CMTS jhajjar all BTS Details

Total site details Remarks


Total no of sites 43
IP sites 18 under cmts team
NBSNL sites 15 under cmts team
MTE jhajjar 1 under cmts team
BSNL SITES 9 under group team

sites availability
IP sites 99.3 under cmts team
NBSNL sites 98.2 under cmts team
BSNL SITES 99.2 under group team
less than 95%
IP sites nil under cmts team
NBSNL sites 3 under cmts team
BSNL SITES nil under group team
less than 98% and above 95%
IP sites 3 under cmts team
NBSNL sites 3 under cmts team
BSNL SITES 1 under group team
site list whose availabilty less than 98%

NAME OF sites IP downtime in hrs AVAILABILITY

MAROT(43) BSNL 102.21 86.76


Dawla(86) BSNL 53.07 92.91
GOCHHI(48) BSNL 41.54 94.28
BHADANI(81) ATC 34.80 95.00
DHAKLA(9) BSNL 29.03 95.83
DHOUD(20) ATC 21.32 96.94
TE
BSNL
JAHAGIRPUR(10) 22.71 97.83
BIROHAR(41) ATC 14.34 97.94

IP sites BHADANI(81),DHOUD(20),BIROHAR(41)
NBSNL sites MAROT(43),Dawla(86),GOCHHI(48)
BSNL SITES DHAKLA(9), TE JAHAGIRPUR(10
4G sites status
Cat -A 4 NTR media - both link working ok
Cat -B 38 phase -1 Cat -B ,38 sites
Cat -D 1 phase -11 Cat -A ,D 05 sites
CMTS GROUP IP Remarks
OD pad construction completed 11 8 3 0
Installtion completed 11 8 3 0
Media ready 5 5 0 0
EMS tested 5 5 0 0
Media pending 3 3 0 0
Commissioned 5 5 0 0