You are on page 1of 38

By: RAD Mexico & Bynet Data Communication Ltd

November 11th 2013


Rev: 2.1
Mexico City Police
Mobility Communication System
POC Design & Description
Ver. 2.1 11 November 2013

Table Updates

Number: Rev: 1.0


Bynet Data Communications Revisions
Page
Rev Date By Change
Bynet – Shmuel
1.0 21/8/13 Original
A.
1.1 Bynet – Oz RAD integration, Change Procedure
22/8/13
Pozner
1.2 23/8/13 RAD – Jose A.
2.0 22/10/13 Bynet – Shmuel A POC update according to additional
requirements – adding a camera pole at
the road, and PTP backhaul to the police
station
2.1 10/11/2013 Bynet – Shmuel A Doc. Update according to the schedule

2
Mexico City Police
Mobility Communication System
POC Design & Description
Ver. 2.1 11 November 2013

Table of Contents

.1 SYSTEM REQUIREMENTS ……………………………………………………………..4


1.1 INTRODUCTION………………............................................................................. 4
1.2 PARTICIPATING AND RESPONSIBILITY……… ....................................................... 4
1.3 POC GENERAL DESCRIPTION……….. ................................................................ 5

2. SYSTEM SPECIFICATIONS AND ASSUMPTIONS .............................................. 7


2.1 SYSTEM DESCRIPTION........... ............................................................................ 7
2.2 SYSTEM SPECIFICATION..................................................................................... 8

3. BASE STATION SYSTEM DESCRIPTION 11


3.1 BASE STATION POSITION............... .................................................................. 11
3.2 COVERAGE AREA PLANNING................ ............................................................ 12
3.3 SYSTEM DESCRIPTION…….............................................................................. 13
3.4 INSTALLATION DESCRIPTION......... ................................................................... 15
3.5 INSTALLATION ACTIVITIES AND RESPONSIBILITY........ ......................................... 19

4. CAMERA ROAD SITE 20


4.1 CAMERA ROAD SITE POSITION....... ................................................................... 20
4.2 SYSTEM DESCRIPTION.............. ....................................................................... 21
4.3 INSTALLATION DESCRIPTION............ ................................................................ 22
4.4 INSTALLATION ACTIVITIES AND RESPONSIBILITY…… ......................................... 25

5. CCO - POLICE STATION SYSTEM DESCRIPTION............................................ 26


5.1 SYSTEM DESCRIPTION............ ......................................................................... 26

FIGURE 5.1: SYSTEM DESCRIPTION AT THE POLICE STATION ........................ 26


5.2 INSTALLATION DESCRIPTION............ ................................................................ 27
5.3 INSTALLATION ACTIVITIES AND RESPONSIBILITY......... ........................................ 29

6. VEHICLE SYSTEM DESCRIPTION 30


6.1 SYSTEM DESCRIPTION……….. ........................................................................ 30
6.2 CAR KIT DESCRIPTION................ ..................................................................... 31
6.3 INSTALLATION ACTIVITIES AND RESPONSIBILITY ................................................. 36

7. POC TEST DESCRIPTION…............................................................................... 37

8. POC SCHEDULE.................... ............................................................................. 38

3
Mexico City Police
Mobility Communication System
POC Design & Description
Ver. 2.1 11 November 2013

1. System Requirements
1.1 Introduction

 The proposed system shall support the following requirements:


 A real time video connection from a vehicle which shall be driving along
Arco Norte Highway to the designated CCO (Command Center
Operation at police station at Pachuca).
 The system demonstration shall tack place at Police station at Pachuca
The demonstration shall include the following issues:
o A real time video connection from a pole installed along the highway
(Cam Site#1) To CCO.
o A real time video connection from a vehicle while driving at the
Mobility area To CCO.
o PTP Radio link operation for backhaul connectivity.

1.2 Participating and Responsibility


 Table 1.2 describes all the participant people at the POC project.

Company Name Responsibility Email


Bynet Asher Ilan Project Manager ASHER@BYNET.CO.IL
Bynet Shmuel Azulay System Engineer shmuela@BYNET.CO.IL

Table 1.2: Participant people at the POC project.

 Table 1.2- A describes all the companies responsibility.

Company Responsibility
o System Configuration, Operation and testing.
Bynet
o Advise and check MEI installation.
RAD Mexico o System Elements, cables supply according to the BOM
o The entire system element Installation.
o Supply and installation of all the construction at the
following sites:
 Base Station.
MEI  Police station.
 Camera site at the road.
o Supply a basket crane for the Base Station and for the
camera site pole; for the elements installation
o Supply and drive at the vehicle for the Demo.
Table 1.2- A: Companies responsibility

4
Mexico City Police
Mobility Communication System
POC Design & Description
Ver. 2.1 11 November 2013

1.3 PoC General Description


The PoC shall take place at the location as describe on the Map at figure 1.3:
 CCO

 The CCO shall be at the police station at Pachuca, the customer need
to coordinate a room for the demonstration.
 The CCO shall connect to the system via a PTP Radio Link from the
Base Station at the Mobility area*
Note *) depending LOS Condition between the Base Station to the
Police station

 Mobility Area

 Coverage area distance - The distance of the road at the POC shall be
approximately 5 [Km] according to figure 1.3.
 Vehicle
 One Vehicle shall drive along the road on both ways.
 Vehicle Speed shall be no more than 200 [Km/h].

 Application service type

 One stream of video from the vehicle to the CCO at 2Mbps capacity
 One stream of video from a camera site installed along the highway
(Cam Site#1) To CCO at 2Mbps capacity.

5
Mexico City Police
Mobility Communication System
POC Design & Description
Ver. 2.1 11 November 2013

Police station at Pachuca

PTP Backhaul
Radio Link
Mobility Area

Figure 1.3: POC Map

6
Mexico City Police
Mobility Communication System
POC Design & Description
Ver. 2.1 11 November 2013

2. System Specifications and Assumptions

2.1 System Description


 The system is a Wireless System is consist of the following:

 Mobility communication system supporting the following:


 Mobility communication from a Police vehicle while it is driving
along the road at the Mobility area.
Assumption – the vehicle, MEI shall supply it and drive for the
demonstration.
 Video camera installed at the pole at the road at the Mobility area.
 PTP Radio Link for connect the Mobility System to the Police station at
Pachuca, for the customer system demonstration.
Assumption – The operation of the PTP radio link is depending of clear
Line Of Sight between the Base Station at the road to the Police station
at Pachuca.

 The wireless system includes One (1) Base Station (BS) and One (1) vehicle.
 Figure 2.1 describe system architecture.

Mobility Mobility
Coverage area Coverage area

Cam Site
PTP Radio Link

Base Station

Police Station at Pachuca

Figure 2.1: System architecture

7
Mexico City Police
Mobility Communication System
POC Design & Description
Ver. 2.1 11 November 2013

2.2 System Specification


The system specifications and assumptions are described at table 2.2.

General Description
 Mobility - Approximately 5 [Km]
Distance Line
 PTP – 23 [Km]
 Number - One vehicle
Vehicles
 Max speed is up to 200 [Km/h]
 Mobility - Open area with bridges along the highway
Area Type
 PTP – Open area, Urban area
 One stream of video from or to the vehicle at 2Mbps capacity.
Application service type:
 One stream of video from a pole installed along the highway (Cam Site#1) To CCO at 2Mbps capacity.
Base Station Networking Backbone Connectivity Yes, PtP radio link from Base Station to Police station
Technical Specification
Police
Specification Mobility Base Station
Vehicle Cam Site Station
 Mobility = 5.4(1) [GHz] band
Operation Frequency Band  PtP Backhaul to the police station = 5.8(1) [GHz]
(1)
Note - The final Operation frequencies shall determine at the sites after site survey and spectrum availability
Mobility and PtP Backhaul to the police station= 10 or 20 (2) [MHz]
Channel Band Width (2)
Note - The final CBW Operation shall determine at the sites after system pretesting.

8
Mexico City Police
Mobility Communication System
POC Design & Description
Ver. 2.1 11 November 2013

 Mobility = 10 (3) [Mbps] Aggregate


 PtP Backhaul to the police station = 50 (3) [Mbps] Aggregate
(3)
Note -Those values are pending on the final operation Channel
Band Width that shall be determine at the sites, according to the 4 or 8
Aggregate Throughput 4 [Mbps] 20 [Mbps]
following issues: [Mbps]
 Site survey and LOS Condition
 Installation
 Spectrum availability
1.3 [Km]
Coverage area Approx. 5 [Km] according to the map #1 23 [Km]
from BS
Maximum Vehicle Speed 200 [Km/h] No No
Symmetric Data Channel 50%/50%
Master and Slave; HSS cable connected between the Mobility HBS
radio at the Base Station.
HBS Synchronization The PtP shall be installing on the top of the pole 3m above the No No Slave
Mobility HBS - Not Sync, Master Configuration – Sync with HBS is
optional, it shall determine at the system implementation.
Number of Vehicles at the same time at one
1 No No
sector
Number of Base Stations 1 No No No
Number of HBS Radio at the Base Station 2 * HBS Radio at the same Pole No No No
20 [m] at
 PtP = at the top of the pole at15 [m] 3[m] on
Antennas Height 2 [m] existing
 Mobility HBS = 3 [m] under the PtP Tripod
pole
28dbi
Antennas Type 60° Sector Antenna Omni Integrated
External
Total of 4 antennas, two antennas connecting to each HBS Radio
Number of antennas 2 1 1
Unit
10÷30 110V A.C 110V A.C
POE Type 110V A.C 60 Hz Indoor
Ruggedize Indoor Indoor

9
Mexico City Police
Mobility Communication System
POC Design & Description
Ver. 2.1 11 November 2013

Power Supply 110 [V] A.C 10 ÷ 30V D.C 110V A.C 110V A.C
Power Consumption 90 [Watt] for the 2 * HBS + PTP 30 [Watt] 20 [Watt] 30 [Watt]
ODU/POE cable length 25 [m] 3 [m] 5 [m] 100 [m]
RF Coax cable length 1.2 [m] Car Kit No 1.2 [m]

Table 2 – system specification and assumption

01
Mexico City Police
Mobility Communication System
POC Design & Description
Ver. 2.1 11 November 2013

3. Base Station System Description

3.1 Base Station Position

 Figure 3.1 describes the position of the Base Station on a map.

Base Station Position

Figure 3.1 – Base Station position at the map

 Figure 3.1-A describes the pole for the system elements installation at the Base
Station position of the Base Station on

Radio equipment position at


the existing pole

Figure 3.1 A: pole for the system elements installation

00
Mexico City Police
Mobility Communication System
POC Design & Description
Ver. 2.1 11 November 2013

3.2 Coverage Area Planning

 The vehicle shall drive along the road at the coverage area only, at both directions of
the road.
 Figure 3.2-B is describing the Wireless System Coverage area.

The RED line is the


drive road for the
Demo. At the two
direction

HBS#2 Coverage
area

HBS#1 Coverage
area

5 [Km]

Figure 3.2-B: Wireless System Coverage area

02
Mexico City Police
Mobility Communication System
POC Design & Description
Ver. 2.1 11 November 2013

3.3 System Description

 Figure 3.3 is describing the System elements at the Base Station.

Pole

To Road HBS#1 HBS#2


To Road

1.2m RF cable 5m Cat5e


Sync. cable 1.2m RF cable

HSS unit for radios


synchronization – HBS#2
PTP To Police Station
OPTION
Shall be determine at
the site
1.2m RF cable

25m Cat5e cable

110V A.C
Cabinet
110V A.C
110V A.C

2m Eth. cable

2m Eth. cable
2m Eth. cable

110V A.C

Figure 3.3: Base Station system description

03
Mexico City Police
Mobility Communication System
POC Design & Description
Ver. 2.1 11 November 2013

 Figure 3.3 – A is describing the System elements at the Base Station.

PTP Radio and Dual polarization


antenna for the Backhaul
Existing Camera connectivity

4 * 60° Sector antennas


HBS#2
Two antennas at each side connecting to the each HBS
For the Mobility

Pole height - 14 [m]

Two Unit HBS


Radio for the
Mobility

Cabinet Height - 2 [m]

Outdoor Cabinet (Power)

Figure 3.3 – A System installation at the Base Station

04
Mexico City Police
Mobility Communication System
POC Design & Description
Ver. 2.1 11 November 2013

3.4 Installation Description

 Figure 3.4 is describing the System elements at the pole.

PtP radio with external antenna


- Antenna Potion:
* Height = Top of the pole above the existing camera
* Antenna Azimuth = 45°
* Antenna Tilt = 11 °

Four 60° sector antennas at the following


azimuth:
 Two antennas - 104°
HBS#2

 Two antennas - 285°

Two ODU Radio near the antennas,


connected to two sectors antennas via
1.2m RF cable

New Outdoor cabinet including:


- 110V A.C 60Watt with outlets at least 4 ports
- 4 ports switch
Cabinet height 1.5m

Figure 3.4 - System installation elements at the pole

05
Mexico City Police
Mobility Communication System
POC Design & Description
Ver. 2.1 11 November 2013

 Figure 3.4-A is describing the construction for the elements.

Figure 3.4 –A – Elements construction description at the pole

06
Mexico City Police
Mobility Communication System
POC Design & Description
Ver. 2.1 11 November 2013

 Figure 3.4 – B describe the pole that MEI need to supply and install for the PTP Radio
link

Position of the
antenna 1" to 2"

1÷2 meter
Position of the
ODU Radio
Pole need to supply
and install

Existing Pole

Figure 3.4 –B: Pole for the PTP radio link

 Figure 3.4 – C describe the T pole that MEI need to supply and install for the Mobility
Radio link, need TWO T poles.

1" to 2"

Connect to the
existing pole

Position of the
20 cm ODU Radio

80 cm

Figure 3.4 –C: T Pole for the Mobility radio

07
Mexico City Police
Mobility Communication System
POC Design & Description
Ver. 2.1 11 November 2013

 Figure 3.4 – D, describe the outdoor cabinet that MEI need to supply and install at the
existing pole Base Station.

50 cm

30 cm

Shelf for the 3 * POE's


4 outlets power supply
of the power 110V A.C

40 cm

POE

3 holes for the Cat5-e


cable with RJ-45
connector.
One cable for each POE
Hole for the power
110V A.C Switch with power supply
from 110V A.C
1.5 cm

The cabinet shall include a door at the front and shall be installed at the pole.

Figure 3.4 –D: Outdoor cabinet

08
Mexico City Police
Mobility Communication System
POC Design & Description
Ver. 2.1 11 November 2013

3.5 Installation Activities and responsibility

 Table 3.5 describes all the activities for system installation and each responsibility.
 The installation shall start at 25/11/2013, Monday morning from 8:00 AM.
 MEI shall provide at least two teams at this day, One shall install all the elements at
the Base Station and the second will be install the elements at the police station, after
finishing all the installation the PTP alignments shall done with the two teams.
 The two teams need to climb to the poles at the Base Station and the tower at the
police station.
 For the installation at the Base station pole, EMI need to bring a basket crane of at
least 15m height.
 Bynet engineers (Asher and Shmuel) shall advise and check the installation
connection.

Description Responsibility
Equipment including cable supply RAD Mexico
Construction supply and installation MEI
Installation advise along all the installation Bynet
Installation check Bynet
Elements Configuration Bynet
System Operation Bynet
System Test Bynet
Supply an 15m basket crane at the Base Station road for
elements installation at the pole MEI
All the elements installation according to Bynet engineer
advise MEI
Supply pole of 2m (1" up to 2") for the extension to the
PTP radio link (including antenna and HBS radio),
describe at figure 3.4 - B MEI
Supply two units of T pole for the HBS and two sector
antennas, need TWO T pols, describe at figure 3.4-C MEI
Supply and install the outdoor cabinet to the pole,
describe at figure 3.4-D, including the power 110V A.C
outlets, shelf etc. MEI
Supply power supply of 110V A.C inside the cabinet. MEI
PTP radio link alignments to the Police station MEI

Table 3.5: Installation Activities and responsibility

09
Mexico City Police
Mobility Communication System
POC Design & Description
Ver. 2.1 11 November 2013

4. Camera Road Site

4.1 Camera road site Position

 Figure 4.1 describes the position of the camera site on a map.

Base Station Position


Coordinates:

Figure 4.1 – Camera road site position at the map


 The distance of the camera site to the Base Station is 1.4Km.

21
Mexico City Police
Mobility Communication System
POC Design & Description
Ver. 2.1 11 November 2013

4.2 System Description

 Figure 4.2 is describing the System elements at the Base Station.

Pole

110V A.C 110V A.C


Outdoor cabinet

Cross Eth. cable

Figure 4.2: System Description

20
Mexico City Police
Mobility Communication System
POC Design & Description
Ver. 2.1 11 November 2013

4.3 Installation Description

 Figure 4.3 is describing the System elements at the pole.

1m

Concrete cube

Figure 4.3: System Description

22
Mexico City Police
Mobility Communication System
POC Design & Description
Ver. 2.1 11 November 2013

 Figure 4.3-A is describing the pole.

1" to 2"

At least 3m

Figure 4.3-A: pole Description

23
Mexico City Police
Mobility Communication System
POC Design & Description
Ver. 2.1 11 November 2013

 Figure 4.3 – B, describe the outdoor cabinet that MEI needs to supply and install at
the pole.

4 outlets power supply


of the power 110V A.C

30 cm Shelf for the 3 * POE's

30 cm

20 cm

POE

2 holes for the Cat5-e


cable with RJ-45
connector.
One cable for each POE
Hole for the power
110V A.C

1.5 cm

The cabinet shall include a door at the front and shall be installed at the pole.

Figure 4.3 –B: Outdoor cabinet

24
Mexico City Police
Mobility Communication System
POC Design & Description
Ver. 2.1 11 November 2013

4.4 Installation Activities and Responsibility

 Table 4.4 describes all the activities for system installation and each responsibility.
 The installation shall start at 25/11/2013, Monday after finishing the Base Station
installation.
 The team of that work at the Police Station shall install this site after finishing
installation at the police station.
 For the installation at the Base station pole, EMI need to bring a ladder of 3m.
 Bynet engineers (Asher and Shmuel) shall advise and check the installation
connection.

Description Responsibility
Equipment including cable supply RAD Mexico
Construction supply and installation MEI
Installation advise along all the installation Bynet
Installation check Bynet
Elements Configuration Bynet
System Operation Bynet
System Test Bynet
Supply an 3m ladder at the site for elements installation
at the pole MEI
All the elements installation according to Bynet engineer
advise MEI
Supply the construction according to figure 4.3-A. MEI
Supply and install the outdoor cabinet to the pole,
describe at figure 4.3-B, including the power 110V A.C
outlets, shelf etc. MEI
Supply power supply of 110V A.C inside the cabinet. MEI

Table 4.4: Installation Activities and responsibility

25
Mexico City Police
Mobility Communication System
POC Design & Description
Ver. 2.1 11 November 2013

5. CCO - Police Station System Description

5.1 System Description

 The Police Station shall be the place for the customer people
demonstration, the Base Station is connected to the Police station via a
Point to Point radio link from the Base Station pole.
 The Point to point
 Figure 5.1 is describing the System at the Police Station.

Dual Polarization
antenna

To Base Station
ODU Radio

Indoor POE

110V A.C

LCD
110V A.C 110V A.C

Figure 5.1: System description at the Police Station

26
Mexico City Police
Mobility Communication System
POC Design & Description
Ver. 2.1 11 November 2013

5.2 Installation Description

 Figure 5.2 is describing the System elements installation at the pole.


 The antenna and the radio shall be installed at the top of the pole according to the
azimuth describe at figure 5.2.

Antenna Azimuth

Outdoor 100m Cat-5e


cable from the ODU
radio to the Indoor POE
at the demonstration
room

Figure 5.2: System elements installation at the pole

27
Mexico City Police
Mobility Communication System
POC Design & Description
Ver. 2.1 11 November 2013

 The antenna and the ODU radio shall install with the mounting (supply with the
antenna) to the pole, the pole is up to 2".

1" to 2"

ODU Radio Installation description

+ =

28
Mexico City Police
Mobility Communication System
POC Design & Description
Ver. 2.1 11 November 2013

5.3 Installation Activities and responsibility

 Table 5.3 describes all the activities for system installation and each responsibility.
 The installation shall start at 25/11/2013, Monday at parallel with the Base Station
Installation.

Description Responsibility
Equipment including cable supply RAD Mexico
Construction supply and installation MEI
All elements and cables Installation, Including Cat-5e
(supply 100m with the equipment) cable from the ODU
Radio to the demonstration room inside the Police Station. MEI
Elements Configuration Bynet
System Operation Bynet
System Test Bynet
Organize a room for demonstration MEI
Supply and install an a LCD for demonstration with a
MEI
cable for a laptop
110V A.C (at least 3 outlets) for power the following
MEI
elements: POE, Laptop, and LCD).
Supply a computer with the following requirements:
 Demo-VMS currently works on Windows based PCs
only (both x86 and 64 bit versions).
 Demo-VMS has been tested on Windows XP, Windows
Vista, Windows 7 and Windows 8 but may work on
other Windows variants that support the .Net
Framework v4 client.

Table 5.3: Installation Activities and responsibility

29
Mexico City Police
Mobility Communication System
POC Design & Description
Ver. 2.1 11 November 2013

6. Vehicle System Description

6.1 System Description

 All the equipment shall be installed at one (1) cabinet box which shall be
placed at the roof of the vehicle.
 Figure 6.1 is describing the System police vehicle.

HMU
RF cable
RF cable

Cat5e cable

12V D.C

12V D.C

12V D.C

Figure 6.1: System at the police vehicle

31
Mexico City Police
Mobility Communication System
POC Design & Description
Ver. 2.1 11 November 2013

6.2 Car Kit description

 Figure 6.2 is describing the Car Kit.


 The box shall be installed at the vehicle roof with 4 magnets, so it shall
not need any special construction.

Omni Omni
Antenna Box Antenna

50 cm

36 cm
50 cm

20 cm

16 cm
16 cm

Video
Camera

4 Magnets
Omni
Antenna

Figure 6.2: System for Test Vehicle

30
Mexico City Police
Mobility Communication System
POC Design & Description
Ver. 2.1 11 November 2013

Omni
Antenna

HMU
Radio

Video
Camera
POE

12 V D.C
Switch Power In

Figure 6.2—A: System for Test Vehicle-Inside View

Ethernet

12V D.C
Power IN

Magnets
Magnet
s

Figure 6.2—C: System for Test Vehicle – Bottom View

32
Mexico City Police
Mobility Communication System
POC Design & Description
Ver. 2.1 11 November 2013

Omni
Antenna

HMU
Radio

POE

12 V D.C
Power In

Switch
Ethernet
cable
Video
Camera

Power cable
connected to the
Lighter socket

Figure 6.2—D: Place of installation at the Police vehicle roof

33
Mexico City Police
Mobility Communication System
POC Design & Description
Ver. 2.1 11 November 2013

34
Mexico City Police
Mobility Communication System
POC Design & Description
Ver. 2.1 11 November 2013

Figure 6.2—D: Place of installation at the Police vehicle roof

35
Mexico City Police
Mobility Communication System
POC Design & Description
Ver. 2.1 11 November 2013

6.3 Installation Activities and responsibility

 Table 5.3 describes all the activities for system installation and each responsibility.
 The installation shall start at 25/11/2013, Monday.

Description Responsibility
Car kit and equipment including cable supply RAD Mexico
All elements and cables Installation MEI and Bynet
Elements Configuration Bynet
System Operation Bynet
System Test Bynet
Supply a vehicle for demonstration and drive the vehicle
along all the test and demonstration. MEI

Table 5.3: Installation Activities and responsibility

36
Mexico City Police
Mobility Communication System
POC Design & Description
Ver. 2.1 11 November 2013

7. POC Test Description

 Table 7 describes the entire scenarios and tests at the POC.

The purpose of the POC trail is to test Mobility Wireless System specifications
including Capacity Vs. Range Vs. Speed with One Base Station consist of Two HBS
Radio Units
- One Base Station including Two HBS radio connecting back to back configuration
- One Vehicle driving along the coverage area map
- Application - Video from the Vehicle to the BS
- Testing Points: at the Vehicle and the second point shall be at the BS near the Pole
Scenario unless there are a networking connectivity from the Pole to the CCO/Building
Description Vehicle Speed: Vehicle shall be driving along the coverage Road with a different
speeds maximum 200 [Km/h] and sending a video from the local existing camera at
the Vehicle to the BS point test, the vehicle shall drive at both directions of the road
System Coverage Range: The vehicle shall drive in both directions of the road until
the wireless connectivity disconnect to test the maximum coverage area of the wireless
system - WITH LOS CONDITION ONLY
System Capacity: The vehicle shall be driving inside the coverage road area and
shall test the maximum capacity and characteristics of the wireless system.
Test Description Results

Capacity Data rate According to table 2


Coverage area
Total of 5 [Km]; 2.5 [Km] from each side of the BS according to LOS Condition
Range
Vehicle Speed Wireless System Connectivity to up 200 [Km/h] and/or allowed speed on the road
Hand Over Speed According to table 2
Transmitting a video picture from vehicle camera (roof, on the car kit) to the CCO
while driving at the coverage are at the two side of the road
Video Transmitting a video picture from camera site (at the road) to the vehicle while driving
at the coverage are at the two side of the road
Transmitting a video picture from camera site (at the road) to the CCO
Table 7: Test description at the POC

37
Mexico City Police
Mobility Communication System
POC Design & Description

Ver. 2.0 10/11/2013

8. POC Schedule

 Table 8 describes the schedule for the POC.

Date Day Hours Description


Arrival to Mexico City
24/11/2013 Sunday 18:45 Landing at 18:45 flight No. Lufthansa
LH 0498
00:00 – 3:00 Metro site survey
25/11/2013 Monday
08:00 ÷ 18:00 System installation:
 Vehicle
 Base Station
26/11/2013 Tuesday 08:00 ÷ 18:00  Road camera
 Police station
27/11/2013 Wednesday 08:00 ÷ 18:00 System configuration and pretesting
28/11/2013 Thursday 08:00 ÷ 18:00 Customer Demonstration
Customer Demonstration and System
29/11/2013 Friday 08:00 ÷ Finish
Uninstall
30/11/2013 Saturday 9:00 Flight back

Table 8: Schedule for the POC