NAMA PROYEK He
PEMBERI TUGAS : PT MRT JAKARTA Jl.
Te
WAKTU PELAKSANAAN : 20 Bulan Fa
ww
PEMBERI TUGAS
Garis Koordinasi
Garis Perintah Project Manager/ Team Leader
Risk & HSE Manager Site Engineering Manager Site Opersional Manager Site Administrasi Manager Quality Control & Assurance
Ir. Tuch Fatul Anam, MT Ir. Volmer Siregar Ir. Eduard Sudarsono Siregar Luh Putu Dyah Chandrawati, ST Bachrum Achmadi, ST
Security
Junimber Tambunan
Ripsky Rayshanda
Febru Andriawan
Fachrudin R
Sub Kontraktor/Mandor/Pekerja
Salomo Sihombing
Direktur
MAIN EQUIPMENT SCHEDULE
2024 2025
No. Equipment Unit Quantity Capacity MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG
M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18
20 Theodolite unit(s) 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Page 2 of 4
JADWAL PERALATAN UTAMA
2024
No. Equipment Unit Quantity Capacity FEB MAR APR MAY JUN JUL AUG
M1 M2 M3 M4 M5 M6 M7
1
2
3 Excavator PC75 unit(s) 1 0,3m3 1 1
19 Theodolite unit(s) 1 1 1 1 1 1 1
Page 3 of 4
MAIN EQUIPMENT SCHEDULE
2022 2023
No. Equipment Unit Quantity Capacity JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUNE JUL AUG SEP OCT NOV
M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17
Rebar Ø 42 mm, 5
16 Bar Cutter unit(s) 3 1 3 3 3 3 3 3 3 3 3 3 3 2
HP
17 Needle Vibrator (various size) unit(s) 6 200 Hz 2 6 6 6 6 6 6 6 6 6 6 6 4
18 Submersible Pump (4") unit(s) 6 15 HP, 4" 4 6 6 6 6 6 6 6 6 4 4 4 4 4 4
19 Drilling Machine unit(s) 6 26 mm 3 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
20 Grinding Machine unit(s) 6 720 watt 3 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
21 Cutting Torch unit(s) 3 - 3 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
22 Tamping Rammer unit(s) 3 10 kN, 5 HP 1 3 3 3 3 3 2 2 2 1 1 1 1 1 1
23 Total Station unit(s) 3 1 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
24 Theodolite unit(s) 2 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
25 Auto Level unit(s) 3 1 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
26 Lighting Set Arrangement unit(s) 60 400 watt 20 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 30
27 Scaffolds / Pipe Support ls 1 450 kg 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1