Activity ID Activity Name Project Name Project ID Project Location GPS Province District Village Original Start Finish

District Village Original Start Finish 2024 2025


Points Duration
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
B1 Kayghto Secondary School 139d 01-Jun-24 19-Dec-24 19-Dec-24, B1 Kayghto Secondary School

B1.1 Site mobilization and de-mobilization 4d 01-Jun-24 05-Jun-24 05-Jun-24, B1.1 Site mobilization and de-mobilization
A1160 Site Mobilization and de-mobilization
Kayghto Secondary School
240300006 32.122069N,65.750093E Kandahar Shah Wali Kot
khaighato 4d 01-Jun-24 05-Jun-24 Site Mobilization and de-mobilization
B1.2 Construction of 6 + 1 classrooms 77d 06-Jun-24 25-Sep-24 25-Sep-24, B1.2 Construction of 6 + 1 classrooms

B1.2.6 Civil Works 43d 06-Jun-24 07-Aug-24 07-Aug-24, B1.2.6 Civil Works
A1170 Site preparation 4d 06-Jun-24* 11-Jun-24 Site preparation
A1180 Excavation 4d 12-Jun-24* 17-Jun-24 Excavation
A1190 Stone masonry 6d 18-Jun-24* 26-Jun-24 Stone masonry
A1200 Back filling 6d 27-Jun-24* 06-Jul-24 Back filling
A1210 Boulders 1d 06-Jul-24* 07-Jul-24 Boulders
A1220 PCC (M150) 6d 07-Jul-24* 16-Jul-24 PCC (M150)
A1230 RCC (M250) 5d 16-Jul-24* 23-Jul-24 RCC (M250)
A1240 Burnt brick masonry 4d 24-Jul-24* 29-Jul-24 Burnt brick masonry
A1250 Burnt brick pieces 2d 30-Jul-24* 01-Aug-24 Burnt brick pieces
A1260 Construction of blackboard 4d 01-Aug-24* 07-Aug-24 Construction of blackboard
A1340 Sign Board 2d 01-Aug-24* 04-Aug-24 Sign Board
B1.2.8 Finishing 30d 05-Aug-24 17-Sep-24 17-Sep-24, B1.2.8 Finishing
A1270 Supply and installation of wooden windows 3d 05-Aug-24* 08-Aug-24 Supply and installation of wooden windows
A1280 Supply and installation of wooden doors 2d 05-Aug-24* 07-Aug-24 Supply and installation of wooden doors
A1290 Interior cement plaster 4d 07-Aug-24* 13-Aug-24 Interior cement plaster
A1300 Exterior cement plaster 5d 13-Aug-24* 20-Aug-24 Exterior cement plaster
A1310 Marbal 3d 20-Aug-24* 25-Aug-24 Marbal
A1320 Stone pointing 1d 25-Aug-24* 26-Aug-24 Stone pointing
A1330 Wooden frame installation for blackboard 1d 25-Aug-24* 26-Aug-24 Wooden frame installation for blackboard
A1350 construction of chimney 2d 25-Aug-24* 28-Aug-24 construction of chimney
A1360 Vertical roof gutters 2d 28-Aug-24* 01-Sep-24 Vertical roof gutters
A1370 Interior latex wall and ceilling painting 7d 01-Sep-24* 11-Sep-24 Interior latex wall and ceilling painting
A1380 Isogum (Waterproofing) 4d 28-Aug-24* 03-Sep-24 Isogum (Waterproofing)
A1390 Exterior latex wall and parapet painting 4d 03-Sep-24* 09-Sep-24 Exterior latex wall and parapet painting
A1400 Handrails installation 3d 09-Sep-24* 14-Sep-24 Handrails installation
A1410 Covering parapet wall with 24 gauge GI 3d 14-Sep-24* 17-Sep-24 Covering parapet wall with 24 gauge GI

B1.2.7 Electrical Works 6d 18-Sep-24 25-Sep-24 25-Sep-24, B1.2.7 Electrical Works


A1420 Lights 1d 18-Sep-24* 18-Sep-24 Lights
A1430 Double pole switches 1d 18-Sep-24* 18-Sep-24 Double pole switches
A1440 Single pole switches 1d 18-Sep-24* 18-Sep-24 Single pole switches
A1450 Socket 16 Amp 1d 18-Sep-24* 18-Sep-24 Socket 16 Amp
A1460 Copper Wire 1 X 2.5mm² for lighting 1d 18-Sep-24* 18-Sep-24 Copper Wire 1 X 2.5mm² for lighting
A1470 Copper Wire 1 X 4mm² for power 1d 18-Sep-24* 18-Sep-24 Copper Wire 1 X 4mm² for power

Actual Level of Effort summary Page 1 of 3 Project Name:


Actual Work
Kayghto Secondary School
Remaining Work
Critical Remaining Work
Milestone
Activity ID Activity Name Project Name Project ID Project Location GPS Province District Village Original Start Finish 2024 2025
Points Duration
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
A1480 PVC conduit 1" or 25mm 1d 18-Sep-24* 18-Sep-24 PVC conduit 1" or 25mm
A1490 PVC conduit 3" or 75mm 1d 18-Sep-24* 18-Sep-24 PVC conduit 3" or 75mm
A1500 Copper Cable 3 X25mm² or 2 X 25mm² + 1 X25mm² 2d 18-Sep-24* 21-Sep-24 Copper Cable 3 X25mm² or 2 X 25mm² + 1 X25mm²
A1510 Grounding rods (Cu) 2.5 m length 16mm diameter 1d 22-Sep-24* 22-Sep-24 Grounding rods (Cu) 2.5 m length 16mm diameter
A1520 Circuit breaker 20 Amp 1d 22-Sep-24* 22-Sep-24 Circuit breaker 20 Amp
A1530 Circuit breaker 10 Amp 1d 22-Sep-24* 22-Sep-24 Circuit breaker 10 Amp
A1540 Distribution Box 30 x 45cm 22 gauge 1d 22-Sep-24* 22-Sep-24 Distribution Box 30 x 45cm 22 gauge
A1550 MCB 63 Apms 1d 22-Sep-24* 22-Sep-24 MCB 63 Apms
A1560 Joint box 1d 22-Sep-24* 22-Sep-24 Joint box
A1570 Insulation Tape 1d 22-Sep-24* 22-Sep-24 Insulation Tape
A1580 Single device gnag (Boxes) 2d 23-Sep-24* 25-Sep-24 Single device gnag (Boxes)
A1590 320 Watt Monocrystalline PhotoVoltaic (PV) Solar Modules 2d 23-Sep-24* 25-Sep-24 320 Watt Monocrystalline PhotoVoltaic (PV) Solar Modules
A1600 Advanced Solar Inverter + MPPT, with battery equalization function 2d 23-Sep-24* 25-Sep-24 Advanced Solar Inverter + MPPT, with battery equalization function
A1610 200 Ah Sealed Lead Acid, Maintenance-Free, Deep Cycle, GEL Batteries - Fast Charging Technology 1d 23-Sep-24* 23-Sep-24 200 Ah Sealed Lead Acid, Maintenance-Free, Deep Cycle, GEL Batteries - Fast Ch
A1620 Supply and Installation of high quality GI structure for mounting of SOLAR PANELS frame 1d 23-Sep-24* 23-Sep-24 Supply and Installation of high quality GI structure for mounting of SOLAR PANELS
A1630 Supply and installation of high quality Array Junction box 1d 23-Sep-24* 23-Sep-24 Supply and installation of high quality Array Junction box
A1640 Copper Conductor for connection of PV to Inverter 1d 23-Sep-24* 23-Sep-24 Copper Conductor for connection of PV to Inverter
A1650 Copper Conductor for connection of Batteries with Inverter 1d 23-Sep-24* 23-Sep-24 Copper Conductor for connection of Batteries with Inverter
B1.3 Construction of 4 +1 dry latrine 30d 24-Sep-24 06-Nov-24 06-Nov-24, B1.3 Construction of 4 +1 dry latrine

B1.3.1 Civil Works 20d 24-Sep-24 22-Oct-24 22-Oct-24, B1.3.1 Civil Works
A1660 Site preparation 1d 24-Sep-24* 24-Sep-24 Site preparation
A1670 Excavation 3d 25-Sep-24* 29-Sep-24 Excavation
A1680 Stone masonry 4d 30-Sep-24* 05-Oct-24 Stone masonry
A1690 filling 2d 06-Oct-24* 08-Oct-24 filling
A1700 Boulders 1d 09-Oct-24* 09-Oct-24 Boulders
A1710 PCC (M150) 2d 10-Oct-24* 13-Oct-24 PCC (M150)
A1720 RCC (M250) 2d 14-Oct-24* 16-Oct-24 RCC (M250)
A1750 Burnt brick masonry 3d 17-Oct-24* 21-Oct-24 Burnt brick masonry
A1760 Burnt brick pieces 1d 22-Oct-24* 22-Oct-24 Burnt brick pieces
A1770 Ventilation Pipe 1d 22-Oct-24* 22-Oct-24 Ventilation Pipe
A1780 Urine Channel 1d 22-Oct-24* 22-Oct-24 Urine Channel
B1.3.2 Finishing 11d 22-Oct-24 06-Nov-24 06-Nov-24, B1.3.2 Finishing
A1730 Supply and installation of wooden windows 1d 22-Oct-24* 22-Oct-24 Supply and installation of wooden windows
A1740 Supply and installation of wooden doors 1d 22-Oct-24* 22-Oct-24 Supply and installation of wooden doors
A1790 Interior cement plaster 3d 23-Oct-24* 27-Oct-24 Interior cement plaster
A1800 Exterior cement plaster 3d 23-Oct-24* 27-Oct-24 Exterior cement plaster
A1810 Stone pointing 1d 28-Oct-24* 28-Oct-24 Stone pointing
A1820 Vertical roof gutters 1d 29-Oct-24* 29-Oct-24 Vertical roof gutters
A1830 Interior latex wall and ceilling painting 1d 30-Oct-24* 30-Oct-24 Interior latex wall and ceilling painting

Actual Level of Effort summary Page 2 of 3 Project Name:


Actual Work
Kayghto Secondary School
Remaining Work
Critical Remaining Work
Milestone
Activity ID Activity Name Project Name Project ID Project Location GPS Province District Village Original Start Finish 2024 2025
Points Duration
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
A1840 Isogum (Waterproofing) 1d 30-Oct-24* 30-Oct-24 Isogum (Waterproofing)
A1850 Exterior latex wall and parapet painting 2d 30-Oct-24* 02-Nov-24 Exterior latex wall and parapet painting
A1860 Handrails installation 1d 03-Nov-24* 03-Nov-24 Handrails installation
A1870 Covering parapet wall with 24 gauge GI 1d 04-Nov-24* 04-Nov-24 Covering parapet wall with 24 gauge GI
A1880 Water Closet for disabled people 1d 05-Nov-24* 05-Nov-24 Water Closet for disabled people
A1890 Water Tank (hand wash facility) complete Set 1d 06-Nov-24* 06-Nov-24 Water Tank (hand wash facility) complete Set
B1.4 Construction of hand washing facility 8d 07-Nov-24 18-Nov-24 18-Nov-24, B1.4 Construction of hand washing facility

B1.4.1 Civil Works 8d 07-Nov-24 18-Nov-24 18-Nov-24, B1.4.1 Civil Works


A1900 Site preparation 1d 07-Nov-24* 07-Nov-24 Site preparation
A1910 Excavation 1d 09-Nov-24* 09-Nov-24 Excavation
A1920 PCC (M150) 1d 10-Nov-24* 10-Nov-24 PCC (M150)
A1930 Water Tank Stand 1d 11-Nov-24* 11-Nov-24 Water Tank Stand
A1940 Shelter and shade structure 1d 12-Nov-24* 12-Nov-24 Shelter and shade structure
A1950 Water Tank 1d 13-Nov-24* 13-Nov-24 Water Tank
A1960 4'' diameter (GI) pipe with 2' angle iron 1d 14-Nov-24* 14-Nov-24 4'' diameter (GI) pipe with 2' angle iron
A1970 3'' diameter (GI) Columns 1d 16-Nov-24* 16-Nov-24 3'' diameter (GI) Columns
A1980 tap 1/2" along with 1/2" pipes 1d 17-Nov-24* 17-Nov-24 tap 1/2" along with 1/2" pipes
A1990 PPR 32 mm diameter 1d 18-Nov-24* 18-Nov-24 PPR 32 mm diameter
B1.5 Construction of Boundary wall 21d 19-Nov-24 19-Dec-24 19-Dec-24, B1.5 Construction of Boundary wall

B1.5.1 Civil Works 21d 19-Nov-24 19-Dec-24 19-Dec-24, B1.5.1 Civil Works
A2000 Site preparation 1d 19-Nov-24* 19-Nov-24 Site preparation
A2010 Excavation 4d 20-Nov-24* 25-Nov-24 Excavation
A2020 Backfilling 2d 26-Nov-24* 28-Nov-24 Backfilling
A2030 Stone masonry 4d 30-Nov-24* 04-Dec-24 Stone masonry
A2040 Burnt brick masonry 1d 05-Dec-24* 05-Dec-24 Burnt brick masonry
A2050 Plaster Work 3d 07-Dec-24* 10-Dec-24 Plaster Work
A2060 PCC (M150) 3d 11-Dec-24* 15-Dec-24 PCC (M150)
A2070 RCC (M250) 1d 16-Dec-24* 16-Dec-24 RCC (M250)
A2080 Main Gate 1d 16-Dec-24* 16-Dec-24 Main Gate
A2090 Stone pointing 3d 16-Dec-24* 19-Dec-24 Stone pointing
A2100 Painting Works 3d 16-Dec-24* 19-Dec-24 Painting Works

Actual Level of Effort summary Page 3 of 3 Project Name:


Actual Work
Kayghto Secondary School
Remaining Work
Critical Remaining Work
Milestone