You are on page 1of 11

Chemical Engineering Science, 1970, Vol. 25, pp. 61 l-62 1. Pergamon Press. Printed in Great Britain.

Optimization of multi-stage flash evaporation plants


M. A. MANDIL
Chemical Engineering Department, University of Alexandria. Alexandria, U.A.R.

and

E. E. ABDEL GHAFOUR
Atomic Energy Establishment, Cairo, U.A.R.

(First received 2 May 1969; in revisedform 16 October 1969)

Abstract-A new approach to the optimization of multi-stage flash evaporation plants is presented.
While retaining the basic features of current theories, the approach presented involves the use of
relative values of economic parameters rather than their absolute values. The paper deals with a
3-free-design variable problem of constant output while two cost parameters may vary according to
prescribed schedules. Optimization procedures are presented and tested using an illustrative example.

CURRENT theories [4,6,7] concerning optimiza- 1.1 Thermal energy cost term
tion of multi-stage flash evaporation plants are This is given by EpoQ, where Q is taken as the
aimed at clarifying the interrelations between the thermal energy supplied in the brine heater.
major variables involved. The main objective of
the present work, however, is to develop optimi- 1.2 Surface area cost term
zation procedures through a new approach which Among cost items which are proportional to
retains as much as possible the basic features the heating surface area (A) are; installed cost of
of the current theories. Principal optimization heating surface plus its maintenance cost. These
variables considered are; number of stages N. will be allocated to a cost term, C,J. There are
terminal temperature difference TTD, perform- other constructional materials such as walls,
ance ratio R and concentration ratio CR. The foundations and auxiliaries of flashing chambers.
paper deals with a 3-free-design variable prob- In a plant comprising N stages, the cost of such
lem of constant output while two cost parameters items can be incorporated in a cost term;
may vary according to prescribed schedules. FIVpo+J,O (N/F)1’2] [4].
Silver[4] introduced the idea that the unit cost
of fresh water is governed by certain economic 1.3 Sea water make-up cost term
parameters, namely, volume parameter Vpo, Cost of items which are proportional to the sea
Staging parameter Jpo, Surface parameter SD0and water make-up, F,, such as pumping, deaeration
Energy parameter Epo. The present work, though and scale prevention chemicals will be allocated
retaining this basic concept in its early stages of to a cost term, C,F,.
development, it will finally involve the use of the
relative values of such economic parameters 1.4 Remainder cost term
rather than their absolute values. All of the remaining cost items of sea water
conversion are incorporated into a remainder
1. MANUFACTURING COST TERMS cost term, C,F.
All of the items contributing to the manufactur-
ing cost of fresh water are distributed over a set 2. UNIT COST EQUATION
of cost terms, so chosen to cope with optimiza- From the above discussion, the total plant
tion purposes. production cost, C. in cents per day is given by:
611
M. A. MANDIL and E. E. ABDZL GHAFOUR

function of the flashing temperature range FTR


and concentration ratio CR. Also, (C,), and
+C,F, +C,F. (1)
(BP@, are functions of maximum brine tempera-
ture T,,, and brine concentration at outlet of
Hence, the unit cost, C* in cents per pound of brine heater CB,,. It follows then that E is a
fresh water is given by: function of FTR, CR, T,,, and C,,. However
CR is in turn a function of FTR and CsH, and
F TR is equal to (T,,, - TBD) . Therefore it could
be concluded that E is a function of T,,, TBDand
CR. The first two variables upon which E de-
(2) pends take care of the first source of irreversi-
bility, the last namely CR clearly accounts for the
second.
3. INTRODUCING THE CONCEPT OF It is worth mentioning that the minimum-
MINIMUM-POSSIBLE ENERGY
possible energy requirement is different from the
Several attempts[ 1,3,5] have been made, in
thermodynamic minimum energy requirement.
order to calculate the theoretical amount of
While the latter corresponds to isothermal
energy required for the recovery of fresh water
reversible process conducted in differential
from saline water using an isothermal reversible
stages,. E refers to limiting operating conditions
separation process conducted in differential
for a hypothetical plant comprising an infinite
stages. However, when an actual process is
number of stages and infinite heating surface.
analysed quantitatively, it will be readily ap-
Consequently, E is the amount of energy which
parent that it includes two major sources of
must be supplied before getting any product.
irreversibility. The first source being that the
For a finite size plant, to start getting a product,
separation process is by no means isothermal.
an additional amount of energy should be sup-
The second is that the water produced is in
plied. The amount of energy to be used over and
equilibrium with only the final brine concentra-
above E in order to produce one pound of product
tion in each stage instead of the whole range of
(Q/F-E) will, hereafter, be called unit produc-
concentrations from the feed to the discharged
tive energy (UPE) .
brine. These sources of irreversibility were ac-
counted for in the present work by introducing
4. RELATIONSHIPS BETWEEN
the concept of minimum-possible energy require- OPTIMIZATION VARIABLES
ment.
Relationships between principal optimization
A limiting case will now be considered, in
variables will now be given in a form which will
which the desalination plant contains an infinite
facilitate their incorporation in the optimization
number of stages and infinite heating surface
study.
area. In this case, the brine heater temperature
With reference to Fig. 1, and recalling the
rise ATBH will be equal to the elevation in boiling
conventional nomenclature used in connection
point at conditions prevailing at inlet to first
with desalination plants, it is apparent that the
stage, (BPE)o. Therefore, the energy required
mean temperature difference (MTD) , heating
per lb of fresh water in this limiting case, here-
surface required per unit product (A/F), and
after, referred to as minimum-possible energy
thermal energy needed per unit product (Q/F)
requirement and denoted by E is given by:
are given by the following expressions:

E= & (GJ),,(~PE)o.

The recirculation ratio r, by definition, is a 4l - to


612
Optimization of multi-stage flash evaporation plants

and
9_ r
- 1000 (C,)mA TBH.
0F

Taking 1 +At,/TTD as an individual term to be


Tubasi& Tube side
called the thermal driving force function 8, the brine in brineout
- -
above expressions could now be rewritten as
/’ b
follows: / ((E
/ 8
A& / 5
(MTD) = ~3 (4) ,/TTD

A
F =a,.Nln@ (5)
0
where “tloou,
-r

L ‘.
’ &t
ao =NUL\t, -.
.

‘.
(9 =$[a.+:+N(;- 4 (6)

where
1000 (4, A&r (BWo Fig. 1. Temperature changes in stage 1 ATBH= T,--t, =
a1 = L, (c~)~~ At,’ u2 = NAr, ’ Dt,,+ BPE+ TTD.

a,=$(l+ABPE), explicitly in the unit cost equation when given


c in the following form:
and A(BPE) = change in elevation of boiling
point with respect to change in brine temperature C* = Epo(~)+C,(~)+Vpo+J,o(~~‘z
in the evaporator.
From the above definitions of a,, a,, a3 and 8, CR
it follows that: +C8 CR_1
( >
+cr. (11)

(TTD) =s From Eqs. U), (10) and (1 l), it is readily seen


that the unit cost equation could take the form:

EC_
a2
a1 C* = Epoe+Epoa-+(q+&)+S;N
N

(UPE) =
lnf3+ VPo+JPo (N)“2+C.?(&)+cr
F (12)

where SD0= surface parameter = a,C, c/lb.

5. REFORMULATION OF UNIT COST 6. MINIMIZATION OF UNIT COST


EQUATION The volume parameter VP0 is related to the
The performance ratio (R = F/Q) and con- volume of flashing chamber required per unit
centration ratio (CR = F,/ (F, - F) ) will appear product. For a fixed flash chamber height, which
613
M. A. MANDIL and E. E. ABDEL GHAFOUR

is the general practice so far, a certain evaporat- cost ratio, respectively. Recalling that JPo, S,O,
ing area is needed per unit of product. This will F, EPo and a1 have the respective dimensions
lead to the conclusion that VP0is constant. Also, c/d(lb hr), c/lb, Ib/hr, c/B.t.u. and Ib/B.t.u., it
the unit remainder cost C, is constant by defini- could be easily shown that X, and X, are dimen-
tion since it is not proportional to any of the sionless groups.
variables involved. The cost terms E,“( l/alN) X In order that X, might be given in more plau-
( a3 + l/0 - 1) , &ON In 19and JPo (N/F) ‘I2are func- sible representatton, a, and SPo (Sections 4 and 5)
tions of the design variables (0 and N). In are substituted for in the definition of X,.
addition, the cost terms Epoe and C,(CR/(CZ?-
1) ) are functions of the operating variable (CR), &=J$= Ep”/l~ _
(Cd,, &c 2
since E is in turn a function of CR. Therefore, the
cost terms included in Eq. (12) can be divided
1 PO Calu (Cp), A&t (> (FTR)


(13)
into three distinct groups:
Since the rate of recycle flowing in the con-
(a) group of constant terms +1 = VP0+ C, denser tubes is the same as the sum of the flash-
(b) group of terms which are a function of CR ing brine and the distillate, the temperature rise
only. of the brine in the tubes is the same as the
temperature decrease due to the flashing. Thus
At, could be assumed equal to AtsP Hence,

(c) groups of terms that are dependent only


X E = ‘$;y (FTR) (14)
upon &Jand N.
where

(EPo/lOOO) = cost of producing one B.t.u. of


where thermal energy.
(CJU) = cost of transmitting one B.t.u.
JPO Epo through heating surface when
XJ = S,O( p7)1/2 and Xl3 = al~po’

(MTD) is 1°F.
Minimum unit cost of fresh water will be
It is clear now that, X, is the ratio between the
realized when:
cost of producing and transmitting one B.t.u. for
(MT@ and (FTR) of 1°F.

6.1 Optimization for constant economic para-


and since J12and I& are independent, then it is meters
sufficient to have, The minimization of Eq. (12) will now be con-
sidered for such a case where the economic para-
meters may be taken constant leaving 8, N and
&=O and
CR, as the only free variables.
6.1.1 Optimum concentration ratio CR,,,.
In the above form of JIQ,it is seen that two new This is obtained by differentiating e2 with respect
groups have been introduced, namely X, and to CR and setting &+WCR = 0.
X,. These groups by virtue of their definitions
are unit cost ratios and will be called staging-
CR,,, = I+ [$(F),]“. (15)
surface unit cost ratio and energy-surface unit
614
Optimization of multi-stage flash evaporation plants

Evaluation of CRoPt could be obtained through


a graphical procedure or by numerical analysis. 5d \
Optimum concentration ratios at different values 450
of E,,9/C, and T,,,, are given in Fig. 2. 400
6.1.2 Optimum thermal driving force function
350
8,,Pt’Differentiating I,!I~with respect to 0 holding I\

N constant then setting the derivative equal to


zero, &,,, is obtained, CL 250
W
200
2 1

I
@W= 1+ (l+4N2,XE)1/2_ 1’ (16) I50

loo

6.1.3 Optimum heating su$ace A,,,. Substitut-


ing in Eq. (5), Aopt for a certain N is given by: L------
I.5 I.6 I.7 I.8 I.9 2.0
tca&#

A Fig. 2. Optimum concentration ratios TBD= 100°F.


(1 +4N2/&2- I I * (“I
that <Q/F) in this limiting case corresponds to
6.1.4 Optimum performance ratio R,,,.
E, it follows that E still retains its value of a,/al
Substituting in Eq. (lo), R, of the plant for a
certain N is given by: (Eq. (8)).
6.1.5 Optimum terminal temperature differ-

Noting that the optimum energy required for


producing one pound of fresh water (Q/F),pt =
Recalling the assumption of At= = Atat (Section
WL.,,
6), (TTD),,, will be given by:

(S),,, = $z2+F+ (?&+&)‘12]. (19) (TTD),,, = y [(i i-F)1’z-11.@la)


Also, the optimum unit productive energy
As seen from Eq. ( 14)
(UP.@,,, for a given N is determined by the
following equation:

In the limiting case where the desalination (TTD),, = [r+)‘+$$& (FTR)"' -%.
plant contains an infinite number of stages and
infinite heating surface, a hypothesis which (2lb)
could only correspond to a case where the unit
cost of energy is prohibitively high, S,O/E,O and 6.1.6 Optimum brine heater temperature rise.
hence X, would be quite close to zero. If this (ATBH)OPtwith reference to Fig. 1, (ATBH),,ptfor
finding is inserted in Eq. (19) and remarking a certain N is given by:
615
M. A. MANDIL and E. E. ABDEL GHAFOUR

calculated, at which the corresponding value of


N would thus be NoPt for the assumed pair of
X, and X,.
GlU
In order to widen the scope of application of
EPo/lOOO
the proposed optimization procedure, a wide
l/2 enough range of values of X, and X, had to be
x (FTR)
I + BPE. (22) considered. In view of the fact that this would
require lengthy and repetitive calculations, a
It is of interest to note that the number of heat
simple computer program was run on IBM 1620
rejection stages (N,) = A T&A tst,hence which furnished the data presented in Fig. 3.
It is obvious from the above discussiori that
X, and X, will directly determine Nopt and eoPt
which in turn will fix other design features such
as Atat, TTD, ATBH, NJ, R, Q and A for constant
. (23)
economic parameters.

6.1.7 Optimum number of stages N,,,. The


thermal driving force function 8 has been opti- 6.2 Optimization for variable economic para-
mized for a fixed number of stages N. Therefore, meters
a choice of optimum number of stages N,,,, is In order that the procedure developed for
still needed. However, before doing so, the constant economic parameters might be extra-
expressions already obtained above, for eopt and polated to cover the cases where these para-
(UPE),,, will be inserted in +3 which will then meters are variable, it is needed to evaluate the
take the following form: economic parameters that prevail at optimum
conditions.
The basic data needed here are; the pattern of
1+(1+4N2,&2_l variation of unit energy cost with energy use
rate (energy cost schedule), and the pattern of
+x,(z$+ ($+&y}]. variation of unit area cost with heating surface
requirement (area cost schedule).
6.2.1 Optimum concentration ratio CR,,,.
In the applicable range in CR (1.7-2-O) [2], a3
Each point on Fig. 2 represents a particular
can be taken as constant at a value of 0.993.
value of E,O/C, with the corresponding value of
Hence, the above expression is left to be a
function of N, X, and X, alone: CR,,,. In the case of variable economic para-
meters, Epo is variable and dependent upon the
energy use rate, which at this stage would not
SoP &N1’2+Nln l+(1+4N2,?xE)1/2_1 have been determined yet. Hence, values of CR,
[ { I are assumed from which the corresponding EF
could be evaluated for the particular product rate
+o.493++~*+($$2)“2].
(F) being considered. From the energy cost
schedule, values of ED0corresponding to different
Differentiation to find the minimum cost values of EF could be determined, then E,O/C,
contribution of $I~ is not permissible here since calculated. These data will make it possible to
N by definition is necessarily an integer, and construct a curve similar to Fig. 2, with full
therefore discontinuous. understanding that this plot is optimum only at
For each pair of values of X., and X,, the mini- one point, which represents CR,,, for the case
mum value of the cost contribution could be under consideration. On the other hand Fig. 2
616
Optimization of multi-stage flash evaporation plants

L
H
0. 2.4 -
S
‘Z
c”
2 2.2 -

8
$
(r 2.0 -
.c
.z
c
; 1.6-

E
P
- I.6 -
E
‘E
._
= I.4 -
0

0 5 1015202530354045505560665107560659095 0

Optimumnumberof stages, NW

Fig. 3. Optimum number of stages and optimum thermal driving force


function using X, and X, as parameters.

gives all possible optimum concentration ratios needed, which gives the pattern of variation of
for different values of E,O/C,. Hence, CR,,, an adjusted energy parameter (Epo)a with
could be obtained by superimposing the newly (PEF). The adjusted energy parameter which
constructed curve on that given in Fig. 2 for the corresponds to the productive energy require-
same T,, adopted. The optimum concentration ment is defined as follows:
ratio being given by the point of intersection of
the two curves. Q(J%~)Q-~F(&")~
6.2.2 Opt&num design features. In this case,
tEpOja =

Q--EF *
(26)
the adaptation of theory developed to variable
economic parameters needs the introduction of In addition, a modified area cost schedule
new design functions, namely, productive energy would represent the pattern of variation of SPo
function (PEF) and surface function (SF) which with (SF).
are given by: Adopting the use of the term JPo(N/F)‘/’ to
represent the amortized cost of constructional
(PEF) = a, ( UPE) = + (0993 + A) (24) material relating to staging per unit product[4],
the staging parameter JPo for a particular plant is
obtained by dividing the amortized cost of con-
(SF) =$g) =Nln8. (25) structional material relating to staging in the
whole plant by (NF)‘/* where N is any arbit-
Figure 4 gives (PEF)O,, and (SF),,, for each rarily chosen value of number of stages.
pair of unit cost ratios X, and X,. In order to evaluate EPo and S,O that prevail at
A modified energy cost schedule would be optimum conditions, a wide range of (SF) values
617
M. A. MANDIL and E. E. ABDEL GHAFOUR

is considered. For each value of (SF) within from Fig. 4, the unit cost ratios X, and X_, can
such a range, corresponding S,O could be ob- be determined.
tained using the modified area cost schedule. From thereon the same procedure given for
For X, = JPo/SPo(F)‘/*, a set of X, values is constant economic parameters could be
obtained. followed.

0.200
I
NOTATION
heating surface area
(BP; elevation in boiling point
A(BPE) change in elevation of boiling point
with respect to change in brine
temperature in the evaporator
C fresh water production cost per unit
time
c* unit cost of fresh water
Cl2 installed cost and maintenance cost of
a unit surface area.
C, unit remainder cost
ohIO ’ ’ ’ ’ ’ ’ ’ ’ ’ ’ ’ ’ ’ ’ ’ ’ ’ ’ ’ 1 unit cost of make-up sea water
II 12 I3 14 I5 16 17 I6 192021 222324252627262930
Optimum surface function, SF,, (C2 mean specific heat of brine in the
evaporator
Fig. 4. Optimum surface function and optimum productive mean specific heat of brine in brine
energy function using X, and X, as parameters.
(C,)m
heater
CR concentration ratio
Using Fig. 4, each value of (SF) and its corre- EIJO energy parameter, cl1000 B.t.u.
sponding value of X., would give: F fresh water production rate
F, make-up sea water rate
(a) Value of X, that must prevail if (SF) were FTR flashing temperature range
optimum, JIJO staging parameter, c/d(lb.hr)
(b) Value of (PEF),,, that corresponds to L, mean latent heat of vaporization of the
(SF). flashed vapour in the whole evapor-
ator
From the relationship Epo = al &OX,, one could MTD mean temperature difference
calculate a corresponding value of Epo. On the N number of flash stages
other hand, from the modified energy cost sched- Q total thermal energy required
ule (PEF),,, would give another value of EPo. R performance ratio of the plant
These two values of Epo are not necessarily recirculation ratio
equal except when the design is optimum. SJ surface parameter, c/lb
Now, having two sets of values of Epo, these T temperature of brine in the evapora-
are plotted separately versus (SF), giving two tors
curves which if superimposed the point of their t temperature of brine in the condensers
intersection will give (SF),,, and the correspond- T max maximum brine temperature
ing value of Epo that prevails at optimum condi- TBD brine blowdown temperature
tions. From the modified energy cost schedule, to temperature of flashed vapour
the value of E,” just obtained, determines the Ate stage temperature rise in the conden-
optimum productive energy function. While ser
618
Optimization of multi-stage flash evaporation plants

stage temperature drop in the evapor- Greek symbols


ator E minimum-possible energy required
brine temperature rise in the brine per unit of fresh water (Section 3)
heater 8 thermal driving force function (Sec-
stage terminal temperature difference tion 4)
overall heat transfer coefficient Q) group of cost terms (Section 5)
volume parameter, c/lb
staging-surface unit cost ratio Subscripts
energy-surface unit cost ratio opt refers to optimum value

REFERENCES
[ 1] DODGE B. F. and ESHAYA A. M., Thermodynamics of Some Desalting Processes, Advances in Chemistry, Series No.
27. American Chemical Society 1960.
[2] FLUOR CORPORATION LTD., Preliminary Study of an Optimum Nuclear Reactor-Saline Water Evaporator
Process, Office of Saline Water, Research and Development Progress, Rept. No. 34, PB 161010, U.S., Dept. of Interior,
Washington, D.C. 1959.
[3] MURPHY G. W. et al., Minimum energy requirements for sea water conversion processes, O&e of Saline Water
Research and Development Program, Rep. No. 9 1956.
[4] SILVER R. S., Fresh Waterfrom the Sea, Paper Presented during the Symp on Nuclear Energyfor Water Desalination,
International Atomic Energy Agency, Vienna, 1966; Tech. Rep. Series No. 5 1, P. 29.
[5] SPIEGLER K. S., Salt Water Purification 1962.
[6] TRIBUS M. and EVANS R. B., The Thermoeconomics of Sea Water Conversion, University of California, Los Angeles,
Water Resources Center Contribution NO. 61, Rep. NO. 62-53 1963.
171 TRIBUS M. and EVANS R. B., Thermoeconomic Design Under Conditions of Variable Price Structure, Paper Pre-
sented during the First Int. Symp. on Water Desalination, Washington (1965).

APPENDIX 0.12

ILLUSTRATIVE EXAMPLE I
6 O.ll-
For the purpose of illustrating the use of suggested
optimization procedure a numerical example will be taken
g
up. Cost data to be used here are those given by Tribus[7] 7
_ 0.10 -
and Silver[4]. In order that such data might be used without
subjecting the results to be obtained to undue errors, it was .E
decided to use the same plant capacity quoted by Silver, OP
w 0.09 -
namely one million Imperial gallons per day. 8
t
E
0 0.06 -
1. OPTIMUM CONCENTRATION RATIO b
0
1: 1 Basic data
8
(a) Tmax= 250”F, (b) ZBD= lOO“F, & 0.0-r -
tc) C, = 4.08 x lO-4 c/lb[6] I:
(d) Energy Cost Schedule: based upon data given by
Tribus [7] and shown in Fig. A 1.
1
0 0~5XlD6 I06 I.5xlO6 2x106 2.5~10’

1.2 Evaluation of E,” Energy use rate ,000 B.t.u./day


Results shown in Table Al are obtained by following
procedure outlined in Section 6.2.1. Fig. A 1. Energy cost schedule.
The slight variation in Epo with F indicates that E,,Ocould
be taken constant at a value of 0.113 c/l000 E.t.u. Hence, the
use of optimization procedure for constant economic para- 2. OPTIMUM DESIGN FEATURES
meters, Section 6.1.1, is justified. From Fig. 2, the value of 2.1 In an actual case the value of Jpo corresponding to a
CR.,, corresponding to T,,,., = 250”F, Ts, = 100°F and certain set of conditions will be known. For the purpose of
E,“IC, = 277, is found to be 1.76. illustration a value of J,” = 0.30 c/lb. hr is adopted.

619
M. A. MANDIL and E. E. ABDEL GHAFOUR

Table A 1

Assumed values of CR lF in 108% Epo, c/l000 B.t.u.

1.5 1.328 0.114


2.0 1.640 0.112

2.2 Taking U = 400 B.t.u./hr. ft*. “F and noting that A&/


At, is quite close to unity, a0 and (I, are found to be 0.018 and
O-926 respectively (Section 4).
f* 2.09 I,l,l,l,l,l,l,lrl,I,
The (BW$ corresponding to our case is 2.07”F [2].
IO 12 14 &o~ 20 22 24 26 26
Taking Nht, = NAt, = (FTR), a value of a, is calculated function, SF
to be = O-0138(Section 4).
The minimum-possible energy requirement being az/al is Fig. A3. Modified area cost schedule.
0.0149 in 1000 B.t.u./lb (Eq. (8)).
2.3 Based upon energy cost schedule shown in Fig. Al
and area cost schedule given by Tribus [7], the modified cost
schedules shown in Figs. A2 and A3 were obtained.
2.4 Following the steps outlined in Section 6.2.2, the re-
2 0.0900 sults outlined are given in Table A2.
8 2.5 The two sets of values of E,,Ogiven in Table A2 are
0
:

.E
oa660

0.0620
I\
;,,,\-----,_
-
then plotted against (SF) to give two separate curves as
shown in Fig. A4. The point of intersection gives (SF),,
of 18.06 and (E,“) of 0.0785 in c per thousand B.t.u. From
Fig. 4, (PEF),, is then found to be 0.0710 in thousands
“w”
B.t.u.‘s per pound.
E 0.0790 2.6 The remaining design features are then obtained as
t follows:
e
0 0.0740
0 X, = 332, from Fig. 4 or computer results.
6 X, = 1.833, from Fig. 4 or computer results.
$ o~07000
c 0.02 0.04 006 0.06 0.10 0.12 0.14 0.16 N,,,, = 35 stages, from Fig. 3
W
Productive energy function, PEF
(At&,t = v = 4.286”F per stage
Fig. A2. Modified energy cost schedule. I&, = 1.6738, Eq. (16)

Table A2

From Fig. 4
or computer results
Assumed
values Staging Productive Calculated
of Surfacet surface Energy energy Energy+ energy
surface parameter unit surface function parameter parameter
function S,O in cost unit cost (PEF) in Epo in Epo in
(SF) 1O-4c/lb ratio X, ratioXE lOOOB.t.u./lb cllOO0B.t.u. c/lOOOB.t.u.

10 3.100 1.499 102.6 0.11692 0.07353 0.02943


13 2.832 1641 173.8 0.09905 0.07505 0.0455 1
16 2.643 l-758 262.1 0.07981 0.07753 0.06407
19 2.487 1.869 369.2 0.06700 O-07890 0.08492
22 2.350 l-978 494.3 0.06026 0.08034 0.10744
25 2.238 2.077 638.3 0.05069 0.08182 0.13211
28 2.164 2.148 800.0 0.04512 0.08270 0*16011

Walues of SD0 given in this column are obtained from Fig. A3 corresponding to
values of (SF) in the first column of table.
SValues of Epo given in this column are obtained from Fig. A2 corresponding to values
of (PEF) in the fifth column of table.

620
Optimization of multi-stage flash evaporation plants

0.16

0.15

0.14

0.13

0.12

0.11

0.10

0.09

0.08

0.07

0.06

0.05

0.04

0.03

IO II 12 I3 14 I5 16 17 18 19 20 21 22 23 24 25 26 27 28 29
I
'0
Surface fundon, SF

Fig. A4. Evaluation of optimum surface functions.

(TTD),,, = 6*361”F, Eq. (2 la) Unit energy requirement


(BPE) = 2*04”F, for first flashing stage
N, = 2.96 = 3 stages, Eq. (23) e -- 0.07667+0.01490 = 0@9157 thousand B.t.u./lb
(AT,&,t = 12.687”F, Eq. (22) 0F Km
(Ar,&,t = F = 4.229”F for heat rejection stages. 1
R,,, = o-o9157= 10.92

Unit productive energy requirement QoDt= 10’ (089157) = 9.157 x 105thousands B.t.u./day
A.,, = aoF(S = 0.018
(PEF),,, = ($-c)~,, = s = 0.07667thousand B.t.u./lb.
= 135450ft*, Eq. (25).

Resume- Une nouvelle approche est presentee en ce qui conceme I’optimisation eclair Z+plusieurs
&tapes des plantes d’evaporation. Tout en retenant les caracttristiques de base des theories courantes,
I’approche qui est present&e traite de I’utilisation des valeurs relatives des parambtres tconomiques
plutbt que de ieurs valeurs absolues. Cet expose traite d’un probleme variable de 3 modtles libres
de rendement constant, alors que deux parametres de cout peuvent varier selon les programmes
ttablis. Les procedures d’optimisation sont presentees et test&es au moyen d’un exemple illustratif.

Zusammenfassung- Es wird ein neuer Weg zur Optimierung von mehrstufigen Flash-Verdampfungs-
anlagen dargelegt. WPhrend dieser neue Weg die grundlegenden Merkmale der gegenwartigen
Theorien beibehalt, werden hier jedoch mehr die relativen Werte der wirtschaftlichen Parameter
verwendet als die absoluten Werte derselben. In dem Artikel wird ein Problem mit 3 freien Konstruk-
tionsvariablen bei konstanter Leistung beschrieben, wobei zwei Kostenparameter gemlss vorgeschrie-
benen Planen variieren konnen. Die Optimierungsverfahren werden an einem erlautemden Beispiele
geprtift.

621

You might also like