Professional Documents
Culture Documents
Discipline Civil
TABLE OF CONTENTS
1.0 SCOPE
Page 3
2.0 REFERENCE
Page 3
5.0 RESPONSIBILITIES
Page 4, 5 & 6
Page 2 of 9
The scope of work covered under this contract shall comprise of supplying qualified manpower, field and
laboratory equipment, instruments and facilities to conduct and report on the physical and geotechnical
characteristics of the soil and ground water conditions in the plant area. The investigation scheme shall
also consist of laboratory analysis of samples of soil and rock collected from designated locations in this
site as per specification detailed in the document.
The Project is located in the area controlled by the Saudi Industrial Property Authority (MODON) in the
Sudair Industrial City, south of the city of Majmaah in the Riyadh Province. The Site’s altitude is
approximately 700-750 meters above sea level. The location of the site is indicated in the map below:
2.0 REFERENCES
Page 3 of 9
Risk Assessment shall be prepared including mitigation measures, and responsibility for
implementation. This shall be coordinated with site Safety In-charge and attach to this method
statement.
Before commencing any work, all permits shall be checked and ensured that they are valid until
completion of activity.
All works shall be referred to the Drawings and specifications.
All staff and workmen shall wear Personnel Protective Equipment (PPE).
All personnel shall be cautioned while working near live lines and other services.
It shall be ensured that all men working in high-level are wearing necessary safety harness
complying with the safety requirements and following precautionary measures on safety
aspects.
All equipment shall be calibrated and accompanied by the competent operators prior to
commencement of any works.
In case of any emergency please contact the following:
5.0 RESPONSIBILITIES
Below mentioned personnel with the responsibilities entrusted to them shall be responsible for carrying
out below mentioned works. In addition to their roles and responsibilities disseminated in the Project
Quality & EHS Plans and the following specific activity functions shall be carried out:
Reporting to the Project Manager and assisted by construction team as indicated in the project
organization chart.
Ensure that method statement is prepared, established & control measures taken before starting the
work and guiding the team for implementation.
Follow-up & coordinate with design engineering team for preparation of Coordinates drawing Layout.
Conduct training and awareness program for all personnel deployed for the activity.
Page 4 of 9
5.4 Surveyor
Study drawing and establish control points as per plot plan / approved drawing.
Acquire information from reference station/s & datum level provided by client; establish new control
points at site & cross verify with reference station/s and datum level.
Conduct survey, prepare survey report, and maintain records.
Provide route markings and obtain approvals.
Ensure calibration of survey equipment and its maintenance
5.5 QA/QC Engineer
Quality In-charge shall review the method statements and ensure all requirements are included.
Schedule inspection of works in coordination with Site Engineer.
Prepare and maintain inspection logs, records, and obtain approval from client.
Inspecting the calibration certificates of measuring tools.
Maintain third party testing reports.
Review Quality Control records and ensure correctness.
Disseminate HSE requirements specific to the activities involved and facilitate implementation.
Prepare and coordinate the implementation of Risk Assessment plan.
Ensure that work is carried out in safe manner in coordination with Site Engineer, sub-contractors,
etc.
All concerned parties shall be exposed to the method statements applicable to their working scope
and must attend a safety briefing prior to carrying out any works on site.
All personnel shall ensure safe working conditions prior to the start of work.
Great emphasis shall be made on all matters of health, safety, and environmental both in the
workplace, and to the public during the execution of works.
Page 5 of 9
The following are the tools and tackles and Equipment identified for the scope of the work and shall
be deployed as per the requirements:
Crow Bar
Page 6 of 9
a) Prepare all required permits and keep such documents at site always for the
verification by any authorized personnel at any time.
b) Prior to start any excavation works the surveyor shall be establishing, mark and
monument all required levels and co-ordinates for easy access and reference and
furnish a contour drawing showing contour levels at five-meter (5 Meter) intervals.
c) Prepare warning sign boards showing the classification of excavation such as
“shallow’’ or ‘’deep excavation’’ and ‘’Men at work’’ etc.
d) Prepare warning tapes and safety barricades as wide as required in the excavation
areas.
e) Check and assure the accessibility of equipment to be entered at site without causing
any damaged to any of the permanent or temporary properties present at site.
f) Cleaning, grubbing all the desert bushes and its roots shall be removed from the site
and disposed at designated area.
g) The excavated soil shall be safely removed and dumped at temporary dumping area
for final disposal or using for backfilling (After 3rd party testing approved)
h) The excavated bed shall be properly levelled and graded before compaction.
i) Finally, the excavated bed shall be compacted to achieve relative density required as
per project specification.
j) The sub-grade shall be compacted to required density 85% of consolidation and
tested through approved third-party testing agency, witnessed by the owner and
certified by third party inspection team.
k) The excavated sub-grade shall be compacted to required density of consolidation as
per project specification and tested through approved third-party testing agency.
Witnessed by the owner and certified by third party inspection team.
7.2 Backfilling:
a) Prior to start any backfilling works, it is necessary to prepare all fill materials approved and
mark readily available at site.
b) Fill and backfill materials shall be from on-site excavation, designated borrow areas or off
site sources conforming to the following criteria or as recommended by a geotechnical
report.
c) Submittal for fill material shall be prepared in advance and submit to the owner along with
all required all laboratory analysis reports.
Page 7 of 9
A systematic and methodical compaction and testing shall be maintained during backfilling.
Following sequence of works shall be carried out under this section of earthwork.
a) Prior to compaction works the soil material to be compacted shall be tested for finding
out each optimum moisture content, relative density, CBR value etc. and sieve analysis
to qualify the soil as filling material and find us basic technical data or conducting the
compaction test of fills and backfill.
b) The backfill material shall be compacted to require density of 95% consolidation as per
project specification and tested through approved third party testing agency, witnessed
by the owner and certified by the third party inspection team.
c) Samples shall be taken from the site borrow pit, the sample shall be identified with
proper tagging before sending to approved laboratory for conducting required tests.
d) Fill materials shall be arranged as satisfactory material free of any contaminated
material or vegetation in order to comply with project specification of fill material.
Page 8 of 9
To ensure security directives during the execution of earth works, all activities shall be
monitored in compliance with relevant standards, codes and procedures described in the
company manual and project specification as minimum as follows:
Page 9 of 9