Doc. Number :
W-PRO-KSL-2-001
CLIENT
CONTRACTOR
PROJECT NAME
PLTU KALIMANTAN SELATAN
(2X65 MW)
UNDERGROUND GRP PIPE
INSTALLATION METHOD.
PT. PLN (PERSERO)
PT. WUAYA KARYA ~CHENGDA.
PLTU KALIMANTAN SELATAN (2 X 65 MW)
LOCATION : ASAM-ASAM, SOUTH BORNEO, INDONESIA
2 | 19-3-10 :
REV |_DATE DESCRIPTION PREP’D | CHK'D | APP’D£& PLTU KALIMANTAN SELATAN
(2X65 MW)
GaP
Doe. Number : UNDERGROUND FRP PIPE
bahetiatchecgad INSTALLATION METHOD:
‘TABLE OF CONTENTS
GENERAL
REFERENCES
MANPOWER, EQUIPMENT AND TOOLS
FRP PIPE INSTALLATION
Bepe
Page Number
20f7
PAGE
BeEE
Trargraand FAP PipsPLTU KALIMANTAN SELATAN
(2x65 mw) oS
Doc. Number UNDERGROUND FRP PIPE Page Number
Tere ete INSTALLATION METHODS 30f7
1, GENERAL
This instruction is to describe installation method of Underground GRP Pipe of Kalimantan
Selatan 2x65 MW Coal Fired Steam Power Plant.
2. REFERENCES
- Lianyuang Zhongfu Lianzong _: Installation and Burial Of GRP Pipes Manual
Composites Group CO., LTD
= YG-2906C-8-36 Power Plant Pipe Name List
3. MANPOWER, EQUIPMENT & TOOLS
‘No. | MANPOWER DESCRIPTION Qry ‘UNIT
1 | Rigger 4 Persons
Pipe fitter 2 Persons:
3.__[ Supervisor 1 Persons
[No EQUIPMENTS TOOLS [TY UNIT
1. | Crawler Crane 50t T set
2.__| Chain block 2 pes
3.__| Lever Block 2 Pos
4,__| Sling belt 2 roll
5,_ | Joint Tester 1 set
6.__| Hand tools T set
Cndrgrand PRP PipsPLTU KALIMANTAN SELATAN
(265 MW)
Doc. Number :
WK-PRO-KSL-2.001
aD
Page Number
4of7
UNDERGROUND FRP PIPE
INSTALLATION METHODS
4, ERP PIPE INSTALLATION
4.1. Preparation
Conduct initial inspection of facilities projects to install, the product pipe materials, joint
materials and tools when the site,
Check Marking FRP Pipe Product and Material if in Inspection there is a problem in pipe
product (Ex. broken ), then must be report, in order to improve the suppliers, including raw
materials and consumabtres must be reported the stock.
Figure 1. FRP Pipe Double O-Ring Joint
4.2. Joint Pipe
1. Prepared and raise pipe will be joint in to ditch with Crane.
Clean the pipe gully from dirty.
Clean the pipe.
Lubricate ‘O' ring with Greale
Bring the end of pipe to be in the joint by using crane.
‘The second tie pipe by Shing B
7. Combine the two shing belt with Chain lever or Chain block.
8. Combine both ends of the pipe by pulhng chain block and helped lift with crane.
9. Make sure itis correct pipe joint.
10. Pipe joint connection do by following the steps - steps as above.
Traergronnd PRP PipesPLTU KALIMANTAN SELATAN
& (2X65 MW) a oS
UNDERGROUND FRP PIPE Page Number
INSTALLATION METHODS Sof7
Push O-Ring airproof spring gradually
Moving direction 4 Hanging from the
— ground to
op, | Patio Picton
()
\ Le
Figure 2. FRP Pipe Double O-Ring Joint Method
dra FAP Pipes& PLTU KALIMANTAN SELATAN
(2X65 MW) (ia) oS
Doc. Number : UNDERGROUND FRP PIPE Page Number
ferret INSTALLATION METHODS 6of7
43. Hydrotest for O-Ring Joint
Testing is conducted with the aim to find the leak and the strength of operational pressure
both at the joint and the overall installation.
After visually checking the results, then followed by using a pressure tester testing.
Procedure Process Including a Pressure Test
~ Holes in the screw joint first
- Fill with water until it fully through the holes that have been available
- Nipple input on that hole in the screw and plug,
- Tighten the nut with pass key so as not to leak.
~ Pressure tester pumped from 0 up to 3 bar, hold 10 minute
- Check visual, whether there is leakage.
~ Add pressure until 6.5 bar and hold during 30 minute
- Check visual and make sure there is no leakage and decrease pressure on the gauge
pressure,
- Lower the pressure until 0 again with open drain on the pressure tester.
- Noted the results of testing.
‘After all piping is complete plug and pressure test will be returned as the end of the entire
series checking and testing. Testing is done by filling the water up to full installation with the
‘water pump pipe. Further providing pressure to move or less the same as the pressure test
joint.
4.4, Lowering Pipe
If lowering has been done mechanically (using equipment/ tool) so the Nylon sling has to use,
and not permit using Wire Sling because FRP were fragile and cracked materials. Before
lowering, you must making sure that pipe body totally be supported on sand bag and sand layer
and clean from all foreign (sharp/ hard) possible material such as : stone, concreted, block, etc,
which find it into excavating work.
Lift down the pipe slowly and carefully, into clean hole (free from hard stone materials).
Starting from end point step by step, laying on sand bag until finish,
Tree FAP Pipes£ PLTU KALIMANTAN SELATAN
(2X65 MW)
Doe. Number : UNDERGROUND FRP PIPE Page Number
eo INSTALLATION METHODS of 7
Until all pipes laying down into hole, inform to Civil Department (Surveyor) to re-check its
eveling/ elevation position, in order that conformed to determined elevation design.
45. Backfilling
If the result of piping test has been approved by Client, so drain water inside pipe (Release
Procedure), then back filling
See drawing.
secondary Bac
ema boc
\/ (requene)
sau tm sopportin is zone
Figure 3. General procedure for backfilling underground FRP Pipe
Thidrgraimd FAP Pipos