Professional Documents
Culture Documents
METHOD STATEMENT
Project Manager HSQE Advisor Civils Site Manager Client / Clients Representative
ACCEPTED BY CLIENT
AUTHOR REVIEWER APPROVER
(if applicable)
C02 S3 Official
REVISION HISTORY
REVISION STATUS CODE DATE REVISION DESCRIPTION
P01 S3 27/10/2023 Issued for Review/Comment
Page | 1
METHOD STATEMENT
Murphy Prevent Operate Safety
Control our Protect our Protect the
Simple service Plant Documents in
work areas health Environment
Actions damage Safely Place
01 Contractor’s Representative
03 Project Manager
04 Site Engineer
05 Safety Advisor
06 Quality Manager
07 Subcontractors
08 Irish Water/RPS
09
10
11
Page | 2
METHOD STATEMENT
Murphy Prevent Operate Safety
Control our Protect our Protect the
Simple service Plant Documents in
work areas health Environment
Actions damage Safely Place
Contents
Page | 3
METHOD STATEMENT
Murphy Prevent Operate Safety
Control our Protect our Protect the
Simple service Plant Documents in
work areas health Environment
Actions damage Safely Place
2 Reference Documents
Reference should be made to the following documents, when reading this method statement:
• Construction Stage Health and Safety Plan;
• Construction Environmental Management Plan (CEMP);
• Project Quality Plan;
• Contract Drawings;
• Utility Drawings;
• Project Emergency Plan – including rescue procedure for works in cofferdam.
• Shay Murtagh Method Statement for installing precast tank to be issued separately.
• Murphy RAMS Pipework and Ducting Install
• Method Statement from Ward Piling – Appendix D – Steel Sheet Piling Works
3 Pre-commencement Requirements
3.1 General Pre-commencement Requirement
1. All management and operatives will attend a site induction, and will have completed the relevant training
programmes;
2. All operatives will be briefed on the contents of this risk assessment & method statement (RAMS) for the
works to be undertaken, and they will sign to confirm they fully understand its contents
3. Any permits required for the works will be issued, briefed, signed onto by the work team and strictly
adhered to during the works;
4. A Point of Work Risk Assessment (POWRA) shall be carried out at the place of work, immediately prior
to commencement of the works, with the operatives at the start of each shift, and they will all sign to
confirm they fully understand its contents;
5. Any additional hazards raised, will be noted on the Point of Work Risk Assessment, and control measures
put in place, prior to the works commencing;
6. If the conditions change significantly at the place of work, then the Point of Work Risk Assessment will
either be revised, or a new Point of Work Risk Assessment will be carried out;
7. A copy of the RAMS and a daily Point of Work Risk Assessment, will be retained at the place of work for
the following reasons;
• For reference by the work team;
• Briefing additional man power;
• Audit purposes.
8. Upon completion of the shift, the relevant daily Point of Work Risk Assessment and any permits will be
closed out, and will be passed to the Murphy Safety Adviser for filing;
Page | 4
METHOD STATEMENT
Murphy Prevent Operate Safety
Control our Protect our Protect the
Simple service Plant Documents in
work areas health Environment
Actions damage Safely Place
9. All necessary consents will be applied for by the engineer, and once received the works shall commence;
10. This document will make reference to other RAMS if applicable, before the commencement of the works;
11. Documents to be issued prior to the commencement of the works, include but are not limited to:
a. AF1 / AF2;
b. All associated internal Murphy Permits for working (SHESQ);
c. Rescue Plan (SHESQ);
d. Emergency Procedures (SHESQ)
4. Excavator & Movax Hammer Ward Piling Sheet Piling Works Operatives
6. Edge Protection and Access Altrad Services Safe Access to Cofferdam Operatives
5 Methodology
5.1 General
1. All works will be carried out in accordance with the contents, of this method statement & risk assessment;
2. The works as detailed in this method statement, will be carried out under the supervision of the Murphy
construction manager / site foreman / site engineer;
3. Works area’s will be established and demarcated as deemed necessary by the MIL site management
team. Suitable timber skids will be cut as required.
Page | 5
METHOD STATEMENT
Murphy Prevent Operate Safety
Control our Protect our Protect the
Simple service Plant Documents in
work areas health Environment
Actions damage Safely Place
2. Delivery lorries will arrive at the entrance to the wastewater treatment works and be directed to the
laydown areas as indicated in the sketch – Piling Works Layout Plan - included in the next Page.
3. Delivery trucks will be positioned at an off loading location, on the site as deemed necessary by the site
foreman. Trucks to be directed by a competent person;
4. A 60 t CRANE from ECCH will have been taken on to site and positioned prior to arrival. The crane will
be directed to the required position as indicated in the layout provided and be positioned on suitable hard
standing, and set up as the manufacturer’s recommendations and the lift plan requirements.
5. An exclusion zone will be implemented and can be maintained by a spotter during lifting operations. A lift
plan will be put in place to cover all lifting operations. A POWRA and a specific toolbox on Lift Operations
will be completed prior to this activity.
6. Prior notice will be given to the Operations team and no site activities are scheduled for this date.
7. During this activity, there will limited access to the Site and a dedicated observer on Site.
8. All straps will be removed from the load, each individual bundle will be slung as deemed suitable by the
slinger/signaller. Tag lines will be utilised as required to control the load when it is suspended in the air;
9. The load will be pinched to ensure the load is suitably balanced. The load will then be lifted and slued into
the required position and lowered to the ground;
10. The load will be positioned on timber skids and lifting equipment removed;
11. The steps detailed above will be repeated until all bundles have been off loaded;
12. Once all the bundles have been removed, the lorry will be turned and directed off site;
13. A R Duck will be used to move the sheet piles around site as required. Sheet piles will be separated using
an excavator/fork attachment. Once the bundles have been split, they will be suitably slung as required
by the slinger/signaller. Smaller bundles or single sheet piles, will be moved around site as required by
the R Duck and positioned on timber skids.
Page | 6
METHOD STATEMENT
Murphy Prevent Operate Safety
Control our Protect our Protect the
Simple service Plant Documents in
work areas health Environment
Actions damage Safely Place
Page | 7
METHOD STATEMENT
Murphy Prevent Operate Safety
Control our Protect our Protect the
Simple service Plant Documents in
work areas health Environment
Actions damage Safely Place
1. Refer to Ward Piling Temporary Works Design for Pile type and design depth and orientation.
2. A specialist dewatering contractor will commence drilling once sheet piles are completed. 2 no. 250
mm wells will be drilled to a depth of 6.5 meters below ground level, lined with 150mm Boode Ecoline
PVC Casing and Screen (Screen to invert level of IL 37228) filled with 3-5mm washed pea gravel
surround.
3. An external generator and control panel will be provided to supply pumping requirements.
Please refer to sketches below for proposed pump arrangement and for outfall setup. Pumps sizes to
be confirmed once wells are completed and dewatering contractor will insert test pumps to confirm
flows. All flushing and testing of wells will be pumped back in within the perimeters of the cofferdam.
Water Sample will be taken to check turbidity levels of water.
4. Altrad to provide access point and handrails for edge protection – this detail will be forwarded for
review on the next revision of this RAMS and included in Appendix E.
5. Refer to Emergency Plan for the Cofferdam rescue procedure.
6. Excavation works (Phase 1) to commence with 16t R Duck. Excavation materials loaded directly onto
trucks. Phase 1 of excavation will achieve an invert level of I.L. 38095.
7. At this point, ground conditions will be assessed and once these have been determined to be
suitable, a 3t mini digger will be used to excavate to the cone area in the centre – I.L. 36928.
8. An oxygen monitor will be hung next to the excavator to measure the content of oxygen whilst
excavating within the cofferdam. The operator is required to work for 30 minutes then switch off the
machine for a period of 10 minutes to allow the area to fully naturally ventilate. Works may resume
for another 30 minutes followed by a 10 minute rets period. This is to be repeated for the entire
excavation time within the tank. If the oxygen monitor alarm sounds the operator is to leave the tank
immediately via the provided access stairs switching off the machinery in the process. Top man to be
present for the duration of the machine working period to raise the alarm if an emergency situation
arises.
9. A layer of blinding will be poured using a 24m concrete boom pump to form the base of precast
manhole diameter – internal measurement > 2.5 meters to facilitate Shay Murtagh cone section. Hi-
ab to be used to insert manhole into position.
10. 200 mm sludge outlet pipework and 200 mm inlet pipework from Splitter chamber will be installed, an
air test will be completed to conform integrity of the pipelines. A dumpy / laser level will be used to
ensure the correct level is obtained. Pipework will be set out by the site engineer in line with the
Page | 8
METHOD STATEMENT
Murphy Prevent Operate Safety
Control our Protect our Protect the
Simple service Plant Documents in
work areas health Environment
Actions damage Safely Place
design drawings. Levels and falls will be marked on pins on site to provide a reference guide for the
setting out of the base.
11. Both lines to be backfilled with approved materials. Refer to Pipework RAMS. Both pipes to stop 200
mm from sheet piles and finished with blank plates and put a void fill at pipe end.
12. Area to be prepared for Shay Murtagh’s permanent base. Concrete blinding will be pumped using a
concrete pump and levelled off using a grade laser with levels set to suit the underside of the new
clarifier concrete base.
13. A flexible 25mm material to be installed on sheet piles prior to concrete base pour.
14. Backfilling of the clarifier will be carried out by a 1.5t mini excavator and 900mm compact roller.
Access will be provided by overfilling predetermined point between the sheet piles and the tank to
enable pedestrian/walking access on the southerly site and plant access on the Northern side.
Further loads of SR21 T0 material will be placed with the rubber duck where required and spread
with the excavator. An operative will remain top side to reverse in delivery trucks and bank the rubber
duck. Operatives will wear an 02 Monitor, should the alarm sound, all personnel must evacuate the
area. Machinery will be required to shut down every 30 minutes to allow the area to naturally
ventilate.
Once spread to a depth of 150mm each layer is compacted/rolled.
Page | 9
METHOD STATEMENT
Murphy Prevent Operate Safety
Control our Protect our Protect the
Simple service Plant Documents in
work areas health Environment
Actions damage Safely Place
Page | 10
METHOD STATEMENT
Murphy Prevent Operate Safety
Control our Protect our Protect the
Simple service Plant Documents in
work areas health Environment
Actions damage Safely Place
Page | 11
METHOD STATEMENT
Murphy Prevent Operate Safety
Control our Protect our Protect the
Simple service Plant Documents in
work areas health Environment
Actions damage Safely Place
6 Programme
These works are due to commence on the 01st November 2023, and will continue from thereon, as detailed in the
overall construction programme for the project.
7 Quality
All works will be carried out in accordance with Company Quality Procedures and the Employers Requirements.
8 Safety
All works will comply with the Safety Health & Welfare at Work Act 2005, and all other relevant safety legislation,
and in accordance with the Construction Stage Health & Safety Plan.
On a daily basis, the site foreman or a designated person, shall complete a Safe Plan of Action / Point of Work
Risk Assessment. This SPA / POW shall be briefed to all under their control.
Safety shall be promoted by induction and training. All site personnel including sub-contractors, will hold a Safe
Pass Card and Manual Handling, or their entry to site will be forbidden.
All works shall be carried out in a safe and satisfactory manner, using approved certified plant and equipment.
A qualified First Aider shall be present on site during the construction works.
All personnel will be required to wear PPE for the particular works which they undertake, and as a minimum Hard
Hats, Safety Gloves, Safety Glasses, Hi-Visible Jackets or Vests and Steel Toe Cap Boots will be worn.
Notices of the works will be issued to adjoining occupiers, informing them of the nature and timing of the works
outside their properties.
The site entrance, access road, works areas, signs, cones and barriers will be maintained in a clean and tidy
condition.
9 Environmental
Works shall be carried out strictly in accordance with the Construction Environmental Management Plan (CEMP).
Murphy Group will ensure that relevant permits, licenses’ or consents are in place, and their requirements briefed,
to those carrying out the activity before works commence.
Murphy supervision will monitor the noise, dust, vibration, & water associated with these activities. Should any
significant issues be observed, they will contact the Construction Manager and agree measures to be taken to
address them.
Daily visual checks of all site plant and vehicles shall be made, for leakage of fuel or oils. Leaks shall be rectified
immediately, or the item removed from site and replaced.
Fuels, oils, greases and hydraulic fluids shall be stored in bunded containers.
25 litre emergency spill kits shall be available at all times. All spills will be dealt with promptly, and reported to
Murphy site management.
Any waste generated, shall be managed in accordance with the Site Waste Management Plan.
All environmental incidents and non-conformances, shall be dealt with and reported in accordance with the
Construction Environmental Management Plan and the Murphy Procedure – Accidents and Incidents.
Page | 12
METHOD STATEMENT
Murphy Prevent Operate Safety
Control our Protect our Protect the
Simple service Plant Documents in
work areas health Environment
Actions damage Safely Place
Hazardous Substances
Dangerous
Irritant Respiratory Corrosive Toxic to the Oxidising Flammable Explosive
Hazard Environment
Applicable NO NO NO NO NO NO NO NO
SWLs
• N/A
Other:
Safety Boots Hard Hat Safety Gloves Hearing Eye Respiratory
Protection Protection Protection
1. Hi-Viz
Personal Protective Yes Yes Yes Yes Yes No
Yes
Equipment required
2. Coveralls
No
Page | 13
METHOD STATEMENT
Murphy Prevent Operate Safety
Control our Protect our Protect the
Simple service Plant Documents in
work areas health Environment
Actions damage Safely Place
Emergency Procedures • Please refer to the onsite emergency procedures on the notice boards, these are
communicated at the site induction.
Services to be supplied
by Others
• N/A
Page | 14
METHOD STATEMENT
11 Appendices
11.1 Appendix A – Risk Assessment: Cofferdam Construction - Phase 1
No Hazards Risk Persons at Risk Risk Control Measures Residual Risk Further actions
Rating (RR) rating
List what could cause harm from this activity e.g. List what the List who might Decide level of For each hazard, list the measures you will be Decide level of Note any further
working at height, trip hazard, fire, etc. outcomes be harmed and risk without your taking to minimise the risk identified e.g. risk once all your actions here.
could be e.g. how controls in place appointing competent persons, training controls are in
slips, trips, (see below) received, planning, use of personal protective place (see below)
falls, equipment, provision of first aid, etc.
electrocution,
burns etc.
L x S = RR L x S =RR
15 | P a g e
METHOD STATEMENT
3 Use of Tools strains, Site staff, 2x2=4 Competent trained operatives. 1x2=2
Mobile Plant:
Only skilled and trained operatives, to operate
plant.
16 Tonne Wheeled Excavator; All operatives to be inducted onto the Cahir
5 Tonne mini digger WWTP project, and to be briefed on the
contents of this method statement.
30t ward piling excavator General
Movax Hammer Operatives, All plant to be in good working condition, and
Collision with have all the safety guardrails in place.
5 Drilling Rig other plant or Machine 4 x 4 = 16 1x4=4
24m Concrete boom pump site personnel Drivers Correct PPE to be worn at all times:
Hard hat, glasses, gloves, hi-vis, steel-toe cap
1.5 ton excavator Site personnel boots.
900mm Roller
Work areas to be segregated using signs,
cones, barriers, etc.
16 | P a g e
METHOD STATEMENT
17 | P a g e
METHOD STATEMENT
18 | P a g e
METHOD STATEMENT
19 | P a g e
METHOD STATEMENT
20 | P a g e
METHOD STATEMENT
21
METHOD STATEMENT
Site Compound
Offices (Golf
Club)
22
METHOD STATEMENT
Site
Entrance
23
METHOD STATEMENT
11.4 Appendix D– Preliminary Temporary Works Design from Ward and Method Statement
1. TWDC
2. TW DESIGN (EG Consulting Eng)
3. RAMS (Ward Pilling)
24
EG Consulting Engineers Ltd,
Bellanascadden,
Coolboy,
Letterkenny,
Co. Donegal
0861024599
Designed By:
EG Consulting Engineers
Date:
30th October 2023
Cahir WWTW Cofferdam TWs Design 23-056
Design of cofferdam temporary sheet piling system to facilitate the installation of precast Shay
Murtagh concrete structure at Cahir WWTW.
Base of primary dig proposed at 3.50m below GL, with a localised sloping of dig within cofferdam
for installation of central sump.
From IGSL Borehole Log ref: 23137D, the subsoil are reasonable similar in characteristics and
vary in clay make up from silty/gravelly/sandy type clays. With 'N' values ranging from 21-50,
these clays are stiff.
It is proposed to install min 6.6m sheet piles with a 3.1m toe in and cantilevered only.
A 75mm blinding layer to be installed as capping to exposed ground immediately upon reaching
dig level.
3500
Soft Silty Clay
0
00
4
Gravelly Clay (Soft to firm)
Ø1
Murtagh Precast Tank
3100
. .. . .
notes
1m
2m
Soft CLAY
3m
Depth 3.50m
4m
5m
6m
Designer : EG
EG Consulting Reference: 23-056
Contractor: Ward Piling Date: 30/10/2023
Engineers
Rev: 01
SUMMARY
INPUT
SOIL PROFILE
Depth (m) Soil Name y(kN/m³) y'(kN/m³) C(kN/m²) Ø(°) Ka Kp Kac Kpc delta
0.0 Medium Dense
17.00 10.50 0.00 36.00 0.26 3.85 0.00 0.00 0.00
GRAVEL
2.0 Soft CLAY 17.00 7.00 20.00 0.00 1.00 1.00 2.00 2.00 0.00
3.5 Soft to Firm CLAY 17.50 7.50 40.00 0.00 1.00 1.00 2.00 2.00 0.00
5.5 Firm CLAY 18.00 8.00 50.00 0.00 1.00 1.00 2.00 2.00 0.00
6.5 Soft to Firm CLAY 17.50 7.50 40.00 0.00 1.00 1.00 2.00 2.00 0.00
7.5 Medium Dense
17.00 10.50 0.00 36.00 0.26 3.85 0.00 0.00 0.00
GRAVEL
8.7 Dense SAND 19.00 11.00 0.00 34.00 0.28 3.54 0.00 0.00 0.00
9.2 Medium Dense
17.00 10.50 0.00 36.00 0.26 3.85 0.00 0.00 0.00
GRAVEL
SOLUTION
DESIGN SOLUTION
Support Type Fixed Earth Support Toe = 3.08 m
Pressure Model BSC Piling method
Passive Softening Applied
Water Balancing Not Applied
SHEET
Sheet Type Z cm³/m I cm4/m Allowable Stress N/mm² Allowable Moment kNm/m
PU22(-1) 2060.00 46380.00 180.00 371.00
Designer : EG
EG Consulting Reference: 23-056
Contractor: Ward Piling Date: 30/10/2023
Engineers
Rev: 01
Depth
m
0.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
2.0
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
3.0
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
4.0
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
5.0
5.1
5.2
5.3
5.4
5.5
5.6
5.7
5.8
5.9
6.0
6.1
6.2
6.3
6.4
6.5
Frame Information
Designer : EG
EG Consulting Reference: 23-056
Contractor: Ward Piling Date: 30/10/2023
Engineers
Rev: 01
Max Pressure 29.5kN/m² Depth =3.5m Max Bending Moment -82.9kNm Depth =4.6m
30 20 10 0 -10 -20 -30 -40 -50 -60 -70 -80 -90 -100 -110 -120 -130 0 -10 -20 -30 -40 -50 -60 -70 -80 -90
0.0m 0.0m
1.0m 1.0m
2.0m 2.0m
3.0m 3.0m
4.0m 4.0m
5.0m 5.0m
6.0m 6.0m
7.0m 7.0m
Net Pressures kN/m² Bending Moments kNm.
Max Shear Force 128.3kN Depth =6.0m Max Deflection -8.9mm Depth =0.0m
130 120 110 100 90 80 70 60 50 40 30 20 10 0 -10 -20 -30 -40 -50 5 0 -5 -10
0.0m 0.0m
1.0m 1.0m
2.0m 2.0m
3.0m 3.0m
4.0m 4.0m
5.0m 5.0m
6.0m 6.0m
7.0m 7.0m
Shear Forces kN Deflections mm
Designer : EG
EG Consulting Reference: 23-056
Contractor: Ward Piling Date: 30/10/2023
Engineers
Rev: 01
Max Pressure 29.5kN/m² Depth =3.5m
30 20 10 0 -10 -20 -30 -40 -50 -60 -70 -80 -90 -100 -110 -120 -130
0.0m
1.0m
2.0m
3.0m
4.0m
5.0m
6.0m
7.0m
Net Pressures kN/m²
Designer : EG
EG Consulting Reference: 23-056
Contractor: Ward Piling Date: 30/10/2023
Engineers
Rev: 01
Max Bending Moment -82.9kNm Depth =4.6m
1.0m
2.0m
3.0m
4.0m
5.0m
6.0m
7.0m
Bending Moments kNm.
Designer : EG
EG Consulting Reference: 23-056
Contractor: Ward Piling Date: 30/10/2023
Engineers
Rev: 01
Max Shear Force 128.3kN Depth =6.0m
1.0m
2.0m
3.0m
4.0m
5.0m
6.0m
7.0m
Shear Forces kN
Designer : EG
EG Consulting Reference: 23-056
Contractor: Ward Piling Date: 30/10/2023
Engineers
Rev: 01
Max Deflection -8.9mm Depth =0.0m
5 0 -5 -10
0.0m
1.0m
2.0m
3.0m
4.0m
5.0m
6.0m
7.0m
Deflections mm
Designer : EG
EG Consulting Reference: 23-056
Contractor: Ward Piling Date: 30/10/2023
Engineers
Rev: 01
Max Pressure 29.5kN/m² Depth =3.5m
30 20 10 0 -10 -20 -30 -40 -50 -60 -70 -80 -90 -100 -110 -120 -130
0.0m
1.0m
2.0m
3.0m
4.0m
5.0m
6.0m
7.0m
Net Pressures kN/m²
Max Bending Moment -82.9kNm Depth =4.6m
1.0m
2.0m
3.0m
4.0m
5.0m
6.0m
7.0m
Bending Moments kNm.
Designer : EG
EG Consulting Reference: 23-056
Contractor: Ward Piling Date: 30/10/2023
Engineers
Rev: 01
Scheme Specific Notes
Note: Should be read 3.1m
1. This design is based on a “Pre-Driven” method of installation. The PU22 sheets are to be driven to full depth prior
to excavating to include a “toe-in” of 1.3m as shown in design. The sheet piles specified have been selected as a
suitable size and type to suit structural requirements. Further assessment of the soil strata may be required in
order to ascertain the drivability. It may be necessary to use a combination of hammer types and heavier piles to
achieve the full embedment depth as specified in this design. Please note that piling operations using impact or
vibratory hammers can generate large amounts of both noise and ground induced vibrations. It is essential that a
detailed risk assessment is carried out by the contractor in order to assess the effects of piling operations on site
personnel, the general public and adjacent structures / services (see also the residual risk assessment sheet).
2. The temporary works installation has been modelled providing adequate stability at each intermediate installation
stage. No beneficial soil phenomena have been considered to achieve stability during the installation process such
as removal of passive softening of the clay or any form of adhesion/interface friction coefficient.
4. This design includes allowance for the following surcharges. (Note: If the surcharge is not listed below it has not
been considered in this design and should therefore not be within the zone of influence):
a) A uniform surcharge of 10kN/m² at ground level to allow for general site traffic and excavators up to 30Tn
weight working near the excavation.
5. In the interests of design economy, overdig has not been allowed for in the design calculations. The contractor
must therefore ensure that the excavation process is controlled accordingly
6. As soon as the formation level is exposed, it is recommended that blinding concrete should be placed immediately
to prevent degradation of the base. It is recommended that measures are taken to prevent possible uplift due
to groundwater pressure.
7. The contractor should use a suitable “Bond break” medium such as visqueen, between the concrete and sheeting
to aid extraction of equipment.
10. Any significant residual risks remaining after the design process will be documented both on
the relevant page of this design and also on the scheme drawings. It is the contractor’s
responsibility to take steps to reduce these risks to an acceptable level.
11. A fee will be charged for any subsequent revisions to this full design that will require extensive
re-design work.
Scheme Specific Notes
Note: Should be read 3.1m
1. This design is based on a “Pre-Driven” method of installation. The PU22 sheets are to be driven to full depth prior
to excavating to include a “toe-in” of 1.3m as shown in design. The sheet piles specified have been selected as a
suitable size and type to suit structural requirements. Further assessment of the soil strata may be required in
order to ascertain the drivability. It may be necessary to use a combination of hammer types and heavier piles to
achieve the full embedment depth as specified in this design. Please note that piling operations using impact or
vibratory hammers can generate large amounts of both noise and ground induced vibrations. It is essential that a
detailed risk assessment is carried out by the contractor in order to assess the effects of piling operations on site
personnel, the general public and adjacent structures / services (see also the residual risk assessment sheet).
2. The analysis is based on digging to the level required to install the 450x300 RC waler system. Min 7 days must be
allowed prior to further excavation and 21 days prior to fully loading the waler by completing the excavation. The
excavation must not proceed beyond this level until the waler has reached 35N on a cube test result.
3. The temporary works installation has been modelled providing adequate stability at each intermediate installation
stage. No beneficial soil phenomena have been considered to achieve stability during the installation process such
as removal of passive softening of the clay or any form of adhesion/interface friction coefficient.
4. This design includes allowance for the following surcharges. (Note: If the surcharge is not listed below it has not
been considered in this design and should therefore not be within the zone of influence):
a) A uniform surcharge of 10kN/m² at ground level to allow for general site traffic and excavators up to 30Tn
weight working near the excavation.
5. In the interests of design economy, overdig has not been allowed for in the design calculations. The contractor
must therefore ensure that the excavation process is controlled accordingly
6. As soon as the formation level is exposed, it is recommended that blinding concrete should be placed immediately
to prevent degradation of the base. It is recommended that measures are taken to prevent possible uplift due
to groundwater pressure.
7. The contractor should use a suitable “Bond break” medium such as visqueen, between the concrete and sheeting
to aid extraction of equipment.
10. Any significant residual risks remaining after the design process will be documented both on
the relevant page of this design and also on the scheme drawings. It is the contractor’s
responsibility to take steps to reduce these risks to an acceptable level.
11. A fee will be charged for any subsequent revisions to this full design that will require extensive
re-design work.
Residual Risk Schedule
The followings items have been identified as potential residual risks remaining after the design process risk
assessment. Based on the information that we have available, we have allocated each risk a rating number
depending on its potential to cause a problem. Those with a rating of 2, 3 and 4 are highlighted on the scheme
drawing. A further site specific risk assessment must be carried out on these items to assess their importance
and potential consequence and to determine a course of action or monitoring in order to mitigate the risk to
an acceptable level.
Residual Risk Item Risk Rating Key to Risk Rating
Consequences of overdig 2 1 Unlikely to be a problem
Surcharge 2 2 Possible problem
Lack of toe-in 3 3 Probable problem
Groundwater ingress/flooding 2 4 Almost certain to be a problem
Loss of fines 2
Unable to fully pre-drive the sheets 3
Vibration 2
Hard nature of the ground 3
Weight of equipment 2
Hydraulic pre-stressing 3
1. Overdig: In the interests of design economy, overdig has not been allowed for in the design calculations. Specific control
measures should be put in place to ensure that the dig is not allowed to progress beyond the indicated formation level unless
the designer is consulted. Alternatively the design can be redesigned to allow for an overdig allowance.
2. Surcharge: A uniform surcharge of 10kN/m² at ground level to allow for general site traffic and excavators up to 30Tn
weight working near the excavation. It is recommended any heavy plant is set back at least 1.0m from the excavation to
avoid excessive localised surcharges. If the plant exceeds the weight limit of 30Tn, or the total surcharge loading exceeds
the values stated on the design, the scheme needs to be reassessed. All spoil and excavated material should be moved to
outside the zone of influence to avoid additional surcharging of the excavation.
3. Lack of toe-in: Sheet toe in is critical to this design. A monitoring system should be put in place to verify that this has been
achieved. If for any reason the toe-in specified has not been achieved on a significant number of sheets or piles, the
designer must be consulted before the excavation is declared safe to enter.
4. Groundwater ingress and/or flooding: Significant groundwater ingress or flooding is possible in this excavation. The
contractor should include a means of dealing with this within his safety method statement.
5. Loss of fines: Contractor is to monitor the excavation for loss of fines due to the presence of granular material in the earth
strata and a high water table.
6. Unable to fully pre-drive sheets: The design and installation sequence has been prepared on the basis of the sheets being
pre-driven to depth prior to excavating. If this proves difficult to achieve in practice, the installation sequence will need
to be reassessed so as to maintain stability of the excavation at all times.
7. Vibration: This scheme requires that the sheets or piles are pre-driven using vibratory / impact hammers which will impart
vibrations into the ground. The effect of these vibrations needs to be assessed in relation to potential damage and/or
settlement of adjacent structures. PPV data is available for various hammer types to assist in making this assessment.
8. Hard nature of the ground: Contractor to monitor sheet installation due to the hard nature of the ground. Pre Auger
maybe require to help with installation.
9. Weight of equipment: Contractor to ensure that suitable lifting equipment is on site
Ward Piling Cahir WwTW - Cofferdam
Location:
Cahir, Co Tipperary
Prepared By: G. Ward
1
Ward Piling Cahir WwTW - Cofferdam
I have been briefed and understood this method statement and the works
involved:
SIGNATURE
NAME DATE (Sign only if the above SUPERVISOR
(PRINT) ISSUED has been fully covered
and understood)
Thomas Gallogly
Ruairi McKillop
This form and any duplicates to be returned to the safety coordinator for
Ward Piling Ltd and the Principal Contractor.
2
Ward Piling Cahir WwTW - Cofferdam
Index
1. Operations
2. Safety
3. Risk Assessment
4. Resources
5. Attachments
3
Ward Piling Cahir WwTW - Cofferdam
4
Ward Piling Cahir WwTW - Cofferdam
1.0 OPERATIONS
N.B. All Operations under Murphys.
Installation of 76Nr X 7 - 8m long PU22 ( osa ) Larssen type sheet piles to form a
14m dia cofferdam within a live and operational existing waste water treatment
works
All works will be in accordance with EG Consulting Engineers draft design
drawings
Setting out by Murphys Engineer.
A steel pin shall be hammered into the ground to mark the position of each pile.
Plastic mushroom caps will be placed on top for protection
All plant and materials are to be delivered into the site (and later removed) by
road transport, following the prescribed route in keeping with site access and
highway traffic constraints and under traffic marshal / vehicle banksman
instruction.
5
Ward Piling Cahir WwTW - Cofferdam
Access and egress to and from the site will be strictly in accordance with site
policies issued by Murphys. Deliveries by road will be as directed in accordance
with site requirements.
T.M. will be the responsibility of murphys
All delivery vehicles entering, travelling in and exiting the site will have flashing
amber beacons.
Plant and transport travelling through the works will have a vehicle banksman
in attendance at all times.
Plant travelling into the site will have booms or masts folded away from existing
structures, site traffic / personnel and highways at all times.
All plant and stores will be located such that no accidental spillage of hydraulic
or lubricating oils or fuel can contaminate the site. In the event of accidental
spills, a spill kit (absorbent pads and granules) will be kept at point of work.
SDS to be present & driptrays or bunds created to contain a spill
Work will be carried out within the exclusion zone as per attached layout
drawing _ Appendix A
Handling, pitching, driving and extracting (where required) of steel sheet piles
will be carried out using the Movax SG 75V vibratory hammer. The pile is picked
up by the Movax excavator and handled to the vertical position. The pile is
aligned and guided into position by the guidance of the banksman.
The pile pushed into the ground (or clutched in for subsequent piles) in its
correct attitude and alignment and driven a short way down.
The verticality is manually checked by the piling operative with a level and the
driving completed to level or refusal.
6
Ward Piling Cahir WwTW - Cofferdam
Piles will be driven by the vibratory hammer until specified toe level or pile
refusal is reached. Levels will be monitored for record purposes.
I pile toe depths aren’t achieved after all piles are installed with the Movax
SG75V vibro hammer, the DH25 impact hammer will be fitted to the 35T
excavator and the piled impacted to the required depth.
Appendix C
All personell involved in the piling works shall be required to wear ear
protection at 85dB
7
Ward Piling Cahir WwTW - Cofferdam
Emergency procedures will be as per the Murphys’s Health and Safety Plan.
8
Ward Piling Cahir WwTW - Cofferdam
2.0 SAFETY
(a) All plant and equipment shall have current documentation and
certificates.
(b) All personnel will carry all necessary competence cards as required
for the work they are to undertake. SOLOS/CSR / CSCS / CPCS
All personnel will be Safe Pass or CSR qualified to enable them to work in
Republic of Ireland.
All personnel will complete the on-line site induction prior to starting
work.
All personnel will carry and wear all appropriate PPE as required by the
site and appropriate to the work being carried out.
(c) All work will be carried out with due regard to the Company Safety Policy
9
Ward Piling Cahir WwTW - Cofferdam
Likelihood
Likelihood
Severity
Severity
Risk
Risk
Plant access / Interface with Traffic accident Public / Site 3 3 9 When mobilising the TLR and Movax to site and 2 1 3 Murphys/ Piling
egress the public operatives when tracking TLR and Movax to the works area, Supervisor
ensure any Traffic Management required is set
up correctly in accordance with the site rules. An
appropriate number of banksmen are to be in
attendance.
Working at Falls Injury / fatality Site operatives 5 2 10 Suitable edge protection system to be installed 2 1 2 Piling Supervisor
height on all delivery wagon trailers. When working at
height on the TLR or Movax where edge
protection cannot be provided a harness and
lanyard is to be used.
Driving sheet Service strikes Electrocution, Site operatives 3 3 9 Area to be CAT scanned by competent and 2 1 2 Murphys/ Piling
piles flood, fire or trained personnel and all services to be Supervisor
explosion identified and marked with road marking paint
prior to any piling works and as piling works
progress. Assume all cables are live until proven
otherwise.
10
Ward Piling Cahir WwTW - Cofferdam
11
Ward Piling Cahir WwTW - Cofferdam
12
Ward Piling Cahir WwTW - Cofferdam
Mobile plant Interface with Collisions, crush Site operatives 4 2 8 The work area for the TLR and Movax will be 2 1 2 Murphys/ Piling
other plant injuries and segregated from other operations and Supervisor
and possible fatalities pedestrian walkways using Herras fencing /
pedestrians crowd barriers or the like. Personnel to keep
clear of TLR and Movax when moving. All plant
movements to be controlled by competent
banksman.
Manual Lifting over Musculoskeletal Site operatives 4 2 8 Operatives not to attempt loads over 25kg. 1 1 1 Piling Supervisor
Handling capability injuries Operatives to assess load before attempting, do
not lift anything that is beyond your capability.
Welding & Hot works Burns, fire, arc eye Site operatives 4 2 8 Hot Works Permit must be issued before works 2 1 2 Murphys/ Piling
burning commence. Supervisor
13
Ward Piling Cahir WwTW - Cofferdam
General Use of mobile Lack of site Site operatives 4 3 12 Mobile phones are not to be used on site whilst 1 1 1 Piling Supervisor
phones awareness on site except in designated areas.
Leptospirosis Illness or death Site operatives 4 3 12 Adopt good personal hygiene. Wash hands 2 1 2 Piling Supervisor
before eating. No smoking, eating or drinking on / Piling
site. Operatives
Edge Slips & falls Site operatives 4 3 12 Edge protection and ladder access erected by 2 1 2 Murphys
protection and Murphys.
access to
cofferdam
Generating Nuisance and Local residents 3 3 9 Section 61 requirements to be briefed to all 2 2 4 Murphys/ Piling
noise outside disturbance and businesses operatives and supervisor to ensure they are Supervisor
Section 61 adhered to.
agreement
Excavation/drill Collapse of Injury to site Site operatives 4 2 8 Batter sides of excavation. Errect temp fencing 1 1 1 supervisor
ing for test sides personell around the excavation. Maintain an exclusion
holes Site operatives zone for plant operating
falling into
excavation
14
Ward Piling Cahir WwTW - Cofferdam
Excavation of Collapse of Injury to site Site operatives 4 2 8 Erect edge protection. Keep sheet piles high to 1 1 1 Supervisor/site
the cofferdam sides personell form a wall operatives/plant
Site operatives operators
falling in
Access to Slips & falls Injury to site Site operatives 4 3 12 Use propriety access walkway including 1 1 1 Supervisor/Mur
cofferdam operatives handrails phys
Placing Burns to skin. Personal injury Site operatives 4 2 8 All personel placing/leveling concrete to wear 1 1 1 Supervisor/site
concrete in ring Splashing into appropriate PPE, wellington boots, gloves, hi-viz operatives
beam eyes vests, eye protection.
15
Ward Piling Cahir WwTW - Cofferdam
Likelihood of 1 2 3 4 5
accident Rare Unlike Possib Likely Almos
ly le t
Certai
n
5 5 10 15 20 25
Modera High Extreme Extreme Extreme
Catastrophic
te
4 4 8 12 16 20
Severity of accident
16
Ward Piling Cahir WwTW - Cofferdam
4.0 RESOURCES
PLANT
Hitachi 350LC 360o tracked excavator c/w Movax SG75V piling hammer
( Appendix B )
PILE INSTALLATION
PILE EXTRACTION
GENERAL
Site vehicle c/w flame cutting gear, lifting tackle and small tools
Site welfare unit (shared)
Site vehicles c/w burning gear, lifting tackle and small tools
LABOUR
17
Ward Piling Cahir WwTW - Cofferdam
MURPHYS
Foreman:
First Aider –
Murphys First Aider shall be identified on site.
18
Ward Piling Cahir WwTW - Cofferdam
Appendix A
19
Ward Piling Cahir WwTW - Cofferdam
Appendix B
20
Ward Piling Cahir WwTW - Cofferdam
Appendix C
21
METHOD STATEMENT
25
METHOD STATEMENT
26