KSO STC-NRC

MINUTES OF MEETINGS
MNC THEMEPARK PROJECT

Project Title : MNC THEME PARK LIDO


Issue : Weekly Meeting 16 KSO-MWW-GAI-GEOFORCE
Date of Meeting : October, 16th 2019
Time : 09.00 WIB
Venue : KSO SITE OFFICE Office
Checked By :
Approved By :

No ATTENDEES ORGANIZATION Email


1 Chen Fu Kang MNC WAHANA WISATA
2 Bagus P. MNC WAHANA WISATA
3 Nanang MNC WAHANA WISATA
4 Ismail Hatta MNC WAHANA WISATA
5 Deden Is Is M. MNC WAHANA WISATA
6 Hardjimiarso KSO STC-NRC
7 Haris Taning KSO STC-NRC
8 Hapit Sugandi KSO STC-NRC
9 Vinsensius Deno KSO STC-NRC
10 Eka Putra Darma KSO STC-NRC
11 Didik K PT. GEOFORCE INDONESIA
12 Andhi Bayu N PT. GEOFORCE INDONESIA
13 Herman PT. GAI

FINISH STATUS
No MATTERS DISCUSSED ACTION BY
DATE OPEN CLOSE

I. SUBMISSION
1 GAI - KSO - GEOFORCE to submit action plan per 2 weeks. And provide catch
up program. GAI-KSO- 22-Sep-19
For GAI - Make sure all the STA and Grid Plan mentioned in it. Because KSO v
GEOF 30-Sep-19
want to make sure all the work is on strict schedule.

2 KSO to Submit:
e. Cash Flow Projection
Recent Update : Will be submitted today. 18-Sep-19
MWW suggested the updated schedule refer to KSO realization KSO-GAI 30-Sep-19 v
Also submit it for Earthwork & Macro Drain TBD

3 KSO to submit new schedule regarding the site activity which will be carried out
13-Sept-19
next. KSO v
9-Oct-19
4 KSO to submit brochure & Specification of concrete panel. 18-Sep-19
Recent Updates : KSO to expedite the Fencing process
KSO 7-Oct-19 v
16-Oct-19
9 GEOFORCE to submit lagoon membrane design.
GEOF 19-Sep-19 v

10 GAI-KSO-GEOFORCE to submit daily report every day and weekly report every
Monday. All For Info v

11 KSO to submit thesettlement reading as attachment on weekly report.


KSO For Info v

12 Regarding Macro Drainage, KSO to submit : (stageiously)


a. Shopdrawing
b. Material Approval ( Concrete, Pile , Rebar, waterstop,spun pile, etc.) 09/10/201
c. Method Statement KSO 9 v
d. Schedule 16-Oct-19
FINISH STATUS
No MATTERS DISCUSSED ACTION BY
DATE OPEN CLOSE
13 GAI to submit the new Org Chart to owner
GAI 15-Oct-19 v

14 KSO to submit Northern sloping area shop drawing based on Geoforce


recommendation KSO TBD v
FINISH STATUS
No MATTERS DISCUSSED ACTION BY
DATE OPEN CLOSE

II. SITE PROGRESS


1 KSO to consider make subdrain at north theme park in advance to simplyfy the
work sequence & also sediment trap
Recent Update: KSO will coordinate with GAI first. KSO TBD v
GAI to make the boundaries for slurry removal near the buffer slope.

2 KSO to Re-do the Subdrain mock up palced in front of MWW Site Office
KSO TBD v

3 GAI to clear the B.1 area on 1 week.


Recent update: 14 august is ready to be tested.
GAI to submit: handover letter to KSO complete with drawing and
documentation and sign with MWW and KSO. GAI 25-Sep-19 v
Waiting for the administration checklist
Will be submitted by today 2 oct 2019 to KSO

4 KSO Update regarding MWW & KSO Site Office:


KSO already start the ground preparation and will proceed with the site office
mobilization. This
KSO to consider the access. KSO v
Month
Recent Update: LOA already signed by both parties, KSO to proceed.

5 Dredging trial on Friday 20 september 2019.


Recent Update : re-scheduled on 2 october 2019. since GAI have some technical
issue with the dredging pump. 18-Sep-19
Recent Updates: GAI do the testing, MWW need the information of the 2-Oct-19
GAI v
productivity. 16-Oct-19
GAI to calculate the debit to clarify which dredging pump they use today.

6 All the site work have to follow the approved Shop drawing, Method Statement
and material approval. All contractor to make sure all foreman do the work as the
submitted drawing. ALL For Info v

7 GAI to start the Line B after the DB 5 avoiding the DB5 spring water. GAI 18-Sep-19 v
8 KSO subdrain productivity is approximate 30 m'/ day, so GAI have to provide
area as needed to catch up with KSO schedule.
Recent Update : Since last week they cant achived it, so on this week GAI have to GAI For Info v
prepare for 420 m by this week.

9 With the remaining schedule time (8 weeks), GAI to provide working area for
KSO subdrain work with minimum 200m' per week. GAI For Info v

10 Approximately, GAI have to accomplished 2000m3 slurry excavation per day to


catch up the progress. GAI For Info v

11 KSO to proceed with the temporary drain before Sediment Trap after the
16-Oct-19
sediment trap installed. KSO v
23-Oct-19
12 KSO to complete the as built coordinate of subdrain which already installed,
partially. Submit it with submission. Subdrain 2 & 3 KSO 16-Oct-19 v

13 GAI to open 150 m' work area on B2 until B4 to KSO per Tuesday 15 october 2019.
GAI 15-Oct-19 v

14 GAI will mobilize the 6 more RCP dia. 1 m' on Saturday after lunch. So the total
installed is 8 RCP on the area. The installation will be on Sunday. GAI 19-Oct-19 v

15 This Friday GAI will finish 50 m' and handover it to KSO.


GAI 18-Oct-19 v

16 Based on the Clarification MOM between KSO and MWW, KSO is posible to
claim the Material on Site for items HDPE pipe and Spun Pile for Monthly
All For Info v
Progress Payment.
FINISH STATUS
No MATTERS DISCUSSED ACTION BY
DATE OPEN CLOSE

III. SAFETY
1 KSO to aware about sediment trap access road at the northern slope area.
KSO For Info v
2 All Contractor have to use name card at site. KSO TBD v
3 KSO to aware on the backfilling slope area KSO For Info v
4 KSO and GAI to maintain the water quality which run to Lido Lake. KSO For Info v
FINISH STATUS
No MATTERS DISCUSSED ACTION BY
DATE OPEN CLOSE

IV. SITE ISSUE


1 GAI to rebuild maintain the sediment trap because no function.
Today to be inspected. 18-Sept-19
GAI to maintain the water quality especially after rain. GAI v
9-Oct-19

3 GAI to mobilize equipment based on the statement letter.


As per schedule
Recent Update : as per Friday 11 october GAI will mobilize the amphibious GAI 18-Sep-19 v

4 GAI going to devide the team into day shift and night shift
Recent Update: GAI already started the night shift until 10 pm.
MWW comments: Safety personal must be on site to supervise. ALL TBD v

5 KSO requesting not using DCP and only use field CBR and Sand Cone for
Compaction testing. For Info
GEOFORCE will inform quality inspection as per KSO request. MWW v
9-Oct-19

6 MWW request to KSO-GAI-GEOF to conduct meeting every day morning.


As per today, the meeting will conduct every 4 pm. ALL For Info v

7 GAI promised to mobilize eamphibious per 2 october 2019


Recent Updates : GAI mobilized the 1 unit Amphibious Excavator on 12 October GAI 2-Oct-19 v
2019 morning.
8 All Material On Site have to be inspected and accepted by Owner Site Inspector ALL For Info v
9 Daily Report to be submitted every Wednesday or weekly meeting to be sign by
owner site manager. ALL For Info v

10 KSO to put settlement monitoring (reference point) at the edge of the slope which
backfill level already finish (1 meter away from the slope every 50 meters). And KSO For Info v
read it every week.

11 Comencement date for bulk earthwork & macro drain start when the CAR release
by MWW. MWW For Info v

12 KSO site activity on Zone E (8 October 2019 10 am) and zone D (7 October 2019 1
pm) stopped due to the villager issue (Ciletuh Hilir and Wates). MWW to take
notes about this. MWW For Info v

13 DEM will meet the villager who stop the site work and consolidate with them.
MWW-DEM For Info v

14 GAI to aware about the nourthern RCP and install more pipes by next
Wednesday and divert the water from toll road directly to the RCP.
GAI to prepare the material 3 more. GAI 15-Oct-19 v

15 AS per GAI meeting with MWW, Saturday 12 october 2019 GAI will mobilize
6 Dump Truck
1 Amphibious Exc GAI 12-Oct-19 v
1 Bull dozer

16 Per 17 october 2019, Based on MWW info, KSO can continue the site activity on
BC 1 (Previuosly stop due to village issue). KSO 17-Oct-19 v

V. DESIGN ISSUE
FINISH STATUS
No MATTERS DISCUSSED ACTION BY
DATE OPEN CLOSE
2 As agreed on todays meeting,
CBR test should reach >= 5%,
50 cm loose thickness,
Tested using Field CBR, DCP test, & Sand Cone test,
Tested every 50 m' grid/radius.
if the CBR did not reach the requirement, test again nearby the point and do the
ALL FOR INFO v
average.
Agreed today 25 September 2019 :
1. For the valley area excavation using the GEOFORCE recommendation, its not
require CBR 5%, indeed need flat surface only.
2. For other subgrade besides valley, require CBR 5 %

3 KSO will do the works on buffer area, GEOFORCE will provide the
recommendation regarding the soil stability.
To be Submitted to MWW on 13 september 2019 GEOF-MWW 19-Sep-19 v
recent updates : submitted to KSO by MWW per 19 september 2019 (For Info)
FINISH STATUS
No MATTERS DISCUSSED ACTION BY
DATE OPEN CLOSE
5 GEOFORCE to aware about the overlapping on the subdrain which under
geotextile and above it. GEOF For Info v

6 Based on GEOFORCE recommendation, Slurry at buffer area has to be removed


by 4 m thick and replace with sand & gravel material, MWW will settle ASAP.
Recent Update : not using granular anymore. MWW TBD v
KSO to remove the slurry soil at buffer area (section B & C)

7 For the soil testing, All surface have to be tested wheter its achived the MWW-GEOF-
requirement or not. For Info v
KSO
8 Regarding Buffer Area recommendation, using the excavation recommendation
on 18 sept 2019 by geoforce, for the soil treatment after the slurry soil removed
MWW-GEOF TBD v
still outstanding.

9 As per today KSO already give the DCP vs CBR field result for GEOFORCE and
MWW to study for KSO proposal for using field CBR for soil testing. MWW-KSO-
For Info v
GEOF

10 GEOFORCE will provide the formula regarding DCP CBR calculation. GEOF 2-Oct-19 v
11 KSO and GEOFORCE to join and approved the GAI site handover with MWW ALL 27-Sep-19 v
12 Based on P Tjendra Instruction on site, Subdrain 4 change from 2 pipes to 3 pipes,
Subdrain 5 from 2 pipes to 1 pipe.
MWW instruct to make fish bone on the spring water near the DB 5 and KSO to KSO-MWW For Info v
put it in a drawing.

13 KSO to start the subdrain 5 from STA 0+40 due to the macrodrain path crossing it.
KSO to aware about it. KSO-MWW 16-Oct-19 v

VI. MISC.
1 GEOFORCE to value engineering their recommendation for slope stability at
buffer area and present again to MWW.
Recent Updates: refer to the 8 october recommendation sent by geoforce GEOF For Info v

2 Cut off Progress Claim every 25th per month ALL For Info v
3 SM / CM have to on site everyday ALL For Info v
4 PM and SM / CM have to attend weekly meeting. ALL For Info v
5 Next Meeting on KSO site office ALL For Info v
6 KSO to survey existing village access and surrounding area for MWW to consider
and design underpass/boxculvert before backfilling BOH access. 16 ocotber
Recent Updates: Partially next week ALL v
2019

7 KSO still wating for the Draft format of Down Payment and performance bond
from MWW / Owner MWW For Info v

8 Any Changes on design or drawing have to submitted as a formal report/


submission. ALL For Info v