Professional Documents
Culture Documents
1.Frequency Index = Σ
Where
a= constant to each response from 1 to 4.
n= frequency of response
N= total no of responses
A= highest weight (i.e., 4)
2.Severity Index = Σ
Where
a= constant expressing the weight assigned to each response from 1 to 4.
n= frequency of each response
www.irjmets.com @International Research Journal of Modernization in Engineering, Technology and Science
[858]
e-ISSN: 2582-5208
International Research Journal of Modernization in Engineering Technology and Science
( Peer-Reviewed, Open Access, Fully Refereed International Journal )
Volume:03/Issue:09/September-2021 Impact Factor- 6.752 www.irjmets.com
N= total number of responses
A= highest weight (i.e. 4 in this case)
3.Importance Index= Frequency index X Severity index
Table 1. Calculation Of F.I., S.I. & I.I.
F.I= Σ S.I= Σ
S. No. Types Of Factors I.I.=F.I. ×S.I.
Owner
1 0.52 0.68 0.36
Contributed Factors
Contractor
2 0.6 0.72 0.44
Contributed Factors
Consultant
3 0.5 0.76 0.38
Contributed Factors
Equipment
4 0.52 0.77 0.40
Contributed Factors
Material Contributed
5 0.68 0.72 0.48
Factors
Labour Contributed
6 0.59 0.76 0.45
Factors
5 CONCRETING Concreting by
Ready Mix
CU.M 1 5 10
Concrete
(RMC)
Table 4. Reasons For Delay
Delay in
Description of Delay Cost due to Delay (rupees)
days
Downpours 5 47916
Shortage of labor 3 18000
Missing Information 1 1200
Shortage of material 7 153626
Strikes 2 5714
RMC Supplier busy schedule 2 3920
Shortage of steel bars 16mm
2 5000
dia
Cash flow issues 3 6000
Total 25 2,41,376
VI. CONCLUSION
The major delay issue is the ongoing problem encountered by the construction industry for many years. But the
delays can be decreased by proper management, proper interpersonal management, technical management and
by using the technology in construction projects. Proper management gives an idea to handle a construction
project in-time, control the losses and financial management. This research assessed variables responsible for
construction project delays, which were classified into seven groups, based on a literature review and a
questionnaire survey of respondents. This is a list of all the factors and qualities that contribute to construction
delays. Because various companies have different perspectives on the reasons that cause delays, the scores
given by respondents are not all the same. The data collected from the questionnaire survey was analysed. As a
result, you'll get a full list of features that have been rated in order of significance. Significant proportions were
established to evaluate the likelihood and effect of the elements at various phases of the project, based on the
project's requirements, such as the Importance Index (I.I), Frequency Index (F.I), and Severity Index (S.I). Each
study has been graded based on its contribution to the project. These ranks were contrasted in order to have a
better comprehension.
VII. RECOMMONDATION
Contractual agreements are required, and it is advisable that a genuine to goodness approach be followed.
during the project planning and booking stages. For a successful completion of the project, it is critical to
hire competent contractors, and do not allow visit changes of subcontractors in the executing phase.
It is recommended that owners should not pay contractors late in progress payments because this reduces