Standard Information for Non Hazardous Solid Materials Note
Quantity (Bulk) 33.800 Kgs Please enter your quantity
Manpower Working hour 7 Hours/day Standard Working 8 hour per day, minus breaktime 1 hr Proposed Manpower 2 Manpower Manpower Required Manhours 28 Hours Standard Working hour per day Required working days 2 Days Normal, without extra hours Required Storage and Placement 34 m2 1000 Kgs / m2 (standard pallet size) Loading-Unloading Process (Forklift 1.5MT) 1.200 Kgs / Hour Include Certified Operator Required Forklift rental 2 Days Forklift 1.5 MT
Quotation for Loading - Unloading Process for 33.800 Kgs
Description Unit Cost / Unit (IDR) Required Unit Total Cost (IDR) Manpower Cost Hours 500.000 28 14.000.000 Loading - Unloading (Forklift Rental 1.5MT) Days 8.000.000 2 16.000.000 Security and Cleaning fee Days 30.000 2 600.000 Warehouse & Spare requirement m2 130.000 34 4.394.000 Quality Check Days 250.000 2 500.000 Transportation Cost km - 0 0