cost break down for snag clearance of site 413010 and 413042

site id 413042
item material needed/manpowersSource cost (ETB)
1.door grounding medium size Generator rental 2000
welding materials rental 3000
paint for correction market 100

2.Fall arrest signage signage with ties warehouse/w --


car rental 6000
2 daily Daily labors from lemon to 800
3. above ground qc Tl ---- 2000
Site id 413010
1.Dg foundation correction Cement(1bag) market
sand market
water market
mason from lemon 900
DL from lemon 450
2. Earthing correction Bas bar warehouse --
drill rental 1500
generater rental 2000
2 Dl 800
car rental 5000
3.above ground qc TL 2000
Total 24550
cost with profit 34350