CLOSE OUT OF THE RECTIFICATION WORKS FOR W3 (NORTH & SOUTH) AS PER SSE
SECTION 1
1
Project Name : Dubai Creek Harbour Development – Dubai Creek Residences
CLOSE OUT OF THE RECTIFICATION WORKS FOR W3 (NORTH & SOUTH) AS PER SSE
Dubai Creek Harbour Development - Dubai Creek Residences
1. Reference
1.1 Contract Drawings No
5120544/NW3/S/7001
5120544/SW3/S/7001
5120544/NW3/S/5001
5120544/SW3/S/5001
1.2 Specifications E30
1.3 Project Quality Plan TS-ABM-CIV-PQP-0012 R.1
1.4 HSE Plan TS-ABM-CIV-HSE-0014 -R.1
1.5 Structural Assessment & remedial work proposal report Doc. No. SSE-
DXB/EMAAR/DCH/TH/29/2015-REV 3 BY SSE
1.6 Method statement for the rectification works TS-ABM-CIV-MS-0031 R.0
2. Corrective action / method done
2
Project Name : Dubai Creek Harbour Development – Dubai Creek Residences
CLOSE OUT OF THE RECTIFICATION WORKS FOR W3 (NORTH & SOUTH) AS PER SSE
3
Project Name : Dubai Creek Harbour Development – Dubai Creek Residences
CLOSE OUT OF THE RECTIFICATION WORKS FOR W3 (NORTH & SOUTH) AS PER SSE
4
Project Name : Dubai Creek Harbour Development – Dubai Creek Residences
CLOSE OUT OF THE RECTIFICATION WORKS FOR W3 (NORTH & SOUTH) AS PER SSE
5
Project Name : Dubai Creek Harbour Development – Dubai Creek Residences
CLOSE OUT OF THE RECTIFICATION WORKS FOR W3 (NORTH & SOUTH) AS PER SSE
Additional bars of T32 @150mm c/c spacing is embedded at the ends of the wall in the inner
face of the existing bar by chemical anchorage which is recommended by SSE as follows
Scanning is done to identify the reinforcement inside the raft using structure scan mini
as shown below image 1 & 2.
Marking is done on the raft Reinforcement for the drilling as shown in Image 3.
The surface of the Raft concrete where the drilling will be made is cleaned without
dust & debris.
Drill is made above the Raft concrete at the specified location.
Required depth of the drill is made which is proposed by Hilti.
The debris inside the drill is removed by air blower
Then the approved chemical (HILTI RE500) is filled in the drilled hole and the steel
rod is introduced into the drill hole as per Manufacture recommendation.
Pull out test is carried out for the design load & the test report is attached.
Inspection is raised to ensure the reinforcement has been placed as described above
and upon approval further work will be proceeded
Image 1
6
Project Name : Dubai Creek Harbour Development – Dubai Creek Residences
CLOSE OUT OF THE RECTIFICATION WORKS FOR W3 (NORTH & SOUTH) AS PER SSE
Image 2
Image 3
7
Project Name : Dubai Creek Harbour Development – Dubai Creek Residences
CLOSE OUT OF THE RECTIFICATION WORKS FOR W3 (NORTH & SOUTH) AS PER SSE
8
Project Name : Dubai Creek Harbour Development – Dubai Creek Residences
CLOSE OUT OF THE RECTIFICATION WORKS FOR W3 (NORTH & SOUTH) AS PER SSE
9
Project Name : Dubai Creek Harbour Development – Dubai Creek Residences
CLOSE OUT OF THE RECTIFICATION WORKS FOR W3 (NORTH & SOUTH) AS PER SSE
SECTION 2
REMEDIAL MEASURES FOR
LESS COVER
10
Project Name : Dubai Creek Harbour Development – Dubai Creek Residences
CLOSE OUT OF THE RECTIFICATION WORKS FOR W3 (NORTH & SOUTH) AS PER SSE
1. Reference
1.1 Contract Drawings No
5120544/NW3/S/7001
5120544/SW3/S/7001
5120544/NW3/S/5001
5120544/SW3/S/5001
1.2 Specifications E30
1.3 Project Quality Plan TS-ABM-CIV-PQP-0012 R.1
1.4 HSE Plan TS-ABM-CIV-HSE-0014 -R.1
1.5 Structural Assessment & remedial work proposal report Doc. No. SSE-
DXB/EMAAR/DCH/TH/29/2015-REV 3 BY SSE
1.6 Method statement for the rectification works TS-ABM-CIV-MS-0031 R.0
One coat of SIKAGARD 720 EPOCEM from SIKA is coated on the whole area of the
lift pit in the raft of W3 (north & south tower) as per SSE recommendation (Ref. SSE-
DXB/EMMAR/DCH/TH/29/2015 REV 3)
Concrete substrates are prepared mechanically using high pressure water jetting
equipment to remove cement lattice, especially oil or wax containing layers.
Weak concrete were removed and surface defects such as blow holes and voids
must be fully exposed.
All dust, loose and friable material are completely removed from all surfaces before
application of the product, preferably by brush.
The mixing and the application method/tools is made as per Technical data sheet of
SIKAGARD 720 EPOCEM.
11
Project Name : Dubai Creek Harbour Development – Dubai Creek Residences
CLOSE OUT OF THE RECTIFICATION WORKS FOR W3 (NORTH & SOUTH) AS PER SSE
12
Project Name : Dubai Creek Harbour Development – Dubai Creek Residences
CLOSE OUT OF THE RECTIFICATION WORKS FOR W3 (NORTH & SOUTH) AS PER SSE
13
Project Name : Dubai Creek Harbour Development – Dubai Creek Residences
CLOSE OUT OF THE RECTIFICATION WORKS FOR W3 (NORTH & SOUTH) AS PER SSE
14
Project Name : Dubai Creek Harbour Development – Dubai Creek Residences
CLOSE OUT OF THE RECTIFICATION WORKS FOR W3 (NORTH & SOUTH) AS PER SSE
SECTION 4
15
Project Name : Dubai Creek Harbour Development – Dubai Creek Residences
CLOSE OUT OF THE RECTIFICATION WORKS FOR W3 (NORTH & SOUTH) AS PER SSE
1. Reference
2.1 Contract Drawings(5120544/NE2/S/1101 & 5120544/SE2/S/1101)
1.2 Specifications E30
1.3 Project Quality Plan TS-ABM-CIV-PQP-0012 R.1
1.4 HSE Plan TS-ABM-CIV-HSE-0014 -R.1
1.5 Structural Assessment & remedial work proposal report Doc. No. SSE-
DXB/EMAAR/DCH/TH/29/2015-REV 3 BY SSE
1.6 Method statement for the rectification works TS-ABM-CIV-MS-0031 R.0
2. Operating/Working procedure
2.1. The removal of rust is done in the following areas of reinforcement
a. E2 South & North Raft reinforcement which is fixed at site.(5120544/NE2/S/1101 &
5120544/SE2/S/1101).
b. All vertical reinforcement (starter bars,columns,core walls) of all rafts. Columns
(5120544/NE2/S/5001&5120544/SE2/S/5001)&(5120544/NE3/S/5001&5120544/SE3/S/500) and
core walls (5120544/NE2/S/7001 & 5120544/SE2/S/7001) & (5120544/NE3/S/7001 &
5120544/SE3/S/7001) piles starter bars(5120544/NE3/S/0401 & 5120544/SE3/S/0401).
c. Stacked steel in the site premises ,intent to be utilised for balance raft work of E3 & E2
rafts(North & South).
2.2. Fixed reinforcement in raft for Tower E2(North & South)
The whole area of the raft is divided into 4parts (Refer enclosed drawing).
Reinforcement of each part of raft have is cleaned separately as follows
The dust is removed from the surface of the reinforcement by using air Compressor.
The reinforcement is cleaned with the sweet water using high jet water pressure of pressure
ranging from 100 to 120Psi
The Waste water is collected using a dewatering pump and is disposed to the designated area.
Then inspection is raised to the consultant, after approval further activities will be proceeded.
16
Project Name : Dubai Creek Harbour Development – Dubai Creek Residences
CLOSE OUT OF THE RECTIFICATION WORKS FOR W3 (NORTH & SOUTH) AS PER SSE
Then inspection is raised to the consultant, after approval further activities will be proceeded.
2.4. stacked steel in site premises
Two or three platforms is made and the steel rods in which the rust is to be removed is placed above
platform based on convenience.
The dust is removed from the surface of the reinforcement by using air Compressor
The reinforcement is cleaned with the sweet water using high jet water pressure of pressure
ranging from 100 to 120Psi
The Waste water is collected using a dewatering pump and is disposed to the designated area.
Then inspection is raised to the consultant, after approval further activities will be proceeded.
17
Project Name : Dubai Creek Harbour Development – Dubai Creek Residences
CLOSE OUT OF THE RECTIFICATION WORKS FOR W3 (NORTH & SOUTH) AS PER SSE
18
Project Name : Dubai Creek Harbour Development – Dubai Creek Residences
CLOSE OUT OF THE RECTIFICATION WORKS FOR W3 (NORTH & SOUTH) AS PER SSE
19