Professional Documents
Culture Documents
FINAL REPORT
564TH REPORT
OF THE
The Public Works Committee is established pursuant to sections 12A, B and C of the Parliamentary
Committees Act 1991, proclaimed February 1992.
The following members constitute the nineteenth Public Works Committee as reconstituted on
6 May 2014:
Section 12C of the Parliamentary Committees Act 1991 defines the functions of the Public Works
Committee as:
(a) to inquire into and report on any public work referred to it by or under this Act, including-
(i) the stated purpose of the work;
(ii) the necessity or advisability of constructing it;
(iii) where the work purports to be of a revenue-producing character, the revenue that it
might reasonably be expected to produce;
(iv) the present and prospective public value of the work;
(v) the recurrent or whole-of-life costs associated with the work, including costs arising
out of financial arrangements;
(vi) the estimated net effect on the Consolidated Account or the funds of a statutory
authority of the construction and proposed use of the work;
(vii) the efficiency and progress of construction of the work and the reasons for any
expenditure beyond the estimated costs of its construction;
(b) to perform such other functions as are imposed on the Committee under this or any other Act
or by resolution of both Houses.
PART ONE: PREAMBLE AND PROJECT BACKGROUND
The Morgan Water Treatment Plant is located at the commencement of the Morgan to Whyalla
Pipeline, treating water as it is pumped into the pipeline. It has a capacity of 200 megalitres per day
and provides drinking water to around 130,000 people.
The National Health and Medical Research Council is due to release new Health Based Targets for
drinking water. In order to meet these, an upgrade is required of the water treatment plant and its
storage facilities. This upgrade will allow for continuous, close to continuous operation of the plant
as recommended by the guidelines as good practice.
To support the continued pumping, increased storage capacity is required. This will allow a
decoupling of plant and Morgan to Whyalla Pipeline operations, which will enable a more
continuous operation. This project proposes to build a new 30 megalitre earth bund storage as well
as upgrade the 12 megalitre filtered water storage at a cost of $11.344 million (excluding GST).
SA Water informed the Committee that another advantage of the project is the ability to balance
out the power costs with possibility of more pumping at night, and take advantage of night
electricity tariffs. This has the potential to save SA Water hundreds of thousands of dollars.
The major construction works will occur over a 12-month period. Initially the new 30 megalitre earth
bank storage will be constructed to ensure the water treatment plant and pumping continues
uninterrupted. This will ensure there is no disruption to water supply to customers whilst the 12
megalitre filtered water storage is relined. The project is due to reach practical completion by
May 2018.
PART THREE: PROJECT PROPOSAL AND PRE-CONSTRUCTION ASSESSMENTS
Site Ownership
The new earth bank storage facility will be constructed on SA Water land, as well as the works for
the existing filtered water storage. There is no need to acquire additional land and easements as
part of the project.
3.2 Consultation
SA Water informed the Committee it is committed to ensuring a high level of stakeholder
engagement in order to manage expectations, concerns and any other stakeholder issues
associated with the project. It has developed a community and stakeholder engagement strategy to
identify key stakeholders, potential project impacts and highlight the key messages.
The Stakeholder Engagement Team will monitor the progress and effectiveness of the strategy
and provide regular reports to the Project Manager on issues and opportunities identified through
the stakeholder engagement process.
Construction works may create temporary and minor impacts on the neighbouring Morgan Bowling
Club such as the creation of a new club access road, increased highway traffic and general
construction activity during the construction program. The Stakeholder Engagement Team will
ensure that consultation is ongoing throughout the design and construction to minimise impact of
the works wherever possible.
In addition, the design and construct contractor shall submit site specific management plans
detailing how construction impacts such as noise, dust, traffic disruption, and community safety will
be managed and mitigated. A stakeholder management database will be utilised to track issues
raised by stakeholders as well as to provide feedback to the project team.
Through ongoing engagement with key stakeholders, the project team and the design and
construct contractor will target mutually beneficial outcomes through effective communication and
the development of a collaborative culture between the SA Water and external stakeholders.
Communication with various stakeholders is occurring in line with SA Water’s standard
communications process and it will be managed within SA Water current internal resources.
This project has been included in SA Water’s Regulatory Business Proposal for 2016-20, and as
such, the cost is included in SA Water’s current approved capital plan. The project will have no net
impact on SA Water’s overall capital plan, borrowings or contributions to Government.
Operating Costs
SA Water informed the Committee that one of the advantages it anticipates from the project is the
ability to balance out the power costs with the possibility of more pumping at night, taking
advantage of night electricity tariffs. This has the potential to save SA Water hundreds of
thousands of dollars.
4.4 Estimated Net Effect of the Work, and Its Use, of Public Funds
A financial analysis of the project has been undertaken by SA Water in accordance with Treasury
Instructions and corporation guidelines. The analysis is based on a 30-year study period and uses
a cost of capital (discount rate) of 4.6 percent (real, pre-tax), which is SA Water’s regulatory
Weighted Average Cost of Capital (WACC) as determined by the Essential Services Commission
of South Australia (ESCOSA) for the current regulatory period.
Options 2, 3 and 4 were compared against the Base Case to determine the best net present value
(NPV).
Option 1 Option 2
Option 3 Option 4
(Base Case) (Preferred)
NPV ranking 2 1 4 3
Note: 1. All numbers in the above table are discounted real dollars.
The results of the financial analysis indicated that Option 2 is the preferred option. Option 2 is
financially preferred to the Base Case due to ongoing operating cost savings primarily by allowing
SA Water to take better advantage of lower electricity tariffs when they occur. Furthermore, Option
2 will address the identified water quality risks that were not quantified in financial terms under the
Base Case. Option 2 is financially preferred to Option 3 and 4 due to the lower capital cost.
SA Water applied sensitivity testing to the discount rate (increase/decrease 2 percent). The
analysis shows no change in the preferred option (option 2) as the discount rate decreases by 2
percent. When the discount rate increases by 2 percent to 6.6 percent, the preferred option in
terms of the net present value analysis becomes the Base Case and Option 2 moves to second
best. However the Base Case does not address the existing water quality risks that could not be
quantified in financial terms and hence SA Water still prefers Option 2 under the higher discount
rate.
Economic analysis of the project was also conducted by SA Water using a 2.96 percent discount
rate (real, pre-tax) as per the Department of Treasury and Finance guidelines for the evaluation of
public sector initiatives. This analysis differs from the financial analysis presented above by only
the discount rate used. SA Water informed the Committee that the results of the economic analysis
did not change the ranking of the options.
Employment Opportunities
SA Water is aware of the Industry Participation Policy (IPP), administered by the Office of the
Industry Advocate and will ensure that this policy is complied with in relation to this Project. SA
Water estimates that the project will create around 17 new construction jobs.
Activity Commence
Full Financial Approval March 2017
Major Orders Placed April 2017
Start Major Works June 2017
Practical Project Completion May 2018
Final Completion / End Defect Period May 2019
Project Procurement
SA Water has engaged GHD consulting engineers to develop a detailed concept design for the
new storage and associated works. Once the concept design is received, and subject to full
financial approval of the project, SA Water intends to conduct a competitive tender process for the
delivery of a Design and Construct (AS4300) Contract.
SA Water will arrange a select tender to four or five Tier 1 Construction Panel members for the
provision of design and construct services. The contract shall be award for the Design and
Construct Contract in accordance with SA Water’s Delegation of Financial and Procurement
Authority and applicable Department of Treasury and Finance and government policies.
Risk Assessment
SA Water has reviewed this project under the Business Risk Management Policy and Framework,
which requires the identification of risks, their likely impact and severity, and proposed risk
mitigation strategies. The policy and framework are consistent with the Australia/New Zealand Risk
Management Standard AS/NZS ISO 4360.
The extreme and high ranked risks that were identified are all part of the Base Case option and will
be mitigated as part of the proposed upgrade. Those risks are:
SA Water non-compliance with the “continuous water treatment plant operation”
recommendation of the new Health Based Targets for drinking water, and
the loss of opportunity to undertake essential maintenance on the existing 12 megalitre
filtered water storage.
Design and construction risks will continue to be evaluated during the detailed design process via
safety in design and project constructability workshops. There are no extreme or high construction
risks related to the preferred option.
All project risks are logged and monitored in a live risk database and addressed as appropriate by
the team during the life of the project.
4.7 The Efficiency and Progress of the Project and Justification of Any
Expenditure Beyond Estimated Costs
The Committee will monitor the progress of the Morgan Water Treatment Plant Balancing Storage
Project as required by the Parliamentary Committees Act 1991 through the regular reports SA Water
is required to provide prior to the completion of construction (refer to "Further Reporting to the
Committee"). The Committee will provide a further statement to Parliament in the event that
subsequent information provided renders this report inaccurate or misleading.
PART FIVE: CONCLUSION & RECOMMENDATION
The Public Works Committee has examined written and oral evidence in relation to the Morgan
Water Treatment Plant Balancing Storage Project. It has also been assured by SA Water officials
that acquittals have been received from the Department of Treasury and Finance, Premier and
Cabinet and the Crown Solicitor that the works and procedures are lawful. The Committee is satisfied
that the proposal has been subject to the appropriate agency consultation and meets the criteria
for examination of projects as set out in the Parliamentary Committees Act 1991.
Based upon the evidence considered, and pursuant to Section 12C of the Parliamentary Committees
Act 1991, the Public Works Committee reports to Parliament that it recommends the proposed public
work.
M s Annabel Digance MP
PRESIDING MEMBER 22-- March 2017
PART SIX: ATTACHMENTS