MINUTES OF MEETINGS
MNC THEMEPARK PROJECT
FINISH STATUS
No MATTERS DISCUSSED ACTION BY
DATE OPEN CLOSE
I. SUBMISSION
1 KSO - GEOFORCE to submit action plan per 2 weeks. And provide catch up
program. KSO-GEOF 30-Sep-19 v
2 KSO to submit new schedule regarding the site activity which will be carried out
next. KSO 6-Nov-19 v
7 KSO to attach the drone documentation and DEM representatives sign into the
Memo regarding the vandalized fence KSO-MWW 28-Nov-19 v
8 KSO to submit the design of Precast Box Culvert (Macro Drainage) to owner
KSO TBD v
9 KSO to submit the letter regarding the preliminaries claim due to the time
extension because of slurry removal.
10 KSO waiting answer from MWW regarding cost of design Tunnel at BOH Access.
By email dated : November, 18th 2019 , Letter no : 03/AIY/PRP/XI/19 MWW TBD v
3 All the site work have to follow the approved Shop drawing, Method Statement
and material approval. All contractor to make sure all foreman do the work as the
submitted drawing. ALL For Info v
4 KSO to proceed with the temporary drain before Sediment Trap after the
sediment trap installed. KSO finalized superimposed drawing to action KSO 16-Dec-19 v
6 MWW Instruct KSO to clear the ruins and flat the surface on the Fencing Adjacent
to the Villager house in order to be installed by Concrete Fence near the Villager To be
MWW-KSO v
house Noticed
7 KSO quotation submission is waiting the trial to be succeed, KSO will quote when
the triall is suceed. KSO For Info v
8 Progress for trial slurry removal: KSO's still internally doing a negotiation with
dewatering subcontractor KSO For Info v
14 KSO will start the piling on February and if there is any design changes from
Owner, KSO expecting to give the information ASAP. KSO v
15 KSO will move the equipment and start backfilling work to Zone E
KSO For Info v
16 KSO will start the panel fencing construction on Monday , January 20th 2020
KSO For Info v
17 KSO will start to repair the villager's house start from Wednesday, January 15th
KSO For Info v
2020
18 Trial for Slurry Removal will be done with 50 meter length
KSO For Info v
19 KSO already start to make access road to the slurry area from January 22nd 2020,
KSO For Info v
dewatering work will be start on January 29th 2020
FINISH STATUS
No MATTERS DISCUSSED ACTION BY
DATE OPEN CLOSE
20 KSO will start to make embankment around sediment trap area to make it
KSO For Info v
functional in the end of January 2020
III. SAFETY
1 KSO to aware about sediment trap access road at the northern slope area.
KSO For Info v
2 All Contractor have to use name card at site. KSO 2-Jan-20 v
3 KSO to aware on the backfilling slope area KSO For Info v
4 KSO to maintain the water quality which run to Lido Lake. KSO For Info v
5 Instal protection and safety line in slope at on going construction area and at To be
buffer zone area (Zone E), also maintain the access road. KSO v
Noticed
2 All Material On Site have to be inspected and accepted by Owner Site Inspector ALL For Info v
3 Daily Report to be submitted every Wednesday or weekly report to be sign by
owner site manager. ALL For Info v
4 Comencement date for bulk earthwork & macro drain start when the CAR release
by MWW. (1 October 2019) MWW 1-Oct-19 v
6 KSO to aware of GEOFORCE geotextile peg which indicate the soil filling
To be
boundary, otherwise KSO have to clear it. KSO v
Noticed
7 Regarding the concrete pannel fence installation, KSO reporting that their peg has
been moved. And cause the the alignment shifted. MWW For Info v
8 Please make the temporary drain / channel to flow the water from Pond D
To be
KSO v
Noticed
9 Panel fence work still remain continue to be constructed, if any incidents happen
To be
will be notified in Official Report. KSO v
Noticed
10 Please make new settlement plate that already broken (permanent benchmark) at
To be
Zone E (Buffer Zone Area) , and report the monitoring regularly in weekly basic. KSO v
Noticed
11 DCP Test will be done ± 1 meter / more than 90 cm, especially at Subdrain 5
location KSO For Info v
12 In connection with concrete panel fence work, MWW suggest to do the villager
access road first. Detail layout of villager access road will be sent to KSO later. KSO For Info v
2 KSO will do the works on buffer area, GEOFORCE will provide the
recommendation regarding the soil stability.
To be Submitted to MWW on 13 september 2019 GEOF-MWW 19-Sep-19 v
recent updates : submitted to KSO by MWW per 19 september 2019 (For Info)
5 For the soil testing, All surface have to be tested wheter its achived the MWW-GEOF-
requirement or not. For Info v
KSO
6 GEOFORCE will provide the formula regarding DCP CBR calculation. GEOF 2-Oct-19 v
7 MWW instruct to make fish bone on the spring water near the DB 5 and KSO to
put it in a drawing. KSO-MWW For Info v
8 KSO to start the subdrain 5 from STA 0+040 due to the macrodrain path crossing
it. KSO to aware about it. KSO-MWW 16-Oct-19 v
11 The installation of barbed wired in panel fence are facing the village area To Be
KSO v
Noticed
12 KSO to make RFI regarding detail connection Box 2 with Macro Drain Type 2, To Be
KSO v
also detail of chamber for every corner. Noticed
13 Based on As-Built Drawing of Subdrain 2 and 3, KSO to overlay the subdrain
location with the macro drainage drawing. If there is an indication of subdrain To Be
KSO v
and spun pile intersect each other, please send the RFI to MWW. Noticed
14 KSO to make RFI regarding the spun pile position (2B81, 2B82, 2B27, 2B28) due to To Be
KSO v
these spun pile intersect with subdrain position. Noticed
VI. MISC.
1 KSO to survey existing village access and surrounding area for MWW to consider
and design underpass/boxculvert before backfilling BOH access.
Recent Updates: This portion is under KSO design & build ALL 16-Oct-19 v