Professional Documents
Culture Documents
ABSTRACT: To investigate the viability of a steel cable-based system to prevent progressive collapse of
buildings ten tests were conducted on a full scale specimen of a one story building. One side of the floor in
the specimen had steel cables placed within the floor representing new construction and the other side had
cables placed on the outside as a measure of retrofit of existing buildings. The tests and associated analyses
indicated that the system could economically and efficiently prevent progressive collapse of the floor in the
event of a car bomb attack and removal of one of the exterior columns.
INTRODUCTION
Figure 1. The structure of Murrah Federal Building before and after the car bomb attack of 1995
In this case, a car bomb exploded near the reinforced concrete building, shattered one exterior column and damaged a
few members in the vicinity of the explosion, Figure 1. Due to loss of this column which was supporting the load from
3 columns above, the weight of the floors above could not be redistributed to adjacent columns or to the rest of the
structure. As a result, the front half of the building collapsed in a progressive manner resulting in loss of lives of 168
innocent people and injury to many more1.
Copyright © 2003-2004 Iran Civil Center, All rights reserved worldwide. Page 1 of 8
IranCivilCenter.com - Technical and Educational Website of Iranian Engineers
Three main steps to protect buildings against car bomb attacks are shown in Figure 2 and are:
1. Intelligence gathering: By gathering intelligence and information about activities of known terrorist groups
many terrorist attacks have been prevented. This step is of course the most efficient option. However, in many
cases, the attackers are able to keep their plans secret and execute the attack with complete surprise.
2. Access control: By providing barriers near the structure and by preventing the car bomb from being placed
close to the building the damage to the building can be reduced. This solution is also efficient and should be
implemented in critical buildings with high probability of being the target of car bomb attacks. However, in
some cases, the subject building is located in a dense urban area near busy streets and it is not possible to
divert the car traffic away from the building and prevent cars from getting close to the building.
3. Hardening: By hardening the building such that in case of a car bomb explosion near the building, the
catastrophic collapse of the building can be prevented.
This paper focuses on this Step 3 and on testing technologies developed to prevent progressive collapse of buildings in
the event of an external explosion causing loss of one of the main load carrying columns.
Figure 2. Three main steps in protecting buildings against car bomb attacks
Copyright © 2003-2004 Iran Civil Center, All rights reserved worldwide. Page 2 of 8
IranCivilCenter.com - Technical and Educational Website of Iranian Engineers
Figure 3 shows the application of this concept in a building. When a single column is removed and the floor starts to
collapse, the catenary action of the cable prevents the collapse and transfers the load of the floor to neighboring
columns and rest of the structures. Since cables are used in every floor, the loads of all floors above the removed
column will be transferred to the adjacent columns. As a result, although the floors might have relatively large
deformations in the order of 40-60 centimeters, the full progressive collapse and pan-caking of the floors are prevented.
Figure 3. A typical floor with cable before and after removal of middle column
To test the performance of floors reinforced with steel cables, a full size one story building was designed and
constructed. The structural engineers from MKA designed the specimen to simulate a portion of a typical braced frame
steel structure. Figure 4 shows plan view and a cross section of the test specimen. The north side of the specimen had
steel cables inside the floor slab similar to what will be done in a new construction. The south side of the floor in the
test specimen did not have the cables. This side of specimen was tested first as a representative of typical modern steel
structures without hardening. These tests are denoted as Group II tests in Table 1. After completion of these tests, minor
damage to the slab was repaired, the beam connections that were damaged during previous tests were replaced with new
shear tab connections and the retrofit cables added. The specimen at this time represented an existing building
retrofitted by adding cables to it under the floor slab. The cables as a measure of retrofit were added to increase the
resistance of floors to progressive collapse. The added cables are shown in Figure 4 along the south side of the building.
The structural framing to carry the gravity load consisted of steel frames with simple shear connections in both
directions supporting a concrete slab floor cast on the steel corrugated decks. The concrete slab of the floor had only a
negligible amount of reinforcement to prevent shrinkage cracks. However, within about one meter width of the slab,
where the steel cables were placed, larger reinforcing bars were used. On one side of the specimen -North side in Figure
4- four steel cables, each 32mm in diameter, were placed on top of the top flange of the steel beams within the concrete
floor slab. The main purpose of these cables, as mentioned earlier, was to prevent progressive collapse of the floor in
the event of removal of column C1 in Figure 4. For more information and for details of test specimen and test set-up the
reader is referred to the final report of the project2.
Copyright © 2003-2004 Iran Civil Center, All rights reserved worldwide. Page 3 of 8
IranCivilCenter.com - Technical and Educational Website of Iranian Engineers
Construction of test specimen was done in a way similar to what is done in the United States in constructing typical
office buildings with steel structure. The main steps taken in the construction were:
1. The steel members of the structure were fabricated and delivered to UC laboratory.
2. The structure was erected inside Davis Hall laboratory
3. The steel corrugated deck was added and welded to the top flange of the steel beams.
4. The steel cables were placed on top of the steel deck along the north side frame (Fig. 4).
5. The steel mesh reinforcement was placed on steel deck. The rebars within the one meter width on the north
side of the slab were placed.
6. The normal weight concrete was placed on the steel deck.
Test Procedure
Each test consisted of preparing the specimen, removing the lower portion of one of the middle columns, either C1 or
C2 in Figure 4, and using two actuators connected to top of the column to push down the column. It should be
mentioned that after removing the lower portion of the column, the weight of the floor slab supported by this column
would naturally push the floor down. However, the weight of the slab was only part of the total load that would be
present in an actual building.
The total load would include weight of the non-structural elements as well as live load due to weight of the occupants
and the furniture. To create a realistic load pushing Point C1 down, two 60 ton actuators connected to top of the test
columns were used. After removal of the lower portion of the middle column (either C1 or C2 in Figure 4), the actuators
were used to push the column down with a constant velocity of 6mm/second until a prescribed level of displacement
was reached.
Table 1 provides the tests done on the specimen, levels of displacement as well as the force in the column C1 or C2
after removal of its lower portion.
Copyright © 2003-2004 Iran Civil Center, All rights reserved worldwide. Page 4 of 8
IranCivilCenter.com - Technical and Educational Website of Iranian Engineers
Copyright © 2003-2004 Iran Civil Center, All rights reserved worldwide. Page 5 of 8
IranCivilCenter.com - Technical and Educational Website of Iranian Engineers
EXPERIMENTAL RESEARCH
A total of ten tests in three different groups were conducted on the specimen. The tests are given in Table 1. The first
group of three tests was conducted on the north side of the specimen where steel cables were placed inside the floor
slab. The second group of three tests were conducted on the south side where there was no cable used. The last group of
three tests was conducted on the south side also, but, prior to testing; two steel cables were placed on the side of steel
beams along the Axis 2 in Figure 4 and tied at the end to the end columns. The structure with cables added represented
the condition of an existing building after retrofit.
Group I Tests: North Side of Specimen with Cables Placed inside the Floor
The first test on the north side was done by removing Column C1 and pushing the floor at the location of this column 48
centimeters down. The finite element analyses conducted earlier2 had indicated that Column C1 will move downward
53 centimeters under the design dead and live load before coming to a stop. Figure 7 shows the displacement of column
C1 downward versus the load in the column during the test. The “dents” on the curve in Figure 7 indicate local failure
which primarily consisted of failure of bolts in the connections, shown in Figure 8, and local buckling of the web of the
beams. The specimen during the subsequent three tests of this group (i.e. column drop of 53, 61 and 89) behaved more
or less in the same manner as the first test. The maximum load that the cable system could tolerate at the end of 89
centimeter drop test was about 3.1 times the design load as shown in Table 1.
Group III Tests: South Side of Specimen with Cables Added as Retrofit
After finishing Group II tests on the south side, the specimen was retrofitted and two 20 mm diameter steel cables were
added to the side of the beams along Axis 2, Figure 4. As Table 1 indicates the column drops in these three tests were
56, 56 and 89 cm. Figure 9 shows the specimen at the end of the last test of this group4. The main damage to the
specimen was in the form of failure of edge distance of the end shear tab connections as well as weld fracture of one
shear tab. The specimen was able to tolerate about 1.5 times the design load.
Figure 7. Downward movement of column versus load in the column for north side with cables
Copyright © 2003-2004 Iran Civil Center, All rights reserved worldwide. Page 6 of 8
IranCivilCenter.com - Technical and Educational Website of Iranian Engineers
Figure 9. Deflected but not collapsed shape of the retrofitted specimen and the connection
CONCLUSIONS
Based on the performance of full-scale specimen during the tests and the associated analyses, the following conclusions
were reached:
(1) By using steel cables in the floor slabs of steel structures progressive collapse of steel structures could be
easily and economically prevented.
(2) The existing buildings can also be retrofitted to prevent their progressive collapse upon removal of one
column. The retrofit system consisting of cables placed on the side of steel beams could efficiently prevent
progressive collapse of the floors when a column is removed.
(3) The specimen without the cable could resist a load 1.2 times the design load. However, in other situations, the
use of cables or other mechanisms to increase resistance to progressive collapse is recommended.
Copyright © 2003-2004 Iran Civil Center, All rights reserved worldwide. Page 7 of 8
IranCivilCenter.com - Technical and Educational Website of Iranian Engineers
ACKNOWLEDGMENTS
The projects summarized here were sponsored by the General Services Administration, MKA Engineers, American
Institute of Steel Construction and the National Science Foundation of the United States of America.
REFERENCES
1. ASCE, “The Oklahoma City Bombing: Improving Building Performance Through Multi-Hazard Mitigation”,
Report FEMA 277. FEMA Mitigation Directorate, Reston Virginia. 1996.
2. A. Astaneh-Asl, E. A. Madsen, C. Noble, R. Jung, D. McCallen, M.S. Hoehler, W. Li and R. Hwa, “Use of
Catenary Cables to Prevent Progressive Collapse of Buildings”, Report Number UCB/CEE-Steel-2001/02,
Dept. of Civil and Env. Engrg., Univ. of Calif., Berkeley, 2002.
3. A. Astaneh-Asl, B. Jones, Y. Zhao and R. Hwa, “Progressive Collapse Resistance of Steel Building Floors”,
Report Number UCB/CEE-Steel-2001/03, Dept. of Civil and Environmental Engineering., University of
California, Berkeley.
4. S. Tan and A. Astaneh-Asl, “Testing a Retrofit Concept to Prevent Progressive Collapse”, Report Number
UCB/CEE-Steel-2003/02, Dept. of Civil and Environmental Engineering., University of California, Berkeley.
Copyright © 2003-2004 Iran Civil Center, All rights reserved worldwide. Page 8 of 8