Days.

Duration
No. Equipment Activities (days) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
1 Compressor Skid 02 no's Shifting and Installation 4

2 Gas Engine Shifting and Installation 4

3 Cooler Skid Shifting and Installation 2

4 Compressor Accessories Shifting and Installation 10

5 Compressor, Engine and Cooler Alignments 12

6 Gas Scruber Shifting and Installation 4

7 Piping and supports Shifting and Installation 6

8 Main Skid Concrete Grouting 4

9 Cooler Skid/Scruber Skid Grouting 2