PHIL MACRO COMPOSTELASTEEL INC.

- COVERED MULTI-PURPOSE AREA


DEVELOPMENT
CORPORATION 3 WEEKS LOOK AHEAD SCHEDULE
PREVIOUS WEEK THIS WEEK NEXT WEEK WEEK AFTER NEXT WEEK
DATE
DECRIPTIONS / ACTIVITIES PERCENT COMPLETED QUANTITY UOM Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun
START END 22-Feb 23-Feb 24-Feb 25-Feb 26-Feb 27-Feb 28-Feb 1-Mar 2-Mar 3-Mar 4-Mar 5-Mar 6-Mar 7-Mar 8-Mar 9-Mar 10-Mar 11-Mar 12-Mar 13-Mar 14-Mar 15-Mar 16-Mar 17-Mar 18-Mar 19-Mar 20-Mar 21-Mar

I.
MOBILIZATION / DEMOBILIZATION
BOQ
MOBILIZATION / DEMOBILIZATION 20-Feb-21 30-May-21 Plan Lot 0.06155 0.06155 0.06155 0.06155 0.06155 0.06155 0.06155 0.06155 0.06155 0.06155 0.06155 0.06155 0.06155 0.06155 0.06155 0.06155 0.06155 0.06155 0.06155 0.06155 0.06155 0.06155 0.06155 0.06155 0.06155 0.06155 0.06155 0.06155
Actual
II.
Construction of Temporary Facilities
BOQ
PERIMETER BOARD UP 24-Feb-21 9-Mar-21 Plan L.M. 0.07574 0.07574 0.07574 0.07574 0.07574 0.07574 0.07574 0.07574 0.07574 0.07574 0.07574 0.07574 0.07574 0.07574 ###
Actual
BOQ
BUNK HOUSE / TEMPORARY FIELD OFFICE 24-Feb-21 12-Mar-21 Plan Lot 0.08316 0.08316 0.08316 0.08316 0.08316 0.08316 0.08316 0.08316 0.08316 0.08316 0.08316 0.08316 0.08316 0.08316 0.08316 0.08316 0.08316 ###
Actual
BOQ
POWER AND WATER CONNECTIONS 24-Feb-21 30-May-21 Plan Lot 0.05375 0.05375 0.05375 0.05375 0.05375 0.05375 0.05375 0.05375 0.05375 0.05375 0.05375 0.05375 0.05375 0.05375 0.05375 0.05375 0.05375 0.05375 0.05375 0.05375 0.05375 0.05375 0.05375 0.05375 0.05375 0.05375
Actual
III.
EARTHWORKS
BOQ
SITE PREPARATION, LAYOUT & SURVEY 20-Feb-21 28-Feb-21 Plan Lot 0.05049 0.05049 0.05049 0.05049 0.05049 0.05049 0.05 0.05049 ###
Actual
BOQ
STRUCTURAL EXCAVATION 27-Feb-21 12-Mar-21 Plan Cu.m. 0.04419 0.04419 0.04419 0.04419 0.04419 0.04419 0.04419 0.04419 0.04419 0.04419 0.04419 0.04419 0.04419 0.04419 ###
Actual
BOQ
STRUCTURAL BACKFILLING WORKS(FOOTINGS/TIEBEAMS) 20-Mar-21 29-Mar-21 Plan Lot 0.02252 0.02252
Actual
IV.
CONCRETING WORKS(3000 PSI)
BOQ
FOUNDATION 9-Mar-21 25-Mar-21 Plan Cu.m 0.12931 0.12931 0.12931 0.12931 0.12931 0.12931 0.12931 0.12931 0.12931 0.12931 0.12931 0.12931 0.12931
Actual
BOQ
COLUMNS 13-Mar-21 2-Apr-21 Plan Cu.m 0.12095 0.12095 0.12095 0.12095 0.12095 0.12095 0.12095 0.12095 0.12095
Actual
BOQ
MID-BEAMS 20-Mar-21 2-Apr-21 Plan Cu.m 0.07601 0.07601
Actual
V.
STEEL REINFORCEMENT WORKS
BOQ
FOUNDATION 6-Mar-21 25-Mar-21 Plan Kgs 0.02213 0.02213 0.02213 0.02213 0.02213 0.02213 0.02213 0.02213 0.02213 0.02213 0.02213 0.02213 0.02213 0.02213 0.02213 0.02213
Actual
BOQ
COLUMNS 10-Mar-21 2-Apr-21 Plan Kgs 0.04686 0.04686 0.04686 0.04686 0.04686 0.04686 0.04686 0.04686 0.04686 0.04686 0.04686 0.04686
Actual
BOQ
MID-BEAMS 18-Mar-21 2-Apr-21 Plan Kgs 0.02222 0.02222 0.02222 0.02222
Actual
BOQ
OTHERS 6-Mar-21 19-Apr-21 Plan Kgs 0.00962 0.00962 0.00962 0.00962 0.00962 0.00962 0.00962 0.00962 0.00962 0.00962 0.00962 0.00962 0.00962 0.00962 0.00962 0.00962
Actual
VI.
FORMWORKS
BOQ
FOUNDATION 6-Mar-21 25-Mar-21 Plan Sq.m. 0.0566 0.0566 0.0566 0.0566 0.0566 0.0566 0.0566 0.0566 0.0566 0.0566 0.0566 0.0566 0.0566 0.0566 0.0566 0.0566
Actual
BOQ
COLUMNS 10-Mar-21 2-Apr-21 Plan Sq.m. 0.11464 0.11464 0.11464 0.11464 0.11464 0.11464 0.11464 0.11464 0.11464 0.11464 0.11464 0.11464
Actual
BOQ
MID-BEAMS 18-Mar-21 2-Apr-21 Plan Sq.m. 0.07617 0.07617 0.07617 0.07617
Actual
BOQ
ROOF BEAMS 1-Apr-21 19-Apr-21 Plan Sq.m.
Actual
MANPOWER
Plan 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
PROJECT-IN-CHARGE 20-Feb-21 30-May-21 No.
Actual 1 0 0 0 1 0 0
Plan 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
PROJECT ENGINEER 20-Feb-21 30-May-21 No.
Actual 0 0 0 0 0 0 0
Plan 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
SAFETY OFFICER 25-Feb-21 30-May-21 No.
Actual 1 1 1 1 1 1 1
Plan 1 1 1 1 1 1 1 1 1 1 1 1 1
LIASON OFFICER 20-Feb-21 6-Mar-21 No.
Actual 0 0 0 0 0 0 0
Plan 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
NURSE 25-Feb-21 30-May-21 No.
Actual 0 0 0 0 0 0
Plan 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
FOREMAN 25-Feb-21 30-May-21 No.
Actual 1 1 1 1 1 1
Plan 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
SURVEYOR 20-Feb-21 12-Mar-21 No.
Actual 0 0 0 0 0 0
Plan 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
SURVEY AIDE 20-Feb-21 12-Mar-21 No.
Actual 0 0 0 0 0 0
Plan 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
OPERATOR(EQUIPMENT) 27-Feb-21 28-May-21 No.
Actual 1 1 1 1 1 1
Plan 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
RIGGER 27-Feb-21 28-May-21 No.
Actual 1 1 1 1 1 1
Plan 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
STEEL FABRICATOR / WELDER 27-Feb-21 27-May-21 No.
Actual
Plan 8 8 8 8 8 10 10 10 10 10 10 10 10 10 10 10
STEELMAN 6-Mar-21 19-Apr-21 No.
Actual 2 2 2
Plan 4 4 4 4 8 8 8 8 8 8 8 8 8
MASON 9-Mar-21 30-May-21 No.
Actual
Plan 6 6 6 6 6 6 6 6 10 10 10 10 10 10 10 10 10
CARPENTER 5-Mar-21 28-May-21 No.
Actual 2 2 2 7 7 7
Plan 5 5 5 5 6 6 6 6 6 6 6 6 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10
LABOR 23-Feb-21 30-May-21 No.
Actual 2 2 2 5 5 5
Plan 1 1 1 1 1 2 2 2 2 2 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
DRIVER 20-Feb-21 30-May-21 No.
Actual 1 0 1 0 0 0
Plan 1 1 1 1 1 2 2 2 2 2 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
HELPER 20-Feb-21 30-May-21 No.
Actual 1 1 1
Plan 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
CHECKER 25-Feb-21 30-May-21 No.
Actual 1 1 1 1 1 1
Plan 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
WAREHOUSEMAN 25-Feb-21 30-May-21 No.
Actual
Plan 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
ELECTRICIAN 7-Mar-21 30-May-21 No.
Actual 1 1 1 1
Plan
PLUMBER 8-May-21 30-May-21 No.
Actual
Plan
PAINTER 16-Apr-21 30-May-21 No.
Actual
Plan
TINSMITH / TINKER 30-Apr-21 30-May-21 No.
Actual
EQUIPMENT
Plan 1 1 1 1 1 1 1 1 1
MOBILE CRANE 13-Mar-21 28-May-21 No.
Actual
Plan 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
ELF(4-WHEEL TRUCK) 20-Feb-21 30-May-21 No.
Actual 1 1 1 1 1 1
Plan 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
10-WHEELER / BOOMTRUCK 6-Mar-21 26-May-21 No.
Actual
Plan 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
DUMP TRUCK(ISUZU) 27-Feb-21 24-May-21 No.
Actual
Plan 1 1 1 1 1 1 1 1 1 1 1 1 1 1
BACKHOE(1 CU.M) 27-Feb-21 12-Mar-21 No.
Actual 1 1 1 1 1 1
Plan
ROAD ROLLER 15-May-21 21-May-21 No.
Actual
Project No. AV012
Project AVON Boiler House Eff Date: July 7, 2021
Project Location CPIP Batino 3WEEKS LOOK AHEAD Doc Code : IA-PROJECTS-FORM-009
Page: 1 of 1
Owner: Projects
Date 30-Nov-21
Rev.# 0
PREVIOUS WEEK THIS WEEK NEXT WEEK WEEK AFTER NEXT WEEK WEEK AFTER NEXT WEEK
Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun
No. DECRIPTIONS / ACTIVITIES PERCENT COMPLETED Schedule
22-Nov 23-Nov 24-Nov 25-Nov 26-Nov 27-Nov 28-Nov 29-Nov 30-Nov 1-Dec 2-Dec 3-Dec 4-Dec 5-Dec 6-Dec 7-Dec 8-Dec 9-Dec 10-Dec 11-Dec 12-Dec 13-Dec 14-Dec 15-Dec 16-Dec 17-Dec 18-Dec 19-Dec 20-Dec 21-Dec 22-Dec 23-Dec 24-Dec 25-Dec 26-Dec

1 I. Site Mobilization
1.1 Site Safety Induction Previous Current
Plan 100%
1.1.1
Actual 100%
1.1 Area Staking & Clearing Previous Current
Plan 25% 25% 50%
1.1.1
Actual 25% 50%
1.1 Canopy Removal Previous Current
Plan 50% 50%
1.1.1
Actual
1.1 Temporary Facility Previous Current
Plan 100%
1.1.1
Actual
2 II. Civil Works
2.1 Excavation
Plan 50% 50%
2.1.1
Actual
2.1 Rebar work
Plan 7% 7% 7% 15% 7% 7% 15% 14% 7% 7% 7%
2.1.1
Actual
2.1 Shuttering work
Plan 7% 7% 7% 15% 7% 7% 15% 14% 7% 7% 7%
2.1.1
Actual
2.1 Pouring plan
Plan 10% 10% 10% 10% 10% 10% 10% 10% 10% 10%
2.1.1
Actual
2.1 Backfilling & compacting
Plan 17% 17% 17% 17% 16% 16%
2.1.1
Actual
2.1 SUB HEADER
Plan
2.1.1
Actual
2 III. Fabrication plan
2.1 Rebar fabrication
Plan 7% 7% 7% 7% 6% 6% 6% 6% 6% 6% 6% 6% 6% 6% 6% 6% 6% 6%
2.1.1
Actual
MANPOWER
Plan 1
a. SENIOR PROJECT ENGINEER
Actual 1
Plan 1
b. PROJECT ENGINEER
Actual 1
Plan 1
c. SITE ENGINEER
Actual 0
Plan 1
d. SAFETY OFFICER
Actual 1
Plan 1
e. FOREMAN
Actual 1
Plan 5
f. CARPENTERS (5)
Actual 5
Plan 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
g. STEEL MAN (2)
Actual 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Plan 1
h. MASON
Actual 1
Plan 4 4
i. LABORERS (4)
Actual 1 4
Plan 2 2
i. EQUIPMENT OPERATORS (2)
Actual
TOOLS & EQUIPMENT
Plan 1 1
a. BACKHOE/BREAKER
Actual
Plan 1 1
b. 6W MINI DUMP TRUCK (2)
Actual
Plan 1 1 1 1 1 1 1 1 1 1
c. MIXER
Actual
Plan 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
a. WELDING MACHINE
Actual 1 1 1 1
Plan 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
a. 20FT DROPSIDE TRUCK
Actual
Plan 1
a. 30KG JACKHAMMER
Actual
Plan 1 2
a. SHOVEL (4)
Actual
Plan 2 2 2 2 2 2 2 2 2 2
a. CONCRETE VIBRATORS (2)
Actual
Plan 3 3
a. CIRCULAR SAW (3 UNIT)
Actual
Plan 4 4
a. GRINDER (4)
Actual
Plan 1 1
a. OXYACETYLENE
Actual
Plan 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
a. WELDING MASK
Actual
Plan 1 1 1 1 1 1 1 1 1 1 1 1 1 1
a. EXTENSION WIRE
Actual
Plan
a. PPE
Actual
Plan 1 1 1 1
d. SCAFFOLDING
Actual

Prepared & Reviewed by: Reviewed & Approved by: Approved by:

Project Engineer Project Manager Manager - Internal Affairs