You are on page 1of 32

SHAPE Project, Ferring Laboratories Private Limited

3 Month Look ahead Schedule (Mar24 to May'24)

Comments Mar-24 Apr-24 May-24 Contract/ Design


Start Date End Date Status as on
Tasks WW --> 128 129 130 131 132 133 134 135 136 137 138 139 140 Change Materials Equipment Remarks
27.02.2024 Drawing Submittal RFI's
Days --> 4 11 18 25 1 8 15 22 29 6 13 20 27 Orders
6 Sub Station Works 18-Apr-22, Mon 19-May-24, Sun X X X X X X X X X X X
6.1 Watertight Building 18-Apr-22, Mon 25-Nov-23, Sat
6.1.2 Construction Works 10-May-22, Tue 06-Jul-24, Sat X X X X X X X X X X X X X
6.1.2.2 Structural Works (Transformer and DG foundation) 13-Jun-22, Mon 01-May-24, Wed X X X X X X X X X
clearance required
chain link fencing works 01-Apr-24, Mon 21-Apr-24, Sun Not started typical sketch to be X X X
submitted
flooring in dg foundation area 16-Apr-24, Tue 01-May-24, Wed Not started clearance required X X
4.1.2.3 Weather Proofing & Finishing Works 16-Jul-22, Sat 06-Jul-24, Sat X X X X X X X X X X X X X
clearance required
Flooring Works 15-May-24, Wed 21-May-24, Tue not started X
Epoxy only
External paint 1st coat 22-May-24, Wed 27-May-24, Mon work in progress subject to clearance
Internal First Coat of Paint 25-May-24, Sat 30-May-24, Thu not started subject to clearance
7 UG Water tank System 02-May-22, Mon 30-Apr-24, Tue X X X X X X X X X
7.1 Watertight Building 02-May-22, Mon 30-Apr-24, Tue X X X X X X X X X
7.1.1 Construction Activities 09-May-22, Mon 30-Apr-24, Tue X X X X X X X X X
Sub Structure Works 09-May-22, Mon 30-Apr-24, Tue X X X X X X X X X
shed fabrication and sheeting works 15-Jan-24, Mon 15-Mar-24, Fri work in progress X X
pump foundations 01-Apr-24, Mon 04-Apr-24, Thu Not started post anchoring details req X

outside shed area will be


Cover slab Waterproofing 05-Apr-24, Fri 12-Apr-24, Fri Not started started X
After pump foundation
Screed Over Cover slab 13-Apr-24, Sat 19-Apr-24, Fri Not started Dependent X
Finishing Works 20-Apr-24, Sat 30-Apr-24, Tue Not started Dependent X X
10 Boiler House 16-May-22, Mon 14-May-24, Tue X X X X X X X X X X X
10.1 Watertight Building 02-Jun-22, Thu 24-Jan-24, Wed
10.1.2 Construction Activities 02-Jun-22, Thu 14-May-24, Tue X X X X X X X X X X X
10.1.2.2 Super Structure Works 03-Sep-22, Sat 07-Feb-24, Wed
Weather Proofing Works 10-Nov-22, Thu 19-Dec-23, Tue
Joinery & Fixtures 10-Oct-23, Tue 24-Jan-24, Wed
Finishing Works 14-Oct-23, Sat 14-May-24, Tue
railing works 21-Feb-24, Wed 17-Mar-24, Sun work in progress X X
External First coat of Paint 20-Nov-23, Mon 18-Apr-24, Thu work in progress clearance required X X X X X X X
Internal First Coat of Paint 10-Jan-24, Wed 25-Apr-24, Thu work in progress subject to clearance X X X X X X X X
internal paint final coat 26-Apr-24, Fri 06-May-24, Mon Not started subject to clearance
external paint final coat 26-Apr-24, Fri 06-May-24, Mon Not started subject to clearance
handing over 07-May-24, Tue 14-May-24, Tue Not started
11 Tank farm Area 20-Oct-22, Thu 12-Jun-24, Wed X X X X X X X X X X X
11.1 Watertight Building 20-Oct-22, Thu 20-Dec-23, Wed
11.1.2 Construction Works 20-Oct-22, Thu 12-Jun-24, Wed X X X X X X X X X X X
11.1.2.2 Structural Works 19-Nov-22, Sat 12-Jun-24, Wed
subject to tank material
Filling over the Plot ( Inside Fencing Area) 31-Jul-23, Mon 19-May-24, Sun Work in progress X X X X X X X X X X X
clearance
stone pitching 09-May-24, Thu 02-Jun-24, Sun not started drawing required X X X
Fencing Works 19-May-24, Sun 12-Jun-24, Wed work in progress X X
railing works 02-Jan-24, Tue 22-Mar-24, Fri work in progress X X X
road and new footings work 27-Feb-24, Tue 28-Mar-24, Thu Not started
Panel Room Weather Proofing Works 01-Feb-23, Wed 20-Apr-24, Sat X X X X X X X
Internal Paint 1st coat 15-Jan-24, Mon 04-Apr-24, Thu Not started subject to clearance X X X X X
External Painting 1st coat 06-Dec-23, Wed 04-Apr-24, Thu work in progress subject to clearance X X X X X
internal paint final coat 05-Apr-24, Fri 07-Apr-24, Sun Not started subject to clearance
external paint final coat 05-Apr-24, Fri 08-Apr-24, Mon Not started subject to clearance X
handing over 09-Apr-24, Tue 20-Apr-24, Sat Not started X
12 Warehouse Works 05-Jun-22, Sun 27-Oct-24, Sun X X X X X X X X X X X X X
12.1 Watertight building 05-Jun-22, Sun 24-May-24, Fri X X X X X X X X X X X X
12.1.2 Construction Works 05-Jun-22, Sun 27-Oct-24, Sun X X X X X X X X X X X X X
12.1.2.1 Sub Structure 05-Jun-22, Sun 09-Mar-24, Sat X
dockleveller area grade
grade slab works 21-Feb-24, Wed 09-Mar-24, Sat work in progress X
slab pending
loading unloading blockwork 20-Jan-24, Sat 19-Feb-24, Mon work in progress
loading unloading plastering 20-Feb-24, Tue 06-Mar-24, Wed work in progress X
12.1.2.2 GF to FF Lvl Structural Works 04-Aug-22, Thu 10-Jul-23, Mon
Weather Proofing Works 15-Sep-22, Thu 05-Oct-24, Sat X X X X X X X X X X X X X
Second Floor Slab Works 02-Mar-23, Thu 20-Dec-23, Wed
First Floor Weather proofing works QC area 26-May-23, Fri 18-Sep-23, Mon
Staircase 1 mumty works and finishing works 14-Jun-23, Wed 11-Apr-24, Thu X X X X X X
flooring works 01-Feb-24, Thu 14-Mar-24, Thu work in progress X X
railing works 03-Apr-24, Wed 11-Apr-24, Thu Not started X
Staircase 2 mumty works and finishing works 24-Jun-23, Sat 29-May-24, Wed X X X X X X X X X X X X X
flooring works 01-May-24, Wed 29-May-24, Wed Not started X X X X
railing works 30-May-24, Thu 09-Jun-24, Sun Not started
Door window fixtures 01-Nov-23, Wed 24-May-24, Fri X X X X X X X X X X X X
Door fixtures 15-Mar-24, Fri 14-Apr-24, Sun Not started X X X X
except machinary
window fixtures 25-Jan-24, Thu 24-May-24, Fri work in progress X X X X X X X X X X X X
movement entry area
external shaft and façade works 26-Nov-23, Sun 30-Jun-24, Sun X X X X X X X X X X X
completion based on
external shaft block work 01-Feb-24, Thu 11-May-24, Sat work in progress X X X X X X X X X X
clearance
completion based on
external shaft plastering 12-Mar-24, Tue 21-May-24, Tue Not started X X X X X X X X X X
clearance
completion based on
façade 01-May-24, Wed 05-Jun-24, Wed Not started
clearance
Paint works 26-Nov-23, Sun 30-Jun-24, Sun X X X X X X X X X X X
internal painting 26-Nov-23, Sun 13-Jun-24, Thu work in progress clearance requried X X X X X X X X X
external paint 01-May-24, Wed 30-Jun-24, Sun Not started clearance requried
exsiting Qc area 20-Oct-23, Fri 19-Jun-24, Wed X X X X X X X X X X X
toilet plumbing works 28-Feb-24, Wed 29-Mar-24, Fri work in progress shut down required X X X X
flooring works and dado 08-Apr-24, Mon 18-Apr-24, Thu Not started clearance requried X X
sanitary fixtures 19-Apr-24, Fri 29-Apr-24, Mon Not started clearance requried X X
flooring sheet removing 20-Feb-24, Tue 15-Mar-24, Fri work in progress X X
office area painting works 04-Apr-24, Thu 19-Apr-24, Fri Not started clearance requried X X
office area epoxy works 06-May-24, Mon 05-Jun-24, Wed Not started clearance requried
existing hole filling works 10-Mar-24, Sun 25-Mar-24, Mon Not started clearance requried X X X
exsiting warehouse area GF 01-Apr-24, Mon 25-May-24, Sat X X X X X X X X
Demolition works and material shifting 01-Apr-24, Mon 18-Apr-24, Thu Not started clearance requried X X X
blockwork and plaster 15-Apr-24, Mon 03-May-24, Fri Not started clearance requried X X X
doors fixing 15-Apr-24, Mon 21-Apr-24, Sun Not started clearance requried X
flooring works 02-May-24, Thu 12-May-24, Sun Not started clearance requried X
painting 18-May-24, Sat 25-May-24, Sat Not started clearance requried X
existing manufacturing terrace pipe Rack 24-Feb-24, Sat 15-Mar-24, Fri X X
pipe rack foundation works 24-Feb-24, Sat 15-Mar-24, Fri work in progress X X
core cutting
core cutting 15-Feb-24, Thu 06-Mar-24, Wed work in progress X
13 Manufacturing Block 04-Apr-22, Mon 14-Jul-24, Sun X X X X X X X X X X X
13.1 Watertight building 04-Apr-22, Mon 24-Apr-24, Wed X X X X X X X X
13.1.2 Construction Works 04-Apr-22, Mon 14-Jul-24, Sun X X X X X X X X X X X
13.1.2.1 Sub Structure 04-Apr-22, Mon 29-Mar-24, Fri X X X X
staircase4,staircase2 and
Grade slab Works 09-Jul-23, Sun 13-Mar-24, Wed work in progress entrance lobby area X X
pending
Plinth Beams near Staircase-2 10-Mar-24, Sun 20-Mar-24, Wed not started rerouting required X X
Filling up to Plinth Lvl with PCC 22-Mar-24, Fri 29-Mar-24, Fri not started rerouting required X
13.1.2.2 Super Structural Works 20-Jul-22, Wed 29-Aug-23, Tue
First Floor Slab Works 20-Jul-22, Wed 29-Aug-23, Tue
Ground Floor Weather Proofing Works 09-Nov-22, Wed 20-Jan-24, Sat
Flooring works epoxy,kota and tiles 05-May-24, Sun 04-Jul-24, Thu not started clearance req X X X X
Ground Floor Joinery & Fixtures Works 01-Nov-23, Wed 30-Jun-24, Sun X X X X X X X X X X X
Door Fixtures 15-Mar-24, Fri 14-Apr-24, Sun not started fixing based on clearnce X X X X
Window Fixtures 20-Feb-24, Tue 31-Mar-24, Sun work in progress X X X X
Internal First Coat of Paint 01-Apr-24, Mon 30-Jun-24, Sun not started based on clearance X X X X X X X X X
Second Floor Slab Works 20-Oct-22, Thu 11-Oct-23, Wed
First Floor Weather Proofing Works 10-Jan-23, Tue 14-Jul-24, Sun X X X X X X X X X X X
Flooring works epoxy,kota and tiles 15-May-24, Wed 14-Jul-24, Sun Not started X X
Door Fixtures 20-Mar-24, Wed 24-Apr-24, Wed Not started clearance X X X X X
Window Fixtures 20-Feb-24, Tue 31-Mar-24, Sun Not started clearance X X X X
Internal First Coat of Paint 11-Apr-24, Thu 05-Jul-24, Fri Not started clearance X X X X X X
repair and reworks 20-Mar-24, Wed 29-Apr-24, Mon Not started X X X X X X
Terrace Floor Slab Works 10-Jan-23, Tue 31-Jul-23, Mon
Second Floor Weather Proofing Works 26-May-23, Fri 10-Jul-24, Wed X X X X X X X X X X X X X
block work 31-May-23, Wed 03-Jun-24, Mon work in progress material entry area pending X X X X X X X X X X X X X
Wall Plastering 28-Jul-23, Fri 06-Jun-24, Thu Work In progress dependent X X X X X X X X X X X X X
Door Fixtures 22-Mar-24, Fri 24-Apr-24, Wed Not started based on clearance X X X X X
Window Fixtures 11-Feb-24, Sun 27-Mar-24, Wed Not started X X X X
Internal First Coat of Paint 16-Apr-24, Tue 10-Jul-24, Wed Not started based on clearance X X X X X X
foundation works RCC terrace 19-Sep-23, Tue 17-Mar-24, Sun work in progress X X
Flooring works epoxy 20-May-24, Mon 10-Jun-24, Mon Not started based on clearance
Upper Terrace Floor Slab Works 04-Jun-23, Sun 20-Sep-23, Wed
RTO slab 10-Nov-23, Fri 10-Dec-23, Sun
upper terrace finishign works 23-Oct-23, Mon 27-May-24, Mon X X X X X X X X X X X X X
Waterproofing at lower Terrace 20-Jan-24, Sat 27-Mar-24, Wed work in progress X X X X
external painting 1st coat 12-Apr-24, Fri 27-May-24, Mon Not started based on clearance X X X X X X
Door window fixtures 20-Feb-24, Tue 24-Apr-24, Wed work in progress X X X X X X X X
Staircase 1 mumty works & terrace dog house works ofcut 21-Sep-23, Thu 28-Apr-24, Sun X X X X X X X X
flooring work 28-Feb-24, Wed 29-Mar-24, Fri not started X X X X
railing works 30-Mar-24, Sat 12-Apr-24, Fri not started X X
painting works 1st coat 13-Apr-24, Sat 28-Apr-24, Sun not started clearance requried X X
Staircase 2 finishing works 03-Apr-24, Wed 10-May-24, Fri X X X X X
flooring works 03-Apr-24, Wed 18-Apr-24, Thu not started X X
railing works 19-Apr-24, Fri 29-Apr-24, Mon not started X X
painting works 1st coat 30-Apr-24, Tue 10-May-24, Fri not started clearance requried X
Staircase 3 finishing works 05-Dec-23, Tue 14-May-24, Tue X X X X X X X X X X X
pardi and masonry works 05-Dec-23, Tue 09-Jan-24, Tue works in prgress
flooring works 30-Mar-24, Sat 19-Apr-24, Fri not started X X X
railing works 18-Apr-24, Thu 03-May-24, Fri not started X X
painting works 1st coat 04-May-24, Sat 14-May-24, Tue not started clearance requried
Staircase 4 10-Oct-23, Tue 30-May-24, Thu X X X X X X X X X X X
fabrication of Stainless steel 30-Mar-24, Sat 14-May-24, Tue not started X X X X X X X
Erection of stanless steel 04-Apr-24, Thu 24-May-24, Fri not started X X X X X X X
railing works 25-May-24, Sat 30-May-24, Thu not started
painting works 1st coat 31-May-24, Fri 05-Jun-24, Wed not started
external plastering and shaft works 15-Oct-23, Sun 18-Jun-24, Tue X X X X X X X X X X X
front wall clearance
external shaft works 05-Jan-24, Fri 03-Jun-24, Mon work in progress X X X X X X X X X X X X X
pending
external shaft plastering works 04-Apr-24, Thu 18-Jun-24, Tue not started clearance required X X X X X X X X
Toilet works 15-Oct-23, Sun 29-Jun-24, Sat X X X X X X X X X X X X X
plumbing line 15-Oct-23, Sun 28-Mar-24, Thu work in progress X X X X
waterprooofing works 18-Mar-24, Mon 07-Apr-24, Sun work in progress X X X
flooring works and dado 10-Apr-24, Wed 30-Apr-24, Tue not started clearance required X X X
slab cutout reworks 05-Jan-24, Fri 28-Mar-24, Thu X X X X
structural steel works 28-Jan-24, Sun 28-Mar-24, Thu work in progress X X X X
Lift works 13-Feb-24, Tue 16-May-24, Thu X X X X X X X X X X X
lift blockwork,plaster,white wash 13-Feb-24, Tue 16-Mar-24, Sat
lift structure works 01-Apr-24, Mon 16-May-24, Thu not started drawing req X X X X X X X
ramp works 01-Apr-24, Mon 31-May-24, Fri X X X X X X X X X
entrance ramp works 01-Apr-24, Mon 01-May-24, Wed not started X X X X X
ramp flooring works 26-Apr-24, Fri 21-May-24, Tue not started X X X X
ramp railing works 11-May-24, Sat 31-May-24, Fri not started X X X
14 Creche Area 05-Dec-22, Mon 04-May-24, Sat X X X X X X X X X
14.1 Watertight Building 05-Dec-22, Mon 10-Mar-24, Sun X
14.1.2 Construction Works 01-Feb-23, Wed 04-May-24, Sat X X X X X X X X X
14.1.2.1 Sub Structure 01-Feb-23, Wed 27-Jul-23, Thu
14.1.1.2 Structural Works 10-Mar-23, Fri 14-May-23, Sun
Weather Proofing Works 22-Apr-23, Sat 04-May-24, Sat X X X X X X X X X
ramp works and railign works 10-Dec-23, Sun 19-Mar-24, Tue work in progress X X X
flooring works 13-Apr-24, Sat 28-Apr-24, Sun not started subject to clearance X X
Door window fixtures 25-Oct-23, Wed 10-Mar-24, Sun work in progress Toilet doors pending X
wall painting internal and external with final coat 20-Dec-23, Wed 18-Apr-24, Thu work in progress subject to clearance X X X X X X X
toilet plumbing works 02-Mar-24, Sat 11-Mar-24, Mon work in progress X X
Toilet waterproofing works 13-Mar-24, Wed 19-Mar-24, Tue not started X
toilet flooring and dado 21-Mar-24, Thu 29-Mar-24, Fri not started X
pantry works 23-Mar-24, Sat 02-Apr-24, Tue not started X X
handing over 19-Apr-24, Fri 04-May-24, Sat not started X X
15 Scrap Yard 21-Sep-22, Wed 16-May-24, Thu X X X X X X X X X X X
15.1 Watertight Building 21-Sep-22, Wed 16-Dec-23, Sat
15.1.2 Construction Works 15-Nov-22, Tue 16-May-24, Thu X X X X X X X X X X X
15.1.1.2 Structural Works 20-Dec-22, Tue 16-May-24, Thu X X X X X X X X X X X
Weather Proofing Works 25-Feb-23, Sat 16-May-24, Thu X X X X X X X X X
railing works 07-Jan-24, Sun 17-Mar-24, Sun work in progress X X
flooring works 01-Apr-24, Mon 16-May-24, Thu Not started subject to clearance X X X X X
final coat based on
wall painting internal and external including final coat 25-Nov-23, Sat 23-Apr-24, Tue work in progress X X X X X X X X
clearance
handing over 24-Apr-24, Wed 04-May-24, Sat Not started X
16 Engineering Store Works 10-Apr-23, Mon 10-Jun-24, Mon X X X X X X X X X
Watertight Building 10-Apr-23, Mon 10-Mar-24, Sun X
16.1 Construction Works 10-Apr-23, Mon 21-May-24, Tue X X X X X X X X X
16.1.1 Substructure and finishing works 10-Apr-23, Mon 21-May-24, Tue X X X X X X X X X
railing works 31-Dec-23, Sun 15-Mar-24, Fri work in progress X X
Joinery & Fixtures 25-Oct-23, Wed 10-Mar-24, Sun work in progress Toilet doors pending X
Toilet works 20-Feb-24, Tue 06-Mar-24, Wed work in progress X
sanitary fixtures 21-Mar-24, Thu 10-Apr-24, Wed Not started X X X
final coat based on
internal and external paitning works upto final coat 27-Nov-23, Mon 25-Apr-24, Thu work in progress X X X X X X X X
clearance
handing over 26-Apr-24, Fri 21-May-24, Tue not started subject to clearance X X
17 External Piperack 05-Jul-23, Wed 16-Feb-24, Fri
17.1 CONSTRUCTION WORKS 05-Jul-23, Wed 18-Jan-24, Thu
17.1.1 Substructure 05-Jul-23, Wed 26-Jan-24, Fri
Phase1 Manufacturing to scrap yard 05-Jul-23, Wed 26-Jan-24, Fri
phase 2-scrap yard to CCOE tank 04-Aug-23, Fri 17-Sep-23, Sun
phase 3 ccoe to project office 25-Sep-23, Mon 20-Nov-23, Mon
phase 4 project office to creche 01-Nov-23, Wed 30-Dec-23, Sat
18 Engineering office 15-Jun-23, Thu 11-Apr-24, Thu X X X X X X X X X X X X X
18.1 CONSTRUCTION WORKS 15-Jun-23, Thu 11-Apr-24, Thu X X X X X X X X X X X X
18.1.1 superstructure 15-Jun-23, Thu 11-Apr-24, Thu X X X X X X
toilet washbasin platform works 20-Mar-24, Wed 30-Mar-24, Sat X
sanitary installation works 25-Mar-24, Mon 09-Apr-24, Tue Not started subject to clearance X X X X X X X X
Door window fixtures 04-Mar-24, Mon 14-Mar-24, Thu Not started X X X X X X X X X X X
painting works 31-Jan-24, Wed 31-Mar-24, Sun Not started X X X X
handing over 01-Apr-24, Mon 11-Apr-24, Thu Not started X X
19 temporary shed works 05-Jul-23, Wed 26-Oct-23, Thu
19.1 CONSTRUCTION WORKS 05-Jul-23, Wed 26-Oct-23, Thu
19.1.1 Substructure 05-Jul-23, Wed 26-Oct-23, Thu
20 others 10-Mar-24, Sun 11-Jun-24, Tue X X X X X X X X X X X X
storm water drain water, road crossing, chamber,rain
10-Mar-24, Sun 13-May-24, Mon Not started detail drawing req X X X X X X X X X X
water
external process line connection works 12-Mar-24, Tue 26-Apr-24, Fri Not started X X X X X X
road works at loading unloading warehouse 27-Apr-24, Sat 11-Jun-24, Tue Not started drawing req X X X X X
3 Month plan April24 to June 24
Status as on date
SLNo Description Start Date End date 27-3-24 comments unit Total Qty Apr-24 May-24 Jun-24
Zone1 Warehouse First floor QC area 15-Feb-24, Thu 30-May-24, Thu

Except hold area and


Door fixtures ### ### not started loading,unloading area No's 2 2
internal painting ### ### not started clearance required sqm 100 100
shop drawing to be
approved,other vendor
ss trap fixing ### ### not started clearance no's 22 22
Toilet works 25-Mar-24, Mon 29-Apr-24, Mon
shut down required for
core cutting ,
plumbing works ### ### work in progress plumbingline rmt 20 13.75

material approval
flooring works dado ### ### not started required by 30-03-2024 sqm 52 52

material approval
sanitary fixtures Friday, April 19, 2024 ### not started required by 30-03-2024 No's 6 6
Finishing works QC area 10-Apr-24, Wed 30-May-24, Thu

clearance required for


area beyond partition
area/post engineering
office occupation by
floor Tiles works ### ### not started others sqm 135 54.73 80.27
clearance required by 1-
epoxy works ### ### not started 4-2024 sqm 400 400
Zone2 Warehouse Loading unloading area 21-Feb-24, Wed 17-Jul-24, Wed
after shop drawing
insulated rolling shutter and doors ### ### not started approval no's 3 3
window fixtures ### ### not started no's 4 4
internal painting first coat ### ### not started clearance required sqm 210 210
internal painting final coat ### ### not started clearance required sqm 210 210
flooring works epoxy ### ### not started clearance required sqm 100 100

Demolition works of existing steps ### ### not started after fire line rerouting LS 1 1
new steps construction ### ### not started sqm 10 33.33 6.67

ss railing works Sunday, July 7, 2024 ### not started sample to be submitted rmt 10
Zone3 Warehouse ground floor 01-Feb-24, Thu 19-Sep-24, Thu
except staircase2 door
Door fixtures ### ### not started and entrance no's 4 2
staircase 2 , entrance door ### ### not started no's 2
shop drawing to be
approved,other vendor
ss trap fixing ### ### not started clearance no's 12
external shaft works 01-Apr-24, Mon 19-Sep-24, Thu
existing scaffolding removal ### ### not started sqm 800 800
Work to be started after
Block work ### ### not started MEP works sqm 600 190.91
external plaster works Friday, June 21, 2024 ### not started sqm 700 64.62
staircase 1 01-Feb-24, Thu 19-Jun-24, Wed
painting 1st coat works ### ### not started clearance requried sqm 500 500

railing works Friday, May 17, 2024 Friday, May 24, 2024 not started sample to be submitted rmt 50 50
polish works for flooring ### ### not started sqm 100 83.33 16.67
painting final coat ### ### not started clearance requried sqm 500 50
staircase2 01-May-24, Wed 30-Jun-24, Sun
flooring works ### ### not started clearance requried sqm 100 100
painting 1st coat works ### ### not started clearance requried sqm 500 500
railing works ### ### not started rmt 50 37.5 12.5
polish works for flooring ### Friday, June 14, 2024 not started sqm 100 100
painting final coat ### ### not started clearance requried sqm 500 500
window fixtures 01-Sep-24, Sun 02-Sep-24, Mon
window,louvers fixtures entrance ### ### not started no's 2
Zone4 Warehouse triple height 10-Apr-24, Wed 27-Jul-24, Sat
shop drawing submitted
to be approved by 30-3-
double bank louvers ### Sunday, May 5, 2024 not started 24, no's 9 4.5 4.5
internal painting ### ### not started sqm 960 960
grinding works Sunday, June 2, 2024 Friday, June 7, 2024 not started sqm 900 900
depends upon mositure
flooring works Tuesday, July 2, 2024 ### not started content sqm 900
start based on MEP
fire stop wall cutout filling ### Sunday, May 5, 2024 not started clearance sqm 30 23.68 6.32
Zone5 Warehouse second floor 15-Feb-24, Thu 05-Jul-24, Fri
Door fixtures ### ### not started no's 5 5
Door fixtures existing side ### ### not started no's 1 1
window fixtures ### ### not started equipment area no's 2 2
internal painting final coat ### ### not started clearance required sqm 600 600
epoxy flooring ### Friday, July 5, 2024 not started clearance required sqm 500 222.2
shop drawing to be
approved,other vendor
ss trap fixing ### ### not started clearance no's 4 4
Zone6 existing warehouse modification 25-Apr-24, Thu 12-Jun-24, Wed
Existing area A/L,material in and
waste collection out rooms 25-Apr-24, Thu 12-Jun-24, Wed
1 modification
Rate revision required
for existing building
Demolition works ### Friday, May 10, 2024 not started works sqm 150 50 100
blockwork Sunday, May 5, 2024 ### not started sqm 150 150
plaster ### ### not started sqm 300 300
doors fixing ### ### not started no's 7 7
flooring works ### ### not started sqm 30 26.67 3.33
painting Sunday, June 2, 2024 ### not started sqm 300 300
Zone7 Utility area & lower terrace Manufact 19-Sep-23, Tue 10-Jul-24, Wed
khurra fixing ### ### not started no's 10 10
Door fixtures rolling shutter ### ### not started no's 5 1.91
window glass fixing and louvers ### ### not started no's 21 21
fooring works utility area ### ### not started sqm 900 420
diamond cutting for new cutouts ### ### not started scaffolding required rmt 20 20
dog house works ### ### not started no's 2 1.64 0.36
Manufacturing block Ground floor 05-Jan-24, Fri 30-Aug-24, Fri
Zone8 grid P1 to P5
existing scaffolding removal ### ### not started sqm 4100 4100

works held up due to


scaffolding,works to be
shaft block work external ### ### work in progress started after MEP works sqm 1600 277.17 289.76 264.57
shaft plastering works external ### ### not started sqm 2000 761.9 952.38
based on MEP
epoxy grinding works ### Sunday, May 5, 2024 not started completion sqm 1200 947.37 252.63
based on MEP
epoxy flooring 1st coat screed works ### ### not started completion sqm 1200 505.26 694.74
lift1 structure works ### ### not started After clearance MT 2.5 2.5
completion based on
Door fixtures ### ### not started clearance no's 11 10.52 0.48
completion based on
window glass fixtures ### ### not started clearance no's 7 6.7 0.3

louvers ### Friday, June 21, 2024 not started shop drawing approval no's 3 3
rolling shutter ### ### not started no's 2 2
lift pedestal work ### ### not started after structure work no's 2 2
completion based on
fire stop wall cutout filling ### ### not started clearance no's 24 7.64
shop drawing to be
approved,other vendor
ss trap fixing ### ### not started clearance no's 26 26
2 Staircase 1 works 28-Feb-24, Wed 21-Jul-24, Sun
painting 1st coat works ### ### not started clearance requried sqm 700 700
railing works ### ### not started rmt 50 50
polish works for flooring ### Friday, July 5, 2024 not started sqm 150 103.13
painting final coat ### Sunday, July 21, 2024 not started clearance requried sqm 700
3 Staircase 4 works 01-Apr-24, Mon 16-Jun-24, Sun
staircase 4 fabrication and erection
works ### ### not started MT 16 5.65 10.35
staricase 4 railing works Friday, May 31, 2024 Friday, June 7, 2024 not started rmt 25 4.17 20.83
dumb waiter dismantling works and
diamond cutting ### ### not started rmt 5 5
masonry works of dumb waiter Friday, April 12, 2024 ### not started sqm 50 43.33 6.67
Door window fixtures ### ### not started no's 3 3
painting works ### ### not started sqm 300 300
Zone9 First floor grid P1 to P5 20-Mar-24, Wed 27-Jun-24, Thu
1 finishing works 20-Mar-24, Wed 27-Jun-24, Thu
Flooring works epoxy ### Friday, May 31, 2024 not started sqm 1200 1200
completion based on
door fixtures ### ### not started clearance no's 17 17
completion based on
window fixtures ### ### not started clearance no's 17 17
completion based on
rolling shutter ### ### not started clearance no's 1 1

louvers ### ### not started shop drawing approval no's 6 6


completion based on
painting works ### ### work in progress clearance sqm 1500 733.33 500
Zone10 Second floor grid P1 to P5 20-Mar-24, Wed 08-Jul-24, Mon
1 finishing works 20-Mar-24, Wed 08-Jul-24, Mon
Flooring works epoxy ### ### not started sqm 1200 1200
Door fixtures ### ### not started no's 13 4.33
window glass fixtures ### ### not started no's 13 13
rolling shutter Friday, June 28, 2024 Monday, July 8, 2024 not started no's 1 0.14
louvers ### Monday, July 1, 2024 not started no's 1 0.93
painting works ### ### not started sqm 1500 590 616 294
Zone11 Ground floor grid P5 to P10 29-Mar-24, Fri 24-Jul-24, Wed
1 finishing works 01-Apr-24, Mon 21-Jul-24, Sun
wall dismantling works ### ### not started sqm 120 60
Kone material to be
Block works for server room ### ### not started shifted sqm 180 180
Kone material to be
Plastering for server room ### Sunday, April 7, 2024 not started shifted sqm 360 360
flooring works epoxy ### Sunday, July 21, 2024 not started After clearance sqm 850 123 283 246
flooring works tiles,kota,granite ### Sunday, July 21, 2024 not started sqm 350 51 116 102
grade slab works entrance lobby ### ### work in progress after fire line rerouting sqm 35 35
lift2 structure works ### ### not started After clearance MT 2.5 2.5
lift 3 structure works ### ### not started After clearance MT 2.5 2.5
lift 4 structure works ### ### not started After clearance MT 2.5 2.5
Door fixtures ### ### not started no's 11 11
window glass fixtures ### ### not started no's 7 7
rolling shutter ### ### not started no's 2 0.22
louvers Friday, June 14, 2024 Friday, June 21, 2024 not started no's 3 3
2 Staircase 2 works 10-Apr-24, Wed 19-Jul-24, Fri

staircase 2 grade slab works ### ### not started after fire line rerouting sqm 15 15
staircase 2 flooring ### ### not started sqm 40 40
staricase2 railing works ### ### not started rmt 15 3.75
staricase2 painting works Friday, July 12, 2024 Friday, July 19, 2024 not started sqm 220
3 Staircase 3 works 01-May-24, Wed 24-Jul-24, Wed
staircase 3 flooring ### ### not started sqm 150 150
staricase3 railing works ### ### not started sqm 50 10
staricase 3 painting works 1st coat ### ### not started sqm 700
4 toilet works 01-Apr-24, Mon 25-May-24, Sat
sunken filling works ### ### not started sqm 4 4
flooring,dado works ### ### not started sqm 11 11
sanitary fixtures Friday, May 10, 2024 ### not started based on clearance No's 2 2
Zone12 First floor grid P5 to P10 20-Mar-24, Wed 10-Aug-24, Sat
1 finishing works 20-Mar-24, Wed 10-Aug-24, Sat
epoxy works ### ### work in progress sqm 1000 212 220 192
kota,tiles works ### ### work in progress sqm 200 13 2.3
Door fixtures ### ### not started only external doors no's 17 17
window glass fixtures ### ### not started only external doors no's 17 17
rolling shutter ### ### no's 1
louvers ### ### no's 6 6
painting works ### ### work in progress sqm 1500 354 370 323
2 toilet works 01-Apr-24, Mon 27-May-24, Mon
sunken filling works ### ### not started sqm 45 45
flooring,dado works ### ### not started sqm 170 142 28
sanitary fixtures ### ### not started based on clearance no's 11 11
Zone13 second floor grid P5 to P10 20-Mar-24, Wed 18-Jul-24, Thu
PWS foundation ### ### not started no 2 2
epoxy works 1st coat ### ### not started sqm 1200 1200
Door fixtures ### Friday, April 19, 2024 not started no's 13 8.5
window glass fixtures ### Sunday, May 5, 2024 not started no's 13 5.5 7.5
rolling shutter Monday, July 8, 2024 ### not started no's 1
louvers ### ### not started no's 1 1
painting works Friday, April 5, 2024 ### not started sqm 1500 1500
14 Creche 05-Apr-24, Fri 26-Jun-24, Wed
1 finishing works 05-Apr-24, Fri 26-Jun-24, Wed
ramp railing works Friday, April 5, 2024 ### not started rmt 6 6
flooring works ### ### not started sqm 75 75
Door fixtures ### ### not started Toilet doors pending no's 4 4
ventilators Friday, April 26, 2024 ### not started no's 2 2
dog house louvers ### ### not started no's 2 2
wall painting internal and external completion based on
with final coat ### ### work in progress clearance sqm 300 70
Toilet waterproofing works ### Friday, April 12, 2024 not started sqm 5 5
toilet flooring and dado ### ### not started sqm 35 35
handing over Friday, April 19, 2024 ### not started JOB 1 0.67 0.33
15 scrap yard 01-May-24, Wed 16-May-24, Thu
1 finishing works 01-May-24, Wed 16-May-24, Thu

flooring works ### ### not started start based on clearance sqm 40 40
wall painting internal and external completion based on
with final coat ### ### work in progress clearance sqm 580 135
16 Engineering Store Works 10-Apr-23, Mon 12-May-24, Sun
Joinery & Fixtures ### ### work in progress Toilet doors pending no's 2 0.13
toilet plumbing works ### ### work in progress rmt 20 4.32
material approval required
toilet flooring and dado ### Friday, April 26, 2024 not started dado no's 2 2

2.5
sanitary fixtures ### ### not started start based on clearance no's 4 1.5
internal and external paitning works final coat based on
upto final coat ### ### work in progress clearance sqm 850 154 63
17 Engineering office 10-Apr-23, Mon 21-May-24, Tue
Joinery & Fixtures ### ### work in progress crash panel no's 1 1
sanitary fixtures ### ### not started no's 4 4
internal and external paitning works final coat based on
final coat ### ### not started clearance sqm 200 200
18 CCOE tank, panel room 10-Apr-23, Mon 07-Jun-24, Fri
railing works ### ### not started rmt 100 27.2
based on MEP material
soil filling works ### ### not started clearance sqm 2500 2500
based on MEP material
chain link fencing ### Friday, May 17, 2024 work in progress clearance rmt 200 51 30
based on MEP material
stone pitching ### Friday, May 17, 2024 not started clearance sqm 200 86 114
painting final coat ### Friday, June 7, 2024 not started subject to clearance sqm 400 275 125
19 Boiler house 10-Apr-23, Mon 21-Jun-24, Fri
fire stop wall cutout filling ### ### not started subject to clearance no's 12 12
painting final coat internal and
external ### Friday, June 21, 2024 not started subject to clearance sqm 1100 1100
20 UG tank 10-Apr-23, Mon 15-Apr-24, Mon
core cutting Friday, April 5, 2024 ### not started subject to clearance no's 6 6
inside tank epoxy reworks Sunday, April 7, 2024 Friday, April 12, 2024 not started subject to clearance sqm 50 50
tank top waterproofing works ### ### not started sqm 165 165
21 Substation 10-Apr-23, Mon 22-May-24, Wed
fire stop cutout filling ### ### not started subject to clearance no's 4 4
painting final coat ### ### not started subject to clearance sqm 1100 1100
completion based on
flooring works ### ### work in progress clearance sqm 80 40 25.45
21 Pipe rack work PS21a,21b,17a 10-Apr-23, Mon 16-Apr-24, Tue
excavation works ### ### work in progress no's 5 4
pcc works ### ### not started no's 5 5
footing rcc works Sunday, April 7, 2024 ### not started no's 5 5
pedestal works ### ### not started no's 5 5
22 20KL storage tank foundation 10-Apr-23, Mon 04-May-24, Sat

RFI clearance by 30-3-


24,matrix material to be
removed, Ferring
excavation works ### ### not started clearance requried no's 2 2
pcc works ### ### not started no's 2 2
RCC works wall ### ### not started no's 2 2
soil filling works ### ### not started no's 2 2
grade slab works ### ### not started no's 2 2
23 external service 10-Apr-23, Mon 01-Jul-24, Mon
Drawing clearance
storm water drain works ### ### work in progress requried by 5-4-24 rmt 250 120 110
effluent drain works ### Friday, May 31, 2024 work in progress rmt 150 75 75
road works ### Friday, May 31, 2024 work in progress sqm 500 250 250
pathway works ### Monday, July 1, 2024 not started drawing required rmt 200 190
1 Month plan April24

SLNo Description Start Date End date


Zone1 Warehouse First floor QC area 15-Feb-24, Thu 30-May-24, Thu
internal painting ### ###
3 Core cutting for process drain 15-Feb-24, Thu 06-Mar-24, Wed
Toilet works 25-Mar-24, Mon 29-Apr-24, Mon

plumbing works ### ###

flooring works dado ### ###

sanitary fixtures Friday, April 19, 2024 ###


Finishing works QC area 10-Apr-24, Wed 30-May-24, Thu

floor Tiles works ### ###

epoxy works ### ###


9 terrace pipe rack works 24-Feb-24, Sat 15-Mar-24, Fri
Zone2 Warehouse Loading unloading area 21-Feb-24, Wed 17-Jul-24, Wed
1 substructure works 21-Feb-24, Wed 09-Mar-24, Sat
window fixtures ### ###
internal painting first coat ### ###

Demolition works of existing steps ### ###


new steps construction ### ###

ss railing works Sunday, July 7, 2024 ###


Zone3 Warehouse ground floor 01-Feb-24, Thu 19-Sep-24, Thu

Door fixtures ### ###


staircase 2 , entrance door ### ###

ss trap fixing ### ###


external shaft works 01-Apr-24, Mon 19-Sep-24, Thu
existing scaffolding removal ### ###
staircase 1 01-Feb-24, Thu 19-Jun-24, Wed
painting 1st coat works ### ###
staircase2 01-May-24, Wed 30-Jun-24, Sun
window fixtures 01-Sep-24, Sun 02-Sep-24, Mon
Zone4 Warehouse triple height 10-Apr-24, Wed 27-Jul-24, Sat

double bank louvers ### Sunday, May 5, 2024

fire stop wall cutout filling ### Sunday, May 5, 2024


Zone5 Warehouse second floor 15-Feb-24, Thu 05-Jul-24, Fri
Door fixtures ### ###
Zone6 existing warehouse modification 25-Apr-24, Thu 12-Jun-24, Wed
Existing area A/L,material in and
waste collection out rooms 25-Apr-24, Thu 12-Jun-24, Wed
1 modification
Demolition works ### Friday, May 10, 2024
Zone7 Utility area & lower terrace Manufact 19-Sep-23, Tue 10-Jul-24, Wed
finishing works 19-Sep-23, Tue 10-Jul-24, Wed
khurra fixing ### ###
Door fixtures rolling shutter ### ###
window glass fixing and louvers ### ###
diamond cutting for new cutouts ### ###
dog house works ### ###
Manufacturing block Ground floor 05-Jan-24, Fri 30-Aug-24, Fri
Zone8 grid P1 to P5
1 finishing works 05-Jan-24, Fri 30-Aug-24, Fri
existing scaffolding removal ### ###

shaft block work external ### ###

epoxy grinding works ### Sunday, May 5, 2024

epoxy flooring 1st coat screed works ### ###


lift1 structure works ### ###

Door fixtures ### ###

window glass fixtures ### ###


lift pedestal work ### ###

ss trap fixing ### ###


2 Staircase 1 works 28-Feb-24, Wed 21-Jul-24, Sun
painting 1st coat works ### ###
3 Staircase 4 works 01-Apr-24, Mon 16-Jun-24, Sun
staircase 4 fabrication and erection
works ### ###
dumb waiter dismantling works and
diamond cutting ### ###
masonry works of dumb waiter Friday, April 12, 2024 ###
Zone9 First floor grid P1 to P5 20-Mar-24, Wed 27-Jun-24, Thu
1 finishing works 20-Mar-24, Wed 27-Jun-24, Thu

door fixtures ### ###

window fixtures ### ###

painting works ### ###


Zone10 Second floor grid P1 to P5 20-Mar-24, Wed 08-Jul-24, Mon
1 finishing works 20-Mar-24, Wed 08-Jul-24, Mon
Door fixtures ### ###
window glass fixtures ### ###
painting works ### ###
2 Rework and repair 20-Mar-24, Wed 29-Apr-24, Mon
Zone11 Ground floor grid P5 to P10 29-Mar-24, Fri 24-Jul-24, Wed
1 finishing works 01-Apr-24, Mon 21-Jul-24, Sun
wall dismantling works ### ###

Block works for server room ### ###

Plastering for server room ### Sunday, April 7, 2024


flooring works epoxy ### ###
flooring works tiles,kota,granite ### ###
grade slab works entrance lobby ### ###
lift2 structure works ### ###
lift 3 structure works ### ###
lift 4 structure works ### ###
window glass fixtures ### ###
2 Staircase 2 works 10-Apr-24, Wed 19-Jul-24, Fri
staircase 2 grade slab works ### ###
staircase 2 flooring ### ###
3 Staircase 3 works 01-May-24, Wed 24-Jul-24, Wed
4 toilet works 01-Apr-24, Mon 25-May-24, Sat
sunken filling works ### ###
flooring,dado works ### ###
sanitary fixtures Friday, May 10, 2024 ###
Zone12 First floor grid P5 to P10 20-Mar-24, Wed 10-Aug-24, Sat
1 finishing works 20-Mar-24, Wed 10-Aug-24, Sat
epoxy works ### ###
kota,tiles works ### ###
Door fixtures ### ###
window glass fixtures ### ###
painting works ### ###
2 toilet works 01-Apr-24, Mon 27-May-24, Mon
sunken filling works ### ###
flooring,dado works ### ###
Zone13 second floor grid P5 to P10 20-Mar-24, Wed 18-Jul-24, Thu
PWS foundation ### ###
epoxy works 1st coat ### ###
Door fixtures ### Friday, April 19, 2024
window glass fixtures ### Sunday, May 5, 2024
painting works Friday, April 5, 2024 ###
14 Creche 05-Apr-24, Fri 26-Jun-24, Wed
1 finishing works 05-Apr-24, Fri 26-Jun-24, Wed
ramp railing works Friday, April 5, 2024 ###
flooring works ### ###
Door fixtures ### ###
ventilators Friday, April 26, 2024 ###
wall painting internal and external
with final coat ### ###
Toilet waterproofing works ### Friday, April 12, 2024
toilet flooring and dado ### ###
handing over Friday, April 19, 2024 ###
15 scrap yard 01-May-24, Wed 16-May-24, Thu
1 finishing works 01-May-24, Wed 16-May-24, Thu
wall painting internal and external
with final coat ### ###
16 Engineering Store Works 10-Apr-23, Mon 12-May-24, Sun
Joinery & Fixtures ### ###
toilet plumbing works ### ###

toilet flooring and dado ### Friday, April 26, 2024

sanitary fixtures ### ###


internal and external paitning works
upto final coat ### ###
17 Engineering office 10-Apr-23, Mon 21-May-24, Tue
sanitary fixtures ### ###
internal and external paitning works
final coat ### ###
18 CCOE tank, panel room 10-Apr-23, Mon 07-Jun-24, Fri
railing works ### ###

chain link fencing ### Friday, May 17, 2024

stone pitching ### Friday, May 17, 2024


19 Boiler house 10-Apr-23, Mon 21-Jun-24, Fri
fire stop wall cutout filling ### ###
20 UG tank 10-Apr-23, Mon 15-Apr-24, Mon
core cutting Friday, April 5, 2024 ###
inside tank epoxy reworks Sunday, April 7, 2024 Friday, April 12, 2024
tank top waterproofing works ### ###
21 Substation 10-Apr-23, Mon 22-May-24, Wed

flooring works ### ###


21 Pipe rack work PS21a,21b,17a 10-Apr-23, Mon 16-Apr-24, Tue
excavation works ### ###
pcc works ### ###
footing rcc works Sunday, April 7, 2024 ###
pedestal works ### ###
22 20KL storage tank foundation 10-Apr-23, Mon 04-May-24, Sat

excavation works ### ###


pcc works ### ###
RCC works wall ### ###
soil filling works ### ###
23 external service 10-Apr-23, Mon 01-Jul-24, Mon

storm water drain works ### ###


effluent drain works ### Friday, May 31, 2024
road works ### Friday, May 31, 2024
Status as on date
27-3-24 comments unit Apr-24 days Qty per day

not started clearance required sqm 100 10.00 10.00


20.00 0.00
35.00 0.00
shut down required for
work in progress core cutting rmt 13.75 20.00 0.69

material approval
not started required by 30-03-2024 sqm 52 10.00 5.20

material approval
not started required by 30-03-2024 No's 6 10.00 0.60
50.00 0.00

clearance required for


area beyond partition
area/post engineering
office occupation by
not started others sqm 54.73 50.00 1.09
clearance required by 1-
not started 4-2024 sqm 400 10.00 40.00
20.00 0.00
147.00 0.00
17.00 0.00
not started no's 4 5.00 0.80
not started sqm 210 5.00 42.00

not started after fire line rerouting LS 1 7.00 0.14


not started sqm 33.33 10.00 3.33

not started sample to be submitted rmt 10.00 0.00


231.00 0.00
except staircase2 door
not started and entrance no's 2 7.00 0.29
not started no's 5.00 0.00
shop drawing to be
approved,other vendor
not started clearance no's 10.00 0.00
171.00 0.00
not started sqm 800 5.00 160.00
139.00 0.00
not started clearance requried sqm 500 7.00 71.43
60.00 0.00
1.00 0.00
108.00 0.00
shop drawing submitted
to be approved by 30-3-
not started 24, no's 4.5 10.00 0.45
start based on MEP
not started clearance sqm 23.68 25.00 0.95
141.00 0.00
not started no's 5 5.00 1.00
48.00 0.00
Rate revision required
for existing building
works 48.00 0.00
not started sqm 50 15.00 3.33
295.00 0.00
10h 295.00 #VALUE!
not started no's 10 10.00 1.00
not started no's 1.91 64.00 0.03
not started no's 21 0.00 #DIV/0!
not started rmt 20 7.00 2.86
not started no's 1.64 14.00 0.12

238.00 0.00
238.00 0.00
not started sqm 4100 10.00 410.00
works held up due to
work in progress scaffolding sqm 277.17 177.00 1.57
based on MEP
not started completion sqm 947.37 25.00 37.89
based on MEP
not started completion sqm 505.26 25.00 20.21
not started After clearance MT 2.5 10.00 0.25
completion based on
not started clearance no's 10.52 30.00 0.35
completion based on
not started clearance no's 6.7 30.00 0.22
not started no's 2 12.00 0.17
shop drawing to be
approved,other vendor
not started clearance no's 10.00 0.00
144.00 0.00
not started clearance requried sqm 700 7.00 100.00
76.00 0.00

not started MT 5.65 45.00 0.13

not started rmt 5 10.00 0.50


not started sqm 43.33 20.00 2.17
99.00 0.00
99.00 0.00
completion based on
not started clearance no's 17 15.00 1.13
completion based on
not started clearance no's 17 15.00 1.13
completion based on
work in progress clearance sqm 733.33 62.00 11.83
110.00 0.00
110.00 0.00
not started no's 4.33 15.00 0.29
not started no's 13 7.00 1.86
not started sqm 590 76.00 7.76
40.00 0.00
117.00 0.00
111.00 0.00
not started sqm 60 3.00 20.00
Kone material to be
not started shifted sqm 180 4.00 45.00
Kone material to be
not started shifted sqm 360 4.00 90.00
not started After clearance sqm 123 95.00 1.29
not started sqm 51 95.00 0.54
work in progress sqm 35 15.00 2.33
not started After clearance MT 2.5 17.00 0.15
not started After clearance MT 2.5 17.00 0.15
not started After clearance MT 2.5 17.00 0.15
not started no's 7 5.00 1.40
100.00 0.00
not started sqm 15 10.00 1.50
not started sqm 40 7.00 5.71
84.00 0.00
54.00 0.00
not started sqm 4 7.00 0.57
not started sqm 11 21.00 0.52
not started based on clearance No's 15.00 0.00
143.00 0.00
143.00 0.00
work in progress sqm 212 143.00 1.48
work in progress sqm 13 45.00 0.29
not started only external doors no's 17 11.00 1.55
not started only external doors no's 17 11.00 1.55
work in progress sqm 354 128.00 2.77
56.00 0.00
not started sqm 45 15.00 3.00
not started sqm 142 15.00 9.47
120.00 0.00
not started no 2 7.00 0.29
not started sqm 1200 10.00 120.00
not started no's 8.5 30.00 0.28
not started no's 5.5 7.00 0.79
not started sqm 1500 10.00 150.00
82.00 0.00
82.00 0.00
not started rmt 6 10.00 0.60
not started sqm 75 15.00 5.00
not started Toilet doors pending no's 4 0.00 #DIV/0!
not started no's 2 2.00 1.00
completion based on
work in progress clearance sqm 70 132.00 0.53
not started sqm 5 10.00 0.50
not started sqm 35 10.00 3.50
not started JOB 0.67 15.00 0.04
15.00 0.00
15.00 0.00
completion based on
work in progress clearance sqm 135 132.00 1.02
398.00 0.00
work in progress Toilet doors pending no's 0.13 168.00 0.00
work in progress rmt 4.32 50.00 0.09
material approval required
not started dado no's 2 15.00 0.13

not started start based on clearance no's 1.5 10.00 0.15


final coat based on
work in progress clearance sqm 154 167.00 0.92
407.00 0.00
not started no's 4 5.00 0.80
final coat based on
not started clearance sqm 200 5.00 40.00
424.00 0.00
not started rmt 27.2 27.00 1.01
based on MEP material
work in progress clearance rmt 51 118.00 0.43
based on MEP material
not started clearance sqm 86 30.00 2.87
438.00 0.00
not started subject to clearance no's 12 10.00 1.20
371.00 0.00
not started subject to clearance no's 6 1.00 6.00
not started subject to clearance sqm 50 5.00 10.00
not started sqm 165 7.00 23.57
408.00 0.00
completion based on
work in progress clearance sqm 40 60.00 0.67
372.00 0.00
work in progress no's 4 10.00 0.40
not started no's 5 10.00 0.50
not started no's 5 8.00 0.63
not started no's 5 6.00 0.83
390.00 0.00

RFI clearance by 30-3-


24,matrix material to be
removed, Ferring
not started clearance requried no's 2 7.00 0.29
not started no's 2 1.00 2.00
not started no's 2 7.00 0.29
not started no's 2 2.00 1.00
448.00 0.00
Drawing clearance
work in progress requried by 5-4-24 rmt 120 71.00 1.69
work in progress rmt 75 72.00 1.04
work in progress sqm 250 67.00 3.73
1-Apr 2-Apr 3-Apr 4-Apr 5-Apr 6-Apr 7-Apr 8-Apr 9-Apr 10-Apr
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
- - - - - - - - - -

0.69 0.69 0.69 0.69 0.69 0.69 0.69 0.69 0.69 0.69

0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 -

0 0 0 0 0 0 0 0 0 1.09

0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
- - - - - - - - - -
0 0 0 0 0 0 0 0 0 0
0.80 0.80 0.80 0.80 0.80 0.80 0 0 0 0
0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0
- - - - - - - - - -

0.29 0.29 0.29 0 0 0 0 0 0 0


0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0
- - - - - - - - - -
160.00 160.00 160.00 160.00 160.00 160.00 0 0 0 0
- - - - - - - - - -
0 0 0 0 0 0 0 0 0 71.43
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 -

0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0.95
- - - - - - - - - -
0 0 0 0 0 0 0 0 0 1.00
0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
- - - - - - - - - -
#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
0 0 0 0 0 0 0 0 0 1.00
0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 2.86
0 0 0 0 0 0 0 0 0 0

- - - - - - - - - -
- - - - - - - - - -
0 0 0 0 0 410.00 410.00 410.00 410.00 410.00

1.57 1.57 1.57 1.57 1.57 1.57 1.57 1.57 1.57 1.57

0 0 0 0 0 0 0 0 0 37.89

0 0 0 0 0 0 0 0 0 0
0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25

0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35

0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22
0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0
- - - - - - - - - -
100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 0 0
- - - - - - - - - -

0 0 0 0 0 0 0 0 0 0

0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50
0 0 0 0 0 0 0 0 0 0
- - - - - - - - - -
- - - - - - - - - -

1.13 1.13 1.13 1.13 1.13 1.13 1.13 1.13 1.13 1.13

1.13 1.13 1.13 1.13 1.13 1.13 1.13 1.13 1.13 1.13

11.83 11.83 11.83 11.83 11.83 11.83 11.83 11.83 11.83 11.83
- - - - - - - - - -
- - - - - - - - - -
0.29 0.29 0.29 0.29 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
7.76 7.76 7.76 7.76 7.76 7.76 7.76 7.76 7.76 7.76
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
20.00 0 0 0 0 0 0 0 0 0

0 45.00 45.00 45.00 45.00 45.00 0 0 0 0

0 0 90.00 90.00 90.00 90.00 90.00 0 0 0


0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
2.33 2.33 2.33 2.33 2.33 2.33 2.33 2.33 2.33 2.33
0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15
0 0 0 0 0 0.15 0.15 0.15 0.15 0.15
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 -
0 0 0 0 0 0 0 0 0 1.50
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
- - - - - - - - - -
0.57 0.57 0.57 0.57 0.57 0.57 0.57 0.57 0 0
0 0 0 0 0 0 0 0 0.52 0.52
0 0 0 0 0 0 0 0 0 0
- - - - - - - - - -
- - - - - - - - - -
1.48 1.48 1.48 1.48 1.48 1.48 1.48 1.48 1.48 1.48
0.29 0.29 0.29 0.29 0.29 0.29 0.29 0.29 0.29 0.29
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
2.77 2.77 2.77 2.77 2.77 2.77 2.77 2.77 2.77 2.77
- - - - - - - - - -
3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00 3.00
0 0 0 0 0 0 0 0 0 0
- - - - - - - - - -
0.29 0.29 0.29 0.29 0.29 0.29 0.29 0.29 0 0
0 0 0 0 0 0 0 0 0 0
0.28 0.28 0.28 0.28 0.28 0.28 0.28 0.28 0.28 0.28
0 0 0 0 0 0 0 0 0 0
0 0 0 0 150.00 150.00 150.00 150.00 150.00 150.00
0 0 0 0 - - - - - -
0 0 0 0 - - - - - -
0 0 0 0 0.60 0.60 0.60 0.60 0.60 0.60
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0

0.53 0.53 0.53 0.53 0.53 0.53 0.53 0.53 0.53 0.53
0 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0

1.02 1.02 1.02 1.02 1.02 1.02 1.02 1.02 1.02 1.02
- - - - - - - - - -
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09

0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0

0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92
- - - - - - - - - -
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
- - - - - - - - - -
1.01 1.01 1.01 1.01 1.01 1.01 0 0 0 0

0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43

0 0 0 0 0 0 0 0 0 0
- - - - - - - - - -
0 0 0 0 0 0 0 0 0 0
- - - - - - - - - -
0 0 0 0 6.00 6.00 0 0 0 0
0 0 0 0 0 0 10.00 10.00 10.00 10.00
0 0 0 0 0 0 0 23.57 23.57 23.57
- - - - - - - - - -

0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67
- - - - - - - - - -
0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0.40 0
0 0 0 0.50 0.50 0.50 0.50 0.50 0.50 0.50
0 0 0 0 0 0 0.63 0.63 0.63 0.63
0 0 0 0 0 0 0 0 0 0.83
- - - - - - - - - -

0.29 0.29 0.29 0.29 0.29 0.29 0.29 0.29 0 0


0 0 0 0 0 0 0 0 2.00 2.00
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
- - - - - - - - - -

1.69 1.69 1.69 1.69 1.69 1.69 1.69 1.69 1.69 1.69
1.04 1.04 1.04 1.04 1.04 1.04 1.04 1.04 1.04 1.04
3.73 3.73 3.73 3.73 3.73 3.73 3.73 3.73 3.73 3.73
11-Apr 12-Apr 13-Apr 14-Apr 15-Apr 16-Apr 17-Apr 18-Apr 19-Apr 20-Apr
0 0 0 0 0 0 0 0 0 10.00
0 0 0 0 0 0 0 0 0 0
- - - - - - - - - -

0.69 0.69 0.69 0.69 0 0 0 0 0 0

0 0 0 0 5.20 5.20 5.20 5.20 5.20 5.20

0 0 0 0 0 0 0 0 0.60 0.60
- - - - - - - - - -

1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09

0 0 0 0 40.00 40.00 40.00 40.00 40.00 40.00


0 0 0 0 0 0 0 0 0 0
- - - - - - - - - -
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 42.00

0 0 0 0 0 0 0 0 0 0.14
0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0
- - - - - - - - - -

0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0
- - - - - - - - - -
0 0 0 0 0 0 0 0 0 0
- - - - - - - - - -
71.43 71.43 71.43 71.43 71.43 71.43 71.43 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
- - - - - - - - - -

0 0 0 0 0 0 0 0 0 0

0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95
- - - - - - - - - -
1.00 1.00 1.00 1.00 1.00 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
- - - - - - - - - -
#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
0 0 0 0 0 0 0 0 0 0
2.86 2.86 2.86 2.86 2.86 2.86 2.86 0 0 0
0 0 0 0 0 0 0 0.12 0.12 0.12

- - - - - - - - - -
- - - - - - - - - -
410.00 410.00 410.00 410.00 410.00 410.00 0 0 0 0

1.57 1.57 1.57 1.57 1.57 1.57 1.57 1.57 1.57 1.57

37.89 37.89 37.89 37.89 37.89 37.89 37.89 37.89 37.89 37.89

0 0 0 0 0 0 0 0 0 20.21
0.25 0 0 0 0 0 0 0 0 0

0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35

0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22
0 0 0 0 0 0 0 0.17 0.17 0.17

0 0 0 0 0 0 0 0 0 0
- - - - - - - - - -
0 0 0 0 0 0 0 0 0 0
- - - - - - - - - -

0 0 0 0 0.13 0.13 0.13 0.13 0.13 0.13

0.50 0 0 0 0 0 0 0 0 0
0 2.17 2.17 2.17 2.17 2.17 2.17 2.17 2.17 2.17
- - - - - - - - - -
- - - - - - - - - -

1.13 1.13 1.13 1.13 1.13 1.13 0 0 0 0

1.13 1.13 1.13 1.13 1.13 1.13 0 0 0 0

11.83 11.83 11.83 11.83 11.83 11.83 11.83 11.83 11.83 11.83
- - - - - - - - - -
- - - - - - - - - -
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 1.86 1.86 1.86 1.86
7.76 7.76 7.76 7.76 7.76 7.76 7.76 7.76 7.76 7.76
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 1.29 1.29 1.29 1.29
0 0 0 0 0 0 0.54 0.54 0.54 0.54
2.33 2.33 2.33 2.33 2.33 2.33 0 0 0 0
0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0 0
0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15
0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15
0 0 0 0 0 0 0 0 0 0
- - - - - - - - - -
1.50 1.50 1.50 1.50 1.50 1.50 1.50 1.50 1.50 1.50
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
- - - - - - - - - -
0 0 0 0 0 0 0 0 0 0
0.52 0.52 0.52 0.52 0.52 0.52 0.52 0.52 0.52 0.52
0 0 0 0 0 0 0 0 0 0
- - - - - - - - - -
- - - - - - - - - -
1.48 1.48 1.48 1.48 1.48 1.48 1.48 1.48 1.48 1.48
0.29 0.29 0.29 0.29 0.29 0.29 0.29 0.29 0.29 0.29
0 0 0 0 0 1.55 1.55 1.55 1.55 1.55
0 0 0 0 0 1.55 1.55 1.55 1.55 1.55
2.77 2.77 2.77 2.77 2.77 2.77 2.77 2.77 2.77 2.77
- - - - - - - - - -
3.00 3.00 3.00 3.00 3.00 3.00 0 0 0 0
0 0 0 0 0 0 9.47 9.47 9.47 9.47
- - - - - - - - - -
0 0 0 0 0 0 0 0 0 0
0 0 0 0 120.00 120.00 120.00 120.00 120.00 120.00
0.28 0.28 0.28 0.28 0.28 0.28 0.28 0.28 0.28 0
0 0 0 0 0 0 0 0 0 0
150.00 150.00 150.00 150.00 150.00 0 0 0 0 0
- - - - - - - - - -
- - - - - - - - - -
0.60 0.60 0.60 0.60 0.60 0 0 0 0 0
0 0 0 0 5.00 5.00 5.00 5.00 5.00 5.00
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0

0.53 0.53 0.53 0.53 0.53 0.53 0.53 0.53 0.53 0.53
0.50 0.50 0 0 0 0 0 0 0 0
0 0 0 0 3.50 3.50 3.50 3.50 3.50 3.50
0 0 0 0 0 0 0 0 0.04 0.04
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0

1.02 1.02 1.02 1.02 1.02 1.02 1.02 1.02 1.02 1.02
- - - - - - - - - -
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0

0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13

0 0 0 0 0 0 0 0 0 0

0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92
- - - - - - - - - -
0 0 0 0 0.80 0.80 0.80 0.80 0.80 0.80
0 0 0 0 0 0 0 0 0 40.00
- - - - - - - - - -
0 0 0 0 0 0 0 0 0 0

0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43

0 0 0 0 0 0 2.87 2.87 2.87 2.87


- - - - - - - - - -
0 0 0 0 0 0 0 0 0 1.20
- - - - - 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
10.00 10.00 0 0 0 0 0 0 0 0
23.57 23.57 23.57 23.57 23.57 0 0 0 0 0
- - - - - - - - - -

0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67
- - - - - - 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0.50 0.50 0.50 0.50 0 0 0 0 0 0
0.63 0.63 0.63 0.63 0.63 0 0 0 0 0
0.83 0.83 0.83 0.83 0.83 0.83 0 0 0 0
- - - - - - - - - -

0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0.29 0.29 0.29 0.29 0.29 0.29 0.29 0.29 0 0
0 0 0 0 0 0 0 0 0 0
- - - - - - - - - -

1.69 1.69 1.69 1.69 1.69 1.69 1.69 1.69 1.69 1.69
1.04 1.04 1.04 1.04 1.04 1.04 1.04 1.04 1.04 1.04
3.73 3.73 3.73 3.73 3.73 3.73 3.73 3.73 3.73 3.73
21-Apr 22-Apr 23-Apr 24-Apr 25-Apr 26-Apr 27-Apr 28-Apr 29-Apr 30-Apr
10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00 10.00
0 0 0 0 0 0 0 0 0 0
- - - - - - - - - 0

0 0 0 0 0 0 0 0 0 0

5.20 5.20 5.20 5.20 5.20 0 0 0 0 0

0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0.60 0


- - - - - - - - - -

1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09 1.09

40.00 40.00 40.00


40.00 0 40.00 0 0 0 0
0 0 0 00 0 0 0 0 0
- - - - - - - - - -
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
42.00 42.00 42.00 42.00 42.00 0 0 0 0 0

0.14 0.14 0.14 0.14 0.14 0.14 0.14 0 0 0


0 0 0 0 0 0 0 3.33 3.33 3.33

0 0 0 0 0 0 0 0 0 0
- - - - - - - - - -

0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0
- - - - - - - - - -
0 0 0 0 0 0 0 0 0 0
- - - - - - - - - -
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
- - - - - - - - - -

0 0 0 0 0.45 0.45 0.45 0.45 0.45 0.45

0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95 0.95
- - - - - - - - - -
0 0 0 0 0 0 0 0 0 0
0 0 0 0 - - - - - -

0 0 0 0 - - - - - -
0 0 0 03.33 3.33 3.33 3.33 3.33 3.33
- - - - - - - - - -
#VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
0 0 0 0 0 0 0 0 0 0
0.03 0.03 0.03 0.03 0 0 0 0 0 0
0 0 0 0 #DIV/0! 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0.12 0.12 0.12 0.12 0.12 0.12 0.12 0.12 0.12 0.12

- - - - - - - - - -
- - - - - - - - - -
0 0 0 0 0 0 0 0 0 0

1.57 1.57 1.57 1.57 1.57 1.57 1.57 1.57 1.57 1.57

37.89 37.89 37.89 37.89 37.89 37.89 37.89 37.89 37.89 37.89

20.21 20.21 20.21 20.21 20.21 20.21 20.21 20.21 20.21 20.21
0 0 0 0 0 0 0 0 0 0

0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35 0.35

0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22
0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17 0.17

0 0 0 0 0 0 0 0 0 0
- - - - - - - - - -
0 0 0 0 0 0 0 0 0 0
- - - - - - - - - -

0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13

0 0 0 0 0 0 0 0 0 0
2.17 2.17 2.17 2.17 2.17 2.17 2.17 2.17 2.17 2.17
- - - - - - - - - -
- - - - - - - - - -

0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0

11.83 11.83 11.83 11.83 11.83 11.83 11.83 11.83 11.83 11.83
- - - - - - - - - -
- - - - - - - - - -
0 0 0 0 0 0 0 0 0 0
1.86 1.86 1.86 1.86 0 0 0 0 0 0
7.76 7.76 7.76 7.76 7.76 7.76 7.76 7.76 7.76 7.76
- - - - - - - - - 0
- - - - - - - - - -
- - - - - - - - - -
0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0
1.29 1.29 1.29 1.29 1.29 1.29 1.29 1.29 1.29 1.29
0.54 0.54 0.54 0.54 0.54 0.54 0.54 0.54 0.54 0.54
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0.15 0.15 0.15 0 0 0 0 0 0 0
0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0 0
0 0 0 0 1.40 1.40 1.40 1.40 1.40 1.40
- - - - - - - - - -
0 0 0 0 0 0 0 0 0 0
5.71 5.71 5.71 5.71 5.71 5.71 5.71 5.71 0 0
0 0 0 0 0 0 0 0 0 0
- - - - - - - - - -
0 0 0 0 0 0 0 0 0 0
0.52 0.52 0.52 0.52 0.52 0.52 0.52 0.52 0.52 0.52
0 0 0 0 0 0 0 0 0 0
- - - - - - - - - -
- - - - - - - - - -
1.48 1.48 1.48 1.48 1.48 1.48 1.48 1.48 1.48 1.48
0.29 0.29 0.29 0.29 0.29 0.29 0.29 0.29 0.29 0.29
1.55 1.55 1.55 1.55 1.55 1.55 1.55 0 0 0
1.55 1.55 1.55 1.55 1.55 1.55 1.55 0 0 0
2.77 2.77 2.77 2.77 2.77 2.77 2.77 2.77 2.77 2.77
- - - - - - - - - -
0 0 0 0 0 0 0 0 0 0
9.47 9.47 9.47 9.47 9.47 9.47 9.47 9.47 9.47 9.47
- - - - - - - - - -
0 0 0 0 0 0 0 0 0 0
120.00 120.00 120.00 120.00 120.00 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0.79 0.79 0.79
0 0 0 0 0 0 0 0 0 0
- - - - - - - - - -
- - - - - - - - - -
0 0 0 0 0 0 0 0 0 0
5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00 5.00
0 0 0 0 0 0 0 0 0 #DIV/0!
0 0 0 0 0 1.00 1.00 1.00 0 0

0.53 0.53 0.53 0.53 0.53 0.53 0.53 0.53 0.53 0.53
0 0 0 0 0 0 0 0 0 0
3.50 3.50 3.50 3.50 3.50 0 0 0 0 0
0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0

1.02 1.02 1.02 1.02 1.02 1.02 1.02 1.02 1.02 1.02
- - - - - - - - - -
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0

0.13 0.13 0.13 0.13 0.13 0.13 0 0 0 0

0 0 0 0 0 0 0.15 0.15 0.15 0.15

0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92 0.92
- - - - - - - - - -
0 0 0 0 0 0 0 0 0 0
40.00 40.00 40.00 40.00 40.00 0 0 0 0 0
- - - - - - - - - -
0 0 0 0 0 0 0 0 0 0

0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43

2.87 2.87 2.87 2.87 2.87 2.87 2.87 2.87 2.87 2.87
- - - - - - - - - -
1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20 1.20
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
- - - - - - - - - -

0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67 0.67
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
- - - - - - - - - -

0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 1.00 1.00 1.00
- - - - - - - - - -

1.69 1.69 1.69 1.69 1.69 1.69 1.69 1.69 1.69 1.69
1.04 1.04 1.04 1.04 1.04 1.04 1.04 1.04 1.04 1.04
3.73 3.73 3.73 3.73 3.73 3.73 3.73 3.73 3.73 3.73
Manpower deployment plan
SLNO Manpower Apr-24 May-24 Jun-24
1 Mason & helper 16 16 16
2 unskilled 20 20 20
3 carpenter & helper 10 10 10
4 barbender & helper 6 6 6
5 plumber & helper 3 3 3
6 welder & helper 10 10
7 fitter for door windows 2 2 2
8 painters& helper 5 5 5
9 epoxy layman 4 4 4
10 Hilti fire stop 2 2 2
11 Expansion joint layman 2 2 2
12 Tiles,kota,granite Flooring m 10 10 10
Total 90 90 80

You might also like