School.Project Mobilization
School.Project Mobilization 3 11-Mar-24 13-Mar-24 13-Mar-24, 123-23- ENZ School.Project Mobilization
A1000 Confirmation to Start the Works 0 11-Mar-24 Confirmation to Start the Works, 11-Mar-24
A1010 Resouce Mobilization 3 11-Mar-24 13-Mar-24 Resouce Mobilization
123-23- ENZ
School.Roof floorfloor
School.Roof 19 14-Mar-24 01-Apr-24 01-Apr-24, 123-23- ENZ School.Roof floor
123-23- ENZ School.Second Floor.Green Courtyard 22 23-Mar-24 14-Apr-24 14-Apr-24, 123-23- ENZ School.Second Floor.Green Courtyard
A1050 Removal of Finishes 8 23-Mar-24* 30-Mar-24 Removal of Finishes
A1060 Column Surface Preparation 4 27-Mar-24 30-Mar-24 Column Surface Preparation
A1070 Cutting Groove for the Reinforcement Installation 8 29-Mar-24 05-Apr-24 Cutting Groove for the Reinforcement Installation
A1080 Application of Reinforcement grooving 6 02-Apr-24 07-Apr-24 Application of Reinforcement grooving
A1090 CFRP Wrapping 5 06-Apr-24 10-Apr-24 CFRP Wrapping
A1100 Re-installation of finishes 3 11-Apr-24 14-Apr-24 Re-installation of finishes
123-23- ENZ School.Second
School.Second Floor.Blue
Floor.Blue Courtyard
Courtyard 21 23-Mar-24 13-Apr-24 13-Apr-24, 123-23- ENZ School.Second Floor.Blue Courtyard
A1270 Removal of Finishes 5 23-Mar-24* 27-Mar-24 Removal of Finishes
A1280 Column Surface Preparation 3 27-Mar-24 29-Mar-24 Column Surface Preparation
A1290 Cutting Groove for the Reinforcement Installation 6 29-Mar-24 03-Apr-24 Cutting Groove for the Reinforcement Installation
A1300 Application of Reinforcement grooving 4 02-Apr-24 05-Apr-24 Application of Reinforcement grooving
A1310 CFRP Wrapping 4 06-Apr-24 09-Apr-24 CFRP Wrapping
A1320 Re-installation of finishes 3 10-Apr-24 13-Apr-24 Re-installation of finishes
A1340 Removal of Finishes and Protection 3 16-Apr-24 19-Apr-24 Removal of Finishes and Protection
Actual Level of Effort Remaining Work Milestone Page 1 of 2 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
ENZ School Classic Schedule Layout 13-Mar-24 09:14
Activity ID Activity Name Original Start Finish 2024
Duration March April May
10 17 24 31 07 14 21 28 05 12 19 26
A1220 Final Inspection and Handing Over 0 14-May-24 Final Inspection and Handing Over,
Actual Level of Effort Remaining Work Milestone Page 2 of 2 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation