You are on page 1of 9

Evaluation, Rehabilitation Planning, and Stay-Cable

Replacement Design for the Hale Boggs Bridge


in Luling, Louisiana
Armin B. Mehrabi, M.ASCE1; Christopher A. Ligozio, P.E.2; Adrian T. Ciolko3; and Scott T. Wyatt4
Downloaded from ascelibrary.org by George Washington University on 02/22/15. Copyright ASCE. For personal use only; all rights reserved.

Abstract: The Hale Boggs Bridge opened to traffic on October 5, 1983. At the time, it was the first U.S. cable-stayed crossing over the
Mississippi River. The PE 共polyethylene兲 protective sheathing was damaged in many of the cables before and during installation, and after
the opening of the bridge to traffic. Repairs were attempted to correct the defects in cable sheathing. Many of the repairs performed poorly
and failed to protect the main tension element. The condition of 39 out of 72 cables indicated a critical need for repair and timely action
was recommended. To address these damages, and to assure the structural integrity of the bridge structure, several strategies involving a
range of repair and replacement options were evaluated using life cycle cost analysis. It was concluded that the strategy to replace all
cables presents the best value among evaluated alternatives. The design of the complete 72 cable array replacement is the first occasion
on which this process is attempted in North America. The final design of the replacement cables is heavily influenced by the geometric
restrictions of the existing anchorage locations. The replacement cables are being designed for a 75-year design life and incorporated with
the latest advancements in corrosion protection and vibration control. Maintenance of traffic design is an essential part of the project. The
bridge is a critical regional link and constitutes a hurricane evacuation route. Traffic maintenance during cable replacement was designed
to be as unobtrusive to the public and commerce as practical. This paper describes efforts associated with cable condition assessment,
rehabilitation strategy, and design considerations and concepts, undertaken by the writers since 2002 to improve the condition of this
major river crossing.
DOI: 10.1061/共ASCE兲BE.1943-5592.0000061
CE Database subject headings: Bridge, cable-stayed; Replacement; Louisiana; Polyethylene; Grouting; Rehabilitation; Durability;
Nondestructive tests; Corrosion; Life cycles.
Author keywords: Stay cable; Cable stayed bridge; Cable replacement design.

Introduction struction of this bridge. The original stay cables are comprised of
an uncoated parallel wire cable with bond socket, button head-
The Hale Boggs Bridge, also known as the Luling Bridge, in style anchorages. The corrosion protection system is composed of
Luling, La. opened to traffic in 1983. At the time, it was the first high-density polyethylene sheathing filled with cementitious
cable-stayed bridge over the Mississippi River and had several grout, which was pressure injected, following cable erection on
unique features, including a weathering steel superstructure, dis- the superstructure. The most significant problems with the stay
tinguishing it from all other cable-stayed bridges in North cables were those associated with defects and damage to the pro-
America. tective high-density polyethylene 共PE兲 sheathing of the main ten-
After 25 years in service—years that encompassed frequent sion elements 共MTEs兲 of these prefabricated stay cables. On the
repairs to the cables, protective sheathing, and anchorage Luling Bridge, the protective sheathing for the cables was dam-
components—the Hale Boggs Bridge will need to undergo com- aged before and during installation, and deterioration of this im-
plete replacement of its stay-cable system. The potential for portant cable corrosion protection element continued after the
stay-cable durability performance problems arose during the con- bridge opened to traffic. Today, stay cables are commonly ex-
pected to attain a design life of 50 years or more, in contrast to the
1
Project Consultant and President, Bridge Engineering Solutions, PC,
25-year cable service life attained in this instance.
P.O. Box 1565, Lewiston, NY 14092. Twenty-one cables required the repair of PE pipe cracking
2
Senior Structural Engineer, CTLGroup, 5400 Old Orchard Rd., before and during cable erection. Although analysis and docu-
Skokie, IL 60077. mentation of the root cause of early pipe cracking is lacking in the
3
Principal in Charge and Senior Principal Engineer, CTLGroup, 5400 literature, it is likely that the pipe splits and cracks were associ-
Old Orchard Rd., Skokie, IL 60077 共corresponding author兲. ated with sustained stress and deformation during extended stor-
4
Senior Structural Engineer, CTLGroup, 5400 Old Orchard Rd., age of the prefabricated, ungrouted, sheathed cables on reels.
Skokie, IL 60077. Many of these 21 early repairs failed during pressure grouting,
Note. This manuscript was submitted on October 1, 2008; approved
and the repairs were repeated in place. In April 1985, more cracks
on July 20, 2009; published online on June 15, 2010. Discussion period
open until December 1, 2010; separate discussions must be submitted for were detected in two backstay cables’ protective sheathing. The
individual papers. This paper is part of the Journal of Bridge Engineer- cable manufacturer electrowelded the cracks in November of that
ing, Vol. 15, No. 4, July 1, 2010. ©ASCE, ISSN 1084-0702/2010/4-364– year. Later, cracks developed in these PE weld repairs. In the
372/$25.00. winter of 1985, new cracks were detected in three other cables. In

364 / JOURNAL OF BRIDGE ENGINEERING © ASCE / JULY/AUGUST 2010

J. Bridge Eng. 2010.15:364-372.


Downloaded from ascelibrary.org by George Washington University on 02/22/15. Copyright ASCE. For personal use only; all rights reserved.

Fig. 1. Elevation of the Luling Bridge 共photo courtesy of LADOTD兲

Fig. 2. Luling Bridge during construction 共photo courtesy of


LADOTD兲

1990, after 7 years of service, all cables were wrapped with a


white-color ultraviolet protection 共Tedlar兲 tape after existing splits Recent Inspection and Condition Assessment
and cracks were filled with epoxy. The ultraviolet protective tape
installation was intended to impede ultraviolet-induced PE mate- In 2002, LADOTD authorized the initiation of a detailed condi-
rial deterioration and reduce temperature fluctuations in the origi- tion assessment and rehabilitation study of Luling Bridge stay-
nal black-color PE which could also contribute to the rate of cable cable array. The department’s vision was to assess cable array
deterioration. condition and project future maintenance and rehabilitation needs
The first evidence of damage to the ultraviolet protective tape and costs. The state of art in cable condition assessment technol-
was detected in 1995. Subsequent inspections showed the exis- ogy and improvements in stay-cable design, materials, and fabri-
tence of exposed and rusted stay-cable wires, uncapped grout cation had changed dramatically since the bridge was designed in
ports, and extensive water leakage, cementitious grout efflores- the 1970s, during the infancy of cable-stayed bridge construction
cence, and presence of corrosion within the deck-level anchorage in North America. The department was motivated to extract the
sockets. Despite these inspection and repair efforts through the fullest potential service life possible for its valuable infrastructure
1980s and 1990s, the stay cables’ corrosion protection system was asset, taking advantage of stay-cable engineering innovations.
ineffective and continued to provide inadequate corrosion protec- The overall evaluation and rehabilitation program was divided
tion, permitting wire corrosion to occur and water to intrude into into three phases. Phase I of the evaluation program had the ob-
the anchorages. The Louisiana Department of Transportation De- jectives of assessing the extent of reported problems with the
velopment 共LADOTD兲 sought a long-term solution that would MTEs and ascertaining the overall integrity of stay cable array.
minimize the need for costly, difficult to forecast cable mainte- Phase II of the investigation, completed in 2006, consisted of
nance and repair, and preserve and potentially extend the bridge hands-on inspection of the suspect locations and critical elements
service life. including stay cables, anchorages and their vicinity, and condition
rating of the cables. Phase III, and an ongoing program that began
in 2007, includes the design of the repairs and cable replacement.
Bridge Description
Phase I
The Luling Bridge is a twin-pylon, cable-stayed bridge with a Phase I of the evaluation program was intended to assess and
main span of 372 m and two stayed side spans of 151 and 155 m. categorize the cable condition, select techniques to assess the ex-
The bridge crosses the Mississippi River at Luling, La. and car- tent of problems in the stay cables and their MTE, and to ascer-
ries four lanes of Interstate 310 traffic. Fig. 1 shows an elevation tain the overall integrity of the stay-cable array. This initiating
of the bridge. The pylons are a modified A-shape, and the deck phase of the investigation included:
cross section is composed of twin 4.3-m-deep steel trapezoidal • A review of bridge details and prior bridge evaluations and
box girders with a total width of 25.1 m, all made of weathering investigations;
steel. • Laser-based cable force and damping measurements and geo-
The stay cables are arranged in two planes and are grouped by metric survey; and
pairs or fours. There are 24 such cable groupings and a total of 72 • Representative cable and anchorage inspection and sheathing
cables. Stay cables are composed of parallel 6.4-mm diameter dissection.
wire bundles consisting of 103, 211, 271, or 307 wires. The wire The cable force measurement and analysis showed no evi-
bundle is encased within a black polyethylene 共PE兲 pipe, and the dence that stay cables had suffered significant structural damage
space among wires is grouted. An ultraviolet protection tape is to date; nevertheless, cable durability was a significant concern.
helically wound around the PE pipe with 50% overlap. Fig. 2 Inspection of deck-level anchorages showed signs of corrosion
shows the bridge during construction, highlighting superstructure and presence of moisture in cable anchorages, and ingress and
configuration. accumulation of water inside the sockets. Inspection of selected

JOURNAL OF BRIDGE ENGINEERING © ASCE / JULY/AUGUST 2010 / 365

J. Bridge Eng. 2010.15:364-372.


rate of approximately 50 ft/min. The buggy rides along the cables
on large diameter rollers. A motorized traction wheel design had
been rejected early in the design phase, since it would potentially
damage the cables’ ultraviolet protection tape.

Inspection Procedures
The inspection began in April 2006, and with 8.9 km of cable to
ride, was expected to take 12 weeks to complete. Two inspectors
rode in the hoist, observing, hammer-sounding and digital tap
testing the cable cover pipe and ultraviolet protection tape to lo-
cate the damage. Infrared thermography was used selectively to
detect open splits in the PE cover pipes beneath the ultraviolet
Downloaded from ascelibrary.org by George Washington University on 02/22/15. Copyright ASCE. For personal use only; all rights reserved.

protection tape, as well as potential voided zones in cementitious


grout.
Detailed examinations of the MTE 共steel wire兲 condition were
made where wires were exposed by defects and deterioration in
Fig. 3. Inspection buggy in use the protective elements. As the inspection progressed, the inspec-
tion teams carefully recorded observations. Cable diameter was
verified periodically and wherever an unusual change appearing
cable surfaces revealed the ineffective repair of cover pipes, in the cross section of the cable sheathing was visible. A laser
which had originally split during the grouting process, creating distance-meter was used to measure the locations of key features
the potential exposure of steel wires to the environment. from either the upper or lower cable exit points. Thanks largely to
Further, structural evaluation and cable damping mea- good weather, the inspection was completed in 9 weeks.
surements revealed that most of the cables possessed low Additionally, cable anchorages were inspected. Anchorage in-
damping capability and were susceptible to wind-induced vi- spection included visual examination of the bearing plates, shim
brations, potentially introducing repetitive bending stresses near plates, and the exterior of the anchorage sockets. End caps were
anchorages—impairing the cables’ fatigue endurance. It became opened to observe the condition of the wire button heads and
apparent that categorizing and studying stay cable arrays’ long- interior of the socket. Each cable, immediately above the anchor-
term durability and maintenance needs and costs would require a age, passes through an anchorage box within the cross girder. The
more detailed inspection protocol and methods to assess the ex- cables were not accessible for direct visual inspection in this re-
tent of cable damage. gion. To gain access to the cables, the neoprene washers at the
exit points had to be removed and the inspection was performed
Phase II using a videoscope.
In 2004, Phase II commenced with planning and development of
a comprehensive cable condition analysis approach methodology. Inspection Observations
Technology was needed for identifying hidden cable damage and The damage observed in the anchorage zones mainly comprised
for accessing the stay cables for their full length. corrosion of sockets and button heads, missing or broken seals at
A range of nondestructive testing 共NDT兲 techniques capable of the joint between the transition pipe and PE pipe, and uncapped
detecting flaws in materials and assemblies were sought to aug- grout ports. With time, precipitation found its way into the an-
ment visual inspection. Full-scale mockups of stay cables with chorage boxes through gaps in and around neoprene washers at
intentionally inflicted PE flaws in the form of splits, with and the cable exit points, and collected behind the bearing plates.
without epoxy repair, and wrapped with ultraviolet protective Broken seals and ports also allowed water to accumulate within
tape, were fabricated. Candidate NDT methods offered advan- the cable in the transition zone and inside the sockets. Because of
tages and disadvantages, in terms of effectiveness, efficiency, poor access, detailed assessment of corrosion and cross-sectional
adaptability to field conditions, and cost 共Ligozio and Mehrabi area loss of wires inside the socket and in the transition zones
2005兲. could not be performed. Hence, there remained uncertainty re-
The second challenge confronting the Phase II condition as- garding the condition of the MTEs in these areas. Details of this
sessment was an efficient, safe access for inspectors over the en-
investigation can be found in Mehrabi and Ligozio 共2007兲 and
tire length of the cables. It was quickly determined that the best
Mehrabi et al. 共2006兲.
approach would be to use a manned inspection vehicle that crawls
Inspection of the free length discovered a variety of damage
along the stay cables. The design and fabrication of the inspection
vehicle required considerable time added to the cost of inspection. conditions in the cable free length. These included:
However, this approach offered significant benefits such as thor- • Longitudinal and transverse splits in the PE pipe, some cov-
oughness of inspection, improved safety and comfort for inspec- ered by ultraviolet protection tape and some not 共see Fig. 4兲;
tors, reusability of the vehicle for future bridge inspections, and • Bulges and holes in the PE;
minimal user and environmental impact especially for the mini- • Burst and damaged tape 共see Fig. 5兲, exposure and
mal interruption to traffic. The inspection buggy is shown in use degradation/corrosion of grout filler and steel wires 共see
during an inspection in Fig. 3. The buggy was custom fabricated Fig. 6兲;
of aluminum for weight savings and is configured for the bridge’s • PE joint separations and failure of previous repairs;
specific cable geometry. It is propelled along the cable groups via • Grout voids and delamination; and
a wire rope, by an electric winch motor attached to the tower, at a • Damage to ultraviolet protection tape 共see Fig. 7兲.

366 / JOURNAL OF BRIDGE ENGINEERING © ASCE / JULY/AUGUST 2010

J. Bridge Eng. 2010.15:364-372.


Downloaded from ascelibrary.org by George Washington University on 02/22/15. Copyright ASCE. For personal use only; all rights reserved.

Fig. 4. PE pipe split; the ultraviolet protection tape is missing Fig. 7. Separation of PE transverse joints

Cable Condition Rating


Three levels of damage severity were established for cable con-
dition rating; Level 1 or satisfactory, Level 2 or poor, and Level 3
or critical. These condition ratings were intended to semiquanti-
tatively reflect the cables’ future durability for rehabilitation plan-
ning. Table 1 describes these severity levels in general terms.
The severity levels were assigned to the observed condition of
the corrosion protection barrier elements, namely, the ultraviolet
protection tape, the PE pipe, and the cement grout, and their abil-
ity to protect the MTE, the condition of the steel wires in the
anchorage zones—based on conditions observed within the an-
chorage sockets, and the need for action or repair.
Condition Level 1 encompassed cables with sound and well-
functioning prior repairs, in the form of welding or epoxy fillers.
Normal aging and weathering of ultraviolet protection tape, minor
delamination of PE from grout filler, and light rust inside the
anchorage sockets and on wire button heads fell into this cat-
egory. Level 1 anomalies were those that would not require any
immediate corrective action; future repairs would be warranted
Fig. 5. Burst and damaged protective tape when future inspections revealed increasing deterioration rates.
Condition Level 2 included ultraviolet protection tape damage
and nicks, grout voids, repair sleeves, PE bulges, major tape
wrinkles, and moderate corrosion inside the anchorage sockets. At
a minimum, locations with this level of damage severity needed
to be monitored routinely and a plan for repair/correction should
be developed for implementation in the near future.

Table 1. Damage Severity Levels


Severity
level Status Description
1 Satisfactory Minor deterioration and anomalies with
little or no likely impact on protection.
2 Poor Deterioration of the protective elements
and potential for their further degradation.
Cables with this level of damages need to
be routinely monitored and corrective
action needs to be planned.
3 Critical Deterioration or potential for deterioration
of the MTEs 共steel wires兲. Action 共repair兲
is necessary. Cables with this level of
Fig. 6. PE sheathing split, not providing protection, and wire is cor- damages shall be closely monitored until
roded repairs are applied.

JOURNAL OF BRIDGE ENGINEERING © ASCE / JULY/AUGUST 2010 / 367

J. Bridge Eng. 2010.15:364-372.


Condition Level 3 encompassed ineffectively repaired and un-
repaired PE splits, holes in PE pipes, exposed grout and wires,
transverse PE joint cracks and separations, and heavy rust inside
the anchorage sockets and on wire button heads. This level of
damage severity necessitates near-immediate repair and close
monitoring until repairs are implemented.
Using the cable condition rating system, condition rating fac-
tors for each cable were established, based on damage accumu-
lated along the free length of cables and within anchorages. Any
cable containing at least one indicator of Level 3 critical damage
was automatically rated with Severity Level 3. All cables, without
exception, contained at least one form of damage or anomalies
Downloaded from ascelibrary.org by George Washington University on 02/22/15. Copyright ASCE. For personal use only; all rights reserved.

with a severity level of 2. There were 39 out of 72 cables that had


been rated as being in critical condition 共Level 3兲, and the remain-
ing 33 cables were rated as being in Poor Condition 共Level 2兲. Fig. 8. Cost comparison among various repair strategies

Rehabilitation Strategies and Cost Study


LCCA
The selection of the most appropriate course of action for bridge
service life extension was based on economic and technical/ A LCCA was performed for the selected strategies over a 75-year
operational factors. To compare and provide guidance for main- planning horizon 共Mehrabi 2007兲. For present value calculations,
tenance and rehabilitation decisions, five repair scenarios, a real discount rate of 3.8% was assumed reflecting a nominal rate
representing a wide range of repair estimates derived for correct- of 5% and inflation rate for the overall economy of 1.2%.
ing defects and damage to the stay cable array noted during the The costs associated with the various options were divided
condition assessment, were studied in a life cycle cost analysis into three groups; initial, distributed/periodic, and vulnerability
costs. The initial costs are related to the installation of a cable
共LCCA兲:
monitoring system, repair, or replacement of cables that will
1. Base Case—Minimal repair to protect exposed wires along
occur one year after project begins. Distributed/periodic costs are
the free length of the cables. Includes monitoring and inspec-
related to inspection, cable force measurement, maintenance of
tion regimen prescribed for Levels 3 and 2 damages; this the monitoring system, and future periodic repairs. Vulnerability
strategy is the highest potential for cable accelerated degra- costs are related to the potential repair/replacement of cables and
dation and failure and the highest vulnerability to storm re- structural repair to the bridge superstructure due to loss of load-
lated damage. carrying capacity of the cables from ongoing corrosion-fatigue
2. Repair All—Repair free length of all cables, clean corroded and extraordinary storm events 共hurricanes兲.
sockets, and provide drainage for anchorage boxes. Includes Costs in each category were assigned two components, agency
monitoring and inspection regimen prescribed for Level 2 cost and users’ cost. Agency cost refers to the actual cost of
damages. New repairs were assumed to be necessary every implementing an event such as contract cost for repair or inspec-
20 years. This strategy represented moderate potential for tion. Users’ cost refers to cost borne by the users of the bridge,
cable failure and moderate vulnerability to storm related i.e., drivers and cars/trucks, for delays or detours related to activi-
damage. ties on the bridge.
3. Repair-Replace Option 1—Replace 20 cables; 13 cables with
anchorage Severity Level 3 and seven cables with most ex- Results of Cost Analyses
tensive Severity Level 3 damages, repair remaining 19 cables
with Severity Level 3, and all Level 2 cables. Includes moni- The first-pass LCCA indicated that the Base Case presents the
toring and inspection regimen prescribed for Level 2 dam- lowest cost 共$0.7 million兲, while the Replace All scenario re-
ages for the repaired cables. New repairs were assumed to be flected the highest potential cost 共$16 million兲 when only initial
needed every 20 years. Low to moderate potential for cable agency costs are considered. The costs of other strategies incre-
ment almost linearly between these two extremes in the order
failure and low to moderate vulnerability to storm related
described above.
damage is anticipated.
When distributed, periodic, and vulnerability agency costs
4. Repair-Replace Option 2— Replace all 39 cables with Sever-
were added, the cost for the Base Case 共$17.5 million兲 became
ity Level 3 and repair all cables with Severity Level 2. In- costliest. In this case, the Repair All strategy results in the lowest
cludes monitoring and inspection regimen prescribed for total cost 共$12.7 million兲 when only agency costs are accounted
Level 2 damages for the repaired cables. New repairs are for. Last, with the users’ costs added, all four strategies involving
assumed to be needed every 20 years. Low potential for repair and replacement compete closely 共around $20 million兲
cable failure and low vulnerability to storm related damage is while the cost for the Base Case 共$35 million兲 is significantly
expected. higher than others. Fig. 8 shows a comparison of costs when all
5. Replace All—Replace all cables. No potential for cable fail- users’ and agency costs are included.
ure and no added vulnerability to storm related damage for In accordance with the economic efficiency theory, a strategy
the bridge structure. Visual inspection will be prescribed only with the lowest present value should be selected as the preferred
once every 20 years and force measurement every five years. strategy. If this rule were to be followed, the Repair All strategy

368 / JOURNAL OF BRIDGE ENGINEERING © ASCE / JULY/AUGUST 2010

J. Bridge Eng. 2010.15:364-372.


should be adopted when only agency costs are considered, and the vertical geometry constraints, and superstructure drainage consid-
Replace All strategy should be selected when agency and users’ erations. Hence, a complete survey of the bridge superstructure
cost are both considered. was performed to establish the current state.
However, taking into account uncertainties and approxima-
tions affecting cost estimates and the sensitivity of present values
to variations of costs and discount rate, such a determination can- Replacement Cable Design
not be made with comfortable certainty. The only strategy that
Parameters considered in identifying candidate cable systems in-
can be ruled out with certainty is the Base Case. The total cost of
cluded adaptability to existing openings, passages, and anchorage
this strategy was considerably higher when compared to the low-
zones, accommodation of erection process related to available
est cost strategy.
spaces near anchorage areas, durability issues and past perfor-
Furthermore, it was recognized that cost efficiency may not be
mance, corrosion protection requirements, ease of future inspec-
the only parameter to be considered in a decision making process.
tion and repair, availability of material and sources in the United
Downloaded from ascelibrary.org by George Washington University on 02/22/15. Copyright ASCE. For personal use only; all rights reserved.

The location of a bridge structure in a highway transportation


States, and cost. There exists two stay systems deemed suitable
network is one parameter that might significantly influence the
for replacing the stays at the Luling crossing; parallel wire and
decision making. The LCCA of a bridge isolated from the re-
parallel strand systems.
gional highway system, though effective and useful, cannot in-
Since 1990, the parallel strand cable has been far more preva-
clude or quantify all contributing cost aspects. The LCCA results
lent for medium length cable-stayed bridges. Presently, strands
were evaluated in conjunction with network or system strategic
are individually greased and sheathed, providing individual cor-
considerations. Another intangible but crucial parameter not con-
rosion protection, and a wedge retention system that allows for
sidered here is the public safety concern, especially in cases of
individual strand installation and replacement has been widely
emergencies related to evacuations caused by natural disasters
adopted. For its several advantages, this system was selected for
known to the region. Bridge closure and traffic limitations neces-
sitated by the unpredictable need for repairs to deterioration the Luling Bridge cable replacement design.
cables, for example, may have consequences above and beyond Structurally, the stiffness of seven wire strands is less than that
economically measurable factors. of the wires. The system’s principal disadvantage for replacing
It was concluded therefore that when the LCCA results are the stay cables of the Luling Bridge, however, is that the anchor-
considered along with the effect of costs not included in the ages are larger in size than those of an equivalent wire system.
analysis, anticipation of lower discount rates, and concerns re- Stay sheathing pipes are larger as well, increasing cable aerody-
lated to highway network system and public safety, the Replace namic profile and wind loads on the bridge superstructure. The
All strategy presented the best value among selected strategies. following sections of the paper discuss issues related to the incor-
The long-term benefits of replacing all cables outweigh the higher poration of a parallel strand-based system.
initial investment when compared to other strategies.
Superstructure Modifications Needed for Candidate Cables
To have the least impact on the bridge, it is believed that it is most
Phase III: Design of Cable Replacement straightforward to match the stiffness of the new cable to that of
Based on the results of the LCCA, the LADOTD elected to ex- the existing. It might be possible to reduce the cable size to an
tend the Luling Bridge service life by replacing all of the stay equivalent strength cable, but extensive modeling and analysis
cables. The project is the first to include the replacement of a will be required to verify that other parts of the bridge do not
complete new stay-cable array in North America; its goal at a become overloaded, as a result of the lower stiffness of the stay
minimum is to restore the load-carrying capacity of the bridge to cables.
its as-designed state, without detriment to the bridge structure. The degree of anchorage modification required will depend on
The project is charged with developing a complete, cost- the selected stay cable supplier’s anchorage and stay pipe dimen-
effective cable replacement scheme that bidders can implement sions. The design team evaluated the feasibility of adapting the
directly with minimal engineering. The project must be designed range of options offered by prevailing stay cable systems, ex-
to minimize the impact on traffic and “maintenance of traffic tracted from manufacturers’ published data. Review of the an-
共MOT兲” costs by maximizing the number of traffic lanes kept in chorage zone dimensions indicated that in order to allow a new
service on the bridge at all times. The cable replacement project parallel strand system to be installed, the existing anchorage
has passed the 95% design completion phase. Construction is ex- openings will be needed to be enlarged to accommodate the larger
pected to begin by the first quarter of 2009. Highlights of the strand anchorages. These alterations increase construction costs
activities related to design are discussed below. and require heightened attention during construction to prevent
damage to adjacent stay cables. Concepts were devised to avoid
enlarging the existing holes in these zones, adapting chair-like
Assessing Current Conditions and Design spacer assemblies, to create distance between the anchor plates
Requirements and the existing holes, therefore providing clearance for the steel
At a minimum, cable replacement must restore the load-carrying anchor pipe in the cable system.
capacity of the bridge. Forces in all 72 stay cables on Luling
Bridge were measured using the laser-based vibration technique. Corrosion Protection Requirements
These new results were compared to estimated forces from mea- The stay cable is required to safely withstand constant tensile
surements performed in 2002, and the final dead loads taken from forces resulting from superstructure dead load and fluctuating live
the table of cable loads from the record drawings. load stresses during service. The high strength MTE materials are
The target geometry to be created by the new stay cable array inherently more susceptible to corrosion and deterioration than
may not match the existing condition, and is being designed the mild steel counterparts used for concrete reinforcement and
taking into account structural capacity, serviceability, roadway structural steel fabrication.

JOURNAL OF BRIDGE ENGINEERING © ASCE / JULY/AUGUST 2010 / 369

J. Bridge Eng. 2010.15:364-372.


In North America, the stay cable design has evolved in 30 In addition, the inspection of existing cables has shown that
years from the bonded posttensioning tendon technology which damage exists in both free length and anchorage regions of
relies on metal or plastic ducts and cementitious grout/filler. It is cables. These damages generate uncertainties in the current load-
noted that the oldest seven-wire prestressing strand-based stay carrying capacities of existing cables. Temporary cables are de-
cable system in the United States is only 24 years old. Because signed for force levels determined by structural analysis and the
there exist no scientific models and durability performance data- geometry of the bridge, including wind and hurricane events, and
bases for reliably forecasting all the corrosion processes to which consist of paired, 27⫻ 15.2-mm diameter strands meeting or ex-
the MTE is susceptible, and because stay cable sheathing ob- ceeding the requirements of ASTM A416. The connection of
scures the MTE from view during periodic bridge inspection, the these cables to the superstructure at the deck level was designed
present corrosion protection philosophy for the tensile element of to be made via waler and to the tower via a temporary saddle. The
cable-stayed bridges in the United States and in Europe is to contractor will be required to provide the suggested design or
provide reliable, compatible, and permanent multilayer corrosion propose a comparable design for LADOTD approval.
Downloaded from ascelibrary.org by George Washington University on 02/22/15. Copyright ASCE. For personal use only; all rights reserved.

barriers which prevent MTE corrosion over the full length of the The temporary cable erection concept was also developed; it
cable. consists of a cable saddle on top of the tower and a spreader
Presently available corrosion barriers encompass, grease- or 共waler兲 beam at the deck anchorages. This system will require
wax-filled individual strand sheathing, individually fusion-bonded that a main span and a back span cable are replaced simulta-
epoxy coating, cementitious grout and other fillers or blocking neously so that the forces in the temporary cables are roughly
compounds, and high-density polyethylene or steel sheathing. balanced. This system has a significant advantage since it does
Sacrificial zinc coatings for strand are frequently used outside the not require that access be maintained to the top of the pylon, and
United States for stay cables are also available. The Post Tension- that all stressing operations can be completed at deck level. The
ing Institute’s 共PTI兲 Recommendations for stay cable design, test- system is designed to accommodate the range of stay cable angles
ing and installation 共2007, 5th Ed.兲 共2001, 4th Ed.兲 requires a and allows the repeated reuse of the saddle and temporary stay
minimum of two nested, qualified barriers for corrosion protec- cable.
tion of the MTE. It is noted that the PTI Cable-Stayed Bridge
Committee does not recognize the sacrificial zinc layer to be one
of those barriers. Design Task D—Design for Peripheral Bridge Elements
The transition zone between cable free length and the cable Peripheral design tasks included design of the drainage system for
anchorage, as well as the anchorage itself, also require corrosion the deck-level anchorage boxes, evaluation of deck-level surface
protection. In the transition zones of stay cables, where continu- drainage, taking into account geometry changes created by cable
ous corrosion barriers applied directly to the MTE are interrupted replacement, enhanced security/antivandalism measures for stay
along the path to the structural anchor, equivalent and compatible cables near deck level, and damping requirements for the replace-
materials are provided to maintain end-to-end protection for the ment cables.
stay cable MTE in these zones.
Security and Antivandalism
Cable Stressing Method Cable security has become an increased concern for bridge own-
Cable stressing can be performed strand-by-strand or by preload- ers, particularly since the events of September 11, 2001. In re-
ing the entire cable 共“multistrand” method兲. The strand-by-strand sponse to the increasing concern over the vulnerability of
method has many practical advantages when compared to multi- prominent transportation structures to vandalism or a terrorist at-
strand method. These include the use of single strand hydraulic tack, the Federal Highway Administration 共FHWA兲 commis-
rams that are significantly lighter, smaller, and easier to operate sioned the Blue Ribbon Panel on Bridge and Tunnel Security. The
than rams required for stressing the whole assembly. Because of culmination of their work, Recommendations for Bridge and Tun-
the unique condition of the anchorage spaces of the Luling nel Security, was published in September of 2003. This document
Bridge, it is preferable that the individual method be used for the provides a framework for assessing the risk of bridge or bridge
stressing of the new replacement cables. Detensioning of existing component in terms of importance, occurrence, and vulnerability
cables, however, will require the use of a single large ram for the to an attack. The three risk factors are assessed qualitatively to
cable, similar to that used for the original stressing of these identify a facility risk score. This score is then compared against
cables. the cost, the effectiveness, and the availability of potential miti-
gation options to determine whether counter measures are pru-
Wind Load Considerations dent. Based on the guidelines of the FHWA document,
The wind load imparted on the bridge by the cables is a direct preliminary analyses have indicated that only the free length of
function of the stay cable sheathing diameter. The existing paral- the cable above the lower end exit point near deck level would
lel wire system is compact and care was taken to ensure that the generate a risk score that necessitates the consideration of counter
replacement system’s wind profile does not overload the structure. measures. Comparison and rating among various countermeasures
A stay cable system which minimizes wind loads would be pre- studied for this design indicated that steel sleeves protecting the
ferred. cables for up to 3.05 m above the deck has the most effect in
reducing the risk.
Temporary Cable Design
Cable Damping Requirement
To protect the bridge structure from excessive force variation dur- The Phase I scope leads to the conclusion that the existing stay
ing removal of existing cables and to eliminate the potential for cables of the Luling Bridge are susceptible to wind-induced vi-
rupture of adjacent cables, temporary cables will be used to carry bration, requiring vibration suppression. Damage to seals and
the dead loads and balance the forces when existing cables are scarring of PE cover pipes at cable exit points were partly attrib-
removed. uted to the past uncontrolled vibration experiences. A vibration

370 / JOURNAL OF BRIDGE ENGINEERING © ASCE / JULY/AUGUST 2010

J. Bridge Eng. 2010.15:364-372.


study has concluded that providing a damping ratio of about 1%
for all cables will suppress vibration for rain-wind induced exci-
tation. Vibration suppression measures were designed. Internal
dampers at cable exit points were recommended. To reduce the
risk of excessive vibration and impact of cables in groups, provi-
sions for transverse cable ties were included in the new cable
design.

Anchorage Drainage
An anchorage box drainage system was designed to address the
issue of water ponding at the lower cable transition zone.
Downloaded from ascelibrary.org by George Washington University on 02/22/15. Copyright ASCE. For personal use only; all rights reserved.

MOT Design
MOT is a critical part of the cable replacement construction pro- Fig. 9. Schematic of construction sequence
cess. The Luling Bridge is a critical regional link and traffic in-
terruptions need to be as unobtrusive to the public and commerce
as is practical. Additionally, the bridge is located in a hurricane tractor to work within a smaller footprint on the bridge for the
region and is a part of hurricane evacuation route. Limitations on majority of the operations. The highline design will be the respon-
traffic control that impact evacuation capacity, including seasonal sibility of the contractor, as the contractor will have specific ca-
timing, have to be considered. pacity requirements depending on their stay system components
Several traffic control scenarios were initially identified and and preferred work methods.
studied. The overall objective of the MOT is twofold: provide
enough work area to facilitate construction and minimize lane Finite-Element Analysis of Construction Sequence
closures and impact on traffic. The selected new stay cable array installation and construction
The ideal scenario would be to maintain traffic on each side of sequence will induce force variations and deformations at the
the bridge during construction to eliminate the need for cross- cross beam ends and the tower. It was verified that the replace-
overs. This scenario will allow the ramps to remain in service ment scheme selected for this project will result in minimal
resulting minimal disruption to local traffic. After studies and changes to the distribution of loads throughout the structure. This
input from contractors, it is believed that the predominance of will be confirmed as the design progresses.
construction work can be accomplished within a 3.73-m work Nevertheless, the design of new and temporary cables and the
area, therefore leaving two lanes in each direction for traffic. This development of construction sequence are affected to varying de-
will provide a relatively narrow but workable area. If a particular grees by the process. Structural analysis is supporting the design
construction operation requires more space, then the barrier can effort, by determining the effect of these variations both locally
be moved during off-peak travel times to provide a wider work and globally.
area. As long as the maximum construction work area width re- At the local level, connections of the temporary cables to the
quirements do not exceed 7.11 m. for any operation during off- cross beam and tower and their local effects on the structure were
peak hours, then the desirable scenario is achievable. investigated. The effects of modifications to the existing structure
for accommodating replacement cable installation were analyzed
locally. Also, eccentric forces generated by cutting cables among
Construction Sequence
a group of cables were studied.
A construction procedure for the replacement activities has been At the global level, the structure as a whole was analyzed for
devised to address the cable replacement cycle process. The con- force variations resulting from installing temporary cables, re-
struction will be limited to one side of the bridge and each quarter moving existing cables, and stressing of replacement cables. The
of the bridge at a time. The sequence starts with placement of a structural analyses were also used to limit the temporary cable
saddle support on top of each leg of pylon. This will be followed stresses during various construction stages.
by the installation of a proposed highline or cableway system to
aid in the stay cable removal and installation. Fig. 9 shows a
schematic of construction process with highline, temporary Summary and Conclusions
cables, and existing cables in place.
Periodic inspections of the Luling Bridge stay cable array identi-
Highline System fied critical breaches in the cable protective sheathing and expo-
The highline system can simplify the installation of both the tem- sure of the MTE of the stay cables to corrosion, with an
porary and the permanent stay cables by supporting the stay cable increasing rate of degradation. Prior to rehabilitation design repair
pipes and reducing cable sag. It will be essential for the removal strategies were identified, and a life cycle-cost analysis was per-
of the existing stay cable. The flexibility of the stay cable is formed to assist in the maintenance decision making. Results in-
significantly less than and the weight significantly more than dicate that when all costs are considered, strategies involving
when it was installed, due to the cement grout installed after comprehensive repair or complete cable replacement compete
erection. Using the highline, the stay cable can be supported at closely, while the cost of “doing nothing” is significantly higher.
intermediate locations and lowered to the deck under controlled LADOTD elected to replace all cables. The earlier-than-expected
conditions. replacement of the stay cable array could have been avoided had
Just as important, using the highline will reduce the need to the stay cables’ external corrosion protection system and moisture
position a mobile crane on the bridge deck, and allow the con- barrier, the PE pipe, been sound and water tight.

JOURNAL OF BRIDGE ENGINEERING © ASCE / JULY/AUGUST 2010 / 371

J. Bridge Eng. 2010.15:364-372.


This cable replacement design, the first of its kind in North dinating the process and overseeing and guiding the project
America, is heavily influenced by the geometric constraint im- implementation. CTLGroup, prime consultant, was joined for this
posed by the existing structure and cost. A cost-effective construc- project by Consultant Armin Mehrabi of Bridge Engineering So-
tion sequence was developed that is expected to minimize the lutions of Lewiston, NY; International Bridge Technologies, Inc.,
impact on traffic. The construction will be limited to one side of of San Diego; and ABMB Engineers, Inc., of Baton Rouge.
the bridge at a time, allowing two lanes of traffic during peak
hours. The recommended, new parallel-strand cable system al-
lows individual strand installation, tensioning, inspection, and re- References
placement. The use of temporary cables minimizes stress
variation in the structure during cable replacement. A “highline” Ligozio, C. A., and Mehrabi, A. B. 共2005兲. “Development and verifica-
cable system is proposed to facilitate lifting and installation of tion of a NDT method for detection of flaws in PE sheathing of stay
cables, reducing the need for construction space with minimal cables.” Proc., 2005 Int. Bridge Conf., Pittsburgh.
Downloaded from ascelibrary.org by George Washington University on 02/22/15. Copyright ASCE. For personal use only; all rights reserved.

interruption to traffic. Most of the recommended bridge rehabili- Mehrabi, A. B. 共2007兲. “The Luling Bridge—Categorization of damages
tation operation will be conveniently concentrated at the deck and comparison among repair strategies.” Rep. to the Louisiana Dept.
level, where the temporary cable anchors and the live 共stressing兲 of Transportation and Development, State Project 700-45-0107, CTL-
end of existing cables and new cable are positioned. Group, Baton Rouge, La.
Mehrabi, A. B., and Ligozio, C. A. 共2007兲. “Cable-stayed bridges—
Discovering alarming distress and damages.” Proc., 2007 Int. Bridge
Conf., Engineers’ Society of Western Pennsylvania, Pittsburgh.
Acknowledgments Mehrabi, A. B., Ligozio, C. A., and Brennan, J. D. 共2006兲. “Structural
evaluation of Luling Bridge stay cable array. Phase II, Supplements 1
The work described in this paper was conducted under Louisiana and 2.” Rep. to the Louisiana Dept. of Transportation and Develop-
State Project No. 700–45-0107 and F. A. P. No. IM-4502共501兲. ment, State Project 700-45-0107, CTLGroup, Baton Rouge, La.
The writers wish to express their appreciation to the Louisiana Post-Tensioning Institute 共PTI兲. 共2007兲. Recommendations for stay cable
Department of Transportation and Development, particularly design, testing and installation, 5th Ed., Post-Tensioning Institute,
Messrs. Paul Fossier, Hossein Ghara, and Gill Gautreau for coor- Phoenix.

372 / JOURNAL OF BRIDGE ENGINEERING © ASCE / JULY/AUGUST 2010

J. Bridge Eng. 2010.15:364-372.

You might also like