Professional Documents
Culture Documents
Construction of bulkheads or plugs may be The notes do not cover bulkheads and
required in urgent or emergency conditions, barriers for retention and control of fill in
when there is little time for rigorous mined stopes. This is another specialist
investigations and analyses, or for preparation application, which involves different principles
of a site. Construction may be in adverse, or of design and construction.
even hazardous conditions.
Modern principles for the design of barriers to The 1970’s and 80’s brought applications of
control inflows of high-pressure water in hard- finite element analysis to the design of
rock mines arose in the South African gold bulkheads and plugs. In mines, there were
mines during the late 1950’s. Inundation of investigations and analyses of the design of
the West Driefontein Mine was the most fill and leaching stope bulkheads. For civil
famous example. Similar experience evolved works, there were published examples of
in US lead-zinc mines, especially in fissured analyses of plugs for dam diversion tunnels
limestone environments. Published and nuclear waste repositories.
applications of barriers to control water in coal
mines date from the 1930’s. Empirical design In contrast, many applications, in both civil
principles evolved in each case, and they and mining environments, have apparently
have largely endured through to current times. been consciously over-designed, since this
has simply involved greater quantities of
In parallel, civil engineers developed empirical concrete and grout.
design guides for plugs in dam diversion
tunnels and hydro-energy intake shafts, Relatively few papers on the design and
based on simple mechanistic principles, construction of bulkheads and plugs have
similar to those underlying designs for mining been published. Many of these date from the
applications. 1950’s and 60’s for mining applications.
Concrete plugs are designed to jointly satisfy Several variables may be incorporated in the
two criteria: design of a concrete plug:
seal a tunnel or shaft, against
leakage through the interface and Length, which is the primary design
surrounding wallrock, variable, given that a plug is
maintain its strength, against shear constructed of concrete, filling the
failure, at the interface (or through shaft or drive. Longer plugs are less
adjacent wallrock). permeable and stronger.
from which a design length may be strength and deformation of a plug, but
estimated; it may involve uncertain estimates of
numerical modelling (in principle). properties of materials and the
influence of reinforcement.
For stability: Modelling may incorporate the flow of
empirical limiting shear stress on the fluids, but flow properties are likely to
interface, from which a design length be so uncertain that the extra time and
may be estimated; cost may not be justified.
analytical limiting shear strength of
design length for a plug can be estimated. surrounding wallrock, through the
selected limiting pressure gradient.
An assessment of the ground conditions at a
site is crucial. The permeability of the
surrounding rock is not explicitly embodied in
the limiting pressure gradient criterion, but is
implicitly through the selected limiting gradient.
The selection of a limiting gradient is based on
precedents, and a general assessment of the
surrounding rock, which each require
professional judgement.
As a plug’s length increases, the interface The limiting shear stress criterion for
shear stress decreases, for a particular strength accounts for:
hydraulic force. Below a limiting shear stress pressure, imposed by gas or water,
for the conditions, a plug is accepted as length and width (or height) of the
having sufficient strength. plug,
shear strength of the interface,
Even at the time there was acceptance that through the selected “allowable” or
the mechanism of a limiting shear stress was limiting shear strength.
a simplification of a complex system. They
recognised that there was likely to be a
gradient of shear stress along an interface.
Nonetheless, the criterion was accepted as a
useful design guide.
The empirical design methods for leakage Analyses can, if required, incorporate:
and strength do not adequately account for generation of heat of hydration in
integrated deformation of the plug and Thus, even though numerical models
wallrock, simulating arching, strains incorporate realistic mechanistic components,
and failure; they are limited by the complex indeterminate
reinforcement in the wallrock and the nature of the interface and its immediate
plug, although only implicitly. surrounds.
Preparation of site
The shear strength and permeability of the
interface between a plug and its wallrock are
critical factors. The site of construction must,
therefore, be thoroughly cleaned of loose and
oily material, including the floor, and loose
rock scaled from walls.
Construction
Plugs are usually constructed of plain
(unreinforced) concrete. Appropriate
standards (eg, AS) may be adopted for the
concrete and its placement. The upstream
end of a plug would usually become
inaccessible, so that formwork may be
wooden or, conveniently in mines, concrete
masonry walls. Cold joints within a plug must
be avoided.
Placement of concrete to form a plug may be Typically, at least one extra cycle of grouting
impractical when, for example: is required for grouted aggregate plugs:
there is no facility to mix or deliver
initially, the aggregate, at low
concrete, pressure;
concrete cannot be physically placed
subsequently, the interface and
at a site,
conditions at the site are hazardous.
remaining voids in the aggregate, at
These circumstances may particularly arise in high pressure;
an emergency, such as a flood or a collapse. finally, the interface and surrounding