1. TITLE 3 of 15
2. SCOPE 3 of 15
3. OBJECTIVE 3 of 15
4. REFERENCES 3 of 15
5. DESCRIPTION OF WORK PROCEDURE 3 of 15
6. INSPECTION OF IMPORTANT EVENT 10 of 15
8. ATTACHMENT
DOCUMENT NO. :
PROCEDURE FOR ASSEMBLY OF CONDENSER P-T 3109-CONS-015
FOR 3 X 330 MW STEAM POWER GENERATION ISSUED DATE :
November 17th, 08
1. TITLE
Procedure for assembly of condenser for 3 x 330 MW steam power
generation.
2. SCOPE
This procedure describes the erection method of condenser in PLTU 1 Jawa
Barat (Indramayu) – Indonesia.
In this connection, if any modification to this instruction shall be carried out
after reviewing it with personnel concerned.
3. OBJECTIVE
This is to assure that the installation of condenser following the client
requirement, code and specification and to obtain good quality workmanship
DOCUMENT NO. :
PROCEDURE FOR ASSEMBLY OF CONDENSER P-T 3109-CONS-015
FOR 3 X 330 MW STEAM POWER GENERATION ISSUED DATE :
November 17th, 08
during the installation works. And this is also as a systematic guidance for
concerned Supervisor or Engineer to assembly the condenser.
4. REFERENCES
4.1. P-T3109-SDCC-001, Guidelines for Establishing Project Procedure.
4.2. E03033-PR-3001 Construction Execution Plan.
4.3. Installation and Maintenance Manual.
4.4. Construction and Vendor Drawing.
5. DESCRIPTION
5.1. General Requirement.
All assemblies should use shop drawing with status for
construction.
Upper part of necks is made by left and right parts. Lower part
of neck is made up of left, middle and right parts. Upper part
of shell is made up of left and right parts. All of the parts will
be welded together after being carried to the field. All the
components of upper of shell will be carried to the field
scatteredly, then will be welded according to the drawing. All
of the parts will pre-assembly in the factory, then taken apart,
transported individually at last.
It’s necessary for discharge chamber to be done water
pressure experiment after being welded (0.525 Mpa). Watering
sealing experiment needs to be done for the whole condenser.
Watering level is height mark +9000. All the parts must be
dried before being delivery.
Cathodic protection is installed in water chamber.
External drilling will be finished completely in the factory
(mounting holes of bypass sinker will be drilled in the field).
DOCUMENT NO. :
PROCEDURE FOR ASSEMBLY OF CONDENSER P-T 3109-CONS-015
FOR 3 X 330 MW STEAM POWER GENERATION ISSUED DATE :
November 17th, 08
Piano wire
End tube seat
14 kg Sagging plate 14 kg
while achieving
metallic luster
Expanding % 4~6 Measure by
coefficient of Ti- vernier caliper
tube
Expanded- mm 33~36 Measure by
connecting depth depth gauge
Ti-tube length mm 0~0.5 Measure by
extended out depth gauge
partition board
Argon arc welding No air cavity and crack Inspect by
of Ti-tube end penetrating
fluid
DOCUMENT NO. :
PROCEDURE FOR ASSEMBLY OF CONDENSER P-T 3109-CONS-015
FOR 3 X 330 MW STEAM POWER GENERATION ISSUED DATE :
November 17th, 08
Material Receiving
Y
B
DOCUMENT NO. :
PROCEDURE FOR ASSEMBLY OF CONDENSER P-T 3109-CONS-015
FOR 3 X 330 MW STEAM POWER GENERATION ISSUED DATE :
November 17th, 08
B
Hanger rod assembly
Condenser neck –
condenser shell
welding.
C Condenser
expansion joint
setting
Y
Condenser
accessories fit-up
and weld
Ti-tube cutting
and expanding
Condenser inside
cleaning
Condenser water
filling test, balancing
and spring support
adjustment
Final Completion
inspection
Condenser handing
over