Professional Documents
Culture Documents
Drilling
Hand-Held
Saw
Floor Saw
Code
of Safe Track Saw
Working
Practice Wire Saw
Hand-Held
Crusher
Burster
Remote
Control Plant
Code of Safe Working Practices
The Drilling & Sawing Association
You Can now view The Drilling and Sawing Code of safe working practice 2020 online and
download a copy directly to your device.
To view this document online scan the QR Code below or visit www.fliphtml5.com/jhfvk/etam
Contents
9.1 Recommended Blade Speeds &
Cutting Depths For Segmented
Diamond Saw Blades.......................96
Index............................................ 109
Introduction
guidance on safe working practices in the
Drilling and Sawing industry in relation to: - It is also stressed that legislation is
constantly changing and that it is not
a) Current legislation; always possible for us to incorporate
b) Practical experience developed changes as quickly as we would like.
by established specialist Therefore, it may be necessary to
contractors over several years; check the latest situation where legal
requirements are critical to a problem.
c) The recommendations from
manufacturers of specialist Recent years have seen an increase
equipment on safe operating in the amount of health and safety
procedures. legislation affecting the construction
industry. Therefore, we have taken this
The advice contained in the Code has opportunity to carry out a complete
been presented in a concise, simplified revision of the Code incorporating
form for easy reference, with the hope legislation introduced up to the date of
that it will be treated as a practical publication.
working book, used by management,
supervisors and operatives at all levels. On many occasions, members will
be working as sub-contractors on a
The statutory provisions on health and construction site, where the client has
safety are incorporated into by three complete responsibility for all health
categories. There are: - and safety requirements. However, as
employers, sub-contractors still have an
a) Acts of Parliament.
obligation to carry out their own work in
b) Regulations made under those a safe manner. Usually this will be done
Acts. on consultation with the main contractor
who will, for example, be providing
c) Approved Codes of Practice. welfare facilities.
These categories are covered in more It is impossible for main contractors to
detail in section 2.1.1, but it is important to fulfil their health and safety responsibilities
stress that the principle piece of legislation unless they are aware of the presence
is the Health and safety at Work etc. Act of our members’ staff on site. Therefore,
1974. Where there are references in this members’ employees working as sub-
Code to “the Act”, this means the Health contractors MUST REPORT THEIR ARRIVAL
and safety at Work etc. Act 1974. ON SITE IMMEDIATELY TO THE SITE
Every effort has been made to identify MANAGEMENT AND MUST ALSO NOTIFY
all the relevant health and safety THEM OF THEIR DEPARTURE. They must be
legislation specifically relating to required to undertake induction health
activities undertaken by Members of the and safety training and follow site rules as
Association. this is part of the regulatory system.
both employers and employees are set from a health and safety point of view.
out in Section 2 and 3 and 9 and 10 of this It is therefore essential that companies
code covering the Act. implement the requirements of these
Attention is drawn to the need for each Regulations with reference to the
company to have a formal Health and provision of Risk Assessments and Method
Safety Policy - see Section 2.1.7. This Statements for each job.
health and safety policy are an absolute It is essential that supervisors at all levels
requirement, where 5 or more persons are made aware of their responsibilities
are employed, and should include a about health and safety. They must
written statement of intent, organisational enforce health and safety rules and
responsibilities and arrangements for standards, and make people understand
managing them. In general terms, that they are designed for their
management have a responsibility to protection.
ensure that work is carried out in a safe
manner and to prevent injury and ill Employees should also be encouraged to
health to employees, the self-employed raise queries regarding health and safety,
and anyone who may be affected by which should be dealt with thoroughly
their undertaking. It is recommended and promptly. By the nature of this
that employers designate a director industry, employees work in small groups
who has specific responsibility for the and are given considerable responsibility.
implementation of a safe system of work Supervisors must be sure that crews
and for compliance with the statutory always have the equipment, training and
requirements. competence to do the job safely.
Under the Management of Health and Apart from their responsibility to their
safety at Work Regulations 1999, every own employees, employers also have
employer is required to appoint one a responsibility to provide protection for
or more competent persons to advise other personnel working at the same
on meeting the requirements of health site and for members of the public. It is
and safety legislation. This person recommended that companies have a
should preferably be someone from the procedure for regular health and safety
employer’s organisation who is suitable inspection of all working operations by
experienced and trained, but it can also a competent person, and that written
be an external consultant if this is not records are kept of these inspections.
possible. These regulations also require
Finally, employers must have effective
employers to carry out a general risk
arrangements for planning, organising,
assessment for the protection of their
controlling, monitoring and reviewing
employees as described in Section 2.3.1
their health and safety systems. The
of this code.
HSE reference guide HSG 65 is a useful
The significant findings of the risk document and outlines the requirements
assessment document must be for health and safety management.
communicated and made available
to employees. Any relevant details of 1.4 Operator Certification
the risk and required control measures The Association attaches great
must be fully detailed and understood. importance to the proper training and
Where appropriate, control measure may assessment of operators. From 2001,
require employees to follow a safe system the DSA Scheme was integrated into
of work, wear appropriate protective the Construction Skills Certification
equipment and receive appropriate Scheme (CSCS). Specific Certificates
information, instruction, training and of Competence in drilling and sawing
supervision. operations will now be issued by NOCN
Introduction
Where sources of this nature are available
The DSA provide an Apprenticeship covering, for example, - the erection and
Training Scheme designed for the Drilling dismantling of scaffolding - we have not
and Sawing Industry. This Scheme enables covered the same ground. This enables
apprentices to obtain an NVQ Diploma this Code to be kept to a manageable
in Drilling and Sawing which together with size and to focus mainly on drilling and
on-site assessments qualifies them for a sawing work.
Specialist CSCS Card.
For further information on the above
The training is delivered through an publications or any other possible sources
e-learning platform and practical sessions of information, please contact the DSA
covering the main disciplines. Office.
The Scheme involves an 18 month
intensive training program in all aspects
of Drilling and Sawing, together with
health and safety and other general
considerations. Any employer or
employee interested in participating in this
Scheme should contact the DSA Office.
Electrical power supplies can come in the All electrical equipment should be
following basic forms: thoroughly checked and tested at
appropriate intervals (now usually 3
415 volt 3 phase - This is only to be monthly) and prior to use on site, and
used for major items of plant. It is not plant and tools should be labelled to
a safe voltage and its installation and this effect. All cables and connections
use must only be arranged through must be of a type suitable for outside
a competent electrician. Ensure work and must always be maintained in
Portable Appliance Test is in date. good condition. The risk of shock through
User checks must be conducted damage to cables and bad connections
weekly, Formal Visual Inspection to be can be minimised using a residual current
completed monthly and Combined protection device. The use of such a
Inspection and Testing every 3 months. device is strongly recommended for
voltages above 110 volts.
240 volt single phase - This is also not a
safe voltage and must only be used in Site electrical installations should be
areas such as office accommodation. treated with the utmost care and only
Where 240 volts is the only supply touched under the supervision of a
available a transformer must be used competent and experience electrician.
REVISED SEPTEMBER 2020 15
Machines must never be wired direct to wall saws, etc. Any member requiring
02 a mains distribution board or other source specific guidance on the use of larger
of electricity supply except by a qualified generators on site should contact the
General Operating Requirements
electrician. DSA.
Where transformers are used to reduce Electrical equipment and installations
the supply to 110 volt these should be form a complex subject and we can
centre tapped and conform to BS 3535. only provide a practical introduction
Plugs and sockets manufactured to BS to this subject. If in doubt, seek
4343 should only be removed or fixed by professional advice.
a competent person. For a 110 volt supply
the plug/socket should be of the “c” type User checks must be conducted
and coloured yellow. 200/230-volt plugs weekly, Formal Visual Inspection to be
etc should be coloured blue and 400/440- completed monthly and Combined
volt coloured red. No appliance should Inspection and Testing every 3 months.
be connected to an electrical system 2.3.4 Lifting Equipment
other than by the correct plug, and fuses
In 1998, the Lifting Operations and
of the correct capacity must be used.
Lifting Equipment Regulations were
Temporary makeshift fuses must not be
introduced and replaced previous
fitted.
legislation. These latest regulations
Cables should not be left trailing in cover the use of cranes, hoists,
positions where they can be damaged. winches and other lifting equipment
Worn, damaged and severed cables within the construction industry,
must be replaced immediately. Great including chains, ropes and other
care must be taken when using water in lifting gear. They lay down the
an area where there are electrical cables intervals at which this equipment
or installations. Any fault in an electrical must be examined and tested by a
appliance or system must be reported to competent person. Full details of the
a responsible person immediately. testing and examination requirements
are laid out in the “Construction
Fire extinguishers for use on electrical Health and safety Manual”.
equipment must be of the appropriate
approved type. Lifting equipment must not be used
unless the relevant current records
Where a mains electrical supply is not can be produced by the owner. In
available, the machine user may decide general, all lifting equipment must
to make use of a temporary supply via a also be marked with its safe working
generator. Because most small generators load and means of identification.
are mobile by design, it is impractical to Under no circumstances must this
expect users to connect them to earth. load be exceeded except for testing
However, if a generator is in one purposes.
place for any length of time it is Lifting equipment should only be used
advisable to have the machine for the job for which it is intended i.e.
earthed correctly. Where this cannot chain slings should not be used for
be done, steps should be taken to towing vehicles.
ensure that the user is protected.
Only accept generators of the single Owners and suppliers of all lifting
voltage 110-volt variety for powering equipment must possess current
small tools etc. Preferably, users should records, and where appropriate a
also specify machines that are centre copy should be kept on the machine.
tapped to earth and should ensure Where equipment is being hired in,
that an earth leakage circuit breaker the hire company must be asked
is fitted. to furnish copies of the relevant
records and the hire order endorsed
Larger generators supplying 415-volt 3 accordingly.
phase may be required for powering
- Fire doors and ceiling tiles The Control of Asbestos Regulations 2012
places duties on employers to protect
In fact, there are still over 4000 employees and others as mentioned
materials and products known to above. This includes self-employed
contain asbestos present in millions of persons. All work with asbestos is covered
buildings throughout the UK. by the Regulations. These Regulations also
cover the precautions required from any
Asbestos insulation board is especially employer carrying out work with asbestos
common in buildings constructed i.e. assessments, planning, training and
before 1980 and was used in fire equipment. They are also supported by
doors, ceiling tiles, internal walls and a new Approved Code of Practice L143
panels. (2012).
If asbestos products remain intact The Control of Asbestos Regulations
and are in good condition, they do prohibits contractors from working on
not pose a risk to health, but if the asbestos coating or insulation (sprayed,
asbestos is in poor condition or is likely lagging/insulation and board) unless
to be damaged or disturbed, there is they have a licence issued by the HSE.
cause for concern. Work with asbestos This is specialist work undertaken only
releases fine fibres which can remain by licensed contractors and requires
airborne for some time and cause special precautions, including periodic
fatal disease. There is no cure. attendance by a UKAS Accredited
a) Where is asbestos found in buildings? It independent analytical organisation for
is most likely in: - air monitoring and inspections before,
during and after the work has been
- Sprayed asbestos and loose packing carried out. The independent analyst also
- used as packing in ceiling voids; issues the final clearance certificate and
- Moulded coatings and laggings - the certificate stating that the area is fit
pipe and boiler insulation; for re-occupation so that normal activities
may be resumed.
- Sprayed asbestos mixed with
asbestos cement - fire protection in There are exceptions to the requirement
ducts, firebreaks, panels, partitions for a licence, but these are complicated,
and around structural steelwork; and it is suggested that drilling and sawing
operatives should refuse to work on
- Insulating boards and some ceiling materials containing asbestos.
tiles;
c) Conclusion
- Asbestos paper - used for insulation
on electrical equipment; It is now thought that repeated low
exposures to asbestos dust can lead
have been trained and that there A tower should have a proper purpose-
should be a permanent record of this built internal access ladder.
training/competence. Towers must
also be inspected by a competent d) Moving a Tower
person after any alteration or any Before moving a tower check that:
event likely to affect its stability. In
addition, if the tower remains erected - There are no overhead power lines
in the same place for more than 7 or obstructions
days it must be regularly inspected
- The ground is firm and level
by a competent person and a written
report made. A Proprietary system - It is only pushed or pulled manually
by Scafftag is a very useful means of from the base
visually checking that the tower is safe
to use and the inspection is in date. - It is never moved in windy
conditions or while there are
The manufacturer or supplier people or materials on the
should provide a proper instruction platforms.
manual giving details of the erection
sequence and bracing requirements. Supervisors should ensure that any
If a tower has been hired, the public rights of way across a site are
hire company should provide this maintained in a safe condition with
information which must be made free and unobstructed access plus
available to the erector. signposts.
mg/m³ or less.
- For temporary fixation on masonry The data was used to estimate typical
or on lean concrete other types of 8-hour time weighted average (TWA)
anchors must be used. exposures. The 8-hour TWA respirable
- The conditions of the diamond tool dust exposures were calculated to
in use (core bit, saw blade) are be 0.1 mg/m³ or less, and the 8 hour
critical for the maximum loads to TWA RCS exposures were calculated
be expected. If the diamond tool to be 0.008 mg/m³ or less. All RCS
is blunt, the forces which can be results were less than one tenth
exerted by the user or the machine the corresponding GB workplace
itself are factors higher than with a exposure limit value (WEL).
sharp tool. The controls used during the tasks
- Damaged and poorly maintained were assessed. Exposure was
equipment or diamond tools can principally controlled by water
cause very strong vibrations and suppression but also included
dynamic loads on the anchor. No segregation and use of respirable
safe working is possible under these protective equipment (RPE) for some
conditions. Lose rebar or other tasks. Job rotation was also reportedly
irregular conditions may lead to used for some tasks during normal
high vibrations even with properly working operations on site.
maintained equipment. Under
such conditions the use of larger
anchor sizes is advisable. For more
information visit Appendix 11.8
Anchoring
- The anchor load in diamond
applications is dominated by tensile
load.
Setting Up Site
Roofs are a serious source of
e) The area must be tidy and free accidents and there must be: -
from rubbish;
- Safe access on to the roof
f) Freedom from extremes of
temperature in the working area. - Safe means of moving across the
Undue cold or heat can make the roof
handling of tools hazardous;
- Safe means of working on the roof
g) Areas behind and underneath
the material being cut must be For short term, the minimum
checked for risks of damage or requirements are purpose made
falling debris. crawling boards and roof ladders.
The Confined Spaces Regulations and access routes can be used safely.
define what is a confined space 3.3.6 Over Water
which includes chambers, vats, tanks,
silos, pits, trenches, pipes. sewers, flues, The Construction (Design and
wells or other similar spaces. They Management) regulations 2015
also define the likely risks including (regulation 26) deals with the
fire and explosion, increased body precautions for persons working
temperature, asphyxiation, drowning over water. As each situation can
etc. vary, the regulations should be
consulted for specific jobs, together
The duties of employers are set out with the appropriate section in the
including the provision of immediate “Construction Health and safety
emergency rescue arrangements Manual”.
and should, where necessary
include the provision of resuscitation 3.3.7 Electric Power Lines
equipment. Work should never be Special care must be taken when
attempted unless there are two working near or under power lines.
or more persons present and they As a guide, no vehicles, plant or
should be adequately trained in equipment should be moved closer
Confined Spaces. The person working than 15 metres of lines suspended
in the confined space should wear a from steel towers or 9 metres of lines
harness and lifeline and one person supported on wooden poles.
should then keep watch and know
what to do in an emergency. Where 3.3.8 Exclusion Zones
vertical access is available a rescue Designed for non-essential persons
tripod must be installed complete with and non-operational plant and
a competent operator and trained machinery are excluded from entry of
first aider. Provision must be made for work.
undertaking emergency procedures.
Systems used for exclusion zones will
It is stressed that work in confined depend on hazards identified in the
spaces should only be undertaken risk assessment.
where there is no practical alternative
The employer must assess the risk of
and where there is a safe system of
entanglement and introduce control
work. A permit-to-work system will be
measures including but not limited to
required. The HSE publish a Code of
(bullet pointed list)
Practice and other information on the
practical aspects of such work. Selection of appropriate PPE i.e.
elasticated wristband where long
3.3.4 Lone Working
sleeves are used, gloves that will tear if
A lone worker (LW) is an employee entangled etc.
who performs an activity that is
carried out in isolation from other - Selection of the correct equipment
workers without close or direct for the task. Selection of the correct
supervision. Such staff may be operating speeds.
exposed to risk because there is - Use of self-feed, automated or
no-one to assist them and so a risk remote controls.
assessment may be required.
- Use of guarding where appropriate.
Minimum requirement should be
chapter 8 barrier systems.
These systems should be used as a
Setting Up Site
We are advising to include a barrier - Support systems/propping
system around the drilling and sawing
operations. This should ensure that - Shores (flying and raking)
people passing by does not get
- Facade Retention Systems & Party
entangled with the rotating core bit.
wall support
Whilst drilling into floors the method
- Edge Protection
statement should include a barrier
system positioned around the danger - Tower Crane Bases
zone removing the entanglement
factor of anyone passing by the - Anchors and Ties
operating drill rig. - Working platforms used for cranes,
Operators should be positioned high reach machines or drilling/piling
in a safe working position away rigs
from rotating parts whilst operating - Support work to party walls, floors
machinery. Attention should be paid and excavations.
to lose fitting garments such as Hi-Viz
Vests All items of temporary works are classified
in BS5975 for the purposes of Design
3.3.10 Temporary Works checking as Class 0, 1, 2 or 3.
Procedures
Class 0 at one end of the scale involves
As defined by the general procedures standard equipment and arrangements
of BS5975:2008. Temporary Works (‘standard solutions’) in straightforward
are an ‘engineered solution’ used to situations; and Class 3 at the other end of
support or protect either an existing the scale involves complex and difficult
structure or the permanent works situations where novel solutions may be
during construction, or to support needed.
an item of plant or equipment, or
the vertical sides or side-slopes of Class 0 to 3 temporary works must be
an excavation during construction managed in accordance with the
operations on site or to provide Temporary works procedures.
temporary access.
All temporary works must be recorded
The following lists typical temporary on the project Temporary Works Register
works seen on demolition projects. together with their classification.
Note this list is not exhaustive:
It may at times be necessary to increase
- Hoardings and site fencing the class due to site conditions causing
a greater risk. Where doubt exists consult
- Traffic and Pedestrian barriers your TWC in consultation with the TWD,
- Site welfare and offices (includes all temporary works shall be designed
temporary units as well as change (including Class 0).
of use of part of the structure to be The design checking requirements for the
demolished) classes are as follows:
- Signage Class 0 - temporary works may be
- Ramps checked by another member of the site
or design team. Standard solutions often
- Exclusion Zones come with manufacturer calculated
working or ultimate capacities but still
- Scaffolding
need to be checked for compliance with
- Tower scaffolds and similar access the design criteria to ensure they will be fit
This type of work includes, but not limited Departures from catalogue design for
to: standard components – medium to
- Shallow trenches and pits, not high risk
exceeding 1.2m depth with no This type of work includes, but not
significant surcharge or groundwater. limited to:
- Low-rise formwork at ground/ - Propping involving multiple props on
excavation level, max 2.4m double multiple levels.
sided, 0.9m single sided,
- Demolition/dismantling methods and
- Standard scaffolds to TG20:13 tables, temporary conditions – generally.
- Site hoarding and fencing up to 2m - Back-propping designs
high.
- Special designed scaffolds.
- Single storey welfare cabins.
- Excavation using waling frames
Class 1 - temporary works can be design
checked by another member of the - Piling, demolition and craneage
design team. platforms; outrigger foundations in
good ground crane exceeds 50T.
Routine Construction Methods - low to
medium risk - Designed lifting equipment.
This type of work includes, but not limited - Barge mounted equipment.
to:
- Conventional tower crane bases
- Use of standard components to unless of complex design
catalogue design for support in pits
and trenches to CIRIA 97 Trenching - Routine stress cases in the
Practice. permanent works resulting from
temporary conditions.
- Designed scaffolds and loading
platforms to TG20:13 tables or - Back-propping designs
software. - Any class 1 method used in an
- Double sided formwork with access unusual or high risk situation.
platforms at ground/excavation - Small facade retention schemes not
level. Single sided formwork to 2.4m. close to public areas.
- Formwork/ falsework at not more - Large basement excavation and
than 6m height, Permanent formwork propping schemes.
e.g. metal decking.
Class 3 - temporary works must be design
- Mobile crane outrigger pads and checked by a third party organisation
foundations in good ground crane independent from the design team
to 50t. organisation.
- Concrete pumps on outriggers/pads Complex, unusual, bespoke construction
with good access / good ground methods - high risk
conditions.
This type of work includes, but not limited
- Site hoarding and fencing greater to:
than 2m high. 2 storey welfare
cabins. - Temporary works combining inter-
acting multiple design
Class 2 - temporary works must
be design checked by someone - Unusual concepts
Setting Up Site
(TWS).
- Partial demolition or modification of Temporary Works - Designated
existing structures Individual (DI) The overall responsibility
- Excavations and cofferdams in tidal for the control of Temporary Works
conditions within any contracting organisation
will lie with the ‘Designated Individual
- Excavations and cofferdams in poor (DI)’. This is set out in Clause 6.3.1.1 of
ground BS 5975:2008.
- (e.g. weak clay fill to deeper than The Designated Individual has,
5m, water bearing fill deeper than unless formally passed on, overall
5m). accountability. The DI is a role defined
- Demolition plant operating on a in BS5975:2008 as the individual
suspended slab where more than within the contracting organisation
the immediate bay floor is vulnerable who is responsible for establishing
and implementing a procedure for
- Use of the existing structure as controlling temporary works.
anchorage for cutting away and
lowering large steel or concrete The procedure should cover the
cantilevered sections management of the design process
and include measures for ensuring
- Pre-weakening and collapse the design function and the roles of
schemes for explosive demolition the Temporary Works Co-ordinator
where the surrounding clear area and Temporary Works Supervisor are
is less than 1x building height in all carried out by competent individuals.
directions.
3.3.12 Temporary Works Co-
- Any class 2 method used in an ordinator (TWC)
unusual or high risk situation.
The TWC should be appointed by and
3.3.11 Roles, Responsibilities & is responsible to the DI as appointed
Training in writing. The TWC should have the
authority to stop works at any time if it
For all sites it is important to establish
is not being carried out satisfactorily.
management procedures and roles
that are suitable for ensuring that all The TWC is responsible for ensuring
temporary conditions are understood, the temporary works design is
and temporary works used where implemented in accordance with
needed. the drawings and specification. It
is preferable that the TWC is not
The procedures must ensure that
responsible for the day to day
experienced and knowledgeable
progress of the temporary works under
persons and organisations specify,
consideration.
design, plan and oversee each
stage of the work. Where several It is the Temporary Works Coordinator’s
organisations are involved the responsibility to ensure that:
procedures for communication and
cooperation between the parties are - He/she is point of contact between
critical. the designer and the site team.
Setting Up Site
considered and mitigated as far Where applicable ensure that
as possible during design. For all detailed Risk Assessments/Method
significant residual risks involving Statements (RAMS) for the erection,
the temporary works designs this use and dismantling of Temporary
should be a formal Design Risk Works are prepared. The Checker
Assessment with residual risks being may require the RAMS form part of
communicated to site. the documentation signed for on the
Check Certificate
- This is particularly important where
unusual arrangements or sequences - Ensure that the design is
of work are involved independently checked for:
- Carry out the design works in - Concept
accordance with the programme of
the works - Structural adequacy
- In addition, the Temporary Works - Compliance with the brief; and a
Designer will normally assist the TWC design check certificate is issued
with the following: - Where appropriate, ensure that the
- Produce outline methods of design is made available to other
working as guidance to be used interested parties, e.g. the structural
in the preparation by the project designer, the Architect, the Resident
team of detailed working method Engineer, the Client’s representative
statements. and the CDM Coordinator.
- Give advice on and assist with The roles and duties set out
the production of Temporary above are based on the model
Works schemes and methods of given in BS5975:2008/2011 for the
construction generally. management of temporary works.
Setting Up Site
to load. The permit to load must be
of a prepared method statement. For issued by a competent person who
clarity this should ideally be based has physically inspected the works
around a sequence of sketches or on site, this may therefore range from
photos illustrating the process step the TWC/TWD depending on the
by step. Any questions and any complexity of the specific element of
concerns raised by the workforce the work being carried out.
should be considered and dealt
with. This aspect is particularly TWC’s will be allocated an
important on demolition and structural appropriate class of authorised
refurbishment jobs where the detailed sign-off by the DI when appointed
experience of some workers may based on the relevant qualifications,
give additional insight to the situation experience and training they hold.
and arrangement of the structures Over this level or for specialist sign-
involved. off the TWC must arrange for an
appropriate competent person to
Where any temporary works systems attend site, inspect and sign-off.
are to remain in-situ on completion
the design must be issued to the Instigate an inspection regime in
permanent works designer for accordance with legal requirements
inclusion in the site health and safety (such as those for scaffolds and
file. excavations) or other periods
determined by the TWC/TWD. The
3.3.17 Erection, Use and inspection arrangements for each
Dismantling (For each item of location and type of temporary
temporary works) works should be identified on the
Erect the temporary works in temporary works register. Some types
accordance with the prepared of temporary works and the structures
design and method statement. This they support are very sensitive to
will be monitored by the TWC and if the sequence in which they are
the scale of the project is relatively dismantled. This includes some
small this may be a visiting role for falsework and propping schemes.
inspections. Interim inspections may All temporary works dismantling
be carried out on site by the TWS. or striking should be carried out to
an agreed and checked method
Report or identify any non- statement, specifying constraints (e.g.
conformances to the TWC who should concrete strength to be achieved
consult the Temporary Works Designer before commencing; or e.g. do not
(TWD) to review the non-conformance remove until bay ahead had been
and any requests for changes to demolished and arisings cleared) and
the design. On a complex or difficult sequence of dismantling. In some
job, the procedures should include instances, sections of e.g. scaffold,
a permit or authorisation to alter the or propping, or additional back-
design. propping need to be either left in or
Loading of the temporary works added.
should also be based around formal This may need additional ties or
authorisation to load which may bracing and following the design to
use a permit based arrangement. an agreed sequence can be critical.
This can also be used to create hold
points. An example of this would be Obviously, it is good design practice
the inspection of a propping scheme for the designer to devise a scheme
before the demolition moves onto the that is as straightforward and robust as
next bay. possible, but in some cases a precise
Setting Up Site
temporary works have been
checked with and approved by the
designer and have been recorded.
- All structural members are correctly
positioned, and no unintended
eccentricities are present
- No ad-hoc solutions to site problems
have been incorporated without
reference to the designer and/or the
TWC and their agreement (in writing
for all situations)
- Tolerances have not been exceeded
- The quality of any welding is
adequate and meets the design
specification
- Temporary props etc have been
fixed in place to prevent them
being knocked or e.g. vibrated and
moving or falling out
- No part of the temporary works is
being used for any purpose other
than that for which is was designed.
Operating Procedures
out using a purpose-built drilling
Diamond drilling rigs can vary in
rig fitted with a drilling motor. Most
design, but the basic principal is the
drills are suitable for drilling holes
same.
through various building materials
The base plate of the drill stand must and into floors and walls. Where
be secured by anchoring systems drilling is required vertically upwards,
recommended by the manufacturer. into ceilings for example, there is a
hazard of residue water from the
The power unit / drill motor is either drilling process flowing back into
electric, hydraulic or rarely air the motor. Therefore, protection
powered. Drilling bits start at 6mm is required or alternatively use a
and can go to as large as 1500mm or motor where water will not affect
even larger. Drilling depths are virtually the mechanics, such as hydraulic or
unlimited using barrel extensions. pneumatic. Where ceilings must be
The smaller the diameter, the greater drilled, consult the drill manufacturer.
the speed of rotation, and except for - The electricity supply on construction
a few special types, all have a water sites should normally be 110 volt and
feed through the driving shaft, to equipment should be designed to
keep the diamonds cool, the cutting operate from this supply. If the supply
face free of grit, and the core drill is 240 volts, then suitable transformer
bit cutting effectively. Water also should be used. If a 240 volt supply
eliminates dust, but this does cause does have to be used a residual
residue slurry that can be removed by current device must be fitted to the
using an industrial vacuum cleaner. source of supply. Electrical power
This technique is used when precise leads should be kept as short as
circular cuts are needed, as holes possible to avoid voltage drop. Also
of almost any diameter can easily ensure the cable is fully unwound
be drilled to create openings for and routed to prevent a fire hazard.
example, for plumbing, electrical and - A physical check should be
heating / ventilation installations. Core carried out to confirm the nature
drilling is commonly used to create of the material being drilled and
the holes for routing cables, placing the presence of any services or
anchor bolts, installing load carrying ACM’s. Never cut through steel
devices or concrete sample analysis. reinforcement or structural steelwork
A core drill bit consists of a steel tube without the client’s permission.
with diamond segments brazed or Water, gas and electricity lines near
laser welded on the drilling end. The work should be turned off.
core bit is mounted on a rotating shaft - Where drilling takes place through
of various types of drilling machines. walls, the rear side must be checked
Core rill machines can be operated in as there may be electrical or other
either vertical or horizontal direction hazardous installations against
and can be powered by electric, the wall. If it is a locked room,
hydraulic or air-powered sources. arrangements must be made to
4.1.2 Installation obtain access to the room and
inspect the rear of the wall before
- The contractor must select a drilling work commences. When drilling
machine that has the capacity to through floors, the cores can drop
drill the size of hole required, and from the bit into the space below.
which has a suitable power unit in Therefore, protection must be
relation to available power supplies provided for people and property
i.e. air, electric or hydraulic. This may
Operating Procedures
accidentally start up. Some drills do
not have a built-in switch, in which include jamming of cores into the risk
case the supply cable must be fitted assessment.
with an in-line switch. Under no - If the bit encounters steel reinforcing
circumstances should a drill motor be bars, relax pressure about one third
used without an on/ off switch. and allow the bit to cut at its own
The water supply should be turned rate. Do not push the bit. Certain
on and adjusted for volume i.e. the manufacturers drill motors are fitted
water should flow continually around with a Rebar button to engage the
the core bit circumference without speed to suit diameter and material
splashing. Do not allow the water - When drilling high PSI concrete or
supply to stop whilst drilling. Failure to concrete with very hard aggregate
do this will result in drying of the core (i.e. river gravel, flint, etc.) the bit
bit and damage or loss of segments. will sometimes glaze over. To open
- Slowly lower the bit onto the surface or redress the bit, do one of the
so that there is no skidding or lateral following: -
movement of the drill bit. - Reduce water flow by half and pour
- Exert steady downward pressure on masonry sand into the hole until the
the bit while drilling. Do not force the bit starts to increase speed, then
bit into the material. gradually increase the water flow
until back to original state.
- Do not stop the flow of water or the
rotation of the bit if the bit is in the - Drill the bit into a soft concrete block,
hole. soft vitrified grinding wheel or cinder
block. Repeat the procedure until
- If the drilling rate decreases, check the diamond is open again.
the core bit. The slower penetration
generally means that segments are - At the completion of drilling, the
glazing and need to be redressed. core bit should be withdrawn whilst
It is important that the diamond the motor is running, and the water
segments keep their sharpness. turned off. The motor can then be
switched off. Should the core be
- During drilling the core barrel can lodged in the barrel, caution must
become lodged between the outer be exercised when removing the
casing and the material causing the core from the bit, as it can drop out
motor to cease rotating. unexpectedly causing an injury.
- Immediately turn the motor off to - When working on the machine with
prevent damage the drill at the top of the column,
ensure that it is locked in position so
- Turn water off that it cannot drop and injure fingers.
- Isolate power supply Before replacing a drill bit, the
machine must be unplugged from
- With the correct spanner fitted to the power source.
the core barrel attempt to turn anti-
clockwise to dislodge the material 4.1.4 Dry Drilling
causing the jam. - When dry drilling, the drill hole
should be cleaned out regularly,
- Alternatively, if this is unsuccessful use
to clear dust and debris. When
a dedicated tool commonly known
dry drilling, the drill hole
as a sparrow core puller to dislodge
the barrel from the material - By using a hand-held variable
speed electric drill with clutch,
minimum.
trailer to form a specialist trailer
- Choose between a slotted and drilling rig capable of being towed
an un-slotted dry diamond core. behind a van or car. These drilling
The un-slotted cores are designed rigs are used for specialist operations
to be used with a dust extraction such as core sampling in roads,
system. If slotted cores are drilling and installation of motorway
used without a dust extraction barriers and runway lights, etc. They
system, this can have adverse are generally self-contained with
effects for a dry core, namely their own water tank and power
shorter segment life and the core source, being engine driven for such
binding or jamming in the hole. operations.
- Pilot drill the structural material - Where a trailer mounted core drill
first with a 13mm (1/2”) masonry is being used, the manufacturer’s
drill. instructions must be followed
regarding the use of stabilising jacks
- Locate the 12mm ‘A’ taper guide and the stability of the machine
rod down through the core and whilst drilling. For example, the
‘push fit’ the rod into an ‘A’ taper machine must be level. The drilling
adaptor. Drill the hole. plate must not leave the ground
- Use a rotary drill fitted with clutch during operation, and the operator’s
and variable speed control. feet must be kept well clear of the
machine, both whilst setting up and
- Do not use hammer action when drilling. Where the trailer is being
drilling with a dry diamond core used on soft or uneven ground,
drill. suitable pads must be fitted beneath
the stabiliser jacks.
- Set the drill motor at the correct
r.p.m. Remember the harder the 4.2 Sawing - Floor Saws
material and larger the diameter
of core, the slower the r.p.m. The 4.2.1 Introduction
softer the material and for smaller The floor saw is either pushed by the
diameter cores, the higher the operator or more generally a self-
r.p.m. ultimately, faster rotational propelled unit, powered by either
speed does not always mean better a diesel or petrol engine or electric
penetration. motor.
- Clear / dust at regular intervals, as Floor saws vary in power from 13 HP
a build-up will cause overheating, to in excess of 84 HP. They are used
extensive clutch wear and a extensively on roads and motorways
possible loss of segment. Use of to cut asphalt and concrete cleanly
dust extraction equipment is highly and quickly to enable efficient repairs
recommended. and alterations to be carried out to
- Rotate core bit when entering and these surfaces.
leaving hole. The advantages of the floor saw over
- Keep machine level. the track/ wall saw is that it does not
require any setting up time has its own
- Do not force the bit. Let it do the power unit and is a very rapid cutting
work. This will prolong its life and machine.
reduce the chance of failure.
For roads, runways, warehouse aprons
and ground floors, this machine is
ideal. Cutting depths can reach
Operating Procedures
Some of the more specialised - It is essential that the speed marked
companies are now using laser on the blade is greater than the shaft
guided machines in factories and speed of the machine.
warehouses to obtain straight and
accurate lines. - A standard diamond blade is used
for most conventional cutting and
With this unit a good operative is a is operated WET. An inadequate
great asset as he can saw straight and water supply can result in destruction
accurate lines over any length, obtain of the blade with a consequent
good blade wear and maintain a risk to anybody nearby. A constant
high speed of cut. supply of water of between 10 - 25
litres per minute must therefore
4.2.2 Installation flow over the blade during sawing.
- Be sure to select the floor saw that Where a water cut-out switch is
will cut the appropriate material to fitted, this must always be in an
the depth required. If necessary, operational condition when using
check with the manufacturers. Also wet cut blades. Dry cutting diamond
avoid sawing any deeper than the blades are also available, but they
required specification. should only be used for applications
designated by the manufacturers.
- Cutting into road stone or loose
materials can increase blade wear - Reinforced abrasive blades are
and sawing costs. primarily designed for dry cutting
although they may be capable of
- Ensure that you have the correct
wet cutting for certain applications.
diamond or abrasive reinforced
blade to match the nature of the - Abrasive blades are only to be
material that you are cutting and to used on materials specified by the
suit the required depth of cut. Use of manufacturers.
the wrong blade can be dangerous.
Further information on blades is - When fitting or replacing a blade,
contained in section 4. the engine must be stopped. Ensure
that the blade is fitted on to the
- It is preferable that the proper pulley flange outer guard plate locating
sizes are fitted to match the diameter pin and that the flange outer guard
of the blade being used, as it can plate is secured tightly. The machine
be dangerous and uneconomical must not be operated where a
to operate the machine at incorrect locating pin has been sheared off or
engine and shaft speeds. This is removed. Otherwise there is a risk of
particularly important where the size considerable premature blade wear
of the blade is being changed. The to the blade centre. Where there is
fitting of a larger or smaller blade provision for fitting a blade on either
will alter the peripheral speed, side of the machine, the shaft on the
unless the correct fittings are used. unused side must have a cover.
Excessive blade speed could result in
breakage and serious injury. A table - Floor saws are generally diesel or
of recommended blades speeds petrol engine driven. Therefore, care
is shown in Appendix 11.1. Always must be taken to ensure that exhaust
consult the machine manufacturer. fumes do not constitute a hazard.
To overcome this problem, electrical
- Incorrect shaft speed can also cause or gas driven saws are available
inefficient cutting. The blade guard operated from either an LPG or
must also be changed to suit the size 415-volt supply. A residual current
of blade. Check with the operating protection device must be used with
Operating Procedures
Vehicle. that the blade and the cut are
accurately aligned. If the machine
4.2.6 Diamond Tipped veers offline, do not damage the
Segmented Blade blade by forcing it back into line.
- MUST be inspected before every use, Steer the machine carefully and stop
including blade, flanges and shafts. cutting if you are unable to line the
blade with the cut, then re- position
- DO NOT use blade that has been and start again.
overheated
- Do not apply excessive pressure
- If there is any sign of damage of forwards, as the blade will rise out of
unusual wear DO NOT use blade or the cut. A deep cut is best achieved
equipment. by making several shallower cuts.
- Only use the correct sized flange for - Keep your body away from the
blade size moving parts of the machine
- Only use the steel centre diamond and know how to stop the unit in
blades manufactured for concrete case of an emergency. Always
saws wear hearing, eye, foot and head
protection as required by the
- DO NOT use a wet blade without regulations.
adequate water supply to the blade
- The engine must be switched off
- DO NOT exceed maximum blade before refuelling and a pump or
speed funnel used for this purpose to avoid
- Mount the blade solidly and firmly, spilling fuel.
Wrench tighten the arbor nut. * During Floor or Track sawing the
- Make sure the blade and flanges blade can become lodged between
are clean and free of dirt and debris the outer side and the material
before mounting the blade on the causing the blade to cease rotating.
saw. - Immediately turn the drive motor off
4.2.7 Operating Procedure to prevent damage.
The track saw consists of a metal rail b) The hydraulic drive unit which
which has a set of supporting feet can be electrically, or diesel
that are secured to the concrete driven. Where, the drive unit
by means of an anchoring system. is electrically driven, it will
The track has a toothed rack for the need a 415/440-volt, 3 phase
sprocket / cog wheel seated in the supply and must be installed
motor house to traverse on. by a qualified electrician,
using an earth leakage
The travelling bogey / motor house is protection device.
secured to the track by runners and
a cog wheel engages the ‘rack’ to 4.3.2 Installation
enable it to travel backwards and - When installing the rail, follow the
forwards along the track or tracks. manufacturer’s instructions. Small
The bogey also houses the hydraulic test holes may be drilled if steel
motor which powers the diamond reinforcing bar is present in the wall,
saw blade. This blade can be as small to ensure that the bar does not lie in
as 450mm diameter to as large as the plane of the cut.
2m or more. The smaller the diameter
the faster the r.p.m. and vice-versa.
- It is preferable that the surface is
smooth and level; if not, packers
The power unit is hydraulic – either
must be used to ensure that the
electric, diesel or petrol powered, and
track is not distorted when being
is operated using the latest equipment
fixed. Particular attention must be
by remote control away from the
paid to: -
surface being worked upon.
a) Ensuring that all supporting
The cutting is carried out by making a
feet are in contact with the
series of passes along the length being
surface without distortion and
cut. The depth of each pass depends
are securely anchored using
upon the type of material, the blade
anchor bolts;
and the operative.
b) Ensuring that all rails are
The operator starts with a small
properly joined allowing the
diameter blade and works upwards
saw head to pass freely;
to finish with one suitable to complete
the depth required. c) Checking that the rail is at
right angles to the surface, if
It is vital to ensure that all sections
necessary, using a spirit level;
being cut or worked upon are
adequately supported, and all d) Inspecting the complete
services made safe. saw assembly including the
blade flanges, shaft and
Wall sawing equipment consists of two
saw blade for damage or
main components: -
malfunctioning.
a) The travelling rail mounted
- Once the saw head is mounted on
on feet or brackets which
Operating Procedures
ensure that the pinion gear meshes saw head. Hoses should never be
properly with the track rack and that dragged over floors because of
the retention rollers are in the locked the risk of damage to the hose or
position. The blade must be securely coupling, and all dirt should be
mounted on the shaft and the blade removed from couplings prior to
nut properly tightened. Ensure that connection. Hose connections
the blade guard is fitted and locked should be checked to make sure
in place before starting the motor that they are correctly made.
and that an adequate water supply
is connected. - Prior to sawing, also check that the
following are tightly fastened: -
- SAFETY STOPS MUST BE USED AT EACH
END OF THE TRACK. These prevent - The bolts and anchors securing the
the saw running off the track. Under rail frames and rails
certain circumstances, the blade - The nut or bolt securing the blade.
can drive itself along the rail, thereby
presenting a considerable health - Ensure that the correct blade guard
and safety hazard. If safety stops are is fitted. A machine should never be
not available, operators must not use operated without guards, and the
the machine until these are fitted. correct size of guard must be fitted
to match the blade size. The special
- The area around the wall saw flush cutting guard should only be
must be cordoned off to prevent used for this application.
bystanders approaching. With
remote controlled saws, the operator 4.3.3 Operating Procedures
must locate the controls in such a - The first saw cut should be made to
position that he can see the saw a cutting depth of 3 - 5 cm to ensure
operating but which is outside the that the blade has a guide and saws
immediate area of the saw and in a straight line.
blade. Any assistants must also stay
outside the immediate area of the - The operative should position
saw whilst it is in operation. themselves, i.e. as close to a
90-degree angle as possible
The area behind the wall must be
checked to ensure that there is - The second cut can then be to
enough clearance area for the saw a greater depth depending on
blade and that it will not interfere with the quality of the concrete and
any installations. the degree of reinforcement.
When longitudinal reinforcement
When a wall saw is used to cut is encountered, it should, as far
an opening in a suspended floor, as possible, be cut through in one
adequate supports must be provided movement. Start with the smallest
to prevent the cut section from size of blade and step up the blade
dropping causing damage or injury. size gradually by regular increments,
Safety barriers both on the floor and as suggested by the manufacturer.
below are required to prevent injury to When doing this, ensure that the
fellow workers or visitors. blade width is greater on the smaller
diameters to allow the blade to sit
- Water is used for cooling the
into the cut.
hydraulic unit and for applying
onto the blade for cooling. Never - When cutting out a wall section,
run the unit without connecting an remember the final cut should not be
adequate water supply. the bottom cut as the weight of the
slab will trap the blade.
- The manufacturer’s instructions
Alternatively, the slab must be tied drilled through the concrete with a
into the surrounding wall. Great care 250 mm diameter core drill. The saw
should be used when removing the track is then inserted in this hole so
wedges or tilting a slab out of the that the saw blade will cut through
opening. A 15 cm thick slab will tilt out the full depth of the concrete using
without touching the surrounding wall. a range of starter and step cutting
blades. This method of sawing does
Proper safe rigging and handling away with over-cutting, but if the
techniques must be used when blade is to protrude into a working
removing slabs. area behind a wall or slab, the
- If a blade jams, the manufacturer’s operator must ensure that there is
instructions should be carefully a 70 cm wide safety area in order
followed to avoid damage to the to provide clearance for the blade
hydraulic motor. Before removing when cutting to full width.
a blade guard, ensure that the - A corner cutting saw is normally
blade has stopped rotating and the
chain driven. Prior to assembly,
machine is switched off. Avoid: -
the chain and chain bar must
a) Jamming the blade when be thoroughly clean and
running at high speed; undamaged. When working, the
operator should avoid dropping
b) Traversing the saw rapidly the saw on the chain and chain
with the blade in the cut bar. Jamming the chain in the
and jamming it at either cut should also be avoided.
end; Should jamming occur, switch off
the machine, remove the chain
c) Cranking the blade in or out
bar and sprocket. Do not release
of the cut too fast.
by using the controls.
- Should a blade become wedged in
the cut, do not attempt to un-jam it 4.4 Sawing – Hand-Held Saws
is using Manual Travel or Depth-of- These machines are by hand and
Cut controls. Remove the blade from used to form cuts into brick or
the saw and use other means. concrete using an electric/hydraulic/
- Where the saw is powered by an air High Frequency power supply.
motor, remember that the motor is
4.4.1 Introduction
ungoverned and can over speed
under no-load conditions. This can - Hand-held saws can be divided into
result in blade damage and possible two categories:
injury. a) The traditional disc cutter
- It is essential that a rail mounted saw with a centre driven
is maintained properly. For example, disc/blade, commonly
check oil levels in the gear box. known as a Cut-off saw,
driven either by a small
- After use, all hoses should be integral petrol engine
disconnected carefully, avoiding or electrically. Chasing
dropping couplings. machines and angle
grinders fall into this
category. These can be
used to form shallow cuts
into brick or concrete.
Operating Procedures
unit which gives a cutting Risk Assessment. Wear a respirator
depth of 300 mm from a and/or face mask in these situations.
400 mm diameter blade.
This is achieved by a - Before using a hand-held saw,
unique design where the ensure that it has been checked
diamond blade is driven over prior to issue and that the
from the periphery instead electrical leads and plugs are
of the centre. It is generally undamaged. Also, be sure that all
used hand-held but can the controls and health and safety
be rail mounted. Pre- cuts devices function properly and that
can be carried out by the guards are securely fixed.
power saw, ensuring cost - Never carry a hand saw by the
effective production and blade or guard, as this may damage
easier, safer results. the blade and/or the machine. If
This machine is ideal for use in, for it shatters, a damaged blade can
instance, restricted areas of space, or represent a considerable hazard.
on low volume low quantity cutting - The saw must be fitted with a blade
contracts, due to its size, its ease of or disc which is suitable for cutting
operation and its short set-up time. the material involved. Diamond
Items a) and b) above can be fitted and reinforced abrasive cutting
with diamond tipped laser-welded discs are available and these may
blades, usually running dry or fitted be used wet or dry. Make sure that
with an abrasive cutting / grinding the maximum speed marked on the
disc for cutting stone or metal. They disc is equal to or above the spindle
are often used to cut re-enforcement speed of the machine.
when crushing or bursting. 4.4.3 Operating Procedures
- Although hand-held tools are flexible - Start the machine in accordance
and easy to use, the operator can with the manufacturer’s instructions.
soon become tired. Accidents can
- Both hands should be used when
occur through fatigue as a result of a
operating the power saw and the
slip or mishandling.
guard must be adjusted to suit the
- Remember the operator should job, so that sparks, material particles
have a certificate for the safe use or pieces of damaged disc cannot
of diamond tipped segmented endanger the operator. Hydraulic
blades. This allows the changing hoses and electric leads must
of the blades and understanding always be kept well away from the
of machine operations. However, operator’s feet possibly by passing
the employer is the person them over the shoulder.
who is responsible for ensuring
- To achieve a clean cut, move the
competency.
blade / disc forwards in the cutting
4.4.2 Installation direction and do not force the wheel
- In particular, the operator’s clothing into the material. Do not change the
must be strong and close fitting. cutting direction as this can place
Heavy-duty, non-slip gloves must be undue strain on the blade causing it
worn, together with safety boots with to shatter or break.
non-slip soles. The operator must also - Cut in a forward motion and use
use proper eye and ear protection shallow and intermittent cutting only.
and must always wear a safety
helmet. Most materials create dust,
not over-reach with the machine 30mm apart and 10mm diameter. The
and never operate it above head beads are separated by small springs,
height. Great caution should be plastic or rubber, depending upon the
used when inserting the blade into type of wire and the manufacturer.
an existing cut as kickback can
occur. To prevent this, keep a firm 4.5.2 Installation / Operation
grip on the machine and check that The wire is positioned over the pulleys
the cut width is greater than the through pre-drilled holes in the
blade width if different blades are concrete that is being cut and back
used. For example, a starter blade over the drive pulley. The wire can be
can be wider than a ring saw blade. of almost any length and is joined by
special crimps.
- Work should be properly supported
so that the cut does not close, The wire is rotated, held under tension
pinching the blade. and pulled through the material being
cut. Water must always be used. This
- Where tools are electrically driven, machine is remote controlled by the
care should be taken to ensure that operator, who should be in a position
the cable is not cut or damaged adequate to view the wire and drive
by the saw blade. If damage does wheel, but not directly in line.
occur, the tool must be exchanged
or repair to the cable must be done - The machine must be installed in line
by a competent person. Beware also with the manufacturer’s instructions.
of water that might reach electrical Providing it is installed properly, it is
parts of the machine as this can safe to use and suffers from a low
cause shocks to the operator and level of noise and vibration when
damage to the machinery. compared with other methods.
Operating Procedures
4.6.1 Introduction separation line is required to avoid
Hydraulic bursters are intended for use damage to structural walls or floors.
in rock or concrete breaking where - Before using the wedge type burster,
explosives cannot be used. They will the pump unit and the burster tool
break up large blocks of material into must be checked to ensure that the
manageable pieces which would operating pressure conforms to the
be uneconomical or impractical to manufacturer’s recommendations
demolish by other means such as rock and that the tool works satisfactorily.
drills etc. Bursters have the advantage
that they are relatively quiet and safe - A liberal coating of special grease
to use. should be applied to the wedges.
c) Do not investigate the filled holes The main difference from bursting is
for the first six to eight hours after that it does not need any diamond
filling. Extra care must be taken holes to be pre-drilled and the
when using a cracking agent resulting rubble is of much smaller
during a period of abnormally high dimensions.
climactic temperatures. Excessive Providing a free or open edge is
heat can affect the rate at which available (If not, one has to be made
the process takes place. by sawing or drilling a separation
d) Follow the manufacturer’s line), the jaws which look either like
instructions with care. a large letter ‘C’ or a crab’s claw,
are installed over the concrete to be
e) Avoid contact between the removed. The power unit is operated,
cracking agent and the skin. Wear the jaws come together, and the
protective clothing, particularly concrete is crushed. This process
goggles, industrial gloves, safety is repeated until the whole area is
footwear and a helmet. removed.
f) Keep the agent away from A selection of crushers is available
children and in a safe store when ranging from lightweight, portable
not in use. units, through to remotely controlled
machine mounted machines.
4.7 Controlled Demolition -
Crushing The advantages of this technique are
no vibration, almost no noise and no
4.7.1 Introduction water.
A crusher unit consists of two main 4.7.2 Installation
components: -
- When moving the crusher, never
a) The crusher itself complete with a lift or drag it by its hydraulic hoses.
crushing piston at one end of the Always use the frame or handles.
jaw and It can weigh up to 45 kg, and care
should therefore be exercised when
b) The hydraulic power pack for
lifting.
operating the piston.
- The power pack may require a flow
Operating Procedures
used incorrectly, so follow the 4. Make sure that hands are
manufacturer’s instructions carefully. removed from the area of
The energy generated by the the piston.
crusher can dislodge small pieces of
concrete which burst away at high 5. Continue the piston stroke
speeds. These can be dangerous and resume crushing.
if the correct protective clothing - When operating the crusher,
is not worn. Always wear a safety take care that nothing is trapped
helmet with visor, safety goggles, between the cylinder and the
gloves, apron, shin protection and crusher arms.
protective footwear.
4.7.4 Other Applications
- Equipment is generally designed
Hydraulically operated crushing jaws
for 24 hour operation. For maximum
may also be fitted to an excavator
performance, there should be two
boom for use in the general
well-trained operators. The cutting
demolition of overhead structures. This
of reinforcing bar etc. may require
application will be subject to the safe
a further operator. Use an abrasive
working practices governing general
wheel or cutting torch for this
demolition work.
purpose.
4.7.3 Operating Procedures 4.8 Thermic Lancing
- Ensure that all hydraulic hoses are 4.8.1 Installation
coupled up securely. - The conventional thermic lance is
- When the crusher is positioned over a length of seam welded mild steel
the concrete, there should be a tube, usually a basic 3 metres long,
gap between the concrete and although several lances may be
the bottom rim of the crusher. The coupled together to increase the
crusher must be positioned squarely length. This tube, which is normally
on the concrete and at right angles available in two sizes, 3/8” (10
to it and must never be operated mm) and 3/4” (20 mm) diameter,
whilst it is at an angle either is threaded at both ends and is
diagonally or axially. The crusher can packed with rods, normally strands of
be forced off the concrete causing iron wire. Other sizes of tube i.e. 1/4”
serious damage to the operator and 5/8” may also be available.
and the machine. This kickback is a - The tube is screwed into a lance
serious risk. holder to which a supply of oxygen is
- To ensure that the crusher is properly also connected by means of a hose,
located, comply with the following preferably of the armoured variety, in
cycle: - which case a hose protection valve
is not needed. This lance holder will
1. Position the crusher also have a guard to protect the
correctly and at right operator. Do not use oil, grease or
angle to the concrete other hydrocarbon materials on any
(diagonally and axially. of the cutting equipment, pipe work
2. Advance the crushing or fittings. If necessary, equipment
piston to the point where it must be degreased.
touches the wall. - A reaction is then caused by
3. Stop the piston and check preheating the lance tip until ignition
the correct positioning takes place, thereby producing
temperatures in the region of 2200
Operating Procedures
generally diesel driven and are
- Care should be taken not to carry designed to power wall saws
out thermic lancing in an area where and other equipment and tools
damage to electrical installations, with corresponding power
gas pipelines or other service ducts is requirements. However, units
a possibility. The location of services powered by a 440-volt 3 phase
should be checked with the client. electrical supply provide an
option where noise or fumes
4.8.2 Operating Procedures
etc. are a consideration.
- Once boring with the lance
has started, the reaction a) Although these units are
is self-generating, and the relatively safe to operate,
velocity of the expelled care should be taken with
gases and vapours assists the following: -Hydraulic
the flow of slag from the hoses and fittings/couplings
hole. Holes up to 3 metres etc. must be checked
can be bored, but the regularly for damage
process is facilitated if the and must be changed
holes are inclined upwards at the manufacturer’s
at 5 - 10 degrees to help the recommended intervals;
flow of slag. Holes can be
b) During transport and
bored downwards but the
storage, hoses should
consumption of lance and
not be unduly stressed or
oxygen will increase due to
kinked;
the extra pressure required
to lift the slag clear. At the c) The hose couplings and the
start of lancing concrete, oil must be kept free from
red hot debris will be thrown contamination, and the correct
back at the operator and a grade of oil must be used;
temporary protection barrier
must therefore be erected in d) The manufacturer’s
front of the operator. instructions must be
followed regarding oil
- It is essential that the operating temperatures
operative has a firm foothold and pressures. It is advisable
and will not trip or fall over to run the motor for 5 - 10
protruding objects. minutes without pressure.
- Periods of work should be e) Machines should not be
governed by the operator’s operated until the oil
fatigue as it is dangerous has reached the correct
to carry out this task when temperature. When external
physically tired. If for any temperatures are low,
reason the operator feels preheating of the oil may
unwell, a doctor must be be recommended.
consulted immediately.
f)Where extension hoses are
NEVER POINT A LANCE AT ANYBODY, used, there will be pressure
PARTICULARLY WHEN LIT. losses from a certain
- It is strongly recommended distance onwards. Check
that a fire warden is posted this situation with the
at the working site for one manufacturers.
hour afterwards to ensure
that there is no risk of fire.
Operating Procedures
- They are very useful for cutting of the chain and bar in falling pieces
window and doorway openings in of concrete. One cubic foot of
brick and block because straight concrete weighs approx. 70 kgs. For
lines can be cut with right angled long cuts, it is advisable to score the
corners, eliminating over cutting. cutting line with the nose of the bar to
They can be operated hand-held or provide a guide groove.
track / rail mounted and cut up to A track can be fitted to assist the
600mm deep. operator with fatigue and keeping a
4.11.2 Installation straight line. In addition: -
- Before operating the tool, attention - Ensure that the hydraulic and water
must be paid to the manufacturer’s hoses are correctly coupled, that the
operating manual and to any chain guard is in place and that the
stickers or tags attached to the blade has the correct tension.
tool or hose. These refer mainly to
precautions regarding the use of - Make sure that the working area is
hydraulic systems including non- free from obstructions and does not
conductive cables. include dangerous terrain including
excessive slopes. Do not overreach
- This tool can be extremely or cut above shoulder height.
dangerous if handled carelessly.
Operators should always wear - Always maintain a safe footing and
full safety equipment including: - balance.
goggles, ear and head protection, - There should be a well-marked and
leg protection, gloves, snug fitting signed working safety zone that
clothing and safety shoes. warns other people against entry.
- Check the working area carefully for - Keep a firm grip on the saw with both
live electrical wiring or other services hands. This helps reduce kickbacks
in or adjacent to the material being and maintain control. Do not let go.
cut. The area must also be properly
ventilated. - Always operate the saw for two
or three minutes away from the
- Before energising the power source, intended cut and then check the
hoses must be connected to the chain tension. Remember that the
chain saw hose couplers and chain is designed to operate in one
properly tightened. The chainsaw direction only.
handles must be kept free of
hydraulic fluid and clean. Make sure - Ensure that the working area is kept
that the power source develops the clear of
correct flow and pressure. - Bystanders when starting or cutting.
- Diamond chain saws must only be - Always observe the rated operating
used for applications for which they speeds. Turn off the power source
are designed i.e. cutting concrete, or set the hydraulic control valve
bricks, natural stone etc. They are to neutral before setting down the
not designed to cut wood. Make machine.
sure that you know the exact nature
of the material you are about to cut. - Ensure that the chain and other
components are regularly checked
- Check that the water supply to the for condition and wear.
blade is adequate.
Diamond chains are extremely
expensive. The manufacturer’s
Operating Procedures
- Be aware of the risks involved with - Always keep your concentration
working on the hydraulic system. on the machine when the control
Follow the service instructions circuit is connected. Always wait
carefully. Cleanliness is extremely until the control circuit has been
important. Beware of components disconnected before entering the
that may still be pressurized even working radius of the machine.
when the machine is shut down. Moving control cables or doing
Always secure moveable parts when anything else that can lead to
servicing the machine. inadvertent movement of the control
Personal Protection levers while the control circuit is
connected can result in serious injury.
- Always wear suitable personal
protection equipment. In certain - When moving the machine in areas
environments, breathing protection where there is a risk of it falling, the
or a gas mask will be necessary. operator must be free from the
control box.
Electrical Connection
- Always stand above the machine
- Always handle electrical equipment while manoeuvring on gradients. The
with respect. This applies specially to machine can start to slide down the
leads and connectors. gradient.
- Check that voltage and fuse values - Never manoeuvre the machine into
are correct before connecting. deep water so that water enters
- Always connect the cable through electrical couplings, mains cable,
an earth fault relay. electric motor or any other electrical
equipment, which can then be
- Make sure the main cable is not damaged.
damaged and that the cable is
the correct dimension in relation to - Use the arm as an extra support
its length as recommended by the while moving on gradients.
manufacturers. A long cable should 4.12.4 Before Operating
have a greater cross-sectional area.
- Directions for changing tools must be
4.12.2 Transporting and Hoisting followed carefully.
- Follow the directions in the operating - Coupling tools manually while the
instructions. control circuit is connected could
- Lift the machine only by the lifting cause fatal injury.
eyes provided. The machine must - Make sure the machine is standing
not be lifted by the arm system. securely.
Make sure nobody is standing under
a suspended machine. - Make sure nobody is standing within
the operating radius of the machine.
- Make sure that the capacity of the
truck or crane being used for hoisting 4.12.5 During Operation
is adequate. This also applies to lifting - Follow the directors in the operating
straps and other lifting gear. instructions
- Always secure the machine - Never stand within the operating
as described in the operating radius of the machine. A burst hose
instructions when transporting on a or a wrong manoeuvre can have
trailer or truck platform. Steel bands serious consequences.
have very low friction on a platform.
Operating Procedures
and take caution when driving the - Do not activate control circuits
machine around corners and over until you are sure that the correct
uneven surfaces machine will be operated.
- Move the outriggers to just above - Always concentrate on the machine
ground level when the control circuit is switched
- In situations where outriggers can’t on.
be deployed the machine can tip - Before entering the risk zone of the
Such as: in confined spaces or when machine, ensure that the control
working close to an obstacle. circuit is switched off, preferably with
- The machine can tip in situations the motor stopped, before entering
where the outriggers cannot be the risk zone of the machine
deployed. - The controls or power cables
- The risk of the machine tipping is must not be driven over
greatly increased when the arm is when working or moving the
swung out to the side machine
A metal bonding matrix holds diamond Most blade cores are tensioned at the
crystals in place. Metal powders such factory so the blade will run straight at
as cobalt, iron, nickel, tungsten, bronze cutting speeds. Proper tension allows
and other metals are used in various the blade to remain flexible enough
combinations. The bonding matrix plays to bend slightly under cutting pressure
several vital roles: and snap back into position. An
arbour hole is precisely bored into the
- Disperses and supports the diamonds centre.
- Provides controlled wear while HOW DO DIAMOND BLADES WORK?
allowing diamond protrusion
Diamond blades do not really “cut”
- Prevents diamond pull-out like a knife…. they grind. During the
- Acts as a heat sink manufacturing process, individual
diamond crystals are exposed on
- Distributes impact and load as the the outside edge and sides of the
diamond crystals grind the cutting diamond segments or rim. These
surface. exposed diamonds do the grinding
work.
In the cutting process, the diamonds
in the metal bond grind the material. The metal bond locks each diamond
Legislation
6.1.1 Scope and Objectives framework and its daughter directives.
This Act is the major piece of This led to a “Six Pack” of regulations
legislation in the United Kingdom for being introduced in 1992, some of
Health and safety. It provides the legal which have already been updated.
framework to promote, stimulate and Refer to section 2.3 for further details.
encourage high standards of Health, Details of current regulations, codes of
safety and Welfare whilst at work. practice, etc. are available from the
The act was created to replace the DSA Office. Details are not included
mass of existing safety legislation in this publication as they change
with one Act applying generally to regularly.
all persons at work, and in doing so 6.1.2 The Health and Safety
replaced a mass of detail with a few Executive
simple and easily assimilated precepts
of general application. It established These two separate bodies (The
the principle that prosecution was not HSE and H&S Commission) were
always the first resort and led to the merged in recent years to become
formation of the Health and Safety the Health and Safety Executive. The
Commission (HSC) and its executive Health and Safety Board through
arm the Health and Safety Executive the HSE Executive takes over the
(HSE) which now operate as one body role for Health and Safety policy
called HSE. The Act ensured for the first setting and has overall responsibility
time that occupational safety should for occupational health and safety
also protect visitors and members regulations in Great Britain. The
of the public from work activities. It Health and Safety Executive and
also placed more emphasis on the Local Authorities are the enforcing
requirement to develop and maintain authorities that work in support of the
safe systems of work rather than board.
industry specific technical standards. The Health and Safety Executive is
The Act requires that workers are the principal authority responsible
actively involved in the procedures for the enforcement of the Act and
for accident prevention in their any associated legislation. Provision
workplace. is made for the appointment of
The Act was originally drafted as an inspectors who have wide ranging
enabling Act. This meant that the powers to enter and inspect
Secretary of State or other Ministers premises at any reasonable time,
are permitted to make regulations accompanied if appropriate by the
under the Act. The enabling powers of police or other authorised person.
the Act are exercised through section Inspectors can basically undertake
15 of the Act whereby either the any investigation considered
Secretary of State or other Ministers necessary. They have greater powers
may without referring the matter to than the Police or Customs and can
Parliament require regulations to demand entry at any time. If entry is
be drawn up by the Executive and denied the Police will do it for them.
submitted through the Executive to
him. Their powers include: -
Legislation
substances is safe and without work to: -
risk to health;
Take reasonable care for the health
c) Provide such necessary and safety of himself and of other
information, instruction, training persons who may be affected by his
and supervision to enable acts or omissions at work;
employees to carry out their
work safely; Co-operate with his employer so far
as is necessary to enable any duty
d) Ensure a safe place of work with or requirement under the Act or
safe access and egress; relevant legislation to be performed or
e) Provide a safe working complied with. In addition, no person
environment with adequate shall intentionally or recklessly interfere
welfare facilities. with, or misuse, anything provided
in the interests of health, safety or
Employers also have a duty to ensure welfare. The term ‘employee’ now
that persons not in their employ, who includes all people receiving training
may be affected by their activities, or work experience.
are not exposed to risks to their health
and safety. 6.1.6 The General Duties of
Manufacturers, etc. regarding
However, the introduction of the
articles and substances for use at
Management of Health and safety
at Work Regulations in 1993 revised in work
1999, brought in specific requirements Under Section 7 of the Act, it is the
for employers as set out in Section duty of any person who designs,
2.3.1 of this code. manufactures, imports or supplies
any article i.e. plant, machinery or
When it is proved that an offence is equipment for use at work, to: -
committed by a limited company
through the neglect of a director or a) Ensure, so far as is reasonably
other official, the person as well as the practicable, that it is designed and
company will be considered guilty constructed to be safe and without
and liable to prosecution. This is also risk to health when being set up,
the case where the offence occurs used, cleaned or maintained by a
with the consent or connivance of person at work. Emphasis is required
an official. Steps have been taken of manufacturers to continually
to introduce stronger legislation on reduce noise and vibration
corporate liability for health and exposure levels.
safety, and there have been many
b) Carry out, or arrange for the
principals denied their liberty!
carrying out, of such testing and
These include the Corporate Man- examination as may be necessary;
slaughter Act and the Health and
c) Carry out such steps as are
Safety (Offences Act) both of which
reasonably practicable to make
express clearer accountability to
sure that adequate information
individuals and the structured penalty
about the use for which the article
that can be imposed.
is designed and has been tested
is provided to persons who will be
using it;
d) Take such steps as are reasonably
practicable to ensure that persons
provided with such information are
Legislation
which they are required by statute to properly maintained, and records
provide in the interests of health and kept of examination and testing.
safety i.e. personal protection equipment d) Where necessary, to monitor the
or training. exposure of workers and carry out
health surveillance.
6.2 Regulations
e) To inform, instruct and train
Most of the main Regulations relevant to
employees about the risks and the
construction work are identified at the
precautions to be taken.
relevant place in this Code. Further details
of the overall list of current Regulations f) For drilling and sawing contractors,
are available on application to the DSA. substances hazardous to health
More detailed information may also occur both in the construction
be available in one of the reference workplace and in the office
publications mentioned in section 1.6 of and workshop environment
this code. etc. Dust, slurries and lubricants
caused by cutting operations are
Specific attention is drawn to the following
typical examples. Therefore, it is
Regulations which have a major impact
mandatory that members prepare
on our work.
a COSHH assessment either
6.2.1 Control of Substances separately or as part of an overall
Hazardous to Health Regulations risk assessment.
2002 (COSHH) 6.2.2 Electricity at Work
This is the latest set of COSHH Regulations 1989
regulations which incorporate The regulations lay down duties
previous amendments. The regulations on employers and employees
impose duties on employers for the regarding electrical equipment
protection of employees who may and the use of electricity, with the
be exposed at work to substances purpose of avoiding personal injury
hazardous to health and of other or death. Specific areas covered
persons who may be affected by such by the Regulations are Selection of
work i.e. third parties. The requirements Equipment, Testing, Responsibilities
for employers are as follows: - including Supervision and Training,
a) An employer must not carry on Precautions and Protection (Earthing,
any work which is liable to expose Insulation etc.)
any employee to a substance The HSE also publish a range of
hazardous to health unless a Guidance Notes on electricity at
suitable and enough assessment work, portable and transportable
has been made of the risks to electric equipment i.e. the electrically
health created by the substance. operated tools and machines used in
b) To introduce appropriate our industry.
measures to prevent or control These Regulations require that “all
the risk. Control is only permitted electrical systems be maintained so
where prevention is impractical, as to prevent, so far as is reasonably
and adequate control must be practicable, danger”. This applies
achieved, if possible, by means to all workplaces and requires
other than personal protection. proper standards of maintenance;
It is only where control measures particularly as far as portable
on their own are inadequate that electrical equipment is concerned.
employers may resort to personal
protection.
Legislation
first action level. To calculate the level
Also, the Electrical Equipment (safety)
of protection required employers
Regulations 1994 require equipment to
can use “the estimated noise value
be of safe construction. All equipment
minus 76 = SNR value for protection
put on for sale must have a CE
i.e. 100dB-76=34dB” This ensures that
identification. Electrical equipment
the level of noise exposure is below
will also be covered by the Provision
80dB with protection in place. The
& Use of Work Equipment Regulations
regulations require the employer to
1998.
make an estimate of the noise value
6.2.3 Noise at Work Regulations for the Risk Assessment an actual
2005 measurement is not required.
Employers are required under this 6.2.4 Reporting of Injuries,
legislation, which came into force on Diseases and Dangerous
6 April 2006, to protect workers who Occurrences Regulations 2013
are exposed to noise. Employees
(RIDDOR 2013)
are required to make proper use
of equipment provided for their These regulations require an employer to
protection. When the sound pressure report certain incidents and occupational
level measure at the operator’s ear diseases to the Health and safety
exceeds 80 dB(A) (the first action Executive.
level), noise levels have to be The following types of incidents require
measured, records have to be kept, reporting: -
workers advised, and ear protectors
issued to anyone who requests them. - Death (must be reported
In addition, all machinery should immediately to the HSE, usually by
be marked with its noise level and phone). Death is also reported to the
maintained to stay within it, although HSE if it occurs within 12 months of an
this tends to be impracticable, due accident at work.
to the differing nature of tool usage.
- Specified injuries to Workers
Good risk assessment may alleviate
(regulation 4). This includes: Any
this problem.
fracture other than to a finger,
Above 85 dB (A), the second action thumb or toe;
level, employers should attempt to
Amputations;
suppress the plant, mark out high
noise zones or machines where ear - Any injury likely to lead to permanent
protectors must be worn, and insist loss of sight or reduction in sight
that they are worn.
- Any crush injury to the head or torso
As well as defining sound ‘action
levels’, the Regulations also deal with - Serious burns which cover more than
Noise Assessments and Reduction, 10% of the body
Training in the wearing of Ear - Serious burns that causes significant
Protection particularly plugs, Provision damage to the eyes, respiratory
of Information to Employees and system or other vital organs
Medical Supervision.
- Any scalping requiring hospital
The measurement of sound is a treatment
technical operation requiring
specialist knowledge and equipment. - Any loss of consciousness caused by
If necessary, call in an independent head injury or asphyxia
assessor. Noise assessments are now
- Any injury arising from working in an
a mandatory requirement prior to
Legislation
holder’ to expect the contractor or one contractor. They can be an
principal contractor to assume the organisation or an individual with
duties of a ‘client’ as the industry enough knowledge, experience and
experts. The Domestic Client can ability to carry out the role.
appoint themselves as a client subject
to written notice of this from the Plan, manage, monitor and co-
Principle Designer. ordinate health and safety in the
preconstruction phase of a project.
This is a summary of roles and duties This includes:
under CDM 2015:
- Identifying, eliminating or controlling
Clients foreseeable risks
Organisations or individuals for whom - Ensuring designers carry out their
a construction project is carried out. duties.
Make suitable arrangements for Prepare and provide relevant
managing a project. This includes information to other duty holders.
making sure that:
Liaise with the principal contractor to
- Other duty holders are appointed help in the planning, management,
monitoring and co- ordination of the
- Enough time and resources are construction phase.
allocated. Clients must also make
sure that: Designers:
- Relevant information is prepared Those who, as part of a business,
and provided to other duty holders prepare or modify designs for a
building, product or prepare or
- The principal designer and principal modify designs to system relating to
contractor carry out their duties construction work.
- Welfare facilities are provided. When preparing or modifying
Domestic clients designs, eliminate, reduce or control
foreseeable risks that may arise during:
People who have construction work
carried out on their own home, or the - Construction
home of a family member, that is not - The maintenance and use of a
done in furtherance of a business, building once are built.
whether for profit or not.
Provide information to other members
Domestic clients are in scope of CDM of the project team to help them fulfil
2015, but their duties as a client are their duties.
normally transferred to:
Principal contractors: Contractors
- The contractor, on a single appointed by the client to co-
contractor project, or the principal ordinate the construction phase of a
contractor, on a project involving project where it involves more than
more than one contractor. one contractor.
However, the domestic client can Plan, manage, monitor and co-
choose to have a written agreement ordinate the construction phase of a
the principal designer to carry out the project. This includes:
client duties.
- Liaising with the client and principal
designer
Those who do the actual construction - Co-operate with others and co-
work. They can be either an individual ordinate work to ensure the health
or a company. and safety of construction workers
and others who may be affected by
Plan manage and monitor the work.
construction work under their control
so that it is carried out without risks to - Report obvious risks.
health and safety. - Comply with the requirements
For projects involving more than one in schedule 3 and part 4 of the
contractor, co-ordinate their activities regulations for any work under their
with others in the project team – in control.
particular, comply with directions - Take account of and apply the
given to them by the principal general principles of prevention
designer or principal contractor. when carrying out their duties.
For single-contractor projects, prepare For DSA members, the most important
a construction phase plan. practical aspect of the Regulations is
Workers: the need to prepare risk assessments
and health and safety method
The people who work for or under statements for each individual
the control of contractors on a project, particularly where that
construction site project covers any unusual risks and
hazards. However, the Association has
They must:
prepared several standard generic risk
- Be consulted about matters which assessments and method statement
affect their health, safety and forms covering the various drilling and
welfare sawing activities and techniques.
- Take care of their own health and These standard documents are for use
safety and that of others who may by members where the project only
be affected by their actions involves basic drilling and sawing tasks
based on marking out by the client’s
- Report anything, they see which is representative. Copies of these
likely to endanger either their own or Standard Risk Assessment and Health
others’ health and safety and safety Method Statement forms
- Co-operate with their employer, are available from the DSA office.
fellow workers, contractors and other Where a job goes beyond simple
duty holders. drilling and sawing or where there is
Legislation
statement should then be prepared undertaking the work safely.
for that job.
Where there are more than 5
It is recommended that members employees, the assessment and the
prepare a Risk Assessment and arrangements for implementation
Method Statement for every job that must be recorded in writing. The
they undertake and that the Method process of risk assessment need not
Statement is incorporated in the Job be complicated, providing it identifies
Sheet supplied to the operatives. This hazards and estimates the amount
file is a record of work undertaken of risk attached. It is only a means to
and or conditions found, which need an end whereby the employer can
to be given to new building owners implement the necessary measures
on completion. It is a Client duty to to protect employees and others. The
ensure that a Construction Phase measures should then be monitored
Health & Safety Plan is prepared by for effectiveness and reviewed
the contractor. If they do not do this, it periodically. Competent people
automatically falls to the contractor to should be appointed to assist with
do so. This includes Domestic clients. this implementation, monitoring and
review.
6.3 EU “Six Pack”
Separate written assessments must
Several Regulations came into force be undertaken in respect of specific
from 1st January 1993, mainly in order regulations dealing with COSHH,
to implement European directives, as Noise, Vibration, Manual Handling
follows. and Personal Protection Equipment.
Alternatively, these may form part of
6.3.1 Management ofHealth and
the general risk assessment. Members
Safety at Work Regulations 1999 requiring further advice on risk
The main requirements on employers are assessments should contact the DSA.
to: -
6.3.2 Provision & Use of Work
a) Undertake risk assessments; Equipment Regulations 1998
b) Manage those risks through These Regulations apply to work
effective Planning, Organisation, equipment provided by employers
Control and Monitoring and Review or by self- employed persons for their
of health and safety arrangements; own work. Work equipment must
be suitable for the work which it is
c) Provide health surveillance where intended.
required by COSHH or other
regulations; The Regulations then lay down
detailed requirements for employers in
d) Appoint a competent person relation to:
(health and safety advisor) to assist
on complying with Health and - Maintenance
safety legal requirements;
- Inspection
e) Organise emergency procedures
to deal with serious and imminent - Information and Training
danger; - Dangerous Parts of Machinery and
f) Co-operate with other employees Guards
at a shared workplace such as a - Controls and Control Systems
construction site;
- Stability
g) Provide employees with information
Legislation
eliminated, to minimise the distance
and consequences of a fall should - Decide if operatives are likely to be
one occur. exposed above the daily exposure
limit value (ELV) (see below), and if
The Regulations require: they are, reduce their exposure to
below that value.
- All work at height is properly planned
and organised. - Provide information and training on
health risks.
- All work at height takes account of
weather that could endanger health - Keep a record of risk assessments
and safety. and control factors.
- Those involved at working at height - Keep health records for operatives
are properly trained and competent. under health surveillance.
- The place where work is done at - Review and update assessments
height is safe. regularly.
- Equipment for work is appropriately The exposure action value (EAV), is
inspected. the daily amount of vibration above
which employers are required to take
- The risks from fragile surfaces are action to control exposure.
properly controlled.
The exposure limit value (ELV), is the
- The risks from falling objects are maximum amount of vibration may
properly controlled. be exposed to in any 8-hr day. The
6.3.7 The Control of Vibration at Regulation allow for a transitional
Work Regulations 2005 period until July 2010, for the limit
value. This only applies to work
Vibration at work in our activity will equipment in use before July 2007.
generally be restricted to Hand Arm
Vibration. The problem at the present time is
working out the values. Manufacturers
Hand Arm vibration can be caused by are obliged to give vibration levels,
the holding of any type and hand tool but these are based on factory tests
that transmits vibration. on brand new equipment.
The effects on people include: The vibration levels are measured in
- Pain, distress and sleep discomfort. metres per second square m/s2, and
the level for (EAV) is 2.5 and for (ELV)
- Inability to do fine work. 5.
- Reduced ability to work in cold The difficulty therefore is to get an
or damp conditions, which would accurate amount of vibration level
trigger painful finger blanching when the tool is being used in site
attacks. conditions. The only way one can do
- Reduced grip strength on the hand this is by attaching an accelerometer
tool might affect the ability to work to the tool, but conditions of tool use
safely. can vary every minute.
- The Regulations require employers to: The best advice at present is to always
have tools in tip-top condition, assess
- Assess the vibration risk. risks and above all apply frequent job
rotation to reduce exposure levels.
- Decide if operatives are likely to be Always encourage operatives to keep
exposed above the daily exposed
hands warm and fingers moving.
Policies 88
07 Policies
This is a sample of recommended
Policies
The Association was established in was integrated into the CSCS Card
1984 to group together organisations Scheme based on the achievement
engaged in: - of an NVQ Diploma Level 2 in Drilling
and Sawing.
- Supplying a professional drilling
and sawing service using Any person requiring further
diamond cutting equipment information on the activities of the
and technology i.e. specialist DSA should contact: -
contractors.
The Drilling and Sawing Association
- Supplying the specialist
machines, tools and accessories Unit 3 Brand Street Nottingham NG2
used in this work i.e. 3GW
for the removal of concrete and other construction materials. The chart below
illustrates some of these benefits:
Appendix 1 94
Appendix 2 96
09 APPENDIX1 Head Office
Daniel House Trinity Road Bootle
Sources of Information
Appendices
Appendices
Suffolk CO10 2WA
E-mail: info@sepa.org.uk
Tel: 01787 881165
Head Office
Fax: 01787 313995
Erskine Court
Website: www.hsebooks.com
Castle Business Park Stirling FK9 4TR
11. THE STATIONERY OFFICE
Tel: 01786 457700 (Formerly HMSO)
Fax: 01786 446885 Website for all branches:
www. thestationeryoffice.com.
8. EMPLOYMENT TRIBUNALS
SERVICE (EMPLOYMENT
TRIBUNALS)
Employment Tribunals Service Head
Office:
Ground Floor
19 - 29 Woburn Place London,
WC1H 0LU
Tel: 020 7273 8575
Fax: 020 7273 8686
E-mail: londoncentralet@ets.gsi.gov.
uk
Website: www.employmenttribunals.
gov.uk
9. EMPLOYMENT TRIBUNALS SERVICE
(EMPLOYMENT APPEALS TRIBUNAL)
England & Wales
Audit House, 58 Victoria Embankment
London EC4Y 0DS
Tel: 020 7273 1041
Fax: 020 7273 1045
Website: www.employmentappeals.
gov.uk
Scotland
52 Melville Street Edinburgh EH3 7HS
Tel: 0131 225 3963
Fax: 0131 220 6694
Appendices
table below gives the recommended operating speeds for various materials. Speeds higher
than these should not be used, but lower speeds may be used safely. For blades to run at
speeds higher than 60 metres per second, contact your blade manufacturer.
30 35 40 45 50 55 60
300 1910 2230 2550 2860 3180 3500 3820
350 / 356 1610 1880 2150 2410 2680 2950 3220
400 / 406 1410 1650 1880 2120 2350 2590 2820
450 / 457 1250 1460 1670 1880 2090 2300 2510
500 / 508 1130 1320 1500 1690 1880 2070 2260
600 / 610 940 1100 1250 1410 1570 1720 1880
700 820 950 1090 1230 1360 1500 1640
750 / 762 750 880 1000 1130 1250 1380 1500
800 / 813 700 820 940 1060 1170 1290 1410
900 / 915 620 730 830 940 1040 1140 1250
1000 / 1020 560 650 750 840 930 1030 1120
1060 / 1066 540 620 710 800 890 980 1070
1100 520 610 690 780 860 950 1037
1200 / 1220 470 550 620 700 780 860 940
1350 420 490 560 630 700 770 850
1500 380 440 510 570 630 700 760
1600 360 420 480 530 590 650 710
1750 330 380 430 490 540 600 650
2000 290 330 380 430 480 520 570
2500 230 270 300 340 380 420 460
2700 210 250 280 320 350 390 420
3000 190 220 250 290 320 350 380
Appendices
Depths
Alignment accuracy for all core drilling diameters and lengths: Centre of circle to be drilled:
± 5 mm (0.2 in) plus 2,5% of the diameter.
Core
drilling
d < 1000mm d ≥ 1000mm
(39.4in) (39.4in)
1 Angle accuracy 1% 2%
2 Directional accuracy in oblique drilling 2% 3%
3 Vertical -- --
4 Horizontal -- --
5 Surface roughing drilled wall (evenness) ± 2 mm ± 3 mm
6 Diameter of deviation from specified ± 2 mm ± 5 mm
dimension
7 Specified depth for pocket hole ± 10 mm ± 15 mm
Appendices
Ceiling or wall thickness
Remark: Tolerances are only valid for ceiling cuts from above
d < 300mm d ≥ 300 - 600mm
(11.8in) (11.8-19.7 in)
1 Angle accuracy 2% 4%
2 Directional accuracy in relation to specified ± 10 mm/m 1
± 20 mm/
dimension in longitudinal direction m1
3 Vertical 2% 4%
4 Horizontal 2% 4%
5 Surface roughing of cut surface (evenness) ± 2 mm ± 5 mm
6 Cut width, deviation from specified ± 10 % ± 10 %
dimension
From target value From
target
value
7 Specified depth ± 10 mm ± 15 mm
1 Angle accuracy 2% 4%
Directional accuracy in relation to specified ± 20 mm/
2 ± 10 mm/m1
dimension in longitudinal direction m1
3 Vertical 2% 4%
4 Horizontal - -
Surface roughing of drilled wall
5 ± 2 mm ± 5 mm
(evenness)
Cut width, deviation from specified
6 ± 10 % ± 10 %
dimension
7 Specified depth at joint depth ± 10 mm ± 15 mm
Appendices
Alignment accuracy for all wheel driven floor saws: ± 10 mm (0.4 in) from target line.
Precondition: a level track next to the cut to cater for the width of the
equipment to be used (max. 1.3m, 51.2 in) is necessary to ensure that
the scheduled requirement figures can be achieved.
Remark: Manually driven machines can be more
accurate than motor driven machines.
1 Angle accuracy 2% 4%
Directional accuracy in relation to specified ± 10 mm ± 20 mm
2 dimension in longitudinal direction, cut 4m long
3 Vertical 2% 5%
4 Horizontal - -
5 Surface roughing of cut surface (evenness) ± 2 mm ± 5 mm
Cut width, deviation from specified dimension ± 10 % ± 10 %
6 From target value From target
value
7 Specified depth at joint depth ± 10 mm ± 15 mm
Appendices
Solid concrete Standard type anchors
Cracked or damaged concrete Anchors with approval for cracked concrete
Lean concrete Chemical anchors or through bolting
Masonry Chemical anchors or through bolting
In case of doubt about the concrete quality, is recommended the use of mechanical
anchors with approvals foe cracked concrete.
For lean concrete or masonry, chemical anchors or through bolting must be used.
This document has been extracted from- The DSA Anchoring Fastening of diamond drilling
and sawing equipment
Appendices
NVQ Qualification Units Tools / Endorsements Card Categories
QCF220 Reshape using Hand 1207 – Power Saw Hand Sawing – Power Sawing
Sawing Techniques 1208 – Ring Saw Hand Sawing – Ring Sawing
1209 – Chainsaw Hand Sawing – Chain Sawing
Chasing machine Chasing machine
Angle grinder Angle grinder
QCF220 Reshape using Hand 1207, 1208 & 1209 Diamond Hand Sawing
Sawing Techniques
QCF221 Form Drill Holes or 1210 – Static Diamond Core Drilling – Drill Rig
Core in Structural Fabric Core Drill
1211 – Trailer Rig Core Drilling – Trailer Rig
Diamond Drill
Percussive drill Percussive drill
Hand-held Diamond Hand-held Diamond
Core Drill Core Drill
QCF222 Form Saw Cuts in 1212 – Self Propelled Sawing – Floor Sawing
Structural Fabric Floor Saw
1213 – Diamond Bladed Sawing – Track Sawing
Track Sawing
QCF223 Carry Out Concrete Concrete Bursting
Bursting Operations
QCF224 Carry Out Concrete 1215 – Portable Portable
Crushing Operations Hand Crusher Hand Crushing
Index 110
Index
Environment 27
10
Entanglement 33
Index
EU \“Six Pack\” 83
A Exclusion Zones 32
Access 24
Air Monitoring 28
F
Air Receivers 14 Fire Precautions 21
Air Tools 19 First Aid 11
Alcohol & Drugs 10 Flammable Liquids 19
Apprenticeship Training 7
G
Asbestos 22
Gas Cylinders 20
C General Duties of Manufacturers 75
Carriageways and Streetworks 31
H
Company Responsibilities 6
Confined Spaces 31 Health and Safety Committees &
Representatives 76
Construction Regulations 80
Health and Safety Policy 76
Controlled Demolition- Bursting 55
Hired Plant 19
Controlled Demolition- Crushing 56
Horseplay 10
Control of Vibration at Work Regulations
2005 85 Hydraulic Power Packs 59
COSHH 77
L
D Legal Publications 86
Diesel 20.20
M
Diesel fumes 20
Diesel Fumes 15 Maintenance & Servicing 17
Index
Over Water 32
V
P Ventilation 24
Personal Protective Equipment 84 Vibration White Finger 14
Petrol 20. 20
Plunge Saws and Corner Cutting Saws 52
W
Pollution 27 Walls 31
Portable Electric Tools 60 Walls and Roofs 31
Provision & Use of Work Equipment 83 Waste 27
Welding & Cutting 18
R Welfare Arrangements 13
Reference Sources 7 Working Practices 5
Refuelling 17 Workplace (Health, safety & Welfare) 84
Regulations 77
Reporting Defective Machinery 19
Y
RIDDOR 79 Young Persons 10
Roofs, Working on 31
S
Sawing - Floor Saws 46
Sawing - Hand-held Saws 52
Sawing - Wall Saws (Rail Mounted) 50
Sawing - Wire Saws 54
Scaffolding 25
Scaffold Towers 25
Scope 5, 73
Site Appraisal 30
Site Working Conditions 30
Storage 19
T
Thermic Lancing 57
Tolerances 27
Trailer Mounted Drill Rigs 46
Training 7
Transport 21
Notes
Notes