org/wiki/Brine_mining#Types_of_brines_used_for_mineral_extraction
https://www.rockstone-research.com/images/pdfs/MGX_TechnicalReportRapidLithiumExtractionProcess.pdf
The highest value is 690 mg/l in Salar de Olaroz mine, Argentina which is exceptional.
A 7500 bpd plant equals a 1200m3 per day plant which is equivalent to 50 m3/h plant that works 24h/day.
With these figures and the parameters below, I calculate costs of ~1550 US$/ton LCE (Lithiumcarbonate) and (898/365=) 2,46 ton LCE/day.
Revenues of ~8,980,000 US$/year (898 ton LCE * 10,000 US$/ton LCE ).