You are on page 1of 2

Parkview_Eleazar Classic Schedule Layout 16-Jan-24 21:27

January 2024 February 2024 March 2024 April 2024 May 2024
31 07 14 21 28 04 11 18 25 03 10 17 24 31 07 14 21 28 05
03-May-24, Parkview_Eleazar

03-May-24, MILESTONES
Project Start
Ground Breaking Ceremony
Excavation Complete
Concrete Topping Off
Project Complete
22-Jan-24, PRE CONSTRUCTION
22-Jan-24, General Requirements
Downpayment
Permits
Mobilization
Construction of Temporary Facilities & Utilities
26-Apr-24, CONSTRUCTION
13-Mar-24, Earthworks
Survey Works (Staking/Layout)
Clearing & Grubbing
Excavation
Hauling & Disposal
Backfilling & Compaction
15-Apr-24, Civil Works
20-Mar-24, Substructure
16-Feb-24, Footing Foundation
Installation of Rebar
Installation of Formworks
Concreting
Formworks Stripping
04-Mar-24, Footing Tie Beam
Installation of Rebar
Installation of Formworks
Concreting
Formworks Stripping
20-Mar-24, Ground Floor
Subgrade Preparation
Installation of Underground Utilities Stubouts
Installation of Vapor Barrier & Soil Termite Solution
Installation of Rebar
Installation of Formworks
Concrete Pouring at SOG
Installation of Rebar & Forms_1st Lift
Concrete Pouring of 1st Lift
15-Apr-24, Superstructure
15-Apr-24, 2nd Floor
Installation of Scaffolding System
Installation of Rebar_Beams
Installation of Formworks
Installation of Slab Embedments
Concrete Pouring
24-Apr-24, Finishing/Architectural Works
Wet Works

Actual Work Critical Remaining Work Summary Page 1 of 2 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
Parkview_Eleazar Classic Schedule Layout 16-Jan-24 21:27
January 2024 February 2024 March 2024 April 2024 May 2024
31 07 14 21 28 04 11 18 25 03 10 17 24 31 07 14 21 28 05
Dry Works
Finishing/Specialty Works
26-Apr-24, MEPS
Installation of 1st Fix (Pipe Rough-ins)
Installation of 2nd Fix (Fittings)
Installation of 3rd Fix (Fixtures)
03-May-24, POST CONSTRUCTIO
Punchlisting Works
Preparation & Submission of Close Out Docu
Demobilization Works

Actual Work Critical Remaining Work Summary Page 2 of 2 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation