All drilling work will be carried out by competent personnel who hold NVQ Level 2 in General Instructions
Land Drilling. Specialist tracing equipment such as the RD8000 / CAT4 Cable Avoidance
Tool All steps detailed in this Method Statement are to be completed sequentially, unless
otherwise instructed by IGL Operations Manager or Supervising Engineer.
Standard Equipment and Materials
water, sometimes containing polymer additive, which is pumped down the centre
of the drill string and returns, with any debris, through the annulus.
System of Work
8. For hollow stem auger recovery no cooling of the drill bit is required.
1. All available plans and other suitable information regarding underground and
overhead services in the area of concern must be referred to when the work is 9. Working areas must be kept clear of cuttings and excessive slurry to avoid a risk of
planned and should be available on site when locating borehole positions. (It should slipping; these will be removed to plastic bulk bags or a designated position near
be noted that service connections from a main service to a building or street light the borehole. Hand tools will be kept in a safe location when not in use.
may not be shown on drawings).
10. Where a deviation from the standard working practice occurs, such as drill tools
2. A visual inspection of proposed exploratory location must be undertaken to identify becoming stuck or rig instability a risk assessment will be completed by the lead
potential underground hazards. For example, locations should be relocated if they driller, which may result in the abandonment of the hole. The IGL Engineer must be
fall within line of two inspection covers or are in close proximity to other signs of informed immediately.
service connections (e.g. telegraph poles).
11. On completion the borehole will be backfilled either with arisings or bentonite
3. Locations will be scanned by the trained operative with an RD4000 / CAT3 CAT prior pellets or installed with a groundwater monitoring standpipe.
to commencement of excavation. If underground services are detected the Contract
Manager/Supervising Engineer should be informed immediately and before
continuing further.
4. The rig is normally mobilised to site in the back of a transit type van or on a plant
trailer, the rig is then tracked to a pre agreed location and set up using the four
hydraulic rams situated on either side of the rig, timbers are often used under each
ram particularly when setting up the rig on soft ground.
5. The mast is then erected using a hydraulic ram – when erect the mast is 4.5m from
ground level.
6. The rig comprises of a percussive hammer located to the site of the drilling head
and is used to drive window or windowless tubes into the ground which are then
extracted using the hydraulic jack system. This can be used as an option to sample
those samples overlying rock head.
7. Rotary coring uses the double tube method which comprises a drill barrel with
cutting bit and semi rigid liner attached to a string of hollow drill rods. Temporary
casing may be used to support the hole through loose or unstable material. The
core is held within the liner, which when full is recovered by with drawing all of the
drill rods and finally the barrel. The drill bit is cooled and kept clear of cuttings by
use of a flushing medium. This is commonly compressed air with water mist or
Hazard/
Work
activity Use of Rotary Percussive Drilling Rig Staff at Risk:
assessed: All Employees
Issued Date: June 2019 Review Date: June 2021 Others at Risk: Sub Contractors, site visitors
CONTROL MEASURES REQUIRED TO REDUCE THE RISK: Work to be undertaken in accordance with the method statement. Where a site is
operating a combination of working activities refer to all relevant/additional risk assessments
Severity
Likelihood
S = Severity
L = Likelihood
R = Risk
The following table provides a means of prioritising risk control actions and gives a guide The following guidelines should be used to determine the response that
to ALARP levels. should be taken to manage the risk to an acceptable level.