KSO STC-NRC

MINUTES OF MEETINGS
MNC THEMEPARK PROJECT

Project Title : MNC THEME PARK LIDO


Issue : Weekly Meeting 28 KSO-MWW-GEOFORCE
Date of Meeting : February, 5th 2020
Time : 09.00 WIB
Venue : KSO Site Office
Checked By :
Approved By :

No ATTENDEES ORGANIZATION Email


1 Bagus Putranto MNC WAHANA WISATA
2 Deden Is Is M MNC WAHANA WISATA
3 Tedi MNC WAHANA WISATA
4 Nanang MNC WAHANA WISATA
5 Haris Taning KSO STC-NRC
6 Hapit S. KSO STC-NRC
7 Eka D. Susila KSO STC-NRC
8 Hendri Rahman KSO STC-NRC
9 Rachmad AW KSO STC-NRC
10 Andhi PT. GEOFORCE INDONESIA

FINISH STATUS
No MATTERS DISCUSSED ACTION BY
DATE OPEN CLOSE

I. SUBMISSION
1 KSO - GEOFORCE to submit action plan per 2 weeks. And provide catch up
program. KSO-GEOF 30-Sep-19 v

2 KSO to submit new schedule regarding the site activity which will be carried out
next. KSO 6-Nov-19 v

3 GEOFORCE to submit lagoon membrane design.


GEOF 19-Sep-19 v

4 Regarding Macro Drainage, KSO to submit : (stageiously)


a. Shopdrawing
b. Material Approval ( Concrete, Pile , Rebar, waterstop,spun pile, etc.)
c. Method Statement
d. Schedule KSO 16-Oct-19 v
Recent Updates: Partially Submitted, Material Spun anc Concrete approval have
been submitted on 6 november 2019

5 KSO to submit Northern sloping area shop drawing based on Geoforce


recommendation KSO TBD v

6 GEOF to propose GEOSCAN quotation and Jamboo bag on 22 november 2019 to


owner GEOF 22-Nov-19 v

7 KSO to attach the drone documentation and DEM representatives sign into the
Memo regarding the vandalized fence KSO-MWW 28-Nov-19 v

8 KSO to submit the design of Precast Box Culvert (Macro Drainage) to owner
KSO TBD v

9 KSO to submit the letter regarding the preliminaries claim due to the time
extension because of slurry removal.
10 KSO waiting answer from MWW regarding cost of design Tunnel at BOH Access.
By email dated : November, 18th 2019 , Letter no : 03/AIY/PRP/XI/19 MWW TBD v

11 KSO to submit the quotation of vertical drain


KSO 13-Dec-19 v
FINISH STATUS
No MATTERS DISCUSSED ACTION BY
DATE OPEN CLOSE
12 KSO to submit the method of statement for spun pile handling and driving,
including the schedule for spun pile delivery and checklist of submission KSO TBD v

II. SITE PROGRESS


1 KSO to Re-do the Subdrain mock up placed in front of MWW Site Office
KSO TBD v

2 KSO Update regarding MWW & KSO Site Office:


KSO already start the ground preparation and will proceed with the site office
mobilization.
KSO to consider the access. KSO TBC v
LOA already signed by both parties, KSO to proceed.
Recent Update : KSO waiting cost approval from MWW (on-going)

3 All the site work have to follow the approved Shop drawing, Method Statement
and material approval. All contractor to make sure all foreman do the work as the
submitted drawing. ALL For Info v

4 KSO to proceed with the temporary drain before Sediment Trap after the
sediment trap installed. KSO finalized superimposed drawing to action KSO 16-Dec-19 v

5 KSO to complete the as built coordinate of subdrain which already installed,


partially. Submit it with submission. Subdrain 2 , 3, 5 & fishbone KSO 13-Dec-19 v

6 MWW Instruct KSO to clear the ruins and flat the surface on the Fencing Adjacent
to the Villager house in order to be installed by Concrete Fence near the Villager To be
MWW-KSO v
house Noticed

7 KSO quotation submission is waiting the trial to be succeed, KSO will quote when
the triall is suceed. KSO For Info v

8 Progress for trial slurry removal: KSO's still internally doing a negotiation with
dewatering subcontractor KSO For Info v

9 Slurry Excavation Trial is to be expected done in 2 weeksfrom today.


KSO 22-Jan-20 v
10 Following up the Concrete fence installation and other work near the Ciletuh
Hilir, KSO is expected to do the repair for the villager house which broke due to
KSO site work. This repairment is to be covered by the CAR which given by KSO v
owner/MWW

11 DEM to ready to accompany KSO to resume the fence installation.


KSO v
12 KSO will do the repairment and resume the fence installation on 15 january 2020
KSO v
13 to anticipate the BMKG letters regarding the high intensity/ extreme weather on
january, MWW ask Kso to be more caution and safety. KSO v

14 KSO will start the piling on February and if there is any design changes from
Owner, KSO expecting to give the information ASAP. KSO v

15 KSO will move the equipment and start backfilling work to Zone E
KSO For Info v
16 KSO will start the panel fencing construction on Monday , January 20th 2020
KSO For Info v
17 KSO will start to repair the villager's house start from Wednesday, January 15th
KSO For Info v
2020
18 Trial for Slurry Removal will be done with 50 meter length
KSO For Info v
19 KSO already start to make access road to the slurry area from January 22nd 2020,
KSO For Info v
dewatering work will be start on January 29th 2020
FINISH STATUS
No MATTERS DISCUSSED ACTION BY
DATE OPEN CLOSE
20 KSO will start to make embankment around sediment trap area to make it
KSO For Info v
functional in the end of January 2020
III. SAFETY
1 KSO to aware about sediment trap access road at the northern slope area.
KSO For Info v
2 All Contractor have to use name card at site. KSO 2-Jan-20 v
3 KSO to aware on the backfilling slope area KSO For Info v
4 KSO to maintain the water quality which run to Lido Lake. KSO For Info v
5 Instal protection and safety line in slope at on going construction area and at To be
buffer zone area (Zone E), also maintain the access road. KSO v
Noticed

IV. SITE ISSUE


1 MWW request to KSO-GEOF to conduct meeting every day morning.
As per today, the meeting will conduct every 4 pm. ALL For Info v

2 All Material On Site have to be inspected and accepted by Owner Site Inspector ALL For Info v
3 Daily Report to be submitted every Wednesday or weekly report to be sign by
owner site manager. ALL For Info v

4 Comencement date for bulk earthwork & macro drain start when the CAR release
by MWW. (1 October 2019) MWW 1-Oct-19 v

5 Every Mobilization and Demobilization of mechinaries have to approve by letter


from MWW and submit to DEM ALL For Info v

6 KSO to aware of GEOFORCE geotextile peg which indicate the soil filling
To be
boundary, otherwise KSO have to clear it. KSO v
Noticed
7 Regarding the concrete pannel fence installation, KSO reporting that their peg has
been moved. And cause the the alignment shifted. MWW For Info v

8 Please make the temporary drain / channel to flow the water from Pond D
To be
KSO v
Noticed
9 Panel fence work still remain continue to be constructed, if any incidents happen
To be
will be notified in Official Report. KSO v
Noticed
10 Please make new settlement plate that already broken (permanent benchmark) at
To be
Zone E (Buffer Zone Area) , and report the monitoring regularly in weekly basic. KSO v
Noticed
11 DCP Test will be done ± 1 meter / more than 90 cm, especially at Subdrain 5
location KSO For Info v

12 In connection with concrete panel fence work, MWW suggest to do the villager
access road first. Detail layout of villager access road will be sent to KSO later. KSO For Info v

13 Box culverts in subdrain 6 to be maintained so that there is no puddle To Be


KSO v
Noticed
14 Access road for villager will be done with compacted subgrade and paving block To Be
KSO v
as the top layer. Noticed
15 KSO will make 3 open spot for the panel fence construction (the detail is waiting To Be
KSO v
confirmation from DEM) Noticed
16 Embankment work at the sediment trap is waiting confirmation from DEM To Be
KSO v
Noticed
17 Use good soil for backfilling. Please remove / clearing the roots first. To Be
KSO v
Noticed
V. DESIGN ISSUE
FINISH STATUS
No MATTERS DISCUSSED ACTION BY
DATE OPEN CLOSE
1 As agreed on todays meeting,
CBR test should reach >= 5%,
50 cm loose thickness,
Tested using Field CBR, DCP test, & Sand Cone test,
Tested every 50 m' grid/radius.
if the CBR did not reach the requirement, test again nearby the point and do the
average. ALL FOR INFO v
Agreed today 25 September 2019 :
1. For the valley area excavation using the GEOFORCE recommendation, its not
require CBR 5%, indeed need flat surface only.
2. For other subgrade besides valley, require CBR 5 %

2 KSO will do the works on buffer area, GEOFORCE will provide the
recommendation regarding the soil stability.
To be Submitted to MWW on 13 september 2019 GEOF-MWW 19-Sep-19 v
recent updates : submitted to KSO by MWW per 19 september 2019 (For Info)

3 GEOFORCE to aware about the overlapping on the subdrain which under


geotextile and above it. GEOF For Info v

4 Based on GEOFORCE recommendation, Slurry at buffer area has to be removed


by 4 m thick and replace with sand & gravel material, MWW will settle ASAP.
Recent Update : not using granular anymore. MWW TBD v
KSO to remove the slurry soil at buffer area (section B & C)

5 For the soil testing, All surface have to be tested wheter its achived the MWW-GEOF-
requirement or not. For Info v
KSO
6 GEOFORCE will provide the formula regarding DCP CBR calculation. GEOF 2-Oct-19 v
7 MWW instruct to make fish bone on the spring water near the DB 5 and KSO to
put it in a drawing. KSO-MWW For Info v

8 KSO to start the subdrain 5 from STA 0+040 due to the macrodrain path crossing
it. KSO to aware about it. KSO-MWW 16-Oct-19 v

9 KSO to proceed the Fishbone on subdrain 3 according to the approved To Be


shopdrawing. No need to install the vertical drain. KSO-MWW v
Noticed
10 As attached on the MOM, there is the fencing area or alignment which cant be
installed on site due to the existing condittion ( there is a drain nearby ) , MWW To Be
KSO-MWW v
instruct to hold the area. (Drawing attached) Noticed

11 The installation of barbed wired in panel fence are facing the village area To Be
KSO v
Noticed
12 KSO to make RFI regarding detail connection Box 2 with Macro Drain Type 2, To Be
KSO v
also detail of chamber for every corner. Noticed
13 Based on As-Built Drawing of Subdrain 2 and 3, KSO to overlay the subdrain
location with the macro drainage drawing. If there is an indication of subdrain To Be
KSO v
and spun pile intersect each other, please send the RFI to MWW. Noticed

14 KSO to make RFI regarding the spun pile position (2B81, 2B82, 2B27, 2B28) due to To Be
KSO v
these spun pile intersect with subdrain position. Noticed
VI. MISC.
1 KSO to survey existing village access and surrounding area for MWW to consider
and design underpass/boxculvert before backfilling BOH access.
Recent Updates: This portion is under KSO design & build ALL 16-Oct-19 v