ROAN CONSTITUENCY COMMUNITY PROJECT PORTFOLIO ROADMAP

START DATE

January 01, 2023


YEAR 2023
QUARTER 1 QUARTER 2 QUARTER 3 QUARTER 4
PROJECTS STATUS START DATE END DATE # of Days REMARKS 01/23 02/23 03/23 04/23 05/23 06/23 07/23 08/23 09/23 10/23 11/23 12/23
Completion of a 1 x 3 Classroom
In Progress 9-Feb 3-May 60 A A A A
Block in Chisokone area
Construction of a boundary wall at
Complete 3-Jan 27-Mar 60 ready for hand over A A A
Kalulu Primary School
Rehabilitation of the bridge in
In Progress 5-Feb 28-Apr 60 A A A
Kansengu Ward
Construction of Market shelter at
In Progress 9-Jan 2-Apr 60 A A A A
Section 25 area
Rehabilitation of the School at awaiting approval of
Scheduled 0
Kansumbi Primary School contract by MLGR
Rehabilitation of Roan Police
In Progress 5-Jan 10-May 90 A A A A A
Station
Water reticulation at Roan Primary
In Progress 9-Jan 10-Feb 25 contractor engaged A A
School
Rehabilitation of Toilets at Roan
In Progress 19-Jan 12-Apr 60 A A A A
Antelope Secondary School
Water reticulation at Nkambo
In Progress 19-Jan 12-Apr 60 A A A A
Primary School
Construction of Refuse Bay at
awaiting identification of site
Mpatamatu Market
no. 3 to erect third refuse
On Hold 9-Jan 2-Apr 60
bay. Contractor awaiting on
A A A A
furhter instruction from PM

Unblocking of Drainages in
In Progress 9-Jan 12-Feb 25 contractor engaged A A
Lumumba ward
Grading and gravelling of roads Proposed 0 procurement stage
Completion of the School Hall at
In Progress 19-Jan 12-Apr 60 A A A A
Twashuka Secondary School
Rehabilitation of Milyashi Police
In Progress 16-Jan 9-Apr 60 A A A A
Post
Construction of the Ablution Block
In Progress 19-Jan 12-Apr 60 A A A A
at Kalulu Primary School
Completion of the Boundary wall at
In Progress 18-Jan 11-Apr 60 A A A A
Kawama Primary School
Installation of the boreholes in
In Progress 26-Jan 1-Mar 25 contractor engaged A A A
Ng’ombe area
Street lighting in Milyashi Ward Complete 24-Jan 17-Apr 60 A A A A
Construction of 1x2 classroom
In Progress 18-Jan 11-Apr 60 A A A A
block at Kasunu Primary School.
Completion of 1x2 classroom block
at Chendmaunga primary school In Progress 31-Jan 24-Apr 60 A A A A

Completion of 1x2 classroom block


at Mansasa west primary school Complete 9-Jan 10-Feb 25 A A

Completion of the boundary wall at


Complete 3-Jan 27-Mar 60 A A A
sec 26 clinic
ZESCO connection at Kalulu
primary school Works to be done by
council. ZESCO connection
paid for. Zesco awaiting for
Scheduled 24-Apr 5-May 10
council to repair vandalised
A A
cables at school before
connection.

Completion of Boundary Wall at


Complete 9-Jan 1-Apr 60 A A A A
Kafubu Primary School