Professional Documents
Culture Documents
Charterhouse Field Cycleway Scheme - Phase 1
Charterhouse Field Cycleway Scheme - Phase 1
Dec'23 31,
Jan '23
7,
Jan
'2414,
Jan'2421,
Jan'2428,
Feb'24 4,
Feb'2411,
Feb'24 18,
Feb'24 25,
Mar'24 Mar
3, '24Mar
10, '24Mar
17, '24Mar
24, '24Apr
31, '247,
Apr'2414,
Apr'24 21,
Apr'24 28,
May'24 May
5, '24May
12, '24
May
19, '24
Jun
26, 2,
'24
Jun'249,
Jun'2416,
Jun'2423,
Jun'2430,
Jul '24
7,Jul
'2414,
Jul'24
21,
Jul'24
28,
Aug'24Aug
4, '24Aug
11, '24Aug
18, '24Sep
25, '241,
Sep'248,
Sep'2415,
Sep'24 22,
Sep'24 29,
Oct'24 6,
Oct'2413, '24
Mode FSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMT
1 Charterhouse Field Cycleway 176 days January 1, 2024 September 2, 2024
Scheme - Phase 1
3 Mobilization and Site Preparation 20 days January 1, 2024 January 26, 2024
5 Provide for the following 18 days January 3, 2024 January 26, 2024 4
items on site
24 Phase 2: Footway/Cycleway 86 days March 25, 2024 July 22, 2024 48,32
Construction
32 Phase 3: Footbridge 40 days January 29, 2024 March 22, 2024 45SS Phase 3: Footbridge Replacement
Replacement
33 Excavate foundation pits and install 117 days May 2, 2024 October 11, 2024 3,28SS,48,32
foundations
45 Phase 4: Drainage Works for 30 days January 29, 2024 March 8, 2024
the River Along the Footpath
46 Protection Works for Runoff 15 days January 29, 2024 February 16, 2024 3
48 Culvert Design and Installation 4 days February 19, 2024 February 22, 2024 3
51 Phase 5: Finishing, Landscaping, 30 days February 12, 2024 March 22, 2024 2
and Restoration
52 Complete landscaping and 20 days February 12, 2024 March 8, 2024 Complete landscaping and restore damaged areas
restore damaged areas
53 Install amenities like benches 5 days March 11, 2024 March 15, 2024 52 Install amenities like benches and waste bins
and waste bins
54 Clean the site thoroughly 3 days March 18, 2024 March 20, 2024 53,52SF Clean the site thoroughly
55 <New Milestone> 0 days March 20, 2024 March 20, 2024 54 3/20
57 Remove temporary facilities and 14 days March 25, 2024 April 11, 2024 Remove temporary facilities and accommodation units
accommodation units
58 Dismantle security fencing 4 days March 25, 2024 March 28, 2024 57SS Dismantle security fencing
59 Conduct a final environmental 7 days March 25, 2024 April 2, 2024 58SS Conduct a final environmental assessment
assessment
Project: Charterhouse Field Cyc Split Inactive Task Duration-only Finish-only Critical
Date: December 6, 2023 Milestone Inactive Milestone Manual Summary Rollup External Tasks Critical Split
Page 1