You are on page 1of 4

rn

----shaft

~
0
--------- Inlet case 0
0
Adjustable ~
wicket gates

§ 1st stage
runner
Support rib
Inlet nozzle
Turbine easel
2nd stage
runner
~
S,
'-

~
0
,,~
0
0
Cl.

-Barrel ~
~
wr ,3

jlouth Fork Dam, circa 1887.


Discharge
- - - nozzle
downstream section of the dam
was built up of mostly rock, many
weighing over 10 tons.
The completed dam stretched
918 ft across the valley and was
over 72 ft high. The earth and

fruE CAUSE OF THE


inward, rock used in its construction was
age runner.
r discharges 10 ft thick at the top and over 220
be; flow ft thick on the valley floor. Run-
n barrel. ning under the center of the dam
>n top of
)Oth wicket
e flow rate JOHNSTOWN was a huge stone culvert used to
discharge water into the South
Fork Creek to be fed to the canal

as a clearwell
1ting the need
at their sites.
FLOOD via the Little Conemaugh River.
The water into the culvert was
controlled by five sets of valves and
cast iron pipes 2 ft in dia. In the
~ gradient for event that the discharge culvert
tion system could not handle water flows dur-
ing heavy rains, a 85 ft wide spill-
, parts of the A new look at the historic Johnstown flood of 1889. way was cut through the solid rock
ins and these of the hillside near the eastern end
re gradients WALTER FRANK of the dam.
eated by the In June of 1852, the valves con-
parate high trolling the flow of water into the
established, culvert were closed. By August the
pumping sta- reservoir was 40 ft deep. Engineers
with a new decided it would be unsafe to fill
engineer for Pennsylvania, de- the reservoir much higher for the
:l SCADA sys- signed the dam, and in 1840, con- first two years. Lack of rain the
~ observation struction began in a valley near the following year depleted the reser-
n May 31, 1889, a wall

0
lydro plant, of rushing water three town of South Fork. Construction voir. The year after, two small
' control sta- stories high struck the was completed in 1852, with delay leaks appeared in the dam and the
and booster city of Johnstown, due mainly to financial difficulties. water had to be let out for repairs.
1e system in- Pennsylvania. In its Considerable care went into the The adverse financial impact of
:ontrol con- 1vake most of the town was de- construction of the new dam. The these events was followed by the
[ controlling opening of the Pennsylvania Rail-
~troyed and over 2,200 lives were valley floor was cleared down to
mtputs at 21 lost. The Johnstown flood was the the bare rock. The upstream part road service between Johnstown
1tion of the of the embankment was built up of and Pittsburgh in 1852. With rail
1vorst civil disaster the United
manpower )rates ever suffered. successive rolled layers of clay and service able to deliver goods faster,
1e water sys- earth, 2 ft thick, which were "pud- cheaper and more reliably, the
The source of the water was a
td reporting failed earth and rock dam 14 mi dled" by letting them sit under wa- canal was doomed. The State put
(7 above the city. The state had op- ter for a few days to create a wa- the whole system up for sale and
erated a canal system between tertight barrier. To add weight and the railroad purchased it along
roject engineer
Philadelphia and Pittsburgh and strength to the embankment, the with the South fork Dam in 1857.
gineers, Inc.,
mne B. Stab- built the dam for dry season stor- core of the dam consisted of shale, The dam suffered a major break
.. age. William E. Morris, principal earth and small stones while the on June 10, 1862, when the up-

__...........l0885~ 7024/88~0005~00631$01 00 + 1 5¢ ' " ,,,, MAY 1988 63


stream portion of the stone culvert downstream part of the gap. This ft high at the entrance to the spill- FIGURE 2
running under the dam collapsed. embankment was built up until it way, 99 ft wide at this point. Al- AFTER
There was little damage to prop- was high enough to enable a road though the spillway had an aver-
erty downstream, but a large sec- to be graded out to it. Then rock, age width of 85 ft, there was one
tion of the dam over the damaged clay, shale and earth were hauled area, 17 5 feet below the bridge,
portion of the culvert collapsed out and dumped. where the width along the bottom
and was washed away. Because the discharge system had was only 69 ft. With these mea-
RECONSTRUCTION been destroyed in the 1862 inci- surements in mind, it would ap-
dent, the water rising in the lake pear that the bridge supports
In 1879 the property was sold to found its way to the stone em- would not affect the discharge of
Benjamin Ruff, who wished to re- bankment and started washing the water. Thus, an array of iron
pair the dam and create a summer away any earth that was mixed screens to prevent the escape of
resort. with the stone. Hay, straw and cut fish were attached to the bridge
Ruff's plan was simple. He would brush were placed across the up- supports.
fill in the gap and rebuild the dam stream face to stop the seepage. Any traffic going to the club
to its original height. When the Then, earth and clay were dumped crossed the top of the dam where
lake filled, the excess water could over the hay and straw to create the crest was fairly flat and 10 ft
be carried off by the existing spill- the watertight section of the dam. wide. If a wagon or carriage was on
way. In October 1879 reconstruc- No rolling or puddling of the the breast, and another wanted to
tion on the dam began. Ruff con- earth was done as in the original cross from the opposite direction, it Station 1
vinced 15 prominent men from the construction. The deposited mate- would have to wait until the other
Station 1 +50 )
Pittsburgh area that his enterprise rial was little more than a colossal completed its crossing. So the top
would be one of the finest resorts railway embankment without the of the original dam was cut 2 ft, From an 1891 ,
in the country. On November 15, strength or watertightness of the giving a road width of 17 ft.
1879, they were granted a charter original. Whenever the lake waters
DECEPTIVE CALM were not as in
under the name of the South Fork reached the top of the repairs, a
peared. The sci
Hunting and Fishing Club. large wooden flume was used to For the next eight years, the
bottom of the I
The upstream entrance of the re- carry the excess water over the top South Fork Hunting and Fishing
reduced the di:
maining part of the culvert was of the rising embankment. Club was one of the finest summer
the height of
boarded up and any type of fill In March 1881, the repaired part resorts in Pennsylvania. To all but
40%. There w:
that could be purchased from local of the dam was higher than the a few, everything appeared tran-
lighter screens :
landowners was used-mud, brush, bottom of the original spillway and quil and safe in the spring of 1889.
bridge. It was a
tree stumps, hay, and even a few water began flowing through it. By However, conditions were ripe for
ft bridge was rr
wagon loads of horse manure. On summer the repairs were com- disaster.
tion than the 1
December 25, after five days of pleted, the lake was stocked with The lake behind the dam had a
the spillway.
rain, the repairs to the dam were fish and the club opened. perimeter of 7 mi to hold 20 mil-
In the origin<
swept away. Work on the breast The road from the town of lion tons of water, meaning the
depth of 10 ft
was resumed in April 1880, but South Fork to the club reached a weight of the repair section was
the dam was sr
this time with slightly more appro- point where the top of the dam four times heavier than the force of
club lowered th
priate methods. was only a few yards to its right the water on it. A few small leaks
2 ft to widen th
A man who had some experi- with the spillway on its left. Since had developed at the South Fork
duced the capac
ence building railway embank- water was now flowing through the Dam, but with the absence of a
by one-fifth. In
ments was employed to supervise spillway and prevented visitors discharge system, the water in the
of the way in w
the work. A double thickness of from crossing to the lake, a bridge lake could not be lowered to make
reconstructed i
hemlock pilings was placed across was constructed. the repairs in a proper manner.
the repaired sect
the culvert entrance. Earth and The foundation of the bridge The bridge supports, with the
was at least 6 i1
large stone were dumped into the consisted of 14 wooden supports 10 iron screens attached to them,
ends of the dam.
It is not uncor
FIGURE 1
earth dams to s1
ORIGINAL DAM DESIGN their centers, tl
Control tower to valves
where the wate
greatest, but wit
nance they can ·
At the South For
the embankmer
have been the h
inches, was the le
On May 28,
Water to started out of ~
Canal east. When the :
Johnstown-Saud
evening, it was t
pour that had eve
in that section of
A schematic of the design for the Johnstown, Pa. South Fork Dam, circa 1840. U.S. Signal Servic

64 CIVIL ENGINEERING
ranee to the spill, FIGURE 2
:it this point. Al, AFTER THE FLOOD
vay had an aver,
ft, there was one
~low the bridge,
:ilong the bottom
W'ith these mea,
1d, it would ap,
1ridge supports
the discharge of
an array of iron
it the escape of
d to the bridge

ing to the club


· the dam where
y flat and IO ft
· carriage was on
other wanted to
)Site direction, it Spillway bottom
Station 1
: until the other Stations 2-10
Station 1 + 50 West End Station 10 + 50 East End
>ing. So the top
m was cut 2 ft, From an 1891 ASCE volume, two views of the South Fork Dam after the flood showing the break area.
t of 17 ft.

were not as innocent as they ap, 6, 10 in. of rain fell in 24 hours sage was never taken seriously.
peared. The screens ran across the over the entire section. The weight and speed of the wa,
ght years, the ter over the dam, 123 tons per sec,
bottom of the bridge supports and During the night small creeks
tlg and Fishing ond, did little damage to the top of
reduced the discharge of water to became roaring torrents ripping
~ finest summer
the height of the bars alone by our trees and debris. The amount the hard packed roadway but it
mia. To all but
appeared tran,
to%. There was also an array of of water entering the lake behind tore at the outer face of the em,
lighter screens at both ends of the the South Fork Dam was 10,000 bankment. The force of the water
spring of 1889. kept washing away the earth and
bridge. It was apparent that the 99 cfm but the spillway only carried
s were ripe for rock, working its way back toward
ft bridge was more of an obstruc, off 6,000 cfm. On the morning of
tion than the narrowest point of May 31, the situation was serious. the lake. Not even the heaviest
the dam had a
the spillway. The lake had risen over 2 ft during stone could long resist and was
o hold 20 mil, soon carried away. By two o'clock,
· In the original plans, a spillway the night and by 10 a.m. the water
, meaning the the water had cut a huge step in
,depth of 10 ft below the crest of was less than a foot from the top of
ir section was
'the dam was specified. When the the dam. A group of day laborers the very center of the dam. The
1an the force of reconstructed embankment be,
:c1ub lowered the crest of the dam were put to work with picks, shov,
:ew small leaks
l ft to widen the roadway, they re, els and a plow and horse on the came thinner and thinner.
le South Fork
.duced the capacity of the spillway western hillside. They hoped to cut
absence of a INVESTIGATION
:by one,fifth. In addition, because a trench so the water through it
e water in the
:of the way in which the dam was would cut a deeper and wider Investigators subsequently con,
.vered to make eluded that "the failure was due to
reconstructed in 1880 and 1881, channel. However, the hillside was
er manner.
·the repaired section settled until it 175 ft across and the workman the flow of water over the top of
ms, with the was at least 6 in. lower than the succeeded in making a trench only the earthen embankment caused
1ed to them, ends of the dam. 2 ft wide and 14 in. deep before by the insufficiency of the waste,

'
j It is not uncommon for the best

earth dams to settle, especially at


hitting rock. The lake continued to
rise. The workmen and plow were
way (spillway) to discharge the
flood water." But the club and its

I their centers, the weakest point


where the water pressure is the
sent to throw up a ridge of earth
on the sagging section of the dam.
members were not deemed respon,
sible. The investigators concluded


! greatest, but with proper mainte, The lake had now grown from its that the original dam had been de,
nance they can be built back up. normal 407 acres to 450 acres. signed and constructed poorly.
1
At the South Fork Dam the part of Around 11:30 a.m. the small The collapse of the culvert in 1862
'the embankment which should mound of earth thrown up by the that caused a break and even the
have been the highest, if only by plow suddenly gave way and the two leaks that had occurred 35
inches, was the lowest. water started over the dam, quickly years before were referred to as
On May 28, 1889, a storm widening out to 50 ft. Parke, the "slight breaks" in support of this
started out of Nebraska moving "resident engineer" at the dam, conclusion.


east. When the storm struck the rushed off to inform the telegraph They also concluded that if the
Johnstown,South Fork area that operator at South Fork to warn the original discharge system had been
evening, it was the worst down, people in the valley below that the installed and was discharging to its
pour that had ever been recorded dam might collapse. Due to the full capacity, if the spillway had
in that section of the country. The confusion of downed lines and the not been obstructed, if the dam
U.S. Signal Service estimated that disbelief of key persons, the mes, had not been cut down and even if

MAY 1988 65
the dam had not sagged, the water earth and rock in this waste could been an emergency spillway in and
still would have crossed over the not have exceeded 34 ,000 cu yd. around stations 1 and 1+50 at
dam and caused a failure. The remaining 16,000 cu yd was least 70 ft wide and at least 3 ft
Based on what was known about consumed excavating the emer, deep (the missing 0.48 ft can be
the original construction at that gency spillway on the western hill, explained by noting the contours
time, there is evidence to support side which was only 175 ft across. of the landscape between station 0
this conclusion. However, the orig, 3. All observers, including Parke, and 1.) This area slopes into the
inal specifications and construe, in the vicinity of the dam before area of stations 1 and 1 + 50 which
tion of the dam were not as the in, the break, stated that water started could have easily been filled by
vestigators believed. The original flowing through the western hill, erosion during the 3 7 years from
dam had been designed and con, side before it started over the dam. the date of construction until the
structed in a way that the "most Parke claims that his men were re, break. Even one year after the '89
extensive rainfall of the century" sponsible for this because they had break, P.F. Brendlinger from ASCE
would not have caused water to dug down the western hillside "no investigated the site and could find
cross over the dam. more than knee deep," or about 14 "but slight traces" of the trench
Due to the lowering of the dam in. Yet later testimony revealed that had been 20 in. deep and 25 ft
during reconstruction and the sag, that the dam sagged at least 6 in. wide.
ging center, the effectiveness of an and 2 ft of height was taken off the 5. On the eastern end of the dam
emergency,spillway in the area top of the dam to make the road where the only altitude measure-
where the trench was cut was elim, wider; however, there was no need ment was taken (station 10+ 50),
inated. The existence of the to cut the 175 ft hillside down to where there would have been no
"emergency" spillway was never re, make the road wider. need to cut down the dam to make
vealed to the investigators. Follow, If the western hillside was not the road wider since the northern
ing are five arguments to support meant to be lower than the top of side of the road is the natural hill-
this finding. the original dam, they would have side, the altitude is 1,613.34. Since
1. In 1839, Morris stated that: "A had to dig down at least 30 in. no cutting down would have oc-
waste or waterway will be exca, when water was already flowing curred there, and since only 4 ft of
vated in the hill at one or both over the dam. puddled dam construction was
ends of the dam, for the discharge Ironically, the area where the needed on the lake side, the
of surplus water in time of floods, trench was cut was 17 5 ft across chances of subsidence would be
the aggregated width of the chan, and so level that workmen could minuscule. Therefore, at least
nels will not be less than 150 ft." cut a trench in less than an hour 1, 613. 34 ft had to be the altitude
For maintenance reasons, acces, that caused water to flow through of the original construction since
sibility, and economic consider a, it. Only superb engineering could the ends of the original dam would
tions, earth and rock dams under have created this situation. The not be rower than the center. Iron-
certain situations have been con, top of the dam that the club re, ically, 1,613.34 is almost exactly 10
structed with more than one spill, constructed was not that level. ft above the bottom of the main
way for hundreds of years. Also, Parke, not knowing that the spillway (1,603.4 ft), just as Morris
In May of 1841, the state had hillside was an emergency spillway specified in 1839 and 1841. That
stopped construction for financial constructed over rock, was amazed would have left an emergency spill-
reasons. Before work was resumed, that the flow of the water through way on the western hillside over
Morris was asked to prepare new the trench did not cut a deeper 3 1/ 2 ft deep and over 70 ft wide-
plans for the dam and specified channel. In addition, on the outlet wide enough to have carried off
that the "waste,way or ways" side of the trench, the escaping the waters of a storm greater than
should not have a width of less water never touched the con, the one of 1889.
than 150 ft. structed portion of the dam which If the reconstruction of the
It is inconceivable that any engi, could have weakened it. Here, too, South Fork Dam had been rebuilt
neer would approve the comple, superior engineering was evident. to the original specifications and
tion of a dam with a waste,way 4. In 1889, the average altitude of construction, the disaster of May
width of 69 ft at its narrowest stations 1 and 1+50, where the 31, 1889, would never have oc-
point, when the specifications flow of water through the trench curred. Granted a break like the
called for 150 ft. could not have affected the level, is one in 1862, when the culvert col-
2. The original construction con, 1,610.24 ft. The average altitude lapsed, could have caused great
tact called for the "excavation of between stations 2 and 10 on the damage. However, the South Fork
earth and rock in wastes 50,000 dam (eliminating the washed out Dam as originally designed by
yards" (note the term "wastes"). section) is 1,610.76 ft. To get a Morris and constructed by More-
The main spillway as it existed roadway width of 17 ft, 2 ft of em, head and Packer would not have
then and does now, is a quadrant bankment was taken off between had water pass over it-the worst
of a circle 310 ft down the center, stations 2 and 10. Add the 2 ft and possible thing that can befall an
an 85 ft average width, with a the average altitude on the dam earth and rock dam-the unques-
maximum height of 52 ft on the would be 1,612.76-this gives a tionable cause of the 1889 Johns-
hillside and 20 ft on the dam side. higher altitude of 2.52 ft above the town disaster. 0
Noting the contours of the hill and hillside stations of 1 and 1+50
the way the spillway fans out as it where there was no need to take Walter Frank, civil engineer, worked for
reaches up, it becomes apparent, off 2 ft. Bethlehem Steel until 1979 and is now
even today, that the removal of There is no doubt that there had with Baden Sports, Renton, Wash.

66 CIVIL ENGINEERING

You might also like