2023 WEEKLY PROGRESS REPORT

Project : THREE STOREY RESIDENCE Date of status report:


Location: 329 Country Club Drive, AAV AUG 12/2023
Project Gen. Manager: Name

Project S u m m a r y:
* SKIMCOATED WINDOW OPENING 89% COMPLETE
* FRONT GROUND FLOOR WINDOW WALL DONE PLASTERING S
* INSTALLATION OF WOOD DOOR JAMBS 90% DONE
* ELECTRICAL SWITCH BOXES & OUTLETS IN PLACE -93% DONE
* SEWER PIPING LAID OUT AT 3RD & 2ND FLOORS - 100% DONE
* Construction schedule ON TRACK
***Material Stock pile of gravel & sand, CHB, Reinforced Steel Bars and bags of cement on site,
Electrical materials ,PPR Water Pipes, Sanitary pipes and Fittings, Steel Scaffoldings

ACTIVITIES DONE
AUGUST 05 to 12
1 Completed CHB wall of Ground Floor front window plastering at Dr. Mariet & Dr. Suzette's
2 Plastering at Ground Floor Courtyard Columns and wall of Dr. Suzette & Dr. Mariet 70%
3 Header of Opening/doors at ground floor 90%
4 Completed plastering at Right Exterior side wall of Ground floor
5 Plastering of Interior walls at Maids/Drivers Quarters 95% done
6 Plastering at Service Stairs walls 98% done
7 Installation of Wood Door Jambs for Bedrooms 100% completed for other rooms 85%
8 Clearing of Right side easement on going
9 Electrical Rough-ins of Outlets & Switches boxes on going -93%completed
10 Waterline and Sewer lines of 3rd and 2nd Floor completed
11 Expediting Plaster finish of window sills and other openings
12 Assisted Skylight Contractors for site assessment

Manpower on site: 29

Equipment: Cut off Machine, Concrete Mixer , Grinder, Drill, PPR Fusing Device
Welding machine, Rotary cutter & other Hand tools

Prepared by: Assistant Project Supervisor Noted by: PROJECT GENERAL MANAGER

Certified by: PROJECT SITE MANAGER Accepted by: OWNER'S REPRESENTATIVE