Work Planning Schedule

Month
Item # Description of Work Mode of work Remarks
and Date
Within
1 Project Plan Approval Manual Client to approve
May 6
Consultant to be supplied
with 2 labourers along with
Plastic rope (100m) and
wooden sticks to mark the
Pits. Consultancy Job will
8 to 12
2 Setting out of Pits Manual finish upto this stage.
May
Further works can be
supervised by the
Consultant in the interest
of client for additional
payment as discussed early
Digging for Pits using HITACHI, 60 cm Top soil 12 to 17th As per availability of
3 Machinery
keep aside of May Machinery
Arranging Coconut Husk , Sterameal @ 5kg per
Within 15th Approximately 20 nos.
4 Pit and Calcium Carbonate @ 1kg per pit at Vehicle Transport
of May Husk per Pit
site
Laying of Coconut Husk and application of 15 th to As per availability of
5 Manual
chemical dust against Termites 20th of May Labourers
Top soil mixed with Calcium Carbonate 1 kg 16 th to 20 As per availability of
6 Manual
per pit May Labourers
Wetting the calcium carbonate mixed Topsoil 20th to 27th As per availability of
7 Manual
for one week May Labourers
Back filling of Topsoil mixed with Sterameal 5 27 May to As per availability of
8 Manual
kg per Pit 30th May Labourers
30 May to As per availability of
9 Irrigation for 1 week in the Pit Manual
5th June Labourers
Purchase of Coconut Seedlings, bringing to site Within 25th As per availability of
10 Manual
and keep under shade May Seedlings in Market
Planting of Coconut Seedlings, together with
6 June to As per availability of
11 preparation of Bunds around the Pit to curb Manual
15th June Labourers
running water

Completion of work is expected before June 15.