SR. NO. POINTS Benefit Status as on 05/10/23 Status as on 02/11/23 Status as on 07/12/23 Status as on 03/01/24 Status as on 03/02/24
Yield improvement by 0.5% = 15 MT = 57 L
Referred to Mr. Dipukumar (in early 2nd week of Order placed,Detail Engineering in
1 Chiller expansion - mainly in U1 pm saving 15th Nov ordered will be placed Delayed , order will be placed this week.
December) ( Purchase) for further needful. progress.Installation by May 1st week
At least in 8 months
Price of Allana & NZ is higher, wait for some more time.
2 Sourcing of imported bone Share pricing comparison Take 1000 mt for 130 ton gelatin Under Review Under Review with Purchase Dept. Under Review with Purchase Dept.
Also review the impact on Customer blends and EDQM
3 Sourcing of Ossein - CJ gelatin Keep exploring, can be helpful in May-2024 Pending Pending Pending Pending
Better chilling, resulting in higher yield Readiness at Vendor works likely by first week of Final inspection in March 1st
4 Graphite heat exchanger Final negotiation going on Ordered , Under manufacturing.
Capacity enhancement March'24 week.Installation by March end.
Structure installation done, System piping and
5 Acid tank scrubber - Compliance Expected in November End of November ,installation will start Inhouse structure is getting ready. installation from 3rd OR 4th Jan. Completion by In Operation
12/1/24
Now Expected in 1st week of january (Elastomer food Received .Will be installed during VECL
6 Votator Alternate pump - screw pump - imported Reducing contamination Expected in November Expected this month Local Roto Pump is awaited by 15th Dec.
grade certificate issue) shutdown in unit 2 c-wing
Parameter and other Details as requested by Lars vide
Review in process, also visit the exhibition and interact LARS will revert in a week based on Parameter Parameters shared to LARS there feed back
7 Bio digestor - to be identified Feasibility study going on latest email is being worked out and anticipated from
with other manufacturers Inputs. expected by next week.
ETP in @ 15 days time i.e. by 15/1/24
Instrumentation dept. is coordinating with Purchase Decision will be taken by Feb end after data
15 Atlas Copco Air Compressor Replacement, savings to be calculated Technical study going on Technical study going on
and Utility. Order may be placed in January 1st week. analysis.
16 Narmada Water Supplies To be followed up for regular supplies Under progress Under progress Under progress Under progress
22 Air cooling system in U-1 C wing similar to U-2 Cwing. Two proposals received.