Parkview_Eleazar Classic Schedule Layout 16-Feb-24 18:05

January 2024 February 2024 March 2024 April 2024 May 2024 June 2024 July 2024 August 2024
14 21 28 04 11 18 25 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11
07-Aug-24, Total

07-Aug-24, Parkview_Eleazar
07-Aug-24, MILESTONES
Project Start
Ground Breaking Ceremony
Excavation Complete
Concrete Topping Off
Project Complete
21-Feb-24, PRE CONSTRUCTION
21-Feb-24, General Requirements
Permits
Mobilization
Construction of Temporary Facilities & Utilities
03-Aug-24, CONSTRUCTION
25-May-24, Earthworks
urvey Works (Staking/Layout)
Clearing & Grubbing
Excavation
Gravel Bedding for Foundation & SOG
Hauling & Disposal
Backfilling & Compaction
10-Jun-24, Civil Works
10-Jun-24, Substructure
15-Feb-24, Footing Foundation
Installation of Rebar at Foundation
Installation of Formworks
Concrete Pouring
Formworks Stripping
02-Mar-24, Footing Tie Beam
Installation of Rebar
Installation of Formworks
Concrete Pouring
Formworks Stripping
10-Jun-24, Ground Floor
Subgrade Preparation
Soil Termite Solution
Installation of Rebar at GF
Installation of Formworks
Concrete Pouring at SOG
Installation of Rebar & Forms_1st Lift
Concrete Pouring of 1st Lift
Installation of Concrete Stairs
21-May-24, Superstructure
21-May-24, 2nd Floor
Installation of Scaffolding System
Installation of Rebar for Columns
Installation of Rebar for 2nd Floor Beams
Installation of Formworks, Rebar, and Embedments for Slab
Concrete Pouring at 2nd Floor Slab, 2nd Lift Columns, and Beams
Stripping of Forms for Slab
Stripping of Forms for Beams

Actual Work Critical Remaining Work Summary Page 1 of 2 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
Parkview_Eleazar Classic Schedule Layout 16-Feb-24 18:05
January 2024 February 2024 March 2024 April 2024 May 2024 June 2024 July 2024 August 2024
14 21 28 04 11 18 25 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11
Stripping of Forms for Columns
Installation of Rebar Columns
Installation of Formworks for Column
Concrete Pouring Columns (Last Lift)
Stripping of Formworks
Installation of Roof Beams
Installation of Formworks
Concrete Pouring at Roof Beams
25-Apr-24, Finishing/Architectural Works
CHB Alignment, Laying, & Filler
Plastering
03-Aug-24, Plumbing
Installation of 1st Fix (Pipe Rough-ins)
Installation of 2nd Fix (Fittings)
Installation of 3rd Fix (Fixtures)
01-Aug-24, Steel Works & Roofing
Fabrication of Steel Trusses
Installation of C Purlins
Installation of G.I. Steel Matting
Installation of Roofing Insulation
Installation of Roofing Sheets
Installation of Bended Accessories
Application of Water Proofing for Concrete G
07-Aug-24, POST CONSTRUCTIO
Punchlisting Works
Preparation & Submission of Close Out D
Demobilization Works

Actual Work Critical Remaining Work Summary Page 2 of 2 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation