MINUTES OF MEETING

SR. NO. POINTS Benefit Status as on 05/10/23 Status as on 02/11/23 Status as on 07/12/23 Status as on 03/01/24 Status as on 03/02/24
Yield improvement by 0.5% = 15 MT = 57 L
Referred to Mr. Dipukumar (in early 2nd week of Order placed,Detail Engineering in
1 Chiller expansion - mainly in U1 pm saving 15th Nov ordered will be placed Delayed , order will be placed this week.
December) ( Purchase) for further needful. progress.Installation by May 1st week
At least in 8 months
Price of Allana & NZ is higher, wait for some more time.
2 Sourcing of imported bone Share pricing comparison Take 1000 mt for 130 ton gelatin Under Review Under Review with Purchase Dept. Under Review with Purchase Dept.
Also review the impact on Customer blends and EDQM
3 Sourcing of Ossein - CJ gelatin Keep exploring, can be helpful in May-2024 Pending Pending Pending Pending
Better chilling, resulting in higher yield Readiness at Vendor works likely by first week of Final inspection in March 1st
4 Graphite heat exchanger Final negotiation going on Ordered , Under manufacturing.
Capacity enhancement March'24 week.Installation by March end.
Structure installation done, System piping and
5 Acid tank scrubber - Compliance Expected in November End of November ,installation will start Inhouse structure is getting ready. installation from 3rd OR 4th Jan. Completion by In Operation
12/1/24
Now Expected in 1st week of january (Elastomer food Received .Will be installed during VECL
6 Votator Alternate pump - screw pump - imported Reducing contamination Expected in November Expected this month Local Roto Pump is awaited by 15th Dec.
grade certificate issue) shutdown in unit 2 c-wing
Parameter and other Details as requested by Lars vide
Review in process, also visit the exhibition and interact LARS will revert in a week based on Parameter Parameters shared to LARS there feed back
7 Bio digestor - to be identified Feasibility study going on latest email is being worked out and anticipated from
with other manufacturers Inputs. expected by next week.
ETP in @ 15 days time i.e. by 15/1/24

One Offer for Spray Dryer Modification received


Collagen plant - commissioning help - aglomerator - Report received, will receive the offer in this month i.e
8 Report received. Offer is awaited from GEA from local vendor. GEA offer will be received by Process Under Review On going
timeline / capex Oct
this week. Upstream Details are awaited.

Site visit to supplier done,Delivery expected


9 Unit I - Primary floculator Expected in November Expected in November end Delayed , expected in this month. Expected by 15th January at site
in FEB
Automated control
10 DCS system - Unit II Order Placed, and technical discussions ongonig Ongoing Ongoing Ongoing On going,
Existing Card outdated
1A Done , 1B will be done in this month. U-2 A-2
11 Aeration Tank Modification Intiated, and on going Phase 1 in November 1B Done , A-2 modification under progress. A-2 under progress
Modification planning is ongoing.
On going for better charging & drying (controlling Shed completed , flooring work is ongoing. Will be
12 Bone Storage capacity increased Finishing by 10 th November Done. Pallet making in progress (In house)
impurities) completed in 15 days.
13 66 KV On Going - Feb 2024 completion expected will be finished by jan 24 Will be finished by Feb 24 Will be finished by Feb 24 Will be finished by Feb 24 end.
Proposals Techno commercial Handed over to Mr.
On going as it is linked with 66 KV commisioning.
14 Solar Rooftop review and discussion in process Ongoing Dipukumar (Purchase) for further needful. One more 1 MW,with purchase for negotiation
However it will be finalised by this month end.
final offer anticipated

Instrumentation dept. is coordinating with Purchase Decision will be taken by Feb end after data
15 Atlas Copco Air Compressor Replacement, savings to be calculated Technical study going on Technical study going on
and Utility. Order may be placed in January 1st week. analysis.

16 Narmada Water Supplies To be followed up for regular supplies Under progress Under progress Under progress Under progress

Few more Hardware items are requested by Vendor


As sugested by supplier tank
17 Waste Water Recycle ( Trial Run ) by Synergy. Initiated from 5th Dec. for additional Hardness removal step. SBL will arrange
prepared,Further feed back is awaited
and inform vendor to restart the trial .

18 Video Conference Room Under Progress. Will be finished by 10th Feb.


Two designs are required for Masar &
19 Toilet Repairs Under Progress. Kharakhadi. Karakhadi guest house toilet
work is in progress.

20 Renovation of Admin Block Under Progress. It is in planning stage.

21 Exploring weiging system on Bone Charging. Under Progress. Supplier identified

22 Air cooling system in U-1 C wing similar to U-2 Cwing. Two proposals received.