You are on page 1of 2

Project

18B00053: Organizational Outcome 1: Ensure Safe and Reliable National Road System: Bridge Program: Replacement of Permanent Weak Bridges - Abusag Bridge
(B04258LZ) along Baybayog - Baggao - Dalin - Sta. Margarita Road

Location Baggao, Cagayan


October 3 - 9, 2021

COMPRESSIVE TESTING LOOK AHEAD SCHEDULE


WEEKLY LOOK AHEAD
NO. PART OF STRUCTURE CASTING DATE 3 4 5 6 7 8 9 REMARKS
Sun Mon Tue Wed Thu Fri Sat
1 CSP Capping Beam for Align. B 16-Sep-21 21 days For Testing
2 Wingwall at Abutment B 16-Sep-21 21 days For Testing
3 Wingwall at Abutment A 18-Sep-21 21 days For Testing
4 Sidewalk at Abut A-Pier 1 18-Sep-21 21 days For Testing
5 Sidewalk at Pier 1-2 18-Sep-21 21 days For Testing
6 Sidewalk at Pier 8-9 19-Sep-21 14 days For Monitoring
7 Sidewalk at Pier 9-10 19-Sep-21 14 days For Monitoring
8 Sidewalk at Pier 6-7 19-Sep-21 14 days For Monitoring
9 Sidewalk at Pier 7-8 19-Sep-21 14 days For Monitoring
10 Sidewalk at Pier 10-11 19-Sep-21 14 days For Monitoring
11 Sidewalk at Pier 11-12 19-Sep-21 14 days For Monitoring
12 Railing Post 21-Sep-21 14 days For Monitoring
13 Sidewalk at Pier 12-13 24-Sep-21 14 days For Monitoring
14 Sidewalk at Pier 13-14 24-Sep-21 14 days For Monitoring
6 0 0 0 2 0 3 11

TOTAL NO. OF SETS 11


FOR TESTING
FOR MONITORING

PREPARED BY VERIFIED BY

BEVERLY SALADINO JAY MAR ISORENA


QC Materials Engineer
Project
18B00053: Organizational Outcome 1: Ensure Safe and Reliable National Road System: Bridge Program: Replacement of Permanent Weak Bridges - Abusag Bridge
(B04258LZ) along Baybayog - Baggao - Dalin - Sta. Margarita Road

Location Baggao, Cagayan


September 10 - 16, 2021

COMPRESSIVE TESTING LOOK AHEAD SCHEDULE


WEEKLY LOOK AHEAD
NO. PART OF STRUCTURE CASTING DATE 10 11 12 13 14 15 16 REMARKS
Sun Mon Tue Wed Thu Fri Sat
1 CSP Capping Beam for Align. B 16-Sep-21 28 days For Testing
2 Wingwall at Abutment B 16-Sep-21 28 days For Testing
3 Wingwall at Abutment A 18-Sep-21 28 days For Testing
4 Sidewalk at Abut A-Pier 1 18-Sep-21 28 days For Testing
5 Sidewalk at Pier 1-2 18-Sep-21 28 days For Testing
6 Sidewalk at Pier 8-9 19-Sep-21 21 days For Testing
7 Sidewalk at Pier 9-10 19-Sep-21 21 days For Testing
8 Sidewalk at Pier 6-7 19-Sep-21 21 days For Testing
9 Sidewalk at Pier 7-8 19-Sep-21 21 days For Testing
10 Sidewalk at Pier 10-11 19-Sep-21 21 days For Testing
11 Sidewalk at Pier 11-12 19-Sep-21 21 days For Testing
10 PCCP STA 450 - 506 RS 28-Sep-21 14 days For Testing
11 PCCP STA 150 - 200 RS 1-Oct-21 14 days For Testing
6 0 0 0 2 0 3 11

TOTAL NO. OF SETS 11


FOR TESTING
FOR MONITORING

PREPARED BY VERIFIED BY

BEVERLY SALADINO JAY MAR ISORENA