Professional Documents
Culture Documents
Abstract: The Hale Boggs Bridge opened to traffic on October 5, 1983. At the time, it was the first U.S. cable-stayed crossing over the
Mississippi River. The PE 共polyethylene兲 protective sheathing was damaged in many of the cables before and during installation, and after
the opening of the bridge to traffic. Repairs were attempted to correct the defects in cable sheathing. Many of the repairs performed poorly
and failed to protect the main tension element. The condition of 39 out of 72 cables indicated a critical need for repair and timely action
was recommended. To address these damages, and to assure the structural integrity of the bridge structure, several strategies involving a
range of repair and replacement options were evaluated using life cycle cost analysis. It was concluded that the strategy to replace all
cables presents the best value among evaluated alternatives. The design of the complete 72 cable array replacement is the first occasion
on which this process is attempted in North America. The final design of the replacement cables is heavily influenced by the geometric
restrictions of the existing anchorage locations. The replacement cables are being designed for a 75-year design life and incorporated with
the latest advancements in corrosion protection and vibration control. Maintenance of traffic design is an essential part of the project. The
bridge is a critical regional link and constitutes a hurricane evacuation route. Traffic maintenance during cable replacement was designed
to be as unobtrusive to the public and commerce as practical. This paper describes efforts associated with cable condition assessment,
rehabilitation strategy, and design considerations and concepts, undertaken by the writers since 2002 to improve the condition of this
major river crossing.
DOI: 10.1061/共ASCE兲BE.1943-5592.0000061
CE Database subject headings: Bridge, cable-stayed; Replacement; Louisiana; Polyethylene; Grouting; Rehabilitation; Durability;
Nondestructive tests; Corrosion; Life cycles.
Author keywords: Stay cable; Cable stayed bridge; Cable replacement design.
Introduction struction of this bridge. The original stay cables are comprised of
an uncoated parallel wire cable with bond socket, button head-
The Hale Boggs Bridge, also known as the Luling Bridge, in style anchorages. The corrosion protection system is composed of
Luling, La. opened to traffic in 1983. At the time, it was the first high-density polyethylene sheathing filled with cementitious
cable-stayed bridge over the Mississippi River and had several grout, which was pressure injected, following cable erection on
unique features, including a weathering steel superstructure, dis- the superstructure. The most significant problems with the stay
tinguishing it from all other cable-stayed bridges in North cables were those associated with defects and damage to the pro-
America. tective high-density polyethylene 共PE兲 sheathing of the main ten-
After 25 years in service—years that encompassed frequent sion elements 共MTEs兲 of these prefabricated stay cables. On the
repairs to the cables, protective sheathing, and anchorage Luling Bridge, the protective sheathing for the cables was dam-
components—the Hale Boggs Bridge will need to undergo com- aged before and during installation, and deterioration of this im-
plete replacement of its stay-cable system. The potential for portant cable corrosion protection element continued after the
stay-cable durability performance problems arose during the con- bridge opened to traffic. Today, stay cables are commonly ex-
pected to attain a design life of 50 years or more, in contrast to the
1
Project Consultant and President, Bridge Engineering Solutions, PC,
25-year cable service life attained in this instance.
P.O. Box 1565, Lewiston, NY 14092. Twenty-one cables required the repair of PE pipe cracking
2
Senior Structural Engineer, CTLGroup, 5400 Old Orchard Rd., before and during cable erection. Although analysis and docu-
Skokie, IL 60077. mentation of the root cause of early pipe cracking is lacking in the
3
Principal in Charge and Senior Principal Engineer, CTLGroup, 5400 literature, it is likely that the pipe splits and cracks were associ-
Old Orchard Rd., Skokie, IL 60077 共corresponding author兲. ated with sustained stress and deformation during extended stor-
4
Senior Structural Engineer, CTLGroup, 5400 Old Orchard Rd., age of the prefabricated, ungrouted, sheathed cables on reels.
Skokie, IL 60077. Many of these 21 early repairs failed during pressure grouting,
Note. This manuscript was submitted on October 1, 2008; approved
and the repairs were repeated in place. In April 1985, more cracks
on July 20, 2009; published online on June 15, 2010. Discussion period
open until December 1, 2010; separate discussions must be submitted for were detected in two backstay cables’ protective sheathing. The
individual papers. This paper is part of the Journal of Bridge Engineer- cable manufacturer electrowelded the cracks in November of that
ing, Vol. 15, No. 4, July 1, 2010. ©ASCE, ISSN 1084-0702/2010/4-364– year. Later, cracks developed in these PE weld repairs. In the
372/$25.00. winter of 1985, new cracks were detected in three other cables. In
Inspection Procedures
The inspection began in April 2006, and with 8.9 km of cable to
ride, was expected to take 12 weeks to complete. Two inspectors
rode in the hoist, observing, hammer-sounding and digital tap
testing the cable cover pipe and ultraviolet protection tape to lo-
cate the damage. Infrared thermography was used selectively to
detect open splits in the PE cover pipes beneath the ultraviolet
Downloaded from ascelibrary.org by George Washington University on 02/22/15. Copyright ASCE. For personal use only; all rights reserved.
Fig. 4. PE pipe split; the ultraviolet protection tape is missing Fig. 7. Separation of PE transverse joints
barriers which prevent MTE corrosion over the full length of the The temporary cable erection concept was also developed; it
cable. consists of a cable saddle on top of the tower and a spreader
Presently available corrosion barriers encompass, grease- or 共waler兲 beam at the deck anchorages. This system will require
wax-filled individual strand sheathing, individually fusion-bonded that a main span and a back span cable are replaced simulta-
epoxy coating, cementitious grout and other fillers or blocking neously so that the forces in the temporary cables are roughly
compounds, and high-density polyethylene or steel sheathing. balanced. This system has a significant advantage since it does
Sacrificial zinc coatings for strand are frequently used outside the not require that access be maintained to the top of the pylon, and
United States for stay cables are also available. The Post Tension- that all stressing operations can be completed at deck level. The
ing Institute’s 共PTI兲 Recommendations for stay cable design, test- system is designed to accommodate the range of stay cable angles
ing and installation 共2007, 5th Ed.兲 共2001, 4th Ed.兲 requires a and allows the repeated reuse of the saddle and temporary stay
minimum of two nested, qualified barriers for corrosion protec- cable.
tion of the MTE. It is noted that the PTI Cable-Stayed Bridge
Committee does not recognize the sacrificial zinc layer to be one
of those barriers. Design Task D—Design for Peripheral Bridge Elements
The transition zone between cable free length and the cable Peripheral design tasks included design of the drainage system for
anchorage, as well as the anchorage itself, also require corrosion the deck-level anchorage boxes, evaluation of deck-level surface
protection. In the transition zones of stay cables, where continu- drainage, taking into account geometry changes created by cable
ous corrosion barriers applied directly to the MTE are interrupted replacement, enhanced security/antivandalism measures for stay
along the path to the structural anchor, equivalent and compatible cables near deck level, and damping requirements for the replace-
materials are provided to maintain end-to-end protection for the ment cables.
stay cable MTE in these zones.
Security and Antivandalism
Cable Stressing Method Cable security has become an increased concern for bridge own-
Cable stressing can be performed strand-by-strand or by preload- ers, particularly since the events of September 11, 2001. In re-
ing the entire cable 共“multistrand” method兲. The strand-by-strand sponse to the increasing concern over the vulnerability of
method has many practical advantages when compared to multi- prominent transportation structures to vandalism or a terrorist at-
strand method. These include the use of single strand hydraulic tack, the Federal Highway Administration 共FHWA兲 commis-
rams that are significantly lighter, smaller, and easier to operate sioned the Blue Ribbon Panel on Bridge and Tunnel Security. The
than rams required for stressing the whole assembly. Because of culmination of their work, Recommendations for Bridge and Tun-
the unique condition of the anchorage spaces of the Luling nel Security, was published in September of 2003. This document
Bridge, it is preferable that the individual method be used for the provides a framework for assessing the risk of bridge or bridge
stressing of the new replacement cables. Detensioning of existing component in terms of importance, occurrence, and vulnerability
cables, however, will require the use of a single large ram for the to an attack. The three risk factors are assessed qualitatively to
cable, similar to that used for the original stressing of these identify a facility risk score. This score is then compared against
cables. the cost, the effectiveness, and the availability of potential miti-
gation options to determine whether counter measures are pru-
Wind Load Considerations dent. Based on the guidelines of the FHWA document,
The wind load imparted on the bridge by the cables is a direct preliminary analyses have indicated that only the free length of
function of the stay cable sheathing diameter. The existing paral- the cable above the lower end exit point near deck level would
lel wire system is compact and care was taken to ensure that the generate a risk score that necessitates the consideration of counter
replacement system’s wind profile does not overload the structure. measures. Comparison and rating among various countermeasures
A stay cable system which minimizes wind loads would be pre- studied for this design indicated that steel sleeves protecting the
ferred. cables for up to 3.05 m above the deck has the most effect in
reducing the risk.
Temporary Cable Design
Cable Damping Requirement
To protect the bridge structure from excessive force variation dur- The Phase I scope leads to the conclusion that the existing stay
ing removal of existing cables and to eliminate the potential for cables of the Luling Bridge are susceptible to wind-induced vi-
rupture of adjacent cables, temporary cables will be used to carry bration, requiring vibration suppression. Damage to seals and
the dead loads and balance the forces when existing cables are scarring of PE cover pipes at cable exit points were partly attrib-
removed. uted to the past uncontrolled vibration experiences. A vibration
Anchorage Drainage
An anchorage box drainage system was designed to address the
issue of water ponding at the lower cable transition zone.
Downloaded from ascelibrary.org by George Washington University on 02/22/15. Copyright ASCE. For personal use only; all rights reserved.
MOT Design
MOT is a critical part of the cable replacement construction pro- Fig. 9. Schematic of construction sequence
cess. The Luling Bridge is a critical regional link and traffic in-
terruptions need to be as unobtrusive to the public and commerce
as is practical. Additionally, the bridge is located in a hurricane tractor to work within a smaller footprint on the bridge for the
region and is a part of hurricane evacuation route. Limitations on majority of the operations. The highline design will be the respon-
traffic control that impact evacuation capacity, including seasonal sibility of the contractor, as the contractor will have specific ca-
timing, have to be considered. pacity requirements depending on their stay system components
Several traffic control scenarios were initially identified and and preferred work methods.
studied. The overall objective of the MOT is twofold: provide
enough work area to facilitate construction and minimize lane Finite-Element Analysis of Construction Sequence
closures and impact on traffic. The selected new stay cable array installation and construction
The ideal scenario would be to maintain traffic on each side of sequence will induce force variations and deformations at the
the bridge during construction to eliminate the need for cross- cross beam ends and the tower. It was verified that the replace-
overs. This scenario will allow the ramps to remain in service ment scheme selected for this project will result in minimal
resulting minimal disruption to local traffic. After studies and changes to the distribution of loads throughout the structure. This
input from contractors, it is believed that the predominance of will be confirmed as the design progresses.
construction work can be accomplished within a 3.73-m work Nevertheless, the design of new and temporary cables and the
area, therefore leaving two lanes in each direction for traffic. This development of construction sequence are affected to varying de-
will provide a relatively narrow but workable area. If a particular grees by the process. Structural analysis is supporting the design
construction operation requires more space, then the barrier can effort, by determining the effect of these variations both locally
be moved during off-peak travel times to provide a wider work and globally.
area. As long as the maximum construction work area width re- At the local level, connections of the temporary cables to the
quirements do not exceed 7.11 m. for any operation during off- cross beam and tower and their local effects on the structure were
peak hours, then the desirable scenario is achievable. investigated. The effects of modifications to the existing structure
for accommodating replacement cable installation were analyzed
locally. Also, eccentric forces generated by cutting cables among
Construction Sequence
a group of cables were studied.
A construction procedure for the replacement activities has been At the global level, the structure as a whole was analyzed for
devised to address the cable replacement cycle process. The con- force variations resulting from installing temporary cables, re-
struction will be limited to one side of the bridge and each quarter moving existing cables, and stressing of replacement cables. The
of the bridge at a time. The sequence starts with placement of a structural analyses were also used to limit the temporary cable
saddle support on top of each leg of pylon. This will be followed stresses during various construction stages.
by the installation of a proposed highline or cableway system to
aid in the stay cable removal and installation. Fig. 9 shows a
schematic of construction process with highline, temporary Summary and Conclusions
cables, and existing cables in place.
Periodic inspections of the Luling Bridge stay cable array identi-
Highline System fied critical breaches in the cable protective sheathing and expo-
The highline system can simplify the installation of both the tem- sure of the MTE of the stay cables to corrosion, with an
porary and the permanent stay cables by supporting the stay cable increasing rate of degradation. Prior to rehabilitation design repair
pipes and reducing cable sag. It will be essential for the removal strategies were identified, and a life cycle-cost analysis was per-
of the existing stay cable. The flexibility of the stay cable is formed to assist in the maintenance decision making. Results in-
significantly less than and the weight significantly more than dicate that when all costs are considered, strategies involving
when it was installed, due to the cement grout installed after comprehensive repair or complete cable replacement compete
erection. Using the highline, the stay cable can be supported at closely, while the cost of “doing nothing” is significantly higher.
intermediate locations and lowered to the deck under controlled LADOTD elected to replace all cables. The earlier-than-expected
conditions. replacement of the stay cable array could have been avoided had
Just as important, using the highline will reduce the need to the stay cables’ external corrosion protection system and moisture
position a mobile crane on the bridge deck, and allow the con- barrier, the PE pipe, been sound and water tight.
interruption to traffic. Most of the recommended bridge rehabili- Mehrabi, A. B. 共2007兲. “The Luling Bridge—Categorization of damages
tation operation will be conveniently concentrated at the deck and comparison among repair strategies.” Rep. to the Louisiana Dept.
level, where the temporary cable anchors and the live 共stressing兲 of Transportation and Development, State Project 700-45-0107, CTL-
end of existing cables and new cable are positioned. Group, Baton Rouge, La.
Mehrabi, A. B., and Ligozio, C. A. 共2007兲. “Cable-stayed bridges—
Discovering alarming distress and damages.” Proc., 2007 Int. Bridge
Conf., Engineers’ Society of Western Pennsylvania, Pittsburgh.
Acknowledgments Mehrabi, A. B., Ligozio, C. A., and Brennan, J. D. 共2006兲. “Structural
evaluation of Luling Bridge stay cable array. Phase II, Supplements 1
The work described in this paper was conducted under Louisiana and 2.” Rep. to the Louisiana Dept. of Transportation and Develop-
State Project No. 700–45-0107 and F. A. P. No. IM-4502共501兲. ment, State Project 700-45-0107, CTLGroup, Baton Rouge, La.
The writers wish to express their appreciation to the Louisiana Post-Tensioning Institute 共PTI兲. 共2007兲. Recommendations for stay cable
Department of Transportation and Development, particularly design, testing and installation, 5th Ed., Post-Tensioning Institute,
Messrs. Paul Fossier, Hossein Ghara, and Gill Gautreau for coor- Phoenix.