The Kolkata Municipal Corporation Page 1 of 1

M D P S (MANIKTOLA DPS)
5, S.N.BANERJEE ROAD.
Standard Form of Work Order

Work Order No:180785

Work Order Issue Date:05-MAR-24


From:
Executive Engineer , M D P S (MANIKTOLA DPS)

5, S.N.BANERJEE ROAD.

To :

CRYSTAL ENGINEERING (W082)

263 UPENDRA NATH BANERJEE ROAD MAIL: 239/3 UPEN BANERJEE ROAD KOLKATA KOLKATA KOLKATA 700060 '

Sub: URGENT REPLACEMENT OF DAMAGED COMPONENTS OF SWF STATION FEEDER PANEL OF ANDREW YULE
MAKE H.T. VCB [6.6KV. 630A) WITH OTHER ALUED WORKS AT DUTTABAGAN DPS UNDER MOPS.

Dear Sir,

Your Tender or Quotation dated 16-AUG-23 for the above work has been accepted by Mpl. Commr, D.G, Dy .CE., Executive Engineer - MD
P S (MANIKTOLA DPS) on 05-MAR-2024 . You are hereby requested to contact ARNAB GANGULY in- charge of the work on for taking up
the work and further advice. You will have to complete the works within stipulated time. The date of completion shall be reckoned from the
date of handing over the site. Please note that the agreement has not yet been accepted. You are to execute the same during the progress of
the work. No final payment can be released without execution of agreemental work. You are to take license from the office of the Labor
Commissioner Govt. of West Bengal. , New Secretariat Building. (11th floor), Kolkata -1 . If you are under the purview of the labor regulation
and abolition rule, 1972.

Yours faithfully

Executive Engineer
M·D P S (MANIKTOLA DPS)

COA: 2.436.60.333.01 .60800.00000

Total Hot -Mix Values: NIL

L 1 Rate: At Par

Order Amount(Rs.) : 395522 (Including Contingency Amount) (GST Rate : 18%)


Time of Completion 7 Day(s)

Copy To:

1.1.T.O
2. Sales Tax Commissioner (Where Applicable) .
3. Labor Commissioner, W.B. New Sect!. Bldg. (11th Floor) (where Applicable)
4. Ward Councillor
5. The Assistant Engineer (C)

Executive Engineer
M D PS (MANIKTOLA DPS)

You might also like