Within
1 Project Plan Approval March Manual Client to approve
31st
Consultant to be supplied
with 2 labourers along with
Plastic rope (100m) and
wooden sticks to mark the
Pits. Consultancy Job will
2 Setting out of Pits April 1 to 7 Manual finish upto this stage.
Further works can be
supervised by the
Consultant in the interest
of client for additional
payment as discussed early
Digging for Pits using HITACHI, 60 cm Top soil 8 to 15th of As per availability of
3 Machinery
keep aside April Machinery
Arranging Coconut Husk , Sterameal @ 5kg per
Within 10th Approximately 20 nos.
4 Pit and Calcium Carbonate @ 1kg per pit at Vehicle Transport
of April Husk per Pit
site
Laying of Coconut Husk and application of 16th to 25th As per availability of
5 Manual
chemical dust against Termites of April Labourers
Top soil mixed with Calcium Carbonate 1 kg 26th to 30th As per availability of
6 Manual
per pit April Labourers
Wetting the calcium carbonate mixed Topsoil 26th to 30th As per availability of
7 Manual
for one week April Labourers
Back filling of Topsoil mixed with Sterameal 5 7th May to As per availability of
8 Manual
kg per Pit 12th May Labourers
7th May to As per availability of
9 Irrigation for 1 week in the Pit Manual
15th May Labourers
Purchase of Coconut Seedlings, bringing to site Within 15th As per availability of
10 Manual
and keep under shade May Seedlings in Market
Planting of Coconut Seedlings, together with 15th May
As per availability of
11 preparation of Bunds around the Pit to curb to 25th Manual
Labourers
running water May

Completion of work is expected before the onset of Monsoon in June.