Professional Documents
Culture Documents
The Contractor shall develop a Project BIM for all disciplines (including all sub-contractors and vendors)
as a minimum to AIA BIM level of development (LOD) 400 and LOD 500, to include infrastructure,
utilities, architectural, structural, MEP/ FLS and other services, and specialist constructions, from the
Design BIM developed by the design consultant(s) to LOD 300. The detailed Project BIM strategy is
included at section 6.1 below.
This model is to be maintained throughout the construction phase with the resulting model transferred
to the Employer for their subsequent use and adaption, with data organization such that it can be
further developed at later Project stages by others. The Contractor’s services pertaining to BIM shall
include the following:
High level BIM management, design and collaboration to ensure integrity of design data and value
through the BIM process comprising:
a) detailed BIM execution plan
b) use of BIM to develop and audit the construction at key stages to ensure compliance to the
program and detection and resolution of clashes/conflicts.
c) intelligent linking of Project documentation (schedules, room data sheets (RDS), equipment, etc.)
to a single-source of information platform - the Project model.
d) quality assurance and quality control (QA/ QC) of modelled information to ensure data integrity.
e) incorporation of all sub-contractor and vendor information into BIM by direct input and the
implementation of collaboration protocols
f) sustainability evaluation.
In the event the Design BIM is not made available to the Contractor at the contract commencement
date, the Contractor will be required to proceed with the Works, based on the Issued for Construction
(IFC) documentation provided, and develop the model once received.
40
Standard Document No.: 1201 (October 2021)
Section 6.1
Building Information Modelling Requirements
Section 6.1 defines the Building Information Modelling (BIM) requirements for the Contractor. The
Contractor shall be responsible for the development of the Project BIM as detailed herein:
Objectives
Use BIM to inform the design & construction programme and to review the design at key
project phases to ensure compliance to programme.
Page: 41
Classification - Public 1
Standard Document No.: 1201 (October 2021)
Objectives
Use appropriate tools and methods to address clash control and omitting it
LOD 400 Fabrication and drawings approval using BIM extractions and CDE gates
i. Develop and submit a pre-contract BIM Execution Plan (BEP) as part of the proposal, the Pre-
Contract BEP is a pre-cursor to the BEP and outlines as a high level, the Contractors proposed
BIM Methodology and proposals for fulfilling the project BIM requirements.
ii. Produce a BIM Execution Plan in coordination with all project parties to successful digital
Delivery of information in accordance with Project Requirements within one (1) month of
Letter of Award. The requirements of the Precontract BEP are defined in the respective section
of this Document.
iii. Ensure roles and responsibilities within the proposed BIM Team are defined and allocated
correctly for the successful delivery of all BIM tasks.
iv. Provide and maintain a Master Information Delivery Plan (MIDP) collating all subcontractor’s
Task Information Delivery Plans (TIDPs) in line with project programme (within one month of
contract award).
v. Provide a Level of Detail (LOD) and a Level of Information (LOI) matrix proposal outlining the
Geometric detail and Design Information Attributes that will be available within the Model at
each stage.
vi. Develop necessary BIM Models (LOD 400/500) to meet the requirements, ensuring that the
BIM models and its content at the development is in accordance with established BIM industry
standards which can be used and relied upon by any project stakeholder within the project
Page: 42
Classification - Public 2
Standard Document No.: 1201 (October 2021)
vii. Ensure latest version of all Design Models are available within the EDMS for all project
stakeholders. Being used to enhance Design development and Design Review meetings.
viii. Maintain a federated model for the respective scope containing latest model version of all
disciplines.
ix. Prepare and provide a BIM training strategy to ensure all project members, including sub-
consultants, have the necessary skills to utilise model outputs.
x. Produce all construction drawings directly from the Design Models. Ensure that there are no
discrepancies between 2D and 3D information.
xi. Ensure 3D Models are clash coordinated ensuring coordination of all building components and
buildability, thus enabling the contractor to progress construction activities at the site in a
timely manner with minimal or no conflicts.
xii. Provide models and information when requested to the Cost Consultants to assist in his cost
advice generally during design development including his carrying out of cost comparisons of
alternative design or construction solutions as necessary or as requested by the Employer.
xiii. Ensure assets information parameters are embedded within the BIM models and fill whatever
applicable according to the defined responsibility.
xiv. Handing over an assets list in the tender stage with all the information needed (should be
defined in deliverables also).
xv. LDC to ensure QA and QC process is in place and carried out on all BIM models and processes.
xvi. Provide BIM Progress reports as requested and BIM Close out report at each Project
Milestones.
xvii. Maintain BIM related Risks and Issues within the overall Project Risk register.
xviii. Capture Lessons Learned
xix. Responsible for incorporating and coordinating any sub-consultant models.
x Plumbing systems, including but not limited to, water distribution, storm drainage, and
sanitary sewerage waste and vent piping, water heaters, and plumbing fixtures.
x Fire suppression systems, including but not limited to, standpipes, sprinkler systems, fire
pumps, and nonwater-based fire-extinguishing systems.
x Electrical systems, including but not limited to, conduit greater than 35mm in diameter,
or bundled conduits, cable-tray, transformers, switchgear, switchboards, panel boards,
generators, lightning protection, and lighting.
x Communication systems, including but not limited to, structured cabling, premise wiring
distribution system, etc.
Page: 43
Classification - Public 3
Standard Document No.: 1201 (October 2021)
x LOD 100 – Essentially the equivalent of conceptual design. The model would consist of
overall building massing and the downstream users are authorized to perform whole building
types of analysis (volume, building orientation, cost per square meter, etc.)
x LOD 200 – Similar to schematic design or design development. The model would consist of
"generalized systems or assemblies with approximate quantities, size, shape, location, and
orientation." Authorized uses would include "analysis of selected systems by application of
generalized performance criteria."
x LOD 300 – The Model Elements are graphically represented within the Model as a specific
system, object, or assembly in terms of quantity, size, shape, location, and orientation. Non-
graphic information may also be attached to the model elements. The model is suitable for
the generation of construction documents. As such, analysis and simulation are authorized
for elements and systems.
x LOD 400 – This level of development is considered to be suitable for shop drawings
production, fabrication, and assembly. The MEA (Model Element Author) for this LOD is most
likely to be the trade contractor or fabricator.
x LOD 500 – As-Built conditions are modeled as constructed assemblies for Maintenance and
operations. In addition to actual and accurate in size, shape, location, quantity, and
orientation, non-geometric information is attached to modeled elements.
Page: 44
Classification - Public 4
Standard Document No.: 1201 (October 2021)
x The capability of setting up and managing a common data environment for the sharing and
transmission of project design information
Page: 45
Classification - Public 5
Standard Document No.: 1201 (October 2021)
l. LOD Matrices specifying which elements will be produced for each discipline and their level
of development including geometrical development and data.
m. Appendices (Any appendices as necessary)
a. The Contractor shall demonstrate BIM model progress and its uses during regular
meetings with the Employer and project team.
b. Autodesk Navisworks to be used as the common collaboration platform for the project,
regardless of the model authoring software used (i.e. – Revit, Bentley, etc.)
d. Through the collaborative process the party, or parties, responsible for making changes
to resolve any conflicts shall be identified. After each model review meeting, a minute of
any required changes shall be distributed to the project team.
Software Description
Autodesk BIM
Used for Revit collaboration along the teams. Is accessible
360/Autodesk from mobile devices and tablets. Work sharing within project
teams.
Construction Cloud
Page: 46
Classification - Public 6
Standard Document No.: 1201 (October 2021)
Software Description
Enscape
For Virtual Reality and real time illustration
c. The software shall support most of publicly add-ins to help/facilitate model authoring.
d. The software shall support multi-location work (cloud-based) and not be attached to a
specific server in a specific location.
Page: 47
Classification - Public 7
Standard Document No.: 1201 (October 2021)
i. All appointed parties are responsible to provide training to upskill and maintain the skills
of their teams and their sub-consultants/sub-contractors for any software used in the
project. All appointed parties shall detail their training plan in case of awarding to satisfy
and achieve all BIM needs and requirements.
j. The Employer may call for training for any software used in the project, Contractor shall
ensure on the training commencement not more than two weeks from the training
request.
k. The Employer is not responsible for any training requirements or technology providing
for external parties in the project. Find below the main training fields needed:
x Software trainings
Page: 48
Classification - Public 8
Standard Document No.: 1201 (October 2021)
Version
Standards
/ Date
Page: 49
Classification - Public 9
Standard Document No.: 1201 (October 2021)
Version
Standards
/ Date
BS 8536-1 Briefing for design and construction. Code of practice for 2015
facilities management (Buildings infrastructure)
BS 8536-2 Briefing for design and construction. Code of practice for 2016
asset management (Linear and geographical
infrastructure)
UK construction industry
x DMT and other authority digital data requirements and specifications, including GIS
and CAD; as well as the Employer electronic media standards.
x Provide GIS files for each Project Stage and authority submissions for review and
acceptance by The Employer.
x Site and its layout finishing plans must-have design levels with GIS control points for
setting out purposes.
x Provide CAD digital modes of all massing, plan, sectional information illustrating the
roads, building massing, plot boundaries, controls, utilities, and infrastructure.
x The CAD data is to be properly layered and coordinated in accordance with DMT and
approved international conventions. Any 3D data used to develop the design to be
included in the final handover, information is to be coordinated with area schedules
and costing data.
Page: 50
Classification - Public 10