1. In PRINCE2, what is a "project tolerance"?

A. The amount of time a task is allowed to take


B. The level of authority given to the project manager
C. The maximum deviation allowed before the project is considered a failure
D. The flexibility allowed within a stage or project plan without the need for
escalation

Answer: D

2. What is the purpose of the PRINCE2 theme "Progress"?


A. To manage changes to the project's baseline
B. To ensure that the project delivers products that meet stakeholder
requirements
C. To monitor and report on the project’s performance
D. To define the approach to quality management

Answer: C

3. Who is responsible for managing the day-to-day work on the project in


PRINCE2?
A. Project Manager
B. Project Board
C. Executive
D. Senior User

Answer: A

4. Which PRINCE2 process involves creating detailed plans for each stage of the
project?
A. Starting up a Project
B. Initiating a Project
C. Managing a Stage Boundary
D. Planning

Answer: D

5. What is the primary purpose of the PRINCE2 theme "Risk"?


A. To identify and analyze project risks
B. To manage changes to the project's baseline
C. To define the roles and responsibilities within the project
D. To ensure that the project delivers products that meet stakeholder
requirements
Answer: A