Standard Information for Non Hazardous Solid Materials Note

Quantity (Bulk) 33.800 Kgs Please enter your quantity


Manpower Working hour 7 Hours/day Standard Working 8 hour per day, minus breaktime 1 hr
Proposed Manpower 2 Manpower Manpower
Required Manhours 28 Hours Standard Working hour per day
Required working days 2 Days Normal, without extra hours
Required Storage and Placement 34 m2 1000 Kgs / m2 (standard pallet size)
Loading-Unloading Process (Forklift 1.5MT) 1.200 Kgs / Hour Include Certified Operator
Required Forklift rental 2 Days Forklift 1.5 MT

Quotation for Loading - Unloading Process for 33.800 Kgs


Description Unit Cost / Unit (IDR) Required Unit Total Cost (IDR)
Manpower Cost Hours 500.000 28 14.000.000
Loading - Unloading (Forklift Rental 1.5MT) Days 8.000.000 2 16.000.000
Security and Cleaning fee Days 30.000 2 600.000
Warehouse & Spare requirement m2 130.000 34 4.394.000
Quality Check Days 250.000 2 500.000
Transportation Cost km - 0 0

Subtotal (IDR) 35.494.000


Tax rate 0%
Other 0
TOTAL 35.494.000