BAITA PLAI PROGRESS UPDATE MAY 2020

EXPECTED DEVELOPMENT SCHEDULE

Month Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20

Underground
General Revision
Preparing Open Stopes
Access Points
Collection Points
Railway
Machinery Order/Delivery
Mining Equipment
Flotation
Crushers
Mills
Classifiers
Hydro-Cyclones
Flotation Cells
Filters
Pumps
Electricals including new secondary cable
Pumps
Laboratory
Tailings Dam
General Maintenance
New Pipeline from Flotation

Underground Overground General

*In accordance to previously announced programme BAITA PLAI PROGRESS UPDATE MAY 2020
UPDATED DEVELOPMENT SCHEDULE
PROGRESS IS BEING MADE

Month Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Update

Underground In Progress and on schedule


General Revision
In Progress and on schedule
Preparing Open Stopes In Progress and on schedule
Access Points
Not yet commenced on schedule
Collection Points
Railway Parts delivered and on site, partially installed and will be completed 1st week of June)
Machinery Order/Delivery All parts ordered and produced, essential equipment on site, balance arrived 21 May and 1st week of July)
Mining Equipment
Flotation
Completed and on site
Crushers
Mills Cleaned, prepared and awaiting mill liners (30-day delivery)
Classifiers Rebuilt existing classifiers , awaiting liners
Manufactured and paid, on the vessel arriving 13 July
Hydro-Cyclones Completed
Flotation Cells
Filters Ordered new filter press to increase efficiency instead of repairing old ones, arriving 13 July
Pumps Not yet commenced
Electricals including new secondary cable Completed
Pumps Repairs completed
Laboratory In Progress (not essential to be completed prior to production)
Tailings Dam
In Progress; ahead of schedule
General Maintenance
Project design completed, sediment tank at flotation plant produced and installed, pipeline commenced and
New Pipeline from Flotation
in progress 5 out of 7Km completed

Completed
On Schedule
Delayed/no impact on opening
Changed planning

*In accordance to previously announced programme BAITA PLAI PROGRESS UPDATE MAY 2020
UPDATED DEVELOPMENT SCHEDULE
PROGRESS IS BEING MADE

Underground

1. General Revision

2. Preparing Open Stopes


&
4. Collection Points

3. Access Points

BAITA PLAI PROGRESS UPDATE MAY 2020


UPDATED DEVELOPMENT SCHEDULE
PROGRESS IS BEING MADE

7.

BAITA PLAI PROGRESS UPDATE MAY 2020


UPDATED DEVELOPMENT SCHEDULE
PROGRESS IS BEING MADE

BAITA PLAI PROGRESS UPDATE MAY 2020


UPDATED DEVELOPMENT SCHEDULE
PROGRESS IS BEING MADE

BAITA PLAI PROGRESS UPDATE MAY 2020


UPDATED DEVELOPMENT SCHEDULE
PROGRESS IS BEING MADE

Before and After Before and After

BAITA PLAI PROGRESS UPDATE MAY 2020