ID Task Task Name Duration Start Finish Predecessors Dec 24,

Dec'23 31,
Jan '23
7,
Jan
'2414,
Jan'2421,
Jan'2428,
Feb'24 4,
Feb'2411,
Feb'24 18,
Feb'24 25,
Mar'24 Mar
3, '24Mar
10, '24Mar
17, '24Mar
24, '24Apr
31, '247,
Apr'2414,
Apr'24 21,
Apr'24 28,
May'24 May
5, '24May
12, '24
May
19, '24
Jun
26, 2,
'24
Jun'249,
Jun'2416,
Jun'2423,
Jun'2430,
Jul '24
7,Jul
'2414,
Jul'24
21,
Jul'24
28,
Aug'24Aug
4, '24Aug
11, '24Aug
18, '24Sep
25, '241,
Sep'248,
Sep'2415,
Sep'24 22,
Sep'24 29,
Oct'24 6,
Oct'2413, '24
Mode FSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMT
1 Charterhouse Field Cycleway 176 days January 1, 2024 September 2, 2024
Scheme - Phase 1

2 Phase 1: Preliminary Works 30 days January 1, 2024 February 9, 2024

3 Mobilization and Site Preparation 20 days January 1, 2024 January 26, 2024

4 Site Clearance 2 days January 1, 2024 January 2, 2024 Site Clearance

5 Provide for the following 18 days January 3, 2024 January 26, 2024 4
items on site

24 Phase 2: Footway/Cycleway 86 days March 25, 2024 July 22, 2024 48,32
Construction

25 Footway/Cycleway Construction 86 days March 25, 2024 July 22, 2024 3

32 Phase 3: Footbridge 40 days January 29, 2024 March 22, 2024 45SS Phase 3: Footbridge Replacement
Replacement

33 Excavate foundation pits and install 117 days May 2, 2024 October 11, 2024 3,28SS,48,32
foundations

45 Phase 4: Drainage Works for 30 days January 29, 2024 March 8, 2024
the River Along the Footpath

46 Protection Works for Runoff 15 days January 29, 2024 February 16, 2024 3

48 Culvert Design and Installation 4 days February 19, 2024 February 22, 2024 3

51 Phase 5: Finishing, Landscaping, 30 days February 12, 2024 March 22, 2024 2
and Restoration

52 Complete landscaping and 20 days February 12, 2024 March 8, 2024 Complete landscaping and restore damaged areas
restore damaged areas

53 Install amenities like benches 5 days March 11, 2024 March 15, 2024 52 Install amenities like benches and waste bins
and waste bins

54 Clean the site thoroughly 3 days March 18, 2024 March 20, 2024 53,52SF Clean the site thoroughly

55 <New Milestone> 0 days March 20, 2024 March 20, 2024 54 3/20

56 Phase 6: Demobilization 30 days March 25, 2024 May 3, 2024 51

57 Remove temporary facilities and 14 days March 25, 2024 April 11, 2024 Remove temporary facilities and accommodation units
accommodation units

58 Dismantle security fencing 4 days March 25, 2024 March 28, 2024 57SS Dismantle security fencing

59 Conduct a final environmental 7 days March 25, 2024 April 2, 2024 58SS Conduct a final environmental assessment
assessment

Task Project Summary Manual Task Start-only Deadline Manual Progress

Project: Charterhouse Field Cyc Split Inactive Task Duration-only Finish-only Critical
Date: December 6, 2023 Milestone Inactive Milestone Manual Summary Rollup External Tasks Critical Split

Summary Inactive Summary Manual Summary External Milestone Progress

Page 1