1. I/We ...............Muhammad Ali...................... submitted the quotation for Enquiry No. “Lan
Networking/Cabling Erection and Jointing through Proper QOI” due on 03/12/2021 at 12:00 noon Meeting
with Concern Team of NLC at Pak Afghan border.

2. I/We thoroughly examined and understood terms & conditions of contract given by the Concern
Department (NLC) in detail meeting/Visit at Site with NLC officers and PTCL Team.

3. I/We hereby interested to work at the following rates. I/We undertake that I/We are not entitled to claim
any enhancement of rates on any account during the validity of rate till Given time period as mentioned
Below.

4. Purchase of Cable and Transportation charges till destination End.

S.no Project Unit(m) Quantity Price Taxes Price Total Amount


with Required Per including Per Amount in Words
Description Unit All Taxes Unit
with
taxes
1 Copper Cable Quantity Quantity Quantity 25,400/- Twenty
Laying mentioned mentioned as mentioned
as Annexure-3 as Five
(exclusive
Digging)
Annexure-3 Annexure-3 Thousand
and Four
Hundred
only

(Signature of Authorized Person)

Place:-_______Chaman___ Name:-___Muhammad Ali_____

Date:-____3 Dec 2021 _________ Validity= Three Days

Name of Firm/Company/Agency (Designation) Contact Details

Muhammad Ali & Sons Pishin


ANNEXURE “3”
Technical Specifications

BOQ for 30 pair Cable Replacement work At Pak Afghan Border

Cash:
Description of Type (If
S.# Qty. Unit Rate Amount
Activity / Item Any)
10 Pairs Each -
8 Ariel Jointing, etc. 20 Pairs Each -
30 Pairs Each -
Purchase of cable Per
9 30 pair 90 282 25,400