You are on page 1of 2

ENZ School Classic Schedule Layout 13-Mar-24 09:14

Activity ID Activity Name Original Start Finish 2024


Duration March April May
10 17 24 31 07 14 21 28 05 12 19 26
123-23- School
ENZ School 65 11-Mar-24 14-May-24 14-May-24, 123-23- ENZ School

123-23- ENZ
School.Project Mobilization
School.Project Mobilization 3 11-Mar-24 13-Mar-24 13-Mar-24, 123-23- ENZ School.Project Mobilization
A1000 Confirmation to Start the Works 0 11-Mar-24 Confirmation to Start the Works, 11-Mar-24
A1010 Resouce Mobilization 3 11-Mar-24 13-Mar-24 Resouce Mobilization
123-23- ENZ
School.Roof floorfloor
School.Roof 19 14-Mar-24 01-Apr-24 01-Apr-24, 123-23- ENZ School.Roof floor

A1230 Removal of Existing finishes 12 14-Mar-24 25-Mar-24 Removal of Existing finishes


A1240 Preparation of Surfaces 6 21-Mar-24 26-Mar-24 Preparation of Surfaces
A1250 Application of CFRP Strips 6 24-Mar-24 29-Mar-24 Application of CFRP Strips
A1260 Re-installation of Finishes 5 28-Mar-24 01-Apr-24 Re-installation of Finishes
123-23- ENZ
School.Second FloorFloor
School.Second 22 23-Mar-24 14-Apr-24 14-Apr-24, 123-23- ENZ School.Second Floor

123-23- ENZ School.Second Floor.Green Courtyard 22 23-Mar-24 14-Apr-24 14-Apr-24, 123-23- ENZ School.Second Floor.Green Courtyard
A1050 Removal of Finishes 8 23-Mar-24* 30-Mar-24 Removal of Finishes
A1060 Column Surface Preparation 4 27-Mar-24 30-Mar-24 Column Surface Preparation
A1070 Cutting Groove for the Reinforcement Installation 8 29-Mar-24 05-Apr-24 Cutting Groove for the Reinforcement Installation
A1080 Application of Reinforcement grooving 6 02-Apr-24 07-Apr-24 Application of Reinforcement grooving
A1090 CFRP Wrapping 5 06-Apr-24 10-Apr-24 CFRP Wrapping
A1100 Re-installation of finishes 3 11-Apr-24 14-Apr-24 Re-installation of finishes
123-23- ENZ School.Second
School.Second Floor.Blue
Floor.Blue Courtyard
Courtyard 21 23-Mar-24 13-Apr-24 13-Apr-24, 123-23- ENZ School.Second Floor.Blue Courtyard
A1270 Removal of Finishes 5 23-Mar-24* 27-Mar-24 Removal of Finishes
A1280 Column Surface Preparation 3 27-Mar-24 29-Mar-24 Column Surface Preparation
A1290 Cutting Groove for the Reinforcement Installation 6 29-Mar-24 03-Apr-24 Cutting Groove for the Reinforcement Installation
A1300 Application of Reinforcement grooving 4 02-Apr-24 05-Apr-24 Application of Reinforcement grooving
A1310 CFRP Wrapping 4 06-Apr-24 09-Apr-24 CFRP Wrapping
A1320 Re-installation of finishes 3 10-Apr-24 13-Apr-24 Re-installation of finishes

123-23- ENZ School.Column


School.Column Jacketing
Jacketing G-R G-R 32 13-Apr-24 14-May-24 14-May-24, 123-23- ENZ School.Co
A1330 Installation of Access Platform 3 13-Apr-24 16-Apr-24 Installation of Access Platform

A1340 Removal of Finishes and Protection 3 16-Apr-24 19-Apr-24 Removal of Finishes and Protection

A1350 Surface Preparation 3 20-Apr-24 23-Apr-24 Surface Preparation


A1360 Reinforcement Installation 15 24-Apr-24 08-May-24 Reinforcement Installation

A1370 Shuttering Works 15 24-Apr-24 08-May-24 Shuttering Works


A1380 GF-First Casting 3 24-Apr-24 26-Apr-24 GF-First Casting

A1390 GF Second Casting 3 27-Apr-24 29-Apr-24 GF Second Casting

A1400 FF- Fist Casting 3 30-Apr-24 02-May-24 FF- Fist Casting


A1410 FF- Second Casting 3 03-May-24 05-May-24 FF- Second Casting

A1420 SF- First Casting 3 09-May-24 11-May-24 SF- First Casting


A1430 SF- Second Casting 3 12-May-24 14-May-24 SF- Second Casting

123-23- ENZ School.Project


School.Project Handing
Handing OverOver 0 14-May-24 14-May-24 14-May-24, 123-23- ENZ School.Pro

Actual Level of Effort Remaining Work Milestone Page 1 of 2 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation
ENZ School Classic Schedule Layout 13-Mar-24 09:14
Activity ID Activity Name Original Start Finish 2024
Duration March April May
10 17 24 31 07 14 21 28 05 12 19 26
A1220 Final Inspection and Handing Over 0 14-May-24 Final Inspection and Handing Over,

Actual Level of Effort Remaining Work Milestone Page 2 of 2 TASK filter: All Activities
Actual Work Critical Remaining Work summary © Oracle Corporation

You might also like