MACRO DRAIN CASTING SEQUENCE SCHEDULE

Start Working Date : 01-Dec-19

A. Box Culvert Type 1 (Sta.0+000~Sta.0+105) - Zone 1


Length = 105 m'
105.00

0.30

17.50 17.50 17.50 17.50 17.50 17.50

STAGE 1 STAGE 2 STAGE 3 STAGE 4 STAGE 5 STAGE 5

Removal of Formwork 2 day 16-Mar-20 18-Mar-20 08-Apr-20 10-Apr-20 01-May-20 03-May-20 24-May-20 26-May-20 16-Jun-20 18-Jun-20 09-Jul-20 11-Jul-20

Casting Sidewall 7 day 08-Mar-20 15-Mar-20 31-Mar-20 07-Apr-20 23-Apr-20 30-Apr-20 16-May-20 23-May-20 08-Jun-20 15-Jun-20 01-Jul-20 08-Jul-20

Rebar Installation 5 day 02-Mar-20 07-Mar-20 25-Mar-20 30-Mar-20 17-Apr-20 22-Apr-20 10-May-20 15-May-20 02-Jun-20 07-Jun-20 25-Jun-20 30-Jun-20 2.00

Formwork Installation 5 day 25-Feb-20 01-Mar-20 19-Mar-20 24-Mar-20 11-Apr-20 16-Apr-20 04-May-20 09-May-20 27-May-20 01-Jun-20 19-Jun-20 24-Jun-20

35.00 35.00 35.00

STAGE 1 STAGE 2 STAGE 3

Casting Bottom Slab 7 day 01-Feb-20 ~ 08-Feb-20 09-Feb-20 ~ 16-Feb-20 17-Feb-20 ~ 24-Feb-20 0.55

Lean Concrete (t=50mm) 5 day 26-Jan-20 ~ 31-Jan-20 0.05


Compacted Sand (t=100mm) 5 day 20-Jan-20 ~ 25-Jan-20 0.10

Pile Head Treatment 11 day 08-Jan-20 ~ 19-Jan-20


Cutting of Pile Head 11 day 27-Dec-19 ~ 07-Jan-20
PDA Test 7 day 19-Dec-19 ~ 26-Dec-19
Erection Spun Pile 17 day 01-Dec-19 ~ 18-Dec-19
Spun Pile Ø500mm L=34m

B. Box Culvert Type 2A (Sta.0+000~Sta.0+110) - Zone 1


Length = 110 m'
110.00

0.30

18.33 18.33 18.33 18.33 18.33 18.33

STAGE 1 STAGE 2 STAGE 3 STAGE 4 STAGE 5 STAGE 5

Removal of Formwork 2 day 03-Apr-20 05-Apr-20 26-Apr-20 28-Apr-20 19-May-20 21-May-20 11-Jun-20 13-Jun-20 04-Jul-20 06-Jul-20 27-Jul-20 29-Jul-20

Casting Sidewall 7 day 26-Mar-20 02-Apr-20 18-Apr-20 25-Apr-20 11-May-20 18-May-20 03-Jun-20 10-Jun-20 26-Jun-20 03-Jul-20 19-Jul-20 26-Jul-20

Rebar Installation 5 day 20-Mar-20 25-Mar-20 12-Apr-20 17-Apr-20 05-May-20 10-May-20 28-May-20 02-Jun-20 20-Jun-20 25-Jun-20 13-Jul-20 18-Jul-20 2.00
Formwork Installation 5 day 14-Mar-20 19-Mar-20 06-Apr-20 11-Apr-20 29-Apr-20 04-May-20 22-May-20 27-May-20 14-Jun-20 19-Jun-20 07-Jul-20 12-Jul-20

36.67 36.67 36.67

STAGE 1 STAGE 2 STAGE 3

Casting Bottom Slab 7 day 19-Feb-20 ~ 26-Feb-20 27-Feb-20 ~ 05-Mar-20 06-Mar-20 ~ 13-Mar-20 0.55

Lean Concrete (t=50mm) 5 day 13-Feb-20 ~ 18-Feb-20 0.05


Compacted Sand (t=100mm) 5 day 07-Feb-20 ~ 12-Feb-20 0.10

Pile Head Treatment 11 day 26-Jan-20 ~ 06-Feb-20


Cutting of Pile Head 11 day 14-Jan-20 ~ 25-Jan-20
PDA Test 7 day 06-Jan-20 ~ 13-Jan-20
Erection Spun Pile 17 day 19-Dec-19 ~ 05-Jan-20
Spun Pile Ø500mm L=34m