Three cores we have to take(1st at ground floor column,2nd core at 1st floor slab/beam and 3rd core at 2nd

floor column)

10 rebound Hammer (3 Nos, at ground floor columns ,3nos.at 1st floor slab & beams & 4 Nos. at 2nd floor slab & Beams)

10 UPV (3 Nos, at ground floor columns ,3nos.at 1st floor slab & beams & 4 Nos. at 2nd floor slab & Beams)

2 Carbonation (1st and 2nd floor column)

2 Half cell potentiometer (1st and 2nd floor column)