 Hafnarfjörður | Iceland | Tel: + 354 596 2100 | sales@proteinplant.is | proteinplant.is 15
HPP Solutions | Gjáhella 4 | 221 Hafnarfjörður | Iceland | Tel: + 354 596 2100 | sales@proteinplant.is | proteinplant.is 16
HPP Solutions | Gjáhella 4 | 221 Hafnarfjörður | Iceland | Tel: + 354 596 2100 | sales@proteinplant.is | proteinplant.is 17
HPP Solutions | Gjáhella 4 | 221 Hafnarfjörður | Iceland | Tel: + 354 596 2100 | sales@proteinplant.is | proteinplant.is 18
Annex 2
ORGALIME - Supplementary Conditions for the Supervision of Installation
of Mechanical, Electrical and Electronic Products - S 2012 S

HPP Solutions | Gjáhella 4 | 221 Hafnarfjörður | Iceland | Tel: + 354 596 2100 | sales@proteinplant.is | proteinplant.is 19
HPP Solutions | Gjáhella 4 | 221 Hafnarfjörður | Iceland | Tel: + 354 596 2100 | sales@proteinplant.is | proteinplant.is 20

You might also like