PROJECT : EXPANSION OF PTB & AIRSIDE AT RGIA

CLIENT : GHIAL

CONTRACTOR : L&T Construction

Dense Asphalt Concrete (PMB-40) -Checklist for Rolling Pattern

Dispatch Time: 15:20 Date: 7/19/2019

Temperature at Plant 163˚C

Temperature at Site 159˚C Rolling Temp.at End of compaction (˚C ): 100

S.NO. Time Rolling Pattern Yes/No Temperature Remarks (if any)

1 16:00 Stand out 159 ° C

2 16:10 Paving Starts 157 ° C

3 16:20 Paving Ends 153° C

4 16:35 Plain Pass 145° C Two Pass

5 16:50 Vibratory Rolling 1ST pass 141 ° C

6 16:58 Vibratory Rolling 2nd pass 138 ° C

7 17:05 Vibratory Rolling 3rd pass 133 ° C

8 17:12 Plain Pass 128 ° C

9 17:35 PTR. Rolling 120 ° C Three Pass

10 17:45 Finishing Ro;;ing 113° C One Plain Pass

Contractor's Representative Client's Representative


PROJECT : EXPANSION OF PTB & AIRSIDE AT RGIA

CLIENT : GHIAL

CONTRACTOR : L&T Construction

Dense Asphalt Concrete (PMB-40) -Graph


LANE -1
TIME VS TEMP RECORD
TIME Hours TEMP
15:20 0.00 163

16:00 0:40 159

16:10 0:50 157

16:20 1:00 153

16:35 1:15 145

16:50 1:30 141

16:58 1:38 138

17:05 1:45 133

17:12 1:52 128

17:35 2:15 120

17:45 2:25 113

185

175
TIME VS TEMP
165 163
159 157
155 153
145 145
141
138
135 133
128
125
120
115 113
105

95

85
15:20 16:00 16:10 16:20 16:35 16:50 16:58 17:05 17:12 17:35 17:45

Contractor's Representative Client's Representative